C100 Cryomodule. Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint

Similar documents
R.Bachimanchi, IPAC, May 2015, Richmond, VA

ABSTRACT 1 CEBAF UPGRADE CAVITY/CRYOMODULE

RF System LSD Work. William Merz

Digital LLRF Test on the Renascence Cryomodule

Low-Level RF. S. Simrock, DESY. MAC mtg, May 05 Stefan Simrock DESY

Microphonics. T. Powers

R100 Microphonics. Kirk Davis, Mike Drury, Leigh Harwood, Mark Wiseman, etc. Andrew Hutton

Update 5/19/11. Kirk Davis, Mike Drury, Leigh Harwood, Mark Wiseman, etc. Andrew Hutton

LLRF Operation and Performance of the European XFEL. An overview

Waveguide Arc Restrike Test Results Abstract Background

INSTALLATION AND FIRST COMMISSIONING OF THE LLRF SYSTEM

Digital Self Excited Loop Implementation and Experience. Trent Allison Curt Hovater John Musson Tomasz Plawski

ALICE SRF SYSTEM COMMISSIONING EXPERIENCE A. Wheelhouse ASTeC, STFC Daresbury Laboratory

Physics Requirements Document Document Title: SCRF 1.3 GHz Cryomodule Document Number: LCLSII-4.1-PR-0146-R0 Page 1 of 7

Design & Implementation of the LLRF System for LCLS-II. Andy Benwell (SLAC Spokesperson) LLRF 2017 October 16, 2017

SNS CRYOMODULE PERFORMANCE*

RENASCENCE * PERFORMANCE AND PROBLEMS ON FIRST TEST Feedthrough leaks sub 70 K. End group quenching

Overview of ERL Projects: SRF Issues and Challenges. Matthias Liepe Cornell University

Status of berlinpro and BESSY II Installation of SSA. Helmholtz-Zentrum Berlin for materials and energy (HZB)

DEVELOPMENT OF A BETA 0.12, 88 MHZ, QUARTER WAVE RESONATOR AND ITS CRYOMODULE FOR THE SPIRAL2 PROJECT

State of the Art in RF Control

RF STATUS OF SUPERCONDUCTING MODULE DEVELOPMENT SUITABLE FOR CW OPERATION: ELBE CRYOSTATS

S. Ghosh On behalf of Linac, IFR, Cryogenics, RF and beam transport group members. Inter University Accelerator Centre New Delhi India

The low level radio frequency control system for DC-SRF. photo-injector at Peking University *

Commissioning of the ALICE SRF Systems at Daresbury Laboratory Alan Wheelhouse, ASTeC, STFC Daresbury Laboratory ESLS RF 1 st 2 nd October 2008

5.5 SNS Superconducting Linac

Borut Baricevic. Libera LLRF. 17 September 2009

SRF EXPERIENCE WITH THE CORNELL HIGH-CURRENT ERL INJECTOR PROTOTYPE

ESS RF Development at Uppsala University. Roger Ruber for the FREIA team Uppsala University

Superconducting RF cavities activities for the MAX project

Superstructures; First Cold Test and Future Applications

Upper limit of the electron beam energy at the CEBAF 2D injector spectrometer and its functionality

Cavity Field Control - RF Field Controller. LLRF Lecture Part3.3 S. Simrock, Z. Geng DESY, Hamburg, Germany

To produce more powerful and high-efficiency particle accelerator, efforts have

ESS RF Source and Spoke Cavity Test Plan

CEBAF Overview June 4, 2010

HIGH POWER PULSED TESTS OF A BETA=0.5 5-CELL 704 MHZ SUPERCONDUCTING CAVITY

Advance on High Power Couplers for SC Accelerators

FLASH. FLASH Training: RF Gun. FLASH: the first soft X-ray FEL operating two undulator beamlines simultaneously. Siegfried Schreiber, DESY

High Power Couplers for TTF - FEL

CEBAF waveguide absorbers. R. Rimmer for JLab SRF Institute

SNS LLRF Design Experience and its Possible Adoption for the ILC

Status of superconducting module development suitable for cw operation: ELBE cryostats

