CONSERVATORY ROOF INSTALLATION GUIDE Issue

Eurocell conservatory roof system. Installation manual Issue 3

Synseal assembly guide 2009:Synseal assembly guide /2/09 12:38 Page 1. Conservatory Roof Assembly Guide

skypod INSTALLATION GUIDE CONTENTS Issue 2 If in doubt at any stage NOW INCLUDES ACUTE BE SAFE WHEN WORKING AT HEIGHT

Installation Guide Simplicity Alfresco. V1.9 Lu070318

ENGINEERING STRENGTH INSTAL L AT I O N M A NUAL OUR STRENGTH IS OUR STRENGTH

assembly guide effective from April 2005

Installation Guide Contemporary Alfresco V1.3 LU

Installation guide. Step-by-step instructions

skypod INSTALLATION GUIDE Issue 2 CONTENTS 1. Preparing to install 3 2. Installation 4 3. Installing jack rafters Installation examples 11

NEW skypod INSTALLATION GUIDE

SIMPLER BETTER FASTER

Skypod. Pitched PVC-U skylights. Installation guide PITCHED PVC-U SKYLIGHTS ISSUE 1

Section 1 Specifications..

PRODUCT GUIDE K2. THE COMPLETE CONSERVATORY COMPANY

Installation Guide. Evolve bi-fold. 8. Door restrictor- optional p9. 1. Before you start p2. 9. Adjustment. 2. Measuring and surveying p2

Guardian warm roof conversion system. Installation Guide

Classicroof. Low Pitch Lean-to. Installation Guide SEPT 2015 V3

Synseal assembly guide 2009:Synseal assembly guide /2/09 12:38 Page 1. Conservatory Roof Assembly Guide

NEW equinox INSTALLATION GUIDE Issue

Skypod. Pitched PVC-U skylights. Installation guide PITCHED PVC-U SKYLIGHTS ISSUE 1

Installation Guide Simplicity 16. V2.9 Lu171117

Skypod. Pitched PVC-U skylights. Installation guide PITCHED PVC-U SKYLIGHTS ISSUE 1

ultraframe Classic Low Pitch Lean-to Installation Guide

The Leka System Installation Guide

Installation Guide Simplicity 6. v3.5 lu171117

utopia Window & Door Products Orangery Home Extension Products Conservatory Products Skylight Products

NEW equinox INSTALLATION GUIDE Issue

GROWING BETTER THROUGH DESIGN. 6ft Lean-To LEAN-TO. Assembly Instructions 04/02

Assembly Guide. Conservatory Roof. 1. Before you start p2. 8. Sealing. 2. Box gutter. 9. Ridge top caps. 3. Eaves beam. 4. Rafters. 10.

INSTALLATION GUIDE SLIMLINE ROOF LANTERN 4 PANE CONFIGURATION

Dura-Lock Roof System

Curium 19H Installation Instructions & Parts List

patio door installation guide

Installation Guide. Bi-fold Doors

Curium 19.4H Installation Instructions & Parts List

TRADITIONAL GABLE ATTACHED PATIO AND CARPORT. Your complete guide to building an ATTACHED Outback TRADITIONAL GABLE PATIO or CARPORT

DUTCH GABLE FREESTANDING CARPORT

Conservatory roof system

Radon 07 Installation Instructions & Parts List

Cardo DOOR & RETURN SHOWER ENCLOSURE INSTALLATION PLEASE READ THESE INSTRUCTIONS CAREFULLY.

Dubnium 11 Installation Instructions & Parts List

Safety Glasses Safety Gloves Ladders Measuring Tape Spirit Level String Line. Tin-Snips Rivet Gun Caulking Gun Silicone Socket Set

Stratco Sanctuary INSTALLATION BEFORE YOU START TOOLS REQUIRED GUIDE

SMART SYSTEMS VISOGLIDE+ INSTALLTION GUIDE

Roof Lantern. Installation Guide. Scan to view the installation guide on your mobile or tablet

Installation - Sub Cills

Gallium 03 Installation Instructions & Parts List

SLIDING MECHANISM TROLLEY CATCH TROLLEY ASSEMBLY FLOOR GUIDE

CURVED ROOF ASSEMBLY INSTRUCTIONS ATTACHED VERANDAH. Your supplementary guide to building an ATTACHED CURVED ROOF VERANDAH or PATIO BEFORE YOU START

