NER300 Offshore Wind Park Nordsee One. Tobias Griesshaber Shareholder representative of Innogy SE on behalf of project Nordsee One GmbH

Similar documents
Gwynt y Môr Offshore Wind Farm

UK offshore wind industry progress to cost reduction

The offshore wind puzzle getting the pieces right

Rampion Offshore Wind Farm Meet The Buyer Event

Jørn Scharling Holm DONG Energy

Offshore Wind Risks - Issues and Mitigations

Tidal Energy. Transmission & Distribution Network. Wind Energy. Offshore Substation. Onshore Substation. Tidal Stream Energy.

Wind Energy Technology Roadmap

Onshore & Offshore Engineering and Management of Subsea Cables and Pipelines

Offshore wind what s it all about? 01/11/2017 Owen Murphy & Andrew Tipping

Offshore Renewables Institute

The European context; an overview of the Ocean Energy (Europe) strategic roadmap. Kasparas Kemeklis, OEE

Strategic Partnerships in Offshore Project Installations and Wind Farm Operation

Enabling Array Cable Cost Reduction

Weather Down Time in Offshore Wind Installation Works: Assessment and Potential R&D Work Lines

Oil and Gas Diversification: High Potential Areas, Key Challenges (Operations & Maintenance) BVG Associates ~ Alan Duncan

The WindFloat Project

Next generation WTG foundation and WTG installation. WindDays Rotterdam, 14 June 2018 Arnoud Bosch Engineering Director

Ocean energy State of the industry and Ocean Energy Forum Roadmap. Remi GRUET, CEO, Ocean Energy Europe

Accelerating the Deployment of Offshore Renewable Energy Technologies. IEA Implementing Agreement on Renewable Energy Technology Deployment

Offshore Wind Floating Turbines

European Wind Energy Technology Roadmap

The future of offshore wind in the US

The potential for windpower in the Baltic Sea

Cost of energy going below 100/MWh; the opportunities and barriers

Technical aspects of Offshore Wind Farms

Seagreen Wind Energy Limited C/o SSE Renewables 1 Waterloo Street Glasgow G2 6AY

NSRI/ORE Subsea Technological Challenges in Offshore Wind

Dinamarca el major acceso al Mar del Norte para proyectos offshore

Re-use & Decommissioning in The Netherlands: A Joint Effort

Oil and gas diversification Offshore wind NORWEP

DONG ENERGY LEADING THE ENERGY TRANSFORMATION

Wind Turbine Decommissioning in the UK Offshore Zone

Model project plan for Borssele (Innovation) Wind Farm Site V

RENEWABLE ENERGY SOLUTIONS. oceaneering.com

Oil and gas diversification Offshore wind NORWEP

The WindFloat Project. February 2010

Offshore Renewable. Energy Conversion platforms Coordination. Action

Optimizing wind farms

Maasvlakte CCS Project - ROAD

The first Floating Wind Turbine in France (SEM-REV) I. Le Crom, ECN, EERA Deepwind 19/01/2018

WAVE & TIDAL SERVICES WAVE & TIDAL

World Offshore Wind Market Forecast Prospects, Technologies, World Markets

Phil de Villiers 17 April Offshore Wind Accelerator (OWA)

The offshore wind market deployment: forecasts for 2020, 2030 and impacts on the European supply chain development

DNV GL s Offshore wind cost reduction manifesto

SHAPING THE FUTURE OF OFFSHORE WIND

Certified quality for offshore wind farms. We certify offshore projects independently, proficiently, and reliably.

Policy Research Corporation

Offshore Wind Energy in Germany: System Benefits and Cost Reduction Potentials

3. Existing uncertainties

Coastal Virginia Offshore Wind partnership with Orsted. February 2018 Update

ENGINEERING SERVICES CONSULTANCY

Strategic Innovation Acceleration - UK marine energy industry: pathway to commercialisation Simon Robertson

Offshore Renewable Energy Conversion platforms - Coordination Action

Pelastar TLP Floating Wind Turbine Foundation

DONG ENERGY LEADING THE ENERGY TRANSFORMATION INNOVATION IN OFFSHORE WIND POWER

Energy Transition Partner. Created and produced by

European funding opportunities for Ocean Energy

NURTURING OFFSHORE WIND MARKETS GOOD PRACTICES FOR INTERNATIONAL STANDARDISATION

North East England: Offshore wind market opportunities

Sustainable solutions for your onshore wind power projects siemens.com/wind

OFFSHORE ENERGY DIVISION OFFSHORE WIND SOLUTIONS

25+ YEARS OF EXPERIENCE. NIRAS OFFSHORE WIND 25+ years of experience

Experience with Connecting Offshore Wind Farms to the Grid

Passion at work. Renewables

Research, testing and demonstration.

