At generating sites with 1200MW or greater of installed generating capacity.

Similar documents
ReliabilityFirst Regional Criteria 1. Disturbance Monitoring and Reporting Criteria

PRC Disturbance Monitoring and Reporting Requirements

PRC Compliance Using Bitronics 70 Series Recorders

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Final ballot January BOT adoption February 2015

NORMES DE FIABILITÉ DE LA NERC (VERSION ANGLAISE)

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

Standard VAR Voltage and Reactive Control

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

Standard Development Timeline

(Circuits Subject to Requirements R1 R5) Generator Owner with load-responsive phase protection systems as described in

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules. 45-day Formal Comment Period with Initial Ballot June July 2014

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

5. Effective Date: On the first day of the first quarter, after applicable regulatory approval.

A. Introduction. VAR Voltage and Reactive Control

VAR Voltage and Reactive Control

VAR Voltage and Reactive Control. A. Introduction

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

VAR Generator Operation for Maintaining Network Voltage Schedules

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Standard TOP Monitoring System Conditions

Wind Power Facility Technical Requirements CHANGE HISTORY

Implementation Plan Project Modifications to PRC Reliability Standard PRC-025-2

Standard VAR b Generator Operation for Maintaining Network Voltage Schedules

Interconnection-Wide Oscillation Analysis: Baselining Oscillation Modes in the North American Power System Objective Purpose

generation greater than 75 MVA (gross aggregate nameplate rating) Generation in the ERCOT Interconnection with the following characteristics:

VAR Generator Operation for Maintaining Network Voltage Schedules

Standard BAL b Automatic Generation Control

THIS DOCUMENT IS RETIRED BY FERC EFFECTIVE SEPTEMBR 5, 2018.

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Standard BAL Frequency Response and Frequency Bias Setting

Standard PRC Coordination of Generating Unit or Plant Voltage Regulating Controls with Generating Unit or Plant Capabilities and Protection

1

Final ballot January BOT adoption February 2015

Transmission Interconnection Requirements for Inverter-Based Generation

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS

WECC Standard VAR-002-WECC-2 Automatic Voltage Regulators

Standard PRC Coordination of Generating Unit or Plant Capabilities, Voltage Regulating Controls, and Protection

Standard BAL-005-0b Automatic Generation Control

Standard BAL b Automatic Generation Control

Standard BAL b3 Automatic GenerationBalancing Authority Control DRAFT

VAR Generator Operation for Maintaining Network Voltage Schedules

System Operating Limit Definition and Exceedance Clarification

Transmission System Phase Backup Protection

Standard Development Timeline

Standard Development Timeline

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Standard PRC Coordination of Generating Unit or Plant Capabilities, Voltage Regulating Controls, and Protection

SYNCHROPHASOR TECHNOLOGY GLOSSARY Revision Date: April 24, 2011

Module 11a. Initiating Cause Code Form 4.X RELIABILITY ACCOUNTABILITY

Standard COM Communications

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell

VAR Generator Operation for Maintaining Network Voltage Schedules

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements

BED INTERCONNECTION TECHNICAL REQUIREMENTS

4.2.1 Generators Transformers Transmission lines. 5. Background:

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION

E N G I N E E R I N G M A N U A L

August 25, 2017 VIA ELECTRONIC FILING

Setting and Verification of Generation Protection to Meet NERC Reliability Standards

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

VAR Generator Operation for Maintaining Network Voltage Schedules

Standard MOD Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions

August 25, Please contact the undersigned if you have any questions concerning this filing.

Standard MOD Area Interchange Methodology

ESB National Grid Transmission Planning Criteria

Standard MOD Verification of Models and Data for Generator Excitation Control Sys tem or Plant Volt/Var Control Functions

Standard Development Timeline

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

Standard Development Timeline

GridLiance Reliability Criteria

Recently, the SS38 Working Group on Inter-Area Dynamic Analysis completed two study reports on behalf of the UFLS Regional Standard Drafting Team.