Corner Potting Store Assembly Instructions

GROWING BETTER THROUGH DESIGN LEAN-TO. Lean-To. Assembly Instructions 04/02

CLEARSPAN GABLE STRATCO OUTBACK ASSEMBLY INSTRUCTIONS. WITH GAZEBO END ATTACHED PATIO

INSTALL IN 2 DAYS. *Assumes 3-man fitting team. equinox. Tiled roof system. Installation guide ISSUE 1

SLIDING MECHANISM TROLLEY CATCH TROLLEY ASSEMBLY FLOOR GUIDE

GROWING BETTER THROUGH DESIGN. Regent Royale Rosette Regal GREENHOUSE. Assembly Instructions 04/02

ultraframe Classic Installation Guide

Ultraroof380 Cornice Installation

SLIDING MECHANISM TROLLEY CATCH TROLLEY ASSEMBLY FLOOR GUIDE

4. Partially open the operating panel and tilt the top toward the interior of the door (Figure 4). Lift the panel off the sill and set it aside.

Method of Build 1. Fire. Sound

B A T H R O O M G L A S S

Assembly Instructions 10 X 10 Aluminum Roof Support

Zero Threshold TM. Hints and Tips Handbook. Birdlip. Burford. Blockley. Bourton

Potting Store Assembly Instructions

STRATCO GABLE HOMESHED STRATCO GABLE HOMESHEDS STUBBIE INSTALLATION GUIDE

Xenon 05 Installation Instructions & Parts List

Assembly Instructions 10 X 10 Aluminum Frame Building

Vi - BOX GUTTER COMPONENT REFERENCE

IF INSTALLING ANY OF THE PORTMAN SELF CLOSING SYSTEMS, PLEASE READ THE CORRESPONDING FITTING INSTRUCTIONS SUPPLIED WITH THE CLOSING SYSTEM FIRST

Block Frame Inovo Patio Door/Transom/Sidelite Field Mulling Instructions. simonton.com/installation. If mulling sidelites, skip to Step 5.

method of build Komfire-75 partitioning system 75mm Steel Stud & Plasterboard Partitioning System with Square Aluminium Cover Trims KOMFORT

PRODUCT INFORMATION MANUAL SECTION: 16 FIXED METAL AWNINGS FIXED METAL AWNINGS

COMPONENTS OF THE CLICKFAST FASCIA AND GUTTER SYSTEM 5: INTERNAL MITRE

FITTING INSTRUCTIONS FOR FOLDING SLIDING DOOR SYSTEM SF75H

Installation Instructions

THERMO-FIT REPLACEMENT WINDOW INSTALLATION INSTRUCTIONS (BRICKMOULD / NO NAILING FLANGE)

PATIO INSTALLATION MANUAL

For Installer. Duration Windows. Assembly Guide Durafold 1000

INSTALLATION INSTRUCTIONS. Thermal Entrances AA 250/AA 425 THERMAL DOOR WITH TRIFAB 601/601T FRAMING

Method of Build 1. General

THANK YOU FOR PURCHASING FROM HERITAGE PATIOS

Platinum Swing Panel Installation Instructions

Clopay Models 835/837 Sliding Door System Installation Guide

Vanity Installation Instructions

Quick Hook SS & LS Standard and Low Height Hooks for Side Mount Rails

Patented Rail-Free Mounting System for Composition/Asphalt Shingle Roofs

Allora ALCOVE ENCLOSURE INSTALLATION BEFORE INSTALLATION CHECK THAT YOUR ALLORA SHOWER ENCLOSURE SYSTEM IS UNDAMAGED

Greenhouse Assembly Instructions

Installation Instructions

SLIDING DOOR for CORNER installation ONLY - this door closes to side panel -

ATLANTIS RAIL Contact Information

Connect Transit Shelter

MULTISPAN GABLE WITH HIP END ATTACHED PATIO

The Edwardian Installation Guide. The Edwardian

Gardman Lean-to Greenhouse Assembly Instructions

16ft Polytunnel Assembly Instructions

Hinge Door + Side Panel

Installation Guidelines

Transcription:

