SURGE PROPAGATION AND PROTECTION OF UNDERGROUND DISTRIBUTION CABLES

Similar documents
Effect of High Frequency Cable Attenuation on Lightning-Induced Overvoltages at Transformers

A Study on Lightning Overvoltage Characteristics of Grounding Systems in Underground Distribution Power Cables

Effect of Shielded Distribution Cables on Lightning-Induced Overvoltages in a Distribution System

Modeling insulation in high-voltage substations

Simulation and Analysis of Lightning on 345-kV Arrester Platform Ground-Leading Line Models

The Analysis Results of Lightning Overvoltages by EMTP for Lightning Protection Design of 500 kv Substation

A Simple Simulation Model for Analyzing Very Fast Transient Overvoltage in Gas Insulated Switchgear

2000 Mathematics Subject Classification: 68Uxx/Subject Classification for Computer Science. 281, 242.2

Analysis of MOV Surge Arrester Models by using Alternative Transient Program ATP/EMTP

Electric Stresses on Surge Arrester Insulation under Standard and

Simulation of Short Circuit and Lightning Transients on 110 kv Overhead and Cable Transmission Lines Using ATP-EMTP

Lightning performance of a HV/MV substation

When surge arres t ers are installed close to a power transformer, overvoltage TRANSFORMER IN GRID ABSTRACT KEYWORDS

Chapter 1. Overvoltage Surges and their Effects

How To Ground Electronic Equipment In Southern Company? Imagination at work

SWITCHING OVERVOLTAGES IN A 400-KV CABLE SYSTEM

Transmission of Electrical Energy

Maximum Lightning Overvoltage along a Cable due to Shielding Failure

Simulation of Lightning Transients on 110 kv overhead-cable transmission line using ATP-EMTP

New Modeling of Metal Oxide Surge Arresters

Analysis of lightning performance of 132KV transmission line by application of surge arresters

Measurements for validation of high voltage underground cable modelling

Tab 8 Surge Arresters

TECHNICAL NOTE 2.0. Overvoltages origin and magnitudes Overvoltage protection

Lab 1: Pulse Propagation and Dispersion

Parameters Affecting the Back Flashover across the Overhead Transmission Line Insulator Caused by Lightning

A SIMPLIFIED LIGHTNING MODEL FOR METAL OXIDE SURGE ARRESTER. K. P. Mardira and T. K. Saha s: and

Online Localisation of Partial Discharge Using Pulse Propagation Parameters in Medium Voltage Cable Network

Lightning Performance Improvement of 115 kv and 24 kv Circuits by External Ground in MEA s Distribution System

Electric Power Systems Research

THE PROPAGATION OF PARTIAL DISCHARGE PULSES IN A HIGH VOLTAGE CABLE

Session Four: Practical Insulation Co-ordination for Lightning Induced Overvoltages

PREVENTING FLASHOVER NEAR A SUBSTATION BY INSTALLING LINE SURGE ARRESTERS

University of Zagreb Faculty of Electrical Engineering and Computing

High Voltage Induced By Transmission Lines Due To Lightning Case Study

Utility System Lightning Protection

VFTO STUDIES DUO TO THE SWITCHING OPERATION IN GIS 132KV SUBSTATION AND EFFECTIVE FACTORS IN REDUCING THESE OVER VOLTAGES

Pre location: Impulse-Current-Method (ICE)

EXPERIMENTAL INVESTIGATION OF A TRANSIENT INDUCED VOLTAGE TO AN OVERHEAD CONTROL CABLE FROM A GROUNDING CIRCUIT

Published in: Proceedings of the International Conference on Power Systems Transients (IPST 2009)

High voltage engineering

CLU Arrester. Certified Test Report. IEEE Standard C

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

Transformers connected via a cable Overvoltage protection

Lightning Overvoltages on Low Voltage Circuit Caused by Ground Potential Rise

Cross-bonding cable and box model based on pulse reflection measurement

Underground System Design TADP 547

MV Power Cable Diagnostics by Frequency Domain Spectroscopy. Peter Werelius Programma Electric AB

Lightning Protection of Distribution Substations by Using Metal Oxide Gapless Surge Arresters Connected in Parallel

Investigation of skin effect on coaxial cables

Prediction of Transient Transfer Functions at Cable-Transformer Interfaces

Electromagnetic Shielding Analysis of Buildings Under Power Lines Hit by Lightning

CVVOZE Power Laboratories (CVVOZEPowerLab)