Voltage and Reactive Procedures CMP-VAR-01

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

Use of Synchrophasors to Detect Control System and Circuit Breaker Reclosing Issues

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition

Table of Contents. Introduction... 1

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS

Power Plant and Transmission System Protection Coordination

ATTACHMENT - AESO FUNCTIONAL SPECIFICATION

Southern Company Interconnection Requirements for Inverter-Based Generation

May 30, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme Docket No. RM15-13-_

Remedial Action Scheme Definition Development

HOOSIER ENERGY REC, INC. Requirements for Connection of Generation Facilities. to the HE Transmission System

Cover Sheet. Technical Justification Retirement of WECC Regional Reliability Standard VAR-002-WECC-2 Automatic Voltage Regulators (AVR)

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

Functional Specification Revision History

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

September 19, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme

FACILITY RATINGS METHOD TABLE OF CONTENTS

Power Plant and Transmission System Protection Coordination

Considerations for Power Plant and Transmission System Protection Coordination

Transcription:

A. Introduction 1. 2. Number: 3. Purpose: To provide FRCC requirements for installation of Disturbance Monitoring Equipment (DME) and reporting of Disturbance data to facilitate analyses of events and verify system models. 4. Applicability: 4.1 Transmission Owner (TO) within the FRCC. 4.2 Generator Owner (GO) within the FRCC. 5. Effective Date: One year after FERC Approval Deleted: TBD B. : R1. Sequence of Event (SOE) Recording: [ Risk Factor: Lower ] - [ Time Horizon: Long-Term Planning ] R1.1 Location : SOE recording functionality shall be available at the following locations: R1.1.1 R1.1.2 At transmission stations with more than four (4) transmission lines operated above 200kV or installed at an alternate station within two (2) transmission busses (non-tapped) from that station (alternate station must contain 4 or more transmission lines and both stations shall be under same ownership). At Interregional transmission interconnections operating at 200kV or above, or installed within two (2) transmission busses (non-tapped) away from that location (facilities under same ownership). Deleted: (SER) equipment Deleted: In general, Deleted: ER Deleted: installed Deleted: major Deleted: a Deleted: away R1.1.3 At generating sites with 1200MW or greater of installed generating capacity. R1.1.4 At additional locations required by the FRCC that are specifically identified in Appendix A of this standard. R1.2 The specific location of SOE recording functionality selected to satisfy the criteria contained in R1.1.1 R1.1.3, is the responsibility of the TO or GO with the exception of locations specified in R1.1.4. Deleted: and Deleted: ER Deleted: will normally be Page 1 of 12

R1.3 Monitoring : R1.3.1 R1.3.2 R1.3.3 R1.3.4 Transmission circuit breaker positions note1 Generator circuit breaker positions (at transmission stations regardless of voltage level) Protective relay system trip note1 Relay protection communication note1 note1: For equipment operating at 200 kv or greater Deleted: R1.3.5 Recordings shall be available for at least 10 calendar days. R1.4 Recording : R1.4.1 SOE recording shall time stamp received events with a resolution of 1 millisecond(ms) or less note 2. R1.4.2 SOE recorded events shall have a timing error of 4ms (or less) note 2. note 2: Sequence of event recording can be provided as part of another device, such as a Supervisory Control and Data Acquisition (SCADA) Remote Terminal Unit (RTU), a generator plant Digital (or Distributed) Control System (DCS) or part of fault recording equipment. Timing of events must be synchronized to Universal Coordinated Time (UTC). R2. Fault Recording (FR) : [ Risk Factor: Lower ] - [ Time Horizon: Long-Term Planning ] R2.1 Location : FR functionality shall be installed at the following locations: R2.1.1 At transmission stations with more than four (4) transmission lines operated above 200kV or installed at an alternate station within two (2) transmission busses (non-tapped) from that station (alternate station must contain 4 or more transmission lines and both stations shall be under same ownership). Deleted: ER Deleted: SER Deleted: GPS or a timing standard in order to satisfy the recording criteria standard. (including Digital Fault Recorders (DFR)) Deleted: In general, Deleted: major Deleted: Deleted: away R2.1.2 At Interregional transmission interconnections operating at 200kV or above, or installed within two (2) transmission busses (non-tapped) away from that location (facilities under same ownership). Page 2 of 12