1.00 - Introduction This installation guide has been created to assist in constructing a Liniar conservatory roof from a kit format. Please note, each roof has been individually designed to meet specific criteria and to suit the shape and dimensions specified. There may be variants in assembly depending on the roof criteria, but the manual should cover all eventualities. The roof will be provided with a roof layout plan. Ensure that all dimensions and details are correct to the survey supplied before the installation can proceed. Also check that all packages and boxes are present. These will be labelled in accordance to paperwork provided upon delivery. TO ENSURE THE CORRECT FUNCTIONING OF LINIAR ROOFS, IT IS IMPERATIVE THAT THE INSTRUCTIONS IN THIS GUIDE ARE FOLLOWED, IN THE CORRECT ORDER. Care of Products When storing, handling or erecting your Liniar roof, please keep the following in mind : When unwrapping, take care not to damage products with a knife. Always check the components before installing. PVCu components should not be left out in freezing conditions. Do not leave coloured foiled components in their wrapping in direct heat or sunlight. Store polycarbonate roof panels in a dry safe area. Take care when fitting caps/trims with any type of force. Sealing It is imperative that the correct sealant is used when sealing the roof. The diagrams below show the sealants required dependent upon the glazing material. SCG-TEC BASED SEALANTS LOW MODULUS NEUTRAL CURE For a perfect colour match, use the Liniar Approved range. See www.liniar.co.uk/supplies for details. Further Assistance Your roof kit should include all the information you need but if you do need to get in touch with any queries, please use the contact details on the back cover. Videos Self cleaning glass Polycarbonate glazing Standard sealed units To watch videos about the Liniar roof, please visit www.liniar.co.uk/videos and filter by Conservatories. 2

1.01- Tools Required Tools & Consumables Required Angle Grinder Chasing out masonry for flashing Cordless Drill With Pozi bits and suitable drills for pilot holes in PVCu and aluminium SDS / Hammer Drill With appropriately sized masonry bits for proprietary fixings Hand Saw Notching frames Utility Knife General use Clamps Secure eaves beams in place when drilling and fixing Glazing Hammer Fitting trims and caps Angle Finder General measuring and checking of angles/pitches Spirit Level General level checking Tape Measure General measuring and checking 10mm and 17mm Spanners Securing jack rafters (10mm) and fitting internal radius covers (17mm) 10mm Socket Wrench Secure all roof bars 60mm diameter drill bit / hole saw Multi-Positional outlet in guttering 2.5mm Allen Key Tighten the grub screws in the D-Ring connectors Low modulus neutral cure sealant With silicone gun Suitable PVCu Adhesive Securing trims and mouldings in place 3

2.00 Lantern Roof Assembly External Cover Glazing Ridge Jack Rafter Bar Hip Bar Transom Bar Glazing Retainer Tie Bar Eaves Beam / Wall Rail Installation Steps 4 Eaves Assembly Section 3.01, pages 8-9 Wall Rail Assembly Section 3.02, pages 10-11 Glazing Retainer Assembly Section 3.03, pages 12-13

Hip Bar & Ridge Assembly Section 3.04, pages 14-15 Transom Bar Assembly Section 3.05, pages 16-17 Jack Rafter Assembly Section 3.06, pages 18-19 Internal Trims Assembly Section 3.07, pages 20-21 Tie Bar Assembly Section 3.08, pages 22-23 Glazing Assembly 1 Section 3.09, pages 24-25 Roof Bar Top Cap Assembly Section 3.10, pages 26-27 Weather Seal Assembly Section 3.11, pages 28-29 Ridge Cover Assembly Section 3.12, pages 30-31 Glazing Assembly 2 Section 3.13, pages 32-33 Bar End Caps & Internal Cover Assembly Section 3.14, pages 34-35 Guttering Assembly Section 3.15, pages 36-37 5

3.00 Preparation A liniar lantern roof assembly will be supplied with either an eaves beam or wall rail. These are fitted to supporting structures typically window frames (with structural mullions) or timber sub frames. This section of the manual details preparatory checks and adjustments to be made before installation of a liniar lantern roof. Eaves Beam Wall Pivot Rail Aligned with inside face of frames Roof membrane / finish Timber sub frame Window Frame Supporting Frames Sub Frame Related Components Layout paper work 6