RESEARCH, TESTING AND DEMONSTRATION

Offshore Wind Project Logistics & Unique Site Technology Investigation Fabrication - Installation

OFFSHORE WIND ACCELERATOR (OWA)

Taiwan Offshore Wind. Specialist technical issues affecting project development in Taiwan. 4 th Asia Offshore Wind Day.

U.S. Job Creation in Offshore Wind. A Report for the Roadmap Project for Multi-State Cooperation on Offshore Wind

FoundOcean All-Energy Presentation May The experts in subsea grouting for the offshore energy construction industry

Sustainable solutions for your onshore wind power projects siemens.com/wind

The Energy Sector of the Blue Economy Kristian Petrick eco-union

German Market andprojects revisited

DNV GL Marine Renewables

An ETI Perspective. Lessons learnt from UK offshore renewables innovation

Opportunities for Offshore Wind Development in the U.S.

Neart na Gaoithe Offshore Wind Farm. Project Update 2018

Exploring the impact of innovative developments to the installation process for an

What onshore can learn from offshore tendering. Mark Duppen BLIX Consultancy - 13 June 2018

Long Distance Subsea Power Transmission and Distribution

Offshore Wind Supply Chain Opportunities with Innogy Renewables UK Ltd

Offshore Cable Installation. November 2010 John Davies Global Marine Systems Limited

Offshore Renewable Energy Conversion platforms - Coordination Action

ENERGY TECHNOLOGY ROADMAPS SYNTHESIS: OCEAN ENERGY. 1. Overview, Discussion. 2. International Energy Agency, Ocean Energy Systems

Inter Array Cable Technology Development. Jeremy Featherstone Product Development Director JDR Cable Systems Ltd

SET-PLAN IMPLEMENTATION

the future of electricity

IHO Presentation Offshore Renewables

Environmental and non-technical impacts of lean principles applied to offshore wind farms

Galloper Wind Farm Limited. Galloper Wind Farm Project Environmental Statement Chapter 1 Introduction October 2011 Document Reference 5.2.

Blue growth. Stijn Billiet. DG Maritime Affairs and Fisheries

Driving Cost Reductions in Offshore Wind THE LEANWIND PROJECT FINAL PUBLICATION

The Verification Path

An Energy Utility Perspective and Approach to Airborne Wind

SET-PLAN IMPLEMENTATION

EC proposal for the next MFF/smart specialisation

Totally Integrated Power (TIP) for the Oil and Gas Industry

Transcription:

NER300 Offshore Wind Park Nordsee One Tobias Griesshaber Shareholder representative of Innogy SE on behalf of project Nordsee One GmbH Brussels, 15 December 2017 1

Agenda General project overview & timeline Project impressions Lessons learned Stakeholder management Permitting Financing & Innovation Risk management Movie about wind turbine installation in 2017 2

General overview Distance to shore 45 km Water depth (LAT) 26 m 29 m Capacity 332 MW (54 x 6.15 MW) Wind speed 9.8 m/s at hub height (90 m) Yearly output 1.2 TWh Nordsee One Shareholders NER300 funding Northland Power (85%) and Innogy SE (15%) EUR 70 mn O&M route: 26 nm (48 km) CTV 1.5 hrs Lifetime 25 years Commissioning 2017 Operation base 3

Construction progress has just come to an end Most of the activities were performed within the schedule Actual vs. original (grey) planning 2014 2015 2016 2017 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Permit: BSH Approval 2 nd -3 rd -4 th Foundation (Basic Detailed) Installation Cable Fabrication Substation Topside Installation Turbine Fabrication Foundation Installation Cable Installation Substation Jacket Install Substation Topside Inst./Commissioning Turbine Installation Turbine Commissioning Installation export cable 1 st Feed-in 100% Feed-in (only 18 days delay!) Last WTG section take-over FC assumption Installation Fabrication Commissioning Financial Close Today 4