HIGH POWER INPUT COUPLERS FOR THE STF BASELINE CAVITY SYSTEM AT KEK

EXPERIMENTAL RESULT OF LORENTZ DETUNING IN STF PHASE-1 AT KEK-STF

THE CRYOGENIC SYSTEM OF TESLA

Tuning systems for superconducting cavities at Saclay

Theory and Practice of Cavity Test Systems. Tom Powers

HIGH POWER COUPLER FOR THE TESLA TEST FACILITY

Resonator System for the BEST 70MeV Cyclotron

Engineering Challenges and Solutions for MeRHIC. Andrew Burrill for the MeRHIC Team

Beam Diagnostics, Low Level RF and Feedback for Room Temperature FELs. Josef Frisch Pohang, March 14, 2011

SRF Advances for ATLAS and Other β<1 Applications

XFEL Cryo System. Project X Collaboration Meeting, FNAL September 8-9, 2010 Bernd Petersen DESY MKS (XFEL WP10 & WP13) 1 st stage. Possible extension

Review on Progress in RF Control Systems. Cornell University. Matthias Liepe. M. Liepe, Cornell U. SRF 2005, July 14

Third Harmonic Superconducting passive cavities in ELETTRA and SLS

Predictions of LER-HER limits

Uppsala, June 17 th - 19 th, 2013

LARGE SCALE TESTING OF SRF CAVITIES AND MODULES

Slide Title. Bulleted Text

Status of the European XFEL Accelerator Construction Project. Reinhard Brinkmann, DESY

Direct Digital Down/Up Conversion for RF Control of Accelerating Cavities

Vibration studies of a superconducting accelerating

SUPERCONDUCTING PROTOTYPE CAVITIES FOR THE SPALLATION NEUTRON SOURCE (SNS) PROJECT *

Frequency Tuning and RF Systems for the ATLAS Energy Upgrade. Gary P. Zinkann

A few results [2,3] obtained with the individual cavities inside their horizontal cryostats are summarized in Table I and a typical Q o

DESIGN OPTIONS FOR CEBAF ENERGY UPGRADE

Processing and Testing of PKU 3-1/2 Cell Cavity at JLab

FREIA Facility for Research Instrumentation and Accelerator Development Infrastructure and Control Architecture

Progresses on China ADS Superconducting Cavities

SLHiPP-2, Catania, Italy. A cryogenic system for the MYRRHA linac. Nicolas Chevalier, Tomas Junquera

Design of the 352MHz, beta 0.50, Double- Spoke Cavity for ESS

FLASH at DESY. FLASH. Free-Electron Laser in Hamburg. The first soft X-ray FEL operating two undulator beamlines simultaneously

Advances in CW Ion Linacs

Project X Cavity RF and mechanical design. T. Khabiboulline, FNAL/TD/SRF

Liquid Helium Heat Load Within the Cornell Mark II Cryostat

Behavior of the TTF2 RF Gun with long pulses and high repetition rates

Phase Drift Budget Analysis for 12 GeV 1497 MHz LLRF System

3.9 GHz System (AH1) XFEL WP46

Niowave s Growth and the Role of STTR in its Development

Development of Superconducting CH-Cavities for the EUROTRANS and IFMIF Project 1

FLASH rf gun. beam generated within the (1.3 GHz) RF gun by a laser. filling time: typical 55 μs. flat top time: up to 800 μs

Tests of the Spoke Cavity RF Source and Cryomodules in Uppsala

THE HIGH LUMINOSITY PERFORMANCE OF CESR WITH THE NEW GENERATION SUPERCONDUCTING CAVITY

Amit Roy Director, IUAC

LLRF Plans for SMTF. Ruben Carcagno (Fermilab) Nigel Lockyer (University of Pennsylvania) Thanks to DESY, PISA, KEK, Fermilab, SLAC Colleagues

Maurizio Vretenar Linac4 Project Leader EuCARD-2 Coordinator

Design and performance of LLRF system for CSNS/RCS *

LCLS-II LLRF Prototype Testing and Characterization. Larry Doolittle, Brian Chase, Joshua Einstein-Curtis, Carlos Serrano LLRF 17,

Superconducting RF System. Heung-Sik Kang

Low Level RF Systems

Acceleration of High-Intensity Protons in the J-PARC Synchrotrons. KEK/J-PARC M. Yoshii

Software Requirements Specification for LLRF Applications at FLASH Version 1.0 Prepared by Zheqiao Geng MSK, DESY Nov. 06, 2009