Measure Length, Width and Diagonals of Frames / Supporting Structures Measure the roof area you will be working on and check that all the frames have been installed square and are the correct size. The internal frame dimensions will be provided within the paperwork for the roof kit. Ensure suitable clearance around the subframe for the roof bar end caps (LZMP0052). Liniar provides a report detailing the height required whenever a wall pivot rail is used. Check level Use a spirit level and level up if necessary before the eaves beams are fitted. Check Bill of Materials Use the paperwork that came with your roof kit to make sure you have received all the components that are listed before you start. Remove Dummy Sashes and Glazing Remove dummy sashes and any glazing from frames to allow ease of eaves installation. This is because the eaves is fixed from the underneath so dummy sashes / glazing prevent access. * The installer must ensure suitable lateral and vertical support is provided. Liniar accepts no responsibility for the overall structural stability of the conservatory or for the failures of its fixings, members or existing structures * 7

3.01 Eaves Beam Assembly This section shows the correct procedure for installing the eaves beams. If the roof kit uses a wall rail rather than an eaves beam see 3.02 Wall Rail Assembly, pages 10-11. Ensure all fixings are located in the eaves pivot prior to fixing to the frame. They cannot be inserted once the eaves beam is in the final position. LZFX0001 LZFX0020 Related Components Eaves Assembly Vertical Cleats LZFX0004 LZFX0001 LZFX0020 LZFX0018 8

LZAL0071 Eaves reinforcing if applicable Align with inside face of frames Ensure protective tape is removed before fixing * Check correct number of fixings in Eaves Beams prior to fixing in position * A continuous bead of appropriate sealant should be applied to the two inner legs on top of frames before positioning the eaves beams to create a weathertight seal. The eaves beams can then be positioned as instructed in the paperwork for the roof kit. Connect the eaves beams with the cleats provided as shown below. The roof kit will include the correct cleats. Once the eaves beams are positioned on the frames (aligning the inside edges) they can be fixed to the frames with appropriate fixings at no greater than 600mm intervals, leaving 150mm from corners of frames, as shown below. Installing Cleats 1. 2. 3. 150mm 150mm No greater than 600mm intervals 9

3.02 Wall Pivot Rail Assembly This section shows the correct procedure for installing the wall pivot rail. Ensure all fixings are located in the wall pivot rail prior to fixing to the frame. They cannot be inserted once the wall pivot rail is in the final position. LZFX0001 LZFX0020 Related Components WALL PIVOT RAIL ASSEMBLY LZSU0001 LZFX0004 LZFX0001 LZFX0020 LZFX0018 10

The wall pivot rail assembly eliminates the need for the use of rainwater goods. It is ideal for use in lantern roof applications. We suggest that the timber sub-frame is dressed with the roof membrane/finish before the roof is installed. Run two lines of appropriate sealant around the perimeter and apply a line of sealant to mitre cuts. Bed the wall pivot rail into the sealant. The wall pivot rail should then be secured with appropriate proprietary fixings at 600mm centres (150mm from corners). LZAL0028 Wall Pivot Rail Fix the wall pivot rail onto a bed of sealant Timber sub frame Roof membrane / finish Ensure suitable clearance around the subframe for the roof bar end caps (LZMP0052). Liniar provides a report detailing the height required whenever a wall pivot rail is used. Mitred corner joints are joined with flat cleats and sealed at the mitred joint. 11

3.03 Glazing Retainer Assembly Ensure the glazing retainers are installed prior to fitting the bars. Glazing retainers sit at the bottom of all glazed units * * * * * * * * * * * * * * * * * Indicates position of glazing retainers Related Components Glazing Retainer Assembly LZSU0087 12