R2.1.3 R2.1.4 At generating sites with 1200MW or greater of installed generating capacity. At additional locations required by the FRCC that are specifically identified in Appendix A of this standard. Deleted: and R2.2 The determination of specific equipment locations selected to satisfy the criteria contained in R2.1.1 R2.1.3, is the responsibility of the TO or GO with the exception of locations specified in R2.1.4. Deleted: will be R2.3 Monitoring : R2.3.1 R2.3.2 R2.3.3 R2.3.4 Transmission lines operated at 200 kv or above Transformers with secondary (low voltage) windings operating at 200 kv or above. Generator or Generator Step-up (GSU) transformers connected at 200 kv or above note 3. Electrical quantities to be recorded for each monitored element shall be sufficient to determine the following: R2.3.4.1 Three phase-to-neutral voltages note 4. R2.3.4.2 Three phase currents and neutral currents. R2.3.4.3 R2.3.4.4 Polarizing currents and voltages, if used. Frequency. R2.3.4.5 Megawatts (MWs) and megavars (MVARs). note 3: Where location meeting the installation criteria include multiple units that have outputs connected to a common collector bus, FR functionality may be installed on the common bus. note 4: Generator voltages may be monitored phase-to- ground or phaseto-phase. Deleted: S Deleted: R2.3.5 Recordings shall be available for at least 10 calendar days. Deleted: qualifying sites R2.4 Technical requirements: Page 3 of 12

R2.4.1 R2.4.2 R2.4.3 Recording duration shall be at least 30 cycles in total length with a minimum of 3 cycles of pre-fault data. Minimum sampling rate of 16 samples per cycle. Triggering is to be automatic based on relay operation or abnormal voltage or current conditions. Deleted: and R3. Dynamic Disturbance Recording (DDR): [ Risk Factor: Lower ] - [ Time Horizon: Long-Term Planning ] R3.1 Location and Element : Based on the peninsular geography of the FRCC along with selected locations related to FRCC Special Protection Systems, DDR functionality shall be available on the specific locations and elements identified in Appendix B. R3.2 Monitoring : DDR functionality shall record at least one phase of voltage and current for the elements specified in requirement R3.1. Voltage and/or current recordings shall be from the same phase(s). R3.3 Recording : Electrical quantities to be recorded shall be sufficient to determine the following: R3.3.1 R3.3.2 R3.3.3 Voltage (either directly or readily derivable) Current Frequency (at least one per DDR location) R3.3.4 Megawatts (MWs) and megavars (MVARs) R3.4 Technical : R3.4.1 R3.4.2 Any DDR equipment installed at locations specified in Appendix B shall note 5. provide for continuous recording Existing DDR that do not have continuous recording capability shall be triggered according to the following: R3.4.2.1 Rate-of-change of frequency, rate-of-change of voltage triggers Deleted: R.2.4.4 Time synchronization shall be in accordance with NERC Reliability Standard PRC-018. Deleted:. Deleted: flows Deleted: expressed on a threephase basis (per each monitored line) Deleted: R3.3.5 Recordings shall be available for at least 10 calendar days. Deleted: (equipment) Deleted: after (date TBD) Formatted: Highlight Deleted: with a minimum historical retention period of 10 calendar days. Deleted: s Deleted: which Deleted: DDRs shall be capable of r Deleted: and Page 4 of 12

