International Journal of Scientific & Engineering Research, Volume 4, Issue 7, July ISSN

Similar documents
A REVIEW OF SELF HEALING SMART GRIDS USING THE MULTIAGENT SYSTEM

Reliability Assessment of Distribution Systems Incorporating Feeder Restoration Actions

Distribution system security region: definition, model and security assessment

Performance Analysis of Various Types of Fault Current Limiters Using PSCAD

Enhancement of Fault Current and Overvoltage by Active Type superconducting fault current limiter (SFCL) in Renewable Distributed Generation (DG)

TRADITIONALLY, if the power system enters the emergency

UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS

EMERGING distributed generation technologies make it

Negative-Sequence Based Scheme For Fault Protection in Twin Power Transformer

Minimization of Power Loss and Improvement of Voltage Profile in a Distribution System Using Harmony Search Algorithm

IMPLEMENTATION OF NETWORK RECONFIGURATION TECHNIQUE FOR LOSS MINIMIZATION ON A 11KV DISTRIBUTION SYSTEM OF MRS SHIMOGA-A CASE STUDY

How to maximize reliability using an alternative distribution system for critical loads

Fault Location Using Sparse Wide Area Measurements

Reducing the Fault Current and Overvoltage in a Distribution System with an Active Type SFCL Employed PV System

Directional Overcurrent Relays Coordination Restoration by Reducing Minimum Fault Current Limiter Impedance

Design and Simulation of superconducting fault current limiter

Adaptive Centralized Protection Scheme for Microgrids Based on Positive Sequence Complex Power

Overcurrent relays coordination using MATLAB model

ENHANCED DISTANCE PROTECTION FOR SERIES COMPENSATED TRANSMISSION LINES

Sensitivity Analysis for 14 Bus Systems in a Distribution Network With Distributed Generators

Adaptive Relaying of Radial Distribution system with Distributed Generation

Stability Issues of Smart Grid Transmission Line Switching

Improvement of Electricity Distribution Services Using a DVR with a Constant DC Voltage Source Instaled in MV Connection Substations

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods

Time-current Coordination

Pak. J. Biotechnol. Vol. 13 (special issue on Innovations in information Embedded and Communication Systems) Pp (2016)

AS the power distribution networks become more and more

DG TRANSFER CONNECTION SCHEME IN ACTIVE DISTRIBUTION NETWORKS

Graph Theory-Based Feeder Automation Logic for Low-End Controller Application

Active Power Sharing and Frequency Control of Multiple Distributed Generators in A Microgrid

International Journal of Current Research and Modern Education (IJCRME) ISSN (Online): & Impact Factor: Special Issue, NCFTCCPS -

VOLTAGE sag and interruption are the most important

Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation

Hamdy Faramawy Senior Application Specialist ABB Sweden

SEATTLE CITY LIGHT DISTRIBUTION AUTOMATION

GRID CODE COMPATIBLE PROTECTION SCHEME FOR SMART GRIDS

Real Time Simulation of New Adaptive Overcurrent Technique for Microgrid Protection

OPTIMAL ALLOCATION OF PMU CONSIDERING CONTROLLED ISLANDING OF POWER SYSTEM USING HYBRID OPTIMIZATION ALGORITHM

Optimal sizing of battery energy storage system in microgrid system considering load shedding scheme

Protection Introduction

University of Nevada, Reno. Smart Meter Data-Driven Fault Location Algorithm in Distribution Systems

Optimal PMU Placement in Power System Networks Using Integer Linear Programming

Identification of weak buses using Voltage Stability Indicator and its voltage profile improvement by using DSTATCOM in radial distribution systems

Micro grid Protection Using Digital Relays Mr.Karthik.P 1, Mrs.Belwin J. Brearley 2

A Tutorial on the Application and Setting of Collector Feeder Overcurrent Relays at Wind Electric Plants

Oscillation Ring Test Using Modified State Register Cell For Synchronous Sequential Circuit

ALI UMAIR DETECTION ALGORITHM FOR THE CROSS COUNTRY EARTH FAULTS IN MEDIUM VOLTAGE NETWORK

ONE proposed way of integrating high penetration of DG

Fault Localization using Wavelet Transforms in 132kV Transmission Lines

Differential Protection for Microgrids with Embedded Generations

DC Line Protection for Multi-terminal (MT)- HVDC Systems

A Novel Fuzzy Neural Network Based Distance Relaying Scheme

Fault Detection and Isolation of a Loop Type Low Voltage DC Bus Microgrid

An Adaptive Protection Scheme for Optimal Overcurrent Relay Coordination in Interconnected Power Systems