Ensure gasket is fitted in the correct orientation on all glazing retainers 1. Insert glazing retainer into eaves pivot in this orientation Eaves beam assembly 2. Rotate to final position The eaves beam cloaking foam will overhang the eaves by 15mm. This will eventually be cloaked by the internal eaves cover. Wall rail assembly Eaves beam cloaking foam (LZSU0087) The eaves beam cloaking foam adds extra insulation, minimises condensation on glass and improves the overall aesthetics of the eaves beams. The foam will be supplied in rolls and requires cutting to length to fit the eaves beams. Look for adhesive backed foam 6mm x 60mm. Remove backing tape and apply to the full length of the eaves beam. 13

3.04 Hip Bar and Ridge Assembly The Hip bars are fitted with the ridge to the eaves beam / wall pivot rail. Ensure the ridge is sufficiently supported during this part of the installation of the roof kit. * Ridge requires sufficient support during Installation * Related Components Ridge Assembly Hip Assembly LZPE0012 LZFX0001 LZFX0018 14

See page 17 for bolster bar dimensions 78mm 85mm 96mm Arrow Down LZAL0003 LZAL0007 LZAL0033 The D-ring connector will be pre-set to the correct angle to suit the roof pitch Hip bars should be fitted with end cap mounting brackets in the correct orientation (see above) prior to installation * Hand tighten. Do not use an impact driver * Connect the top end of the hip bars to the D-ring at the end of the ridge by pushing the connector, whilst levering the bar up and down until it clicks into place. Connect the bottom end of the hip bar to the eaves beam, securing it in place with 2 x M6 flange nuts. Align the D-ring connectors with the centre point of the D-ring (shown below). Once bars are positioned, tighten the grub screw to lock the D-ring connector in place with a 2.5mm allen key. 15

3.05 Transom Bar Assembly Transom Bars are fitted to the roof and secured at the ridge and eaves beam / wall pivot rail. Check dimensions from the paperwork for the positioning of the bars. Ensure they are square before securing in position Related Components Transom Assembly LZFX0020 LZFX0018 16

74mm 82mm 86mm Transom bars may come preassembled with a bolster bar LZAL0061 LZAL0062 LZAL0063 * Bottom caps may be square or ogee depending on order requirements * 61mm Transom bars should be fitted with end cap mounting brackets in the correct orientation (see below) prior to installation. The transom bars can then be fitted. Each bar is secured by 4 x M6 flange nuts. This is on the eaves / wall pivot rail and ridge. LZAL0072 Arrow up Standard transom bars (LZAL0061) Arrow Down HD & XHD transom bars (LZAL0062/3) Check the ridge is level once transom bars are fitted using a spirit level. 17

3.06 Jack Rafter Assembly A jack rafter is a bar that connects to a hip bar. Check dimensions from the paperwork for the positioning of the bars. Ensure bars are square before securing in place. Related Components Preassembled in Hip bars Preassembled in Eaves Beams / Wall Pivot Rail Jack Rafter Bar LZFX0018 LZFX0023 LZFX0018 LZFX0020 22 18

73mm 81mm Jack rafters should be fitted with end cap mounting brackets in the correct orientation (see below) prior to installation. Arrow up LZAL0061 LZAL0062 1. Fix bottom of jack rafter in position on eaves beams using 2 x M6 flange nuts. Standard jack rafter bars (LZAL0061) Arrow down 1. HD jack rafter bars (LZAL0062) 2. 2. Slacken the nuts securing the jack rafter fixing arm to allow lateral adjustment. Jack rafter fixing blocks are inserted into the hip bar for each jack rafter, these can be freely adjusted along the length of the hip bar. Locate the jack rafter fixing arm onto the stud protruding from the jack rafter fixing block. 3. Adjust the square not on the jack rafter fixing block to position the jack rafter bar so that the bottom cap is aligned with the hip bar bottom cap. Fit an M6 flange nut to secure in place. 4. Check the bottom caps are aligned at the edges (shown below) and then securely tighten the flange nut, the jack rafter arm nuts and the grub screws in the jack rafter fixing block. Tighten grub screws using a 2.5mm Allen Key. Square nut 3. 4. Align edges of bottom caps of jack rafters and hip bar. 19

3.07 Internal Trim Assembly Internal covers are fitted to the eaves (if fitted) and the underside of the ridge. Internal Ridge Cover If bolster bars are fitted to the roof bars, end caps will need to be fitted to the top and bottom end of each bar Related Components Internal Eaves Beam Cover LZPE0010 Internal Cover Trims LZMP0072 20