Ten years after project acquisition 332 MW are producing green power Financial and permit key milestones Acquisition of project rights by Innogy 2008 Main Permit N1: April 2012 Thank you! NER300 Award by DG CLIMA December 2012 FID by sponsors (incl. new sponsor NPI) December 2014 requirement Financial close with lenders March 2015 Construction Permit Foundations: 03 December 2015 Construction Permit Inter-Array-Cables: 25 April 2016 Construction Permit Offshore-Substation: 08 June 2016 Construction Permit Wind-Turbines: 03 March 2017 Entry into operations: December 2018 5

Agenda General project overview & timeline Project impressions Lessons learned Stakeholder management Permitting Financing & Innovation Risk management Movie about wind turbine installation in 2017 6

Load-out of a 800 ton Monopile 7

Hammering pile with noise mitigation tube to protect marine environment 8

Interarray cable installation with purpose-built vessels 9

Sub-station collecting the electricity at 33 kv and transforming to 150 kv 10

Installation of the last wind turbine (September 2017) 11

12

13

Agenda General project overview & timeline Project impressions Lessons learned Stakeholder management Permitting Financing & Innovation Risk management Movie about wind turbine installation in 2017 14

Stakeholder Management Understand your stakeholders needs Stakeholder analysis is an effort to understand motivation, benefits and pain points of affected parties. The right level of information and involvement will allow steering your project effectively through challenging times, and be rewarding in good times. As a consequence the support of the stakeholder will improve. Structure your stakeholder management by implementing the S.P.O.C. -Principle A Single Point of Contact for a stakeholder or a group of stakeholders ensures one face to the stakeholder, centralized data management and avoids ambiguous information. Examples of key stakeholders for Nordsee One: o Grid operator providing the electricity export connection to shore o Equity investors o Lenders via Facility Agent and their advisory group (technical, legal, tax etc.) o Permitting authorities o Public interest groups 15

Permitting (also applicable to public stakeholders, incl. the EU) Co-operate, communicate and stand by your word Be predictable In Germany, the permitting procedure is very comprehensive with involvement of the authorities at every project phase. Projects need to pass several stage gates. Clearly defining and aligning milestones creates a joint roadmap and provides planning security for all stakeholders. Help the authorities to structure their resources to ensure the permit is issued when required. Be open and transparent In case things are going wrong or milestones are delayed, be as open and transparent as possible. Authorities and public stakeholders support a change more smoothly if they understand why it is required. Communicate transparently to avoid obstacles and ensure co-operation. Take certain decisions early The turbine type (here: 6 MW) is the central item to start with. This also applied to the NER300 funding eligibility already back in 2011! The comprehensive permitting procedure and EIB s DD for NER300 involves metocean data, technology details and encompasses fabrication, transport and installation. As all of the requirements are determined by the turbine, this needs to come first. Predictability and reliability supports your project planning and execution significantly. 16

Financing & Innovation Does this go together well? Financing a mega-project (>1 bn CAPEX) is always a multi-variable moving target Banks & investors seek predictable conditions, ideally regulated returns and use of tested technology McKinsey found out that mega projects are delivered on average o 1 year late o 30% over original budget Nordsee One (1.2 bn ) did very well on Scope (all assets are operational) Time (less then 3 weeks delay compared to baseline) Cost (within budget and contingencies) But experienced Quality issues: chosen foundation technology was innovative and in hindsight encompassed some issues. Innovative blades turned out to require further design adaptations. Financing seeks predictability and track record Innovation is new and usually radical change More knowledge needs to be gathered and shared within and across the sectors But there are limitations to linear thinking and transferability across sectors (onshore wind, O&G) 17

Risk management The key to prepare for the known unknowns and navigate through uncertainty Risk? Yield (un)certainty Offshore installation New technology The word 'risk' derives from the early Italian risicare, which means to dare or to circumnavigate. In this sense, risk is a choice rather than a fate. Peter L. Bernstein 18

Thank you for your attention! 19