PSV3St _ Phase-Sequence Voltage Protection Stage1 (PSV3St1) Stage2 (PSV3St2)

WITH THE advent of advanced power-electronics technologies,

Fuel cell power system connection. Dynamics and Control of Distributed Power Systems. DC storage. DC/DC boost converter (1)

Islanding and Detection of Distributed Generation Islanding using Negative Sequence Component of Current

Smart Grid Where We Are Today?

A decentralized multiagent-based voltage control for catastrophic disturbances in a power system

State Estimation Advancements Enabled by Synchrophasor Technology

No. SSIEC-SEW SHINSUNG. Solid Insulation Eco Load Break Switch (SILO) SILO SERIES 15kV, 27kV 400A, 630A

GRID CONNECTED HYBRID SYSTEM WITH SEPIC CONVERTER AND INVERTER FOR POWER QUALITY COMPENSATION

Annamacharya Institute of Technology and Sciences, Tirupathi, A.P, India

The Impact of Superconducting Fault Current Limiter Locations on Voltage Sag in Power Distribution System

ANALYSIS OF A FLASHOVER OPERATION ON TWO 138KV TRANSMISSION LINES

Locating Double-line-to-Ground Faults using Hybrid Current Profile Approach

Combination of Adaptive and Intelligent Load Shedding Techniques for Distribution Network

ISLANDING DETECTION USING DEMODULATION BASED FFT

FRIENDS Devices and their Coordination

Optimum Coordination of Overcurrent Relays: GA Approach

Relay Coordination in the Protection of Radially- Connected Power System Network

Approach for High voltage transmission line protection by using line trap network & ANN over SVM

A New Approach Applied to Adaptive Centralized Load Shedding Scheme

THERE has been a growing interest in the optimal operation

Intelligent Reconfiguration of Smart Distribution Network using Multi-Agent Technology

DG Allocation and Sizing Based on Reliability Improvement by Means of Monte Carlo Simulation

Locating of Multi-phase Faults of Ungrounded Distribution System

AFTER an overhead distribution feeder is de-energized for

A New Network Proposal for Fault-Tolerant HVDC Transmission Systems

Voltage Support and Reactive Power Control in Micro-grid using DG

EE Lecture 14 Wed Feb 8, 2017

Protection of distributed generation interfaced networks

No. SSIEC-PRC SHINSUNG. Polymer Recloser SIREC SERIES 15kV, 27kV, 38kV 400A, 630A, 800A

A Review on Voltage Stability Margin Improvement with Distributed Generation

The Fault Level Reduction in Distribution System Using an Active Type SFCL

A New Adaptive Wide Area Protection Algorithm for Distribution Networks with Distributed Generation

Methods for Reducing the Activity Switching Factor

Reducing the Effects of Short Circuit Faults on Sensitive Loads in Distribution Systems

DISTRIBUTION SYSTEM PLANNING USING NETWORK RECONFIGURATION FOR LOSS REDUCTION

Notes 1: Introduction to Distribution Systems

ANALYSIS OF OPTIMAL LOCATION OF SUPERCONDUCTING FAULT CURRENT LIMITER FOR THE SMART GRID

Distance Protection for Distribution Feeders. Presented By: Yordan Kyosev, P.Eng. & Curtis Ruff, P.Eng.

Proposed Techniques for Identifying Open and Short Circuit Sections in Distribution Networks

Study on the Improvement of the Special Protection Scheme (SPS) in the Korean power system

Modelling and Simulation of High Step up Dc-Dc Converter for Micro Grid Application

Review of Performance of Impedance Based and Travelling Wave Based Fault Location Algorithms in Double Circuit Transmission Lines

IMPLEMENTATION OF ADVANCED DISTRIBUTION AUTOMATION IN U.S.A. UTILITIES

FAULT PROTECTION OF A LOOP TYPE LOW VOLTAGE DC BUS BASED MICROGRIDS

ANALYSIS OF ACTIVE POWER FILTER FOR HARMONIC VOLTAGE RESONANCE SUPPRESSION IN DISTRIBUTION SYSTEM

Transcription:

International Journal of Scientific & Engineering Research, Volume 4, Issue 7, July-2013 377 Self-Healing Framework for Distribution Systems Fazil Haneef, S.Angalaeswari Abstract - The self healing framework for distribution systems based on multi agent system is constructed. The proposed multi agent system is designed to locate and isolate faults, then decide and implement the switching operations to restore the out-of-service loads. The function of zone agents in the first layer is monitoring, making simple calculations, and implementing control actions. Feeder agents in the second layer are assigned to negotiation. The constraints include voltage limits, line current limits, and radial topology. FLISR (Fault Location/Isolation/Service Restoration) module will help to reduce the gap between an experienced and a new operator, as the network control will effectively move from person dependent to system dependent. This method can significantly decrease the Fault Location/Isolation/ Restoration time, compared to conventional SCADA/DMS system. Index terms Distribution System, Multi-Agent System, Fault Identification, Isolation, Service Restoration, Voltage and current limit constraints Location/Isolation/ Restoration time, compared to 1 INTRODUCTION conventional SCADA/DMS system. FLISR module is a FTER occurrence of any fault, the key challenge to any 'must' in all future Smart Grid control rooms. Apower distribution utility is to locate/ detect the faulty section, Isolate the faulty section and restore un-faulted areas, as quickly as possible. Faster the restorations after fault- better its impact on Reliability Indices and grater is customer satisfaction. In post fault scenario, the efficiency and quality of 'isolation and restoration' depends on the 2 OBJECTIVES The main objective of this thesis is to develop a framework for self-healing in order to obtain FLISR and to find the solution for the proposed algorithm using C Programming experience and skill-set of the individual operator in SCADA/DMS control room. 3 OPERATION MECHANISM FLISR ( Fault Location/Isolation/Service Restoration) The objectives and the two-way communication among the module will help to reduce the gap between an experience control agents are shown in Fig 1. As shown in the figure, and a new operator, as the network control will effectively the objectives common to all agents are the maximization of move from person dependent to system dependent. FLISR the loads restored and the minimization of the number of module is an Advanced Distribution Automation switching operations. Each agent also has an additional application which has very much importance in future objective. For example the initiator feeder agent (i.e., the Smart Grid control rooms. feeder that has been subjected to a fault at one of its FLISR module installed at field can locate or detect the components and hence has at least one out-of service zone) faulty section and automatically generates switching will locate and isolate the faulty zone before beginning the sequence to isolate the section and restore the un-faulted restoration process. The responder feeder agents (i.e., level-1 areas. For that the distribution system is considered as a or immediate-neighbor backup feeders of the initiator) and multi agent system. The control structure has two layers: zone and feeder. The function of zone agents in the first the subcontractor feeder agents (i.e., level-2 or immediateneighbor backup feeders of the responder feeders) will layer is monitoring, making simple calculations, and implementing control actions. Feeder agents in the second layer are assigned to negotiation. The constraints include Fazil Haneef is currently pursuing Masters degree program in Power System Engineering from Valliammai Engineering College under Anna University, Chennai, India. E-mail: ffazhan@gmail.com S. Angaleaswari is currently an Assistant Professor in Department of provide whatever capacity they have to assist with the restoration without violating their operational constraints. This section describes the operating mechanism of each agent and the mechanism for their coordination using twoway communication during both stages of the self-healing operation (i.e., the first stage, which is the detection and isolation of the fault location, and the second stage, which is the restoration of the out-of-service load). Electrical and Electronics Engineering, Valliammai Engineering College under Anna University, Chennai, India. E-mail: spkavisp@gmail.com voltage limits, line current limits, and radial topology. This method can significantly decrease the Fault 3.1 Detection of Fault Location And Isolation Algorithm.