Align holes LZPE0010 Fit the internal cover to the underside of the ridge. If a tie bar is to be fitted, align the hole in the internal ridge cover with the threaded hole in the tie bar ridge block (LZSU0076). Internal Eaves Beam Cover The following is only relevant to roof kits with eaves beams. Align holes Once the eaves covers are in situ, the eaves beam joint covers can be fitted. Use an appropriate adhesive to secure in place. LZMP0001-90 LZMP0003-135 LZMP0018-150 LZMP0004 - Inline If Bolster Bars are fitted to the roof, use a suitable adhesive to secure an end cap to the top and bottom of each bolster bar. LZMP0072 21

3.08 Tie Bar Assembly This section details the method of fixing a tie bar application. *Unless otherwise specified, roof bar mounted ties will be fitted as standard* Tie bar fixed to the eaves beam Tie bar fixed to the bottom of the roof bars Related Components 3 way tie bar boss LZSU0005 LZSU8524 / LZSU8522 LZFX0010 LZSU0076 LZSU8532 LZSU0006 22

Vertical Ties The vertical tie bars are always threaded into the blocks which are prefixed into the ridge. Horizontal Ties (Eaves Mounted) - Horizontal bars are threaded into the blocks which are prefixed into eaves beams. Horizontal Ties (Bar Mounted) Horizontal bars are screwed into fixing lugs that will be prefixed to the roof bars. 3 Way Tie Bars - Insert the horizontal and vertical studs into the three way tie bar boss and tighten the M10 nuts until the correct dimensions are achieved across the eaves beams. Then fit the tie bar boss caps to finish the assembly. 3 way tie bar 23

3.09 Glazing Assembly 1 The roof Is now ready for glazing material to be installed. It is recommended that at least one glazing panel in the centre of the roof is not fitted at this point to allow access to the ridge to fit weather seals and ridge covers. Related Components 24mm Glazing (Typically glass) 25mm Glazing (Typically polycarbonate) LZPE0028 32mm Glazing (Typically polycarbonate) 24

Recommended glazing sequence shown below. 5. 6. 7. 8. 9. 10. 11. 4. 12. 3. 2. 1. 15. 14. 13. A. To install the glazing, push the top end of the glazing panel into the gap between the two black gaskets along the ridge with the bottom end elevated. B. Then lower the bottom end of the glazing panel to rest on the roof bars. C. Finally slide the glazing down until it is resting on the glazing retainer. A. B. C. Glazing resting on glazing retainer. Once the glazing is in position, the glazing retainer trims should then be inserted into the aluminium glazing retainers. * Glazing retainer trims must be fitted before the transom/hip/wall/jack rafter top caps are installed * 25

3.10 Roof Bar Top Cap Assembly Roof bar Top caps at this point. The end of the jack rafter top caps will be compound cut to align with the hip bar top caps. * Roof bar top caps either side of any apertures where the glazing material is not yet installed, should not be fitted. * Top caps should be in contact with the end cap mounting brackets at the end of each roof bar Related Components LZPE0041 LZPE0042 LZPE0043 LZPE0044 26

41mm 56mm 62mm 75mm LZPE0041 LZPE0042 LZPE0043 LZPE0044 Ensure glazing retainer trims are fitted before top caps Top caps should be fitted to the hip bars prior to the jack rafters. This is due to the jack rafter top caps butting up to the hip cap once in position. (See recommended order for fitting top caps below). The top end of the jack rafter top caps have compound cuts which match the angle of the hip bar top caps. 6. 4. 5. 10. 7. 8. 9. 11. 2. 13. Bottom clip (24/25mm glazing) Top clip (32mm glazing) 1. 3. 14. 12. Apply an appropriate sealant to the joint between the jack rafter and hip top caps. 27

3.11 Weather Seal This section shows how to install the weather seal which is positioned at each end of the ridge. Related Components LZSU0066 LZSU0050 28