Power Quality and Reliablity Centre

OVERVOLTAGE PROTECTION OF POLE MOUNTED DISTRIBUTION TRANSFORMERS

ABSTRACTS of SESSION 6

ON-LINE PARTIAL DISCHARGE TESTING OF SOME OF THE WORST PERFORMING CIRCUITS ON A UTILITY DISTRIBUTION SYSTEM

Analysis of Major Changes to Arrester Standards IEC STEVE BREWER

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

Lightning overvoltage and protection of power substations

Modeling of overhead transmission lines with line surge arresters for lightning overvoltages. Poland

Simplified Approach to Calculate the Back Flashover Voltage of Shielded H.V. Transmission Line Towers

2. Current interruption transients

Effect of Shielded Distribution Cable on Very Fast Transients

Testing 320 kv HVDC XLPE Cable System

a) Basic unit of an ideal transmission line b) an ideal transmission line

FERRORESONANCE - its Occurrence and Control in Electricity Distribution Networks

Overvoltage Protection of Light Railway Transportation Systems

A Special Ferro-resonance Phenomena on 3-phase 66kV VT-generation of 20Hz zero sequence continuous voltage

ABSTRACT 1 INTRODUCTION

The relationship between operating maintenance and lightning overvoltage in distribution networks based on PSCAD/EMTDC

ABSTRACT 1.0 INTRODUCTION LIST OF SYMBOLS

Tab 2 Voltage Stresses Switching Transients

Condition Assessment of High Voltage Insulation in Power System Equipment. R.E. James and Q. Su. The Institution of Engineering and Technology

Transmission Line Transient Overvoltages (Travelling Waves on Power Systems)

A Study of Lightning Surge on Underground Cables in a Cable Connection Station

The impact of distributed generation to the lightning protection of modern distribution lines

Research Article A Simplified High Frequency Model of Interleaved Transformer Winding

EI HIGH VOLTAGE INSULATION TESTING POLICY

Extended analysis versus frequency of partial discharges phenomena, in support of quality assessment of insulating systems

LIGHTNING OVERVOLTAGES AND THE QUALITY OF SUPPLY: A CASE STUDY OF A SUBSTATION

For the electronic measurement of current: DC, AC, pulsed..., with galvanic separation between the primary and the secondary circuit.

Partial Discharge Measurement and Monitoring on High Voltage XLPE Cables

Short Circuit and Induced Voltage Transient Study on a Planned 1000 MW HVDC-VSC Cable Link

AORC Technical meeting 2014

MATEFU Insulation co-ordination and high voltage testing of fusion magnets

Selection of MO surge arresters Overvoltage protection

Computer Based Model for Design Selection of Lightning Arrester for 132/33kV Substation

2620 Modular Measurement and Control System

X International Symposium on Lightning Protection

Modeling for the Calculation of Overvoltages Stressing the Electronic Equipment of High Voltage Substations due to Lightning

Earthing of Electrical Devices and Safety

A3-308 HIGH SPEED GROUNDING SWITCH FOR EXTRA-HIGH VOLTAGE LINES

EE 340 Transmission Lines. Spring 2012

EMC standards. Presented by: Karim Loukil & Kaïs Siala

GIS Disconnector Switching Operation VFTO Study

Practical aspects of PD localization for long length Power Cables

Investigation of PD Detection on XLPE Cables

AC/DC Current Probe GCP-100 QUICK START GUIDE ISO-9001 CERTIFIED MANUFACTURER

HVDC Transmission. Michael Muhr. Institute of High Voltage Engineering and System Performance Graz University of Technology Austria P A S S I O N

Transcription:

SURGE PROPAGATION AND PROTECTION OF UNDERGROUND DISTRIBUTION CABLES Jae-bong LEE, Korea Electric Power Research Institute(KEPRI), (Korea), jbonglee@kepco.co.kr Ju-yong KIM, Korea Electric Power Research Institute(KEPRI), (Korea), juyong@kepco.co.kr Chul-bae PARK, Korea Electric Power Research Institute(KEPRI), (Korea), chul93@kepco.co.kr Yeon-ha JUNG, Korea Electric Power Research Institute(KEPRI), (Korea), mywendy@kepco.co.kr ABSTRACT The lightning surge and switching surge could be injected to the underground distribution line through the riser pole in the mixed distribution line of overhead and underground. These surges travel along the cable and are reflected at the end of cable. It can be doubled and affecting underground distribution facilities. We made a underground distribution model representing KEPCO s distribution system. We measured propagation characteristics by applying lightning surges to this underground distribution model. Meanwhile, we simulated this system with ATP-EMTP and compared these results. There were differences between real test measurements and EMTP simulated results. Those differences come from cable parameters and surge wave shapes. To minimize those differences, relative permittivity of the cable insulation material must be measured from the real cable and surge source type should be used. To protect underground distribution system from surge, arrester should be installed at the open terminal in which doubled voltage are reflected. KEYWORDS URD, Surge, Protection, EMTP, Cable INTRODUCTION Underground distribution of Korean distribution system became 12% in 2006, and in Seoul 50%. The more economy grows, the more underground distribution system increases. Overhead distribution lines are protected from lightning by installing arresters, while underground distribution lines have the only riser pole arrester. In the underground distribution line, during lightning surge discharge through arrester residual voltage is applied to the cable and travel along the cable line. This traveling surge is reflected at the terminal with doubled voltage and travels again. This traveling surge could make a fault at the weakened insulation point. To analyze traveling surge mechanism and solve the problem, we constructed a field test model of underground distribution line and applied impulses and measured voltages. We also simulated our test model with ATP-EMTP(Electro-Magnetic Transient Program) and compared the results of field test and EMTP simulation. To accord EMTP results with field test results, we tuned parameters of EMTP. Until now it has been rare to verify EMTP simulation results by field test results. Therefore the result of EMTP not accepted easily. If EMTP parameters fixed precisely we can simulate various cases which are difficult to test in the real underground distribution system. Through this process we can make a solution for the surge protection of underground distribution system. CONSTRUCTION OF UNDERGROUND DISTRIBUTION LINE FOR TEST We constructed a underground distribution line for test with cables, pad-mounted switchgears and pad-mounted transformers used in Korea. Four switchgears, three transformers, two type of cables and joints are installed onto the 4 circuits of 250 m long. This test line connected to the impulse generator through about 100 m long cable. Line length and branching can be varied by switchgear operation. Figure 1: Field test model of underground distribution system

IMPULSE GENERATOR Impulse generator was installed in the high voltage laboratory and connected to the test line with cable and overhead line. Standard impulse voltage (1.2x50 μs ) is 50 kv to protect cable. In case of the impulse current test we applied 8x20 μs, 50 ka. With switchgear SW1 operating to extend cable length to 350.7 m and applying same impulse, the first step voltage is about 2 kv and reflected second step voltage was became 5.2 kv. The impulse propagation velocity is calculated as follows; (350.7x2) / 4.3 [m/ μs ] = 163.1 m/ μs The simplified impulse propagation process is shown in figure 9. We can see how voltages increase by reflecting. IMPULSE VOLTAGE TEST When 50 kv 1.2x50 μs impulse applied to 97.7 m cable, the first step voltage shows 2 kv and the reflected second step voltage shows 5.3 kv from 1.2 μs. Propagation velocity of impulse surge is calculated as follows; (97.7x2) / 1.2 [m/ μs ] = 162.8 m/ μs Figure 6: Impulse voltage wave shape Figure 7: Test result of 350.7m cable line at IVG Figure 2: Impulse voltage test setup Figure 8: Test result of 350.7m cable line at SW4 Figure 3: Impulse voltage wave shape Figure 4: Impulse voltage test for 97.7 m cable line Figure 5: Test result of 97.7m cable line at IVG Figure 8: Simplified impulse propagation process

With switchgear SW1 and SW4 operation to extend cable length to 604.7 m and applying same impulse, the first step voltage is become about 1.8 kv and the reflected second step voltage is become 5.0 kv increased from 7.5 μs. The impulse propagation velocity is calculated as follows; (604.7x2) / 7.5 [m/ μs ] = 161.3 m/ μs Figure 9: Impulse voltage wave shape Figure 10: Voltage variation measured at IVG f = 1/T = 1/(2 μs ) = 500 khz. So the frequency at which cable parameters are calculated should be 500 khz. Generally in the surge simulation, 500 khz has been used and showed good results. To make the propagation velocity from the EMTP calculation accord with that of real test, the relative permittivity of cable insulation has to be changed. In general the relative permittivity of XLPE insulated cables was used 2.3. This value was measured with XLPE material sheet not with cable. But in our EMTP simulation this value gives big errors in propagation velocity of surges. We calculated relative permittivity from the wave propagation in the perfect dielectric media. c v = 1 µε = µ ε Where, v is propagation velocity, µ is a permeability of media, ε is a permittivity of media, c is velocity of light, µ R is relative permeability of media, ε R is relative permittivity of media. From above equation, we got 3.39 for relative permittivity of our cable. This value is quite different from 2.2, which is a common value of XLPE insulation. The surge propagation time of simulation results using 3.39 as relative permittivity of cable insulation was in accord with real test. R R Figure 11: Voltage variations measured at SW1, SW2 Figure 12: Surge waves for real test and EMTP EMTP SIMULATION OF IMPULSE VOLTAGE TEST We make EMTP simulations for our field test model of underground distribution system. In this EMTP simulation we used ramp type source for impulse surge.(see figure 12) This source was typical for simulation of surge propagation these days. As we change the frequency at which the line parameters will be calculated, the resulting surge propagation changes like figure 13. The results from 500 khz were more similar to real test results. The surge propagation results calculated at power frequency of 60 Hz were different from the results of real test. These results will be come from the surge shape of 1.2x50 μs. The duration of rise is 1.2 μs and the most variations of wave shape is occurred within 2 μs, so it can be translated to frequency domain as follows; Figure 13: Surge waves for EMTP frequency