ADVANCES IN CW ION LINACS*

Completion of the first SSR1 cavity for PXIE

INSTRUMENTATION AND CONTROL SYSTEM FOR THE INTERNATIONAL ERL CRYOMODULE

DEVELOPMENT OF A DLLRF USING COMERCIAL UTCA PLATFORM

PROGRESS IN THE ELLIPTICAL CAVITIES AND CRYOMODULE DEMONSTRATORS FOR THE ESS LINAC

DESIGN AND BEAM DYNAMICS STUDIES OF A MULTI-ION LINAC INJECTOR FOR THE JLEIC ION COMPLEX

KEK ERL CRYOMODULE DEVELOPMENT

Transcription:

1 new module

C100 Cryomodule Seven cell Cavity, 0.7 m long (high Q L ) 8 Cavities per Cryomodule Fits the existing Cryomodule footprint

Fundamental frequency f 0 Accelerating gradient E acc 1497 MHz > 20 MV/m Input coupler Q ext 3.2 x 10 7 Active length r/q Tuning sensitivity Pressure sensitivity 0.7 m 1288 Ω/m 0.3 Hz/nm 420 Hz/torr Lorentz force frequency sensitivity K L ~2 Hz/(MV/m) 2

RF System for C100 Cavity LLRF (PC/104) Piezo Driver EPICS RF amp drive Pre-Amp Klystron 13 kw Circulator HV Directional Coupler PS 5 MHz Fiber 5 MHz Fiber HPA Controller (PC/104) Service Building 5 MHz Fiber Cavity Interlocks (PC/104) Stepper Controller (PC/104) Heater Controller (PC/104) Ethernet One LLRF / Cavity One Klystron / Cavity One System / Zone Stepper Piezo Heater HPA Interlocks Cavity Probe Signal Conduit FPC Tunnel

RF System Single Zone Eight 13 kw Klystrons Four HV Power Supply Total (10 + 1 zones) 80 Klystrons (13 kw) 8 Klystrons (8 kw,c100-0)

RF System Single Zone 8 LLRF Controllers Stepper Controller Piezo Amplifier Interlocks Controller High Power Amplifier Controller Cryomodule Heater Controller Total (11 zones) 88 LLRF Controllers

RF System RF board FPGA board PC/104 Modular Interface boards PC power supply

C100 Commissioning Acronyms used in the slides SEL (Self Excited Loop) Cavity resonates at it s own frequency (Phase Locked Loop like) Constant forward power GDR (Generator Driven Resonator) Cavities are locked to reference Forward power not constant (reacts to detuning)

C100 Commissioning RF system commissioned into waveguide shorts SRF commissioning using LLRF Emax for individual cavities Field Emission measurements Q 0 measurement Operable gradient for cryomodule Performed in SEL RF Commissioning & Machine operations Cavities are operated in GDR

C100 Commissioning - Timeline Year Activity 2011 C100-1&2 were installed and commissioned 2012 C100-1&2 were operated during 6 GeV Nuclear Physics run. C100-2 was operated up to 108 MEV and 465 ma May Began 18 month CEBAF shutdown 2013 Installed and commissioned eight C100 cryomodules 2014 January completed C100 commissioning and began beam operation/commissioning March commissioned C100-0 (Installed in Injector)

Gradients in C100 During Commissioning Zone Beam Measurement During Commissioning C100-1 104 MV 94.01 MV C100-2 122 93.8 C100-3 108 76.58 C100-4 93 79.24 C100-5 121 100.31 C100-6 111 101.8 C100-7 104 103.81 C100-8 110 100.17 C100-9 105 101.15 C100-10 106 87.57 C100-0 104 82.3

Operational Experience -CEBAF Commissioning Commissioning 2.2 GeV/pass C100-934 MeV C50-457 MeV C20-808 MeV Injector design energy 123 MeV Opportunities for Improvement Reducing Field Emission Enhanced Cryomodule Heater Configuration Microphonics Detuning Other Observations RF Control Loop Optimization Klystron Drive Cables

Operational Experience - Field Emission Field emission heats beamline Vacuum pump faults Viewer & pump drop cross H&V nested Air Core correctors over BPM Quad Vacuum interlock drops zone out of RF End of Cryomodule

Operational Experience - Field Emission Cavity Gradients impacting Beamline Vacuum activity BEAMLINE VACUUM C100-10 Cav 6 C100-10 Cav 7 GMES MV/m