International Journal of Scientific & Engineering Research, Volume 4, Issue 7, July-2013 378 Once a permanent fault occurs in a distribution feeder, the feeder circuit breaker is tripped in real-time operation. The fault location detection and isolation algorithm is then applied in order to locate and isolate the faulty section from both directions. Fig. 1 Coordination via two-way communication among the control agents As soon as the faulty section is isolated, the upstream out-of-service loads are restored through the closing of the feeder circuit breaker. A restoration algorithm is applied to restore the downstream out-of-service loads. When the faulty section is repaired, the reverse switching sequence is applied so that the distribution system is returned to its normal configuration. Due to the radial topology of the distribution feeders, the occurrence of a fault in a distribution feeder affects only its sections [i.e., sections between the substation and the faulty section as well as the downstream sections, when distributed generation units (DGs) are present]. Therefore, only the control agents of the feeder that has the faulty section will participate at this stage. Due to the voltage potential difference, the normal power flows being from the source to the grid. However, the introduction of DG units may change the direction of power flows from unidirectional to bidirectional. When a fault occurs somewhere in the distribution system, the power flow magnitude and direction change. Fault current flows from the substation and DG units to the lowest potential point at the fault location. Therefore, when a fault occurs in one of the zones between the substation and other zones that involve DG units, the following two conditions apply. The former condition means that there is no fault outside this zone. The latter condition always applies because the former one can be implemented under normal conditions (i.e., a reverse power flow due to a high generation level produced from DG units in the downstream zones). On the other hand, when a fault occurs in a zone that has no downstream zones containing DGs, its entrance breaker current will exceed its limit. Based on these conditions for fault occurrence and on the proposed control structure in Fig. 1 the fault location detection and isolation algorithm for a single fault at a time can be described as follows 1. Monitoring devices using direction and overcurrent relays provide two signals to indicate a change in the status of the current flow. One signal indicates that the magnitude of the current exceeds its limit, and the other indicates the direction of the current. 2. Zone agents utilize these signals in a logic circuit to generate simplified binary status signals (0 or 1), as shown in Fig. 2 Fig. 2 Logic circuits for zone binary signal and fault current flow 3. They then send these binary signals to their feeder agent through inform messages. The fault is fed by both the substation and the DG units in the downstream zones. The current in both boundary breakers of this zone will thus flow into the zone The current in at least one of its breakers will exceed its limit. 4. The feeder agent determines which zone is the faulty zone as shown in Fig. 2 : If it receives a binary signal with a value of one from a type 1 zone, it sends a request message to this zone agent asking it to open its boundary breakers

International Journal of Scientific & Engineering Research, Volume 4, Issue 7, July-2013 379 If it receives a binary signal with a value of one from a type 2 zone, it sends a request message to this zone agent asking it to open its boundary breakers If it receives a binary signal with a value of one from more than one type 2 zones, it sends a request message to the last zone agent (i.e., the zone at the feeder end side) asking it to open its boundary breakers If it receives a binary signal with a value of zero, no action is taken. 3.2 Service Restoration Algorithm. 1. Initiator Control Agent Operating Mechanism: After the fault is isolated, the downstream zones are isolated. The affected zones communicate with their feeder agent (initiator), as shown in Figs. 1, in order to build a restoration plan. 2) To place tie switches between the feeder agents that have accepted proposals and the selected combinations for the restoration in a switch-to- The details of the proposed architecture are as follows: 1. Each zone agent in the out-of-service area sends a request message to the initiator, including its load demand and priority n s Zone index i = wf j j i S i j=1 Where wf j i,s j i : Weighting factor and load demand of be-closed list (SCL) customer j in zone i respectively, ns : Total number of customers in zone i. 2. The initiator control agent starts negotiations using a contract net protocol (CNP) by sending call for proposal (CFP) messages to the responder feeder agents. 3. After the responder feeder agents reply with their proposal messages, which contain their available remaining capacity (ARC), the initiator agent sends these two input items to its decision maker. The input consists of the load demands and priorities from the out-of-service zone agents, and the ARCs from the responder agents. 4. The decision maker component in the initiator agent uses expert-based rules along with the input it has received in order to determine its output. 5. The initiator agent compares the maximum ARC with the total demand from the out-of-service zones Is max (ARC i ) S i i n BF1 i=1 where S i : Load demand of zone i nz : The total number of out-of-service zones nbf1: The total number of responder agents. n z 6. If the above equation is satisfied, the initiator decides to initiate group restoration by restoring all out-of-service zones through one switching operation. 7. The actions of the initiator agent are therefore to send an accept-proposal message to the responder agent that has the highest ARC and to send a request message to its zone agent that is the neighbor of the selected backup feeder asking it to close its tie switch for the completion of the restoration process. 8. If the equation is not satisfied, the initiator decides to initiate zone restoration by building a zone/switch relationship table 9. Based on the zone/switch relationship table and the ARCs communicated from the responder agents, the initiator agent searches for possible combinations of zone restoration. It compares the ARCs with the elements of zone combination, which are listed in descending order based on their priority indices. 10. After checking for the available restoration possibilities, the initiator agent actions are: 1) To send accept-proposal messages to those responders that will be used in the restorations 3) To place the bounded sectionalizing switches of the selected combinations for restoration in a switch-to-be-opened list (SOL) in order to satisfy the radial constraint 4) To update the zone/switch relation table. 11. It then checks to determine whether the table is empty (i.e., whether all zones have been restored). 12. If the table is empty, the initiator sends request messages to the appropriate zone agents asking them to open their sectionalizing switches that are included in the SOL list in order to partition the outage area and then to close their tie switches that are included in the SCL list. 13. If the table is not empty, the initiator sends request messages to the responder feeder agents that are neighbors of the remaining unrestored zone combinations. This request prompts these responders to start negotiations with their neighbors (subcontractors) to find load transfers that can provide additional ARC. The request