or oscillation triggers. R4 R3.4.2.1.1. Oscillation triggers, if available, should be set to trigger for low frequency oscillations in 0.2 to 3.0 Hz range. R3.4.3 Existing DDR that does not have continuous recording capability shall be capable of recording minimum record lengths of not less than three minutes. R3.4.4 Each device shall sample data at a rate of at least 960 samples per second and shall record the RMS value of electrical quantities at a rate of at least 6 records per second. note 5: Capability for continuous recording for devices installed after January 1, 2009. Reporting Criteria for Disturbance Data Recorded by DME Installations: [ Risk Factor: Lower ] - [ Time Horizon: Long-Term Planning ] R4.1 Criteria for events that require the collection of available data from DME installations. Power system disturbances are to be captured by substation monitoring equipment and records made available upon request to the FRCC. For the purpose of this document a disturbance is defined as one of the following conditions: 1. The loss of bulk power transmission that significantly affects the integrity of the interconnected system operation. 2. Loss of generation by a utility or generation supply entity in excess of 2,000 MW. 3. The correct operation of underfrequency load shedding or undervoltage load shedding, that results in loss of load of more than 200 MW. 4. Complete operational failure or shut-down of the bulk-power transmission system 5. Electrical System Separation (Islanding) where part or parts of a power grid remain(s) operational in an otherwise blacked out area or within the partial failure of an integrated electrical system 6. Uncontrolled loss of 300 Megawatts or more of firm system loads for more than 15 minutes from a single incident. R4.2 The TOs and / or GOs shall collect all available and relevant DME recordings as requested by the FRCC. R4.3 The TOs and / or GOs shall provide relevant DME recordings notes 6 and 7 to the FRCC within 20 calendar days of a request by the FRCC. Formatted: Indent: Left: 72 pt Deleted: 2 Deleted: 2 Deleted: 2. Deleted: DDRs Formatted: Indent: Left: 0 pt, Hanging: 46.35 pt Deleted: 3 Deleted: Deleted:. R3.4.5 Deleted: 4 Deleted: Each device Deleted: R.3.4.5 Time synchronization shall be in accordance with NERC Reliability Standard PRC-018. Deleted: Disturbance Criteria for Deleted: owners Deleted: r Deleted: owners Page 5 of 12

note 6: Where significant, records shall be annotated to indicate known equipment time delays or time synchronization issues. note 7: The TO and/or GO is not required to provide DME data to the FRCC for catastrophic events that result from natural disasters. Examples of catastrophic events that are not reportable include, but are not limited to, earthquakes, fires, tornados, hurricanes, landslides, wind shear, major storms (as defined either by the TO and/or GO or an applicable regulatory body), ice storms, and floods. R4.4 The data recorded by DME may be recorded in any format, including the device manufacturer s proprietary format. However, the TO or GO shall, upon request, furnish the data to FRCC in a format such that any software system capable of viewing and analyzing COMTRADE (IEEE Std. Standard C37.111-1999 or successor) files may be used to process and evaluate the data note 8. This requirement is applicable to equipment installed after January 1 st, 2005. note 8: Where agreed upon by the FRCC, data may be provided in other formats such as proprietary or COMTRADE electronic files, for transferring data recordings. The specific format for supplying data is left to the discretion of the TO or GO and FRCC with consideration of the information needed to interpret the recordings. This information may include the items listed below. Deleted: R4.4 Deleted: The TO or GO shall retain copies of the relevant DME recordings that were provided to the FRCC for at least three years from the date of the disturbance. Deleted: 5 Deleted: 7 Deleted: 7 Deleted: requestor R4.5. One line diagram/sketch of the substation where the recordings were made Diagram of portions of the interconnected system Annotation of printed graphs and text Description of the disturbance in sufficient detail for interpretation Where required, further analysis assistance will be provided by the contributing TO or GO to complete the FRCC analysis of a disturbance. Data files reported to FRCC shall be named in conformance with the IEEE Standard C37.232 Recommended Practice for Naming Time Sequence Data Files. Deleted: 6 Deleted: note 8 Page 6 of 12