The foam weather seal is made up from two foam weather seal bungs (LZSU0050) and two foam weather seal masks (LZSU0066). First remove the adhesive backing from one of the foam weather seal bungs and stick it to the second bung. Then remove the backing from both pieces of the weather seal mask and adhere around the edges of the assembled bungs, aligning the bottom edges, as shown below. You will need to trim one of the weather seal masks down to cloak the perimeter of the bung assembly. LZSU0066 LZSU0050 Remove the backing tape from the bottom foam bung and stick over the exposed D-ring area to create a weather tight joint. The weather seal will conform to the pitch of the roof and adhere to the glazing. The edges should be pushed up tight to the end of the hip bar top caps and the end of the ridge. Once in position, seal along the ends of the hip bar top caps and the edge of the fascia trims on the ridge. Seal using an appropriate sealant. 29

3.12 Ridge Cover Assembly This section shows how to fit the ridge cover assembly. The ridge cover and square/round external cover will come pre-assembled with roof kits. The finial and cresting/blanking trim will then be attached to this. In some instances, you may need to scribe the radius covers to suit the hip top caps. 1. Ridge blanking trim and cap Cresting and finial 2. Related Components Ridge Cover Assembly LZPE0023 LZMP0015 LZMP0007 LZMP0008 30

The radius covers will arrive preassembled to the ridge cover. They will require a final seal over the joint with an appropriate colour matching sealant. Fit ridge cover Ridge cross section 1. 2. 1. If fitting the blanking trim and end bosses, secure the blanking trim in place then glue the end boss in place using an appropriate adhesive. 2. If fitting the cresting and finials, first measure the length of crestings required allowing for the finials to be fitted at each end. Slide the crestings into the channel in the ridge cover and repeat until ready to fit the finials. Apply a suitable adhesive to the finials and slide these into the ends of the ridge cover channel. 31

3.13 Glazing Assembly 2 Install the remaining glazing panels, glazing retainer trims and top caps. Related Components 24mm Glazing (Typically glass) 25mm Glazing (Typically polycarbonate) 32mm Glazing (Typically polycarbonate) LZPE0028 LZPE0041 LZPE0042 LZPE0043 32

41mm 56mm 62mm LZPE0041 LZPE0042 LZPE0043 Install remaining glazing panels as shown below (see pages 24-25 for glazing technique). Ensure glazing is resting on the glazing retainer at the bottom of each glazing unit. Once positioned, insert the glazing retainer trims for all remaining glazed units. Fit remaining top caps for transoms (LZPE0041/42/43). Liniar top caps are twin-walled for extra strength, durability and energy efficiency. * Ensure glazing retainer trims are fitted before bar top caps * All remaining top caps fitted 33

3.14 Roof Bar End Caps & Internal Cover Assembly The roof bar end caps are installed to the ends of all bars. Ensure the end cap mounting brackets are present as the caps slide onto them. Related Components LZFX0010 LZMP0052 Internal Covers LZSU0055 LZSU0056 34

All roof bars on a lantern roof use the roof bar end caps (LZMP0052). LZMP0052 1. Insert the 130mm stud (LZSU0055) into the D-ring. 2. You will need to prep the internal cover by drilling a 10mm pilot hole through the centre. 3. Then push the internal cover onto the studding and fit an M10 nut to secure in place. 4. Finally, cap the M10 nut with a nut cap. 35

3.15 Guttering Assembly This section details the installation of the guttering. This is only relevant to roof kits with eaves beams. Related Components Gutter clips to be no greater than 500mm apart. BR834 BR082 LZRG8320 LZRG8720 BR201 36

1. 2. 1. Insert the gutter clips into the eaves beam by pushing in and rotating into place as shown above. Gutter clips should be spaced evenly along the eaves beam at no greater than 500mm intervals. They should also be positioned no greater than 150mm from corners. 2. Determine where the downpipe will be, drill a 60mm hole in the guttering and fit the multi-positional outlet. 3. 3. Install the guttering to the gutter clips by firstly hooking the outside edge on to the end of all the clips. Once attached to all clips, rotate the guttering towards the eaves until it locks into place. 4. 4. Now fit the gutter angle joints, ensuring all seals are in correct position and all clips are in place. 5. Connect the downpipe to the multi-positional outlet. 5. 37

9.00 Notes 38.

. 39