International Journal of Scientific & Engineering Research, Volume 4, Issue 7, July-2013 380 message includes the load demand required for the remaining unrestored zone combinations. 14. After these responders reply with their ARC, the initiator agent repeats steps 9 11. 15. If the table is empty, the initiator sends request messages to the appropriate zone agents to open their sectionalizing switches included in the final SOL list and then to close their tie switches included in the final SCL list. 16. If the table is not empty, the initiator determines the necessity for load shedding of the lowest priority load (i.e., the lowest priority zone index) in the remaining unrestored zone combinations. It then checks to determine whether all zones have been restored, as in step 9. 17. The initiator agent repeats step 16 until the zone/switch relationship table becomes empty, when it then executes step 15 in order to implement the switching actions required for the completion of the restoration process. 3.3 Level - 1 Backup Feeder (Responder) Operating Mechanism. The operating mechanism of each level-1 backup feeder (responder) agent will be as follows: 1. After the responder agent receives a CFP message from the initiator, it starts to build its proposal (ARC) S L = V L * I available 2. It sends query messages to its appropriate zone agents about their spare capacities and bus voltage to include the voltage limit V L 0.9 pu. values 3. Each zone agent replies by sending an inform message that includes the spare capacity of its branch and/or the bus voltage magnitude of its bus: I M (K) = I max (k) I(k) Where I M (k) : Represents the available capacity of each zone before it becomes overloaded and before its protection device operates I max(k) : Upper bound current in branch K I(k) : Magnitude of the current flow in branch k 4. If any zone has more than one branch, it sends the minimum spare capacity of its branches, and a zone with more than one bus sends the lower voltage magnitude of its buses 5. After the responder agent receives these replies, it calculates its ARC as follows I C = min kϵj (I M(k)) I available = min(i C, I V ) Where j : Zones along the restoration path V w : The lowest bus voltage magnitude of the values received from zone agents V min : Minimum allowable voltage magnitude in the network (i.e., 0.9 p.u.) Z path : Series impedance of the path between the substation and the node closest to node w on the restoration path. This impedance could be determined by carrying out offline simulation if the forecasted load is available (i.e., to determine which point among the points located at the end of the feeder will have minimum voltage, hence, its Z path will be used). Another option is to determine Z path for those possible points in advance and based on the received minimum voltage value, the appropriate impedance is used I C : Maximum spare capacity of the restoration path without overloading (current limit constraint) I V : Maximum spare capacity of the restoration path to avoid under-voltage at any node (voltage limit constraint) I available : Maximum spare capacity of the restoration path without violating operating constraints. 6. If this spare capacity I available from this supporting feeder will be used to restore an out-of-service load S L=P L+jQ L at voltage V L This ARC guarantees that voltage limits will not be violated for the restored zones. 7. The responder sends to the initiator agent a propose message that includes this ARC. 8. If the responder receives an accept-proposal message from the initiator, it replies to the initiator by sending an inform message to indicate that it is committed to the completion of the task. 9. If the responder receives from the initiator a request message for additional ARC through load transfer, I V = V w V min Z path

International Journal of Scientific & Engineering Research, Volume 4, Issue 7, July-2013 381 Fig. 3 Flow chart of Overall self healing procedure using agents