Introduce helium gas into cavity vacuum space Run RF to clean cavity surfaces Helium Processing Warm up and pump down to remove residual gas Improves high-field Q, reduces x-ray production and greatly reduces incidence of arcing at the cold ceramic window

Performed on C100-5 cryomodule Helium Processing FE Onset Before He Processing FE Onset After He Processing C100-5 cavity 6 Before and after He processing

In Progress Currently processing the Cryomodules in South Linac Results are encouraging Helium Processing HeProc status and results to date --Michael Drury Today @ 1:30 PM

Operational Experience - Cryomodule Heater Configuration C100-1 Cavities 6 and 7 have very high detuning Total heat vs Detuning in SEL Total Heat 230 W Total Heat 200 W Detuning In Hz

Operational Experience - Cryomodule Heater Configuration When RF was off Only Electric Heat Liquid Level Stable He Level Percentage When RF was on RF + Electric Heat Liquid Level not Stable He Level Percentage

Operational Experience - Cryomodule Heaters Single Heater Control for the Cryomodule He Vessel RETURN RISER Return Header (2 Phase) Return riser became a choke point as additional heat was applied Solution - Individual Cavity Heater Control Supply Header Heater

Cryomodule Heaters In Progress Individual Cavity Heater Control Chassis Plan to test in 0L04 Tentative Start Date 08/03 Dynamic Heater Controls --Tom Powers Today @ 2:30 PM

Microphonics - Mechanical Tuner Modification Design allows for 25 Hz Peak Detuning Actual peak detuning (21 Hz) was higher than expected in first cryomodules (C100-0,1,2,3) A detailed vibration study was initiated which led to the following design change A minor change to the tuner pivot plate substantially improved the microphonics detuning for the CEBAF C100 Cryomodules While both designs meet the overall system requirements the improved design has a larger RF power margin Microphonic C100-1 C100-4 Detuning RMS (Hz) 2.985 1.524 6s(Hz) 17.91 9.14 Cavity 5, C100-1 Cavity 5, C100-5

Operational Experience Microphonics Detuning and Construction C100 Cavity Gradients The drops show the cavity faulting during the day due to construction. RF Power could not compensate for the rapid detuning C100-0 Cavity Gradients Between 7 AM and 5 PM GMES MV/m

Operational Experience Microphonics Detuning Reduced Gradients in C100-0 Plan Collect Microphonics data from all C100s Investigate Piezo Algorithm Possibly switch out C100-0 for later production C100 C100-0 Cavity gradients in MV/m C100-4 Cavity gradients in MV/m C100-8 Cavity gradients in MV/m

Microphonics Detuning Microphonics Detuning Analysis in progress for Injector C100 Collecting data from other C100 when there is an opportunity Find out maximum heat capacity of each C100 C100 microphonics update ---Kirk Davis Today @ 10:30 AM

We observed 4 khz oscillation when LLRF is locked Higher gain Reduced 4 khz oscillation..but control system less stable Loop Phase mismatch between SEL and locked condition Simulation didn t show Latency issue between the two logic chains in the FPGA Systematic 30 degree difference RF Control Loop Optimization Microphonics compensated 4 khz Forward Power in GDR

Operational Experience - Crosstalk on Klystron drive cables Crosstalk on Drive Cables Causing cavity trips on GMES fault Repaired connectors and problem went away Crosstalk on Klystron Internal Cable Terminated the input Still had 15-25 watts forward power and gradient in the cavity! Investigating pulling klystron solenoid and replacing cables with better shielded cables

Current Plans Helium Processing in progress Installation of Individual Cryomodule Heater Control System Microphonics Detuning analysis, Piezo Algorithm studies and Implementation Control Loop Optimization Investigate the loop phase mismatch between SEL and GDR Klystron Drive Cables Detect the source of crosstalk

Summary CEBAF Initial commissioning goals achieved 2.2 GeV/pass 123 MeV from Injector CD4A 5 months ahead of schedule Beam delivery to experimental halls Plans for improving operability

Special Thanks to Trent Allison, Ed Daly, Mike Drury, Arne Freyberger, Curt Hovater, George Lahti, Clyde Mounts, Rick Nelson, Tomasz Plawski and Mike Spata for their contributions in this presentation

Questions?