The permittivity difference between XLPE material and cable probably will be caused by the effect of semiconductive layer and water blocking filled conductor. But it is not the subject of this paper. Meanwhile, as reflection is repeated in the EMTP simulation the amplitude of surge begin to differ from real test result as seen in figure 14. Surge source type has to be changed from 2-slope ramp (Type 13) to two exponentials (Type 15) to minimize the accumulation effect of errors. This can be seen in the figure 14. To minimize errors in EMTP simulation some parameters must be carefully inputted. Especially the relative permittivity of cable insulation, frequency at which line parameters will be calculated and surge wave shapes should be inputted with real value. Figure 16: Impulse current test set for arrester When cable length was 97.7 m, the maximum voltage measured at impulse current generator was within 60 kv. But the peak voltage at switchgear SW1 was 69 kv. It is estimated because the end of cable is not far from the arrester the voltage rise at the end of cable is restricted by arrester. When cable length was 350.7 m, the maximum voltage measured at the end of cable was 98 kv.(figure 19, 20) When cable length was 604.7 m, the maximum voltage measured at the end of cable was 102 kv. (Figure 21, 22) Figure 14: Surge propagations and surge shape IMPULSE CURRENT TEST Figure 17: Impulse current test for cable 97.7 m When lightning surge hit the overhead line, arrester of riser pole discharges surge voltage and limits voltage to the residual voltage level of arrester. But this residual voltage is applied to cable and travels underground distribution line and is reflected at the end of cable. We would like to see this surge propagation in the real test line. From the restriction of test facility, we set the impulse current test configuration of arrester and attached cable line to the arrester terminals. Impulse current shape was 8x20 μs and discharge current was 5 ka. The arrester rating is 18 kv and residual voltage is about 60 kv. Figure 15 and 16 show the test set for impulse current injection to cable and its propagation characteristics. Figure 18: Voltage measured at SW1 Figure 15: Impulse current test set for arrester Figure 19: Impulse current test for cable 350.7 m

Figure 23: Bifurcated cable line Figure 20: Voltage measured at SW4 Figure 21: Impulse current test for cable 604.7 m Figure 24: Voltage measured at ifurcated cable line RESULTS AND DISCUSSIONS Figure 22: Voltage measured at SW1 and SW2 As cable length is increased, the voltage at the end of cable is also increased, but not exceeded twice of arrester residual voltage. The voltage rise at the end of cable and its travelling in the underground distribution line can make faults or degradation of solid insulation especially in the aged insulations. Really in our tests some of elbow joints are faulted by several ten times of impulse tests. BIFURCATED CABLE LINE We tested also for the bifurcated cable lines. Cable line is bifurcated at the switchgear SW1 in figure 23. The maximum voltage was measured to 114 kv at SW2. This voltage is very near to the Basic Impulse Level of 25kV underground distribution system. From the real test and EMTP simulation for the surge inje ction to cable line, we get; 1. To simulate the surge behaviour in cable line with EMTP, cable parameters like relative permittivity should be carefully chosen. 2. Surge is reflected double voltage the end of cable. 3. Although surge is discharged through the arrester at riser pole, residual voltage surge is injected to the cable line and reflected with double voltage. 4. As cable length increase, the end of cable is further from the arrester and the reflected surge voltage is increased. 5. In the real underground distribution system, the reflected double voltage surge is propagated various paths of distribution line and reflected double again at the other ends, this surge can threaten the insulations. Acknowledgments This study was sponsored by ETEP. REFERENCES [1] William E. Shula, 1978, Surge Behaviour of UD Cable System, EPRI, California, USA. [2] EMTP Rule Book [3] ATP Rule Book, ATP Salford Version of EMTP, Volume 1 [4] ATP Rule Book, ATP Salford Version of EMTP, Volume 2 [5] ABB, 1999, Dimensioning, testing and application of metal oxide surge arresters in medium voltage networks