International Journal of Scientific & Engineering Research, Volume 4, Issue 7, July-2013 382 it begins negotiations by sending CFP messages to its neighboring feeders, if available (i.e., level-2 backup feeders or subcontractor agents). 10. This load transfer from a level-1 backup feeder to a level-2 backup feeder would involve the responder securing a margin that could enable it to restore the remaining out-of-service zone combinations. The best amount of the transferred load (TL) is then TL = (load of remaining unrestored zone combinations) - (remaining ARC of this level-1 backup feeder) 11. Due to the discrete nature and possibly the limited ARC of the level-2 backup feeders, the TL cannot be exactly the same as what is required. The responder thus selects its zones to be transferred to the level-2 backup feeder as follows: Transferred zone(s) min (TL, ARC of level 2 BF) 12. After the responder determines the zones to be transferred, it sends a propose message to the initiator with its new ARC 13. If the responder receives an accept-proposal message from the initiator, it sends a confirm message to the subcontractor agent and request messages to the appropriate zone agents asking them to open the bounded sectionalizing switches for the selected zones to be transferred and to close the tie switch to complete the load transfer to the subcontractor. Fig. 4.6 shows the overall procedure for the proposed responder control agent. 4 CONCLUSION The proposed control structure consists of two main types of controllers: zone and feeder. The operating mechanism of each controller has been designed based on the concept of a multi agent system. An expert-based decision maker has been proposed for each agent in order to achieve its objectives and satisfy its constraints. The proposed algorithm is programmed using C Programming and executed successfully. The results show that cooperation among agents through two-way communication provides a good solution for fault location, isolation and service restoration. programming, IEEE Trans. Power Del., vol. 23, no. 3, pp. 1589 1596, ( Jul. 2008). [3] Chen. W, Quantitative decision-making model for distribution system restoration, IEEE Trans. Power Syst., vol. 25, no. 1, pp. 313 321, (Feb. 2010). [4] Fotuhi-Firuzabad.M, Lehtonen. M, Sanaye-Pasand. M and Kazemi.S, Impacts of automatic control systems of loop restoration scheme on the distribution system reliability, IET Gener. Transm. Distrib., vol. 3, no. 10, pp. 891 902, ( 2009). [5] Kanamori. H, Funabashi. T, Kato. T and Suzuoki. Y, Multi-agent based control and protection of power distributed system Protection scheme with simplified information utilization, in Proc. 13th Int. Conf. Intell. Syst. Appl. Power Syst., Arlington, VA, pp. 49 54, (Nov. 2005). [6] Lu. L, Wu. J, Su. S and Lee. T, An autonomous decision approach for fault allocation and service restoration in electrical distribution systems by multi agent system, in Proc. 9th Int. Conf. Hybrid Intell. Syst., Shenyang, China, pp. 89 94, (Aug. 2009). [7] Mallet. S, Grenard. S, Mamo. X and Coste. T, Distribution automation: The cornerstone for smart grid development strategy, in Proc. IEEE Power Energy Soc. General Meeting, Calgary, AB, Canada, pp. 1 6, (2009). [8] Sasaki. H and Nagata. T, An efficient algorithm for distribution network restoration, in Proc. IEEE Power Eng. Soc. Summer Meeting, Vancouver, BC, Canada, vol. 1, pp. 54 59, (2001). [9] Sasaki. H and Nagata. T, A multi-agent approach to power system restoration, IEEE Trans. Power Syst., vol. 17, no. 2, pp. 457 462, (May 2002). [10] Song. B, Li. P, Wang. T and Wang.W, Multi-agent approach for service restoration of microgrid, in Proc. 5th IEEE Conf. Indust. Electron. Appl., Taichung, Taiwan, pp. 962 966, (2010). [11] Tsai. M and Pan. Y, Application of BDI-based intelligent multiagent systems for distribution system service restoration planning, Euro. Trans. Electr. Power, pp. 1783 1801, (2011). [12] Tsai. M, Development of an object-oriented service restoration expert system with load variations, IEEE Trans. Power Syst., vol. 23, no. 1, pp. 219 225, (Feb. 2008). REFERENCES [1] Aboelsood Zidan, and Ehab F. El-Saadany, A Cooperative Multi agent Framework for Self-Healing Mechanisms in Distribution Systems, (April 2012). [2] Castelhano.A, Keel.B, Heydt.G, Jack.N and Pérez-Guerrero. R, Optimal restoration of distribution systems using dynamic