C. Measures: M1. The Transmission Owner and Generator Owner shall each have evidence that SOE functionality is available at locations satisfying the location criteria and equipment requirements of requirement R1 of this standard. M2. The Transmission Owner and Generator Owner shall each have evidence that FR functionality is available at locations satisfying the location criteria and equipment requirements of requirement R2 of this standard. M3. The Transmission Owner shall have evidence that DDR functionality is available at locations satisfying the location / element criteria and equipment requirements of requirement R3 of this standard. M4. The Transmission Owner and Generator Owner shall each have evidence that they collected and provided, disturbance data in accordance with the reporting requirements of requirement R4 of this standard. D. Compliance: 1. Compliance Monitoring Process 1.1 Compliance Monitoring Responsibility: Compliance Monitor: FRCC Regional Entity 1.2 Compliance Monitoring Period and Reset Timeframe: Not Applicable 1.3 Data Retention: None Deleted: note 8: Compliance with this requirement is not effective until the IEEE standard is approved. Formatted: Normal, Indent: Left: 46.35 pt, Hanging: 45 pt, Don't adjust space between Latin and Asian text, Don't adjust space between Asian text and numbers Deleted: R5... [1] Formatted: Bullets and Numbering Deleted: Note the Measures of this Regional Reliability Standard are intended to correlate and supplement the Measures of NERC Reliability Standard, PRC-018-1, Disturbance Monitoring Equipment Installation and Data Reporting. capable of Deleted: ER Deleted: recording Deleted: installed Deleted: capable of Deleted: Fault recording Deleted: installed capable of dynamic disturbance recording Deleted: installed Deleted: and retained Deleted: requested Deleted: M5. Deleted: The FRCC shall have evidence that this standard has been reviewed and updated as necessary within the last ( 5 ) years. Deleted: One calendar year Deleted: The Transmission Owner and Generator Owner shall each retain any Disturbance data provided to the Regional Reliability... [2] Page 7 of 12

1.4 Additional Compliance Information Compliance Elements to be phased-in, according to the Implementation schedule and Compliance section of NERC Reliability Standard PRC-018-1. Formatted Table Deleted: The Transmission Owner and Generator Owner shall demonstrate compliance through selfcertification or audit (periodic, as part of targeted monitoring or initiated by complaint or event), as determined by the Compliance Monitor. Deleted: 1.5 2. Violation Severity Levels (VSLs) 2.1. Lower: There shall be a Lower VSL non-compliance if any of the following conditions is present: 2.1.1 DMEs that meet all the installation requirements (in accordance with Requirement R1, R2 and R3 of this standard) were installed at 90% or more but not all of the required locations/elements. 2.1.2 Recorded Disturbance data that meets all the data reporting requirements of requirement R4 was provided after 20 calendar days of a request from the FRCC but less than 35 days of the request. 2.2. Moderate: There shall be a Moderate VSL non-compliance if any of the following conditions is present: 2.2.1 DMEs that meet all the installation requirements (in accordance with R1, R2 and R3 of this standard) were installed at 80% or more but less than 90% of the required locations/elements. 2.2.2 Recorded Disturbance data that meets all the Disturbance data reporting requirements of requirement R4 was provided after 35 calendar days of a request from the FRCC but less than 50 days of the request.. 2.3. High: There shall be a High VSL non-compliance if any of the following conditions is present: 2.3.1 DMEs that meet all the installation requirements (in accordance with R1, R2 and R3 of this standard) were installed at 70% or more but less than 80% of the required locations/elements. Deleted: Compliance Mitigation Factors The following shall be considered when determining the Violation Severity Levels (VSLs) of noncompliances to this standard: Where post-disturbance data is unavailable from a specified DME device, disturbance data may be provided from alternate DME or other devices such as digital protective relays, phasor measurement units (PMUs) and power quality recorders. Deleted: Disturbance d Deleted: for 90% or more but not all of the required locations. Deleted: for 80% or more but less than 90% of the required locations Page 8 of 12

2.3.2 Recorded Disturbance data that meets all the Disturbance data reporting requirements of requirement R4 was provided after 50 calendar days of a request from the FRCC but less than 65 days of the request. 2.4. Severe: There shall be a Severe VSL non-compliance if any one of the following conditions is present: 2.4.1 DMEs that meet all the installation requirements (in accordance with R1, R2 and R3 of this standard) were installed at less than 70% of the required locations/elements. 2.4.2 Recorded Disturbance data that meets all the Disturbance data reporting requirements of requirement R4 was not provided after receipt of a request from the FRCC. Deleted: for 70% or more but less than 80% of the required locations. Deleted: for less than 70% of the required locations. Page 9 of 12

Appendix A Additional locations specifically required as specified in requirements R1.1.4 and R2.1.4 of this standard. Substation Owner Element (Lines) Basis: Ft. White PEF All 230 kv lines monitor Debary PEF All 230 kv lines monitor Lake Bryan PEF All 230 kv lines monitor Interstate LAK All 230 kv lines monitor Deleted: West Table 1: Table lists the specific locations that require the availability of Sequence of Event (SOE) Recording and Fault Recording (FR) functionalities, in addition to those locations meeting the criteria specified in requirements R1.1 and R2.1 of this standard. Deleted: (SER) capabilities Legend: Monitor - Lack of locations within proximity, meeting required SOE and FR criteria and therefore, potential lack of monitoring capability across a substantial electrical area. Deleted: SER Page 10 of 12

Appendix B Based on the peninsular geography of the FRCC along with selected locations related to FRCC Special Protection Systems, DDR functionality shall be available on the specific elements identified in Table 2 below. Owner Element (Lines) Basis: FPL Duval / Hatch 500 kv Duval / Thalmann 500 kv Duval / Kingsland 230 kv PEF Ft White / Suwannee 230 kv Ft White / Archer 230 kv Ft White / Newberry 230 kv SEC Seminole / Black Creek 230 kv Seminole / Silver Springs No. #1 230 kv FPL Putnam / Volusia 230 kv FPL Malabar / Midway 230 kv FPL Orange River / Andytown 500 kv Orange River / Alva 230 kv TAL Hopkins / Sub 20 230 kv JEA Center Park / Northside 230 kv Center Park /SJRPP 230 kv Center Park / Greenland Center Park / Robinwood PEF Lake Tarpon / Brookridge 500 kv PEF Lake Tarpon / Sheldon Rd #1 230 kv Lake Tarpon / Seven Springs 230 kv Lake Tarpon / East Clearwater 230 kv TEC Big Bend / Manatee 230 kv Big Bend / S. Gibsonton 230 kv Big Bend / Mines 230 kv TEC Gannon / Juneau 230 kv Gannon / Fishhawk 230 kv OUC Stanton / Curry Ford 230 kv Stanton / Taft 230 kv PEF Suwannee / Pinegrove 230 kv Suwannee / Perry 230 kv Suwannee / Ft White 230 kv FPL Charlotte / Whidden #1 230 kv Deleted: at the Deleted: locations Formatted: Centered Formatted Table Page 11 of 12

Charlotte / Ringling 230 kv Charlotte / Ft Myers #1 230 kv TEC Pebbledale / Polk #1 230 kv Pebbledale / Barcola 230 kv Pebbledale / N. Bartow 230 kv FPL Turkey Point / Flagami #1 230 kv PEF Windermere / Southwood 230 kv Windermere / Camp Lake 230 kv Windermere / International Dr. 230 kv Formatted: Centered Formatted: Centered Table 2: Table lists the specific elements that require the availability of Dynamic Disturbance Recording (DDR) equipment capability. Deleted: locations Legend: Metro Coverage - Station visibility required to monitor Special Protection Systems actuation - Site(s) in or near major load centers - Station visibility required due to unmonitored concentration of transmission elements Note: These elements have been determined to provide adequate recording visibility within the FRCC and address the following criteria as they pertain to the FRCC transmission system topology and generation patterns. - Site(s) in or near major load centers - Site(s) in or near major generation clusters - Site(s) in or near major voltage sensitive areas - Site(s) on both sides of major transmission interfaces - A major transmission junction - Elements associated with Interconnection Reliability Operating Limits - Major EHV interconnections between control areas - Coordination with neighboring regions within the interconnection Deleted: location Page 12 of 12

Page 7: [1] Deleted Eric Senkowicz 9/7/2007 9:49:00 AM R5 Standard Review Cycle: [ Risk Factor: Lower ] - [ Time Horizon: Long-Term Planning ] 5.1 5.2 RThe FRCC shall periodically review, update and approve this standard as required RMinimum review cycle is five (5) years. Page 7: [2] Deleted Eric Senkowicz 9/7/2007 10:04:00 AM The Transmission Owner and Generator Owner shall each retain any Disturbance data provided to the Regional Reliability Organization (Requirement 4) for three years. The Compliance Monitor shall retain any audit data for three years.