Company Directive STANDARD TECHNIQUE: TP6F/1. Power Measurement Conventions

Similar documents
Company Directive POLICY DOCUMENT: SD4/7. Relating to 11kV and 6.6kV System Design

Company Directive STANDARD TECHNIQUE: SD1E/2. Technical Requirements for Customer Export Limiting Schemes

STANDARD TECHNIQUE: SD4A/1

SYNCHRONISING AND VOLTAGE SELECTION

Company Directive STANDARD TECHNIQUE: TP14C. Distribution Business Provided Metering Facilities

QUESTIONNAIRE for Wind Farm Power Stations only

ALPHA 50 MULTIFUNCTION METER (ALPHA SERIES)

Single Line Diagram of Substations

ECP GROUND-MOUNTED SWITCHGEAR WITH PROTECTION RELAYS COMMISSIONING PROCEDURE

METERING REQUIREMENTS FOR INTERCONNECTION POINTS OF SERVICE

TABLE OF CONTENT

TS RES - OUTSTANDING ISSUES

Company Directive STANDARD TECHNIQUE : TP21A/2. Relating to Safety Limits for Touch and Step Voltages - Earthing System Design/Assessment

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Australian Standard. Instrument transformers. Part 1: Current transformers (IEC Ed.1.2 (2003) MOD) AS AS

MICROPROCESSOR-BASED METERING EQUIPMENT SECTION 16901C PART 2

ECP HV INSULATION TESTING

Unit 2. Single Line Diagram of Substations

MV network design & devices selection EXERCISE BOOK

Network Monitoring and Visibility Summary

RISH EM 3490 SS Kilowatt Hour Energy Meter With Rs485 RISH EM 3490 SS. Application : Product Features: Indication: Pulse Indication:

Transformer Trainer. Electrical Power Systems PSL20. Learning Outcomes. Key Features. Key Specifications

ALPHA 20 MULTIFUNCTION METER (ALPHA SERIES)

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

Integra 1560 and 1580 Digital Transducer Systems

Impact Assessment Generator Form

Complex Solution for the Distribution Substation REF 542plus. Application and Setting Guide

RISH Master Digital Multifunction Instrument with onsite pluggable output options. Application : Product Features:

Specialists in HV and MV test and diagnostics. Testing in Substations

ECP HV INSULATION TESTING

Table of Contents. Introduction... 1

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

ECP GROUND-MOUNTED SWITCHGEAR COMMISSIONING PROCEDURE

Low Voltage Products. Third Harmonic Filter THF and THF star System components for assembly and retrofitting. Catalogue THFS2GB 03_05 1SCC330004C0201

Electrical Switchgear & Power Transformer Testing. H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E

Data Sheet. RISH Master Record %THD

12/2 Product overview. 12/3 7KT1 14, 7KT1 53 E-counters. 12/9 7KT1 11, 7KT1 12 digital measuring devices. 12/11 7KT1 0 analog measuring devices

Company Directive STANDARD TECHNIQUE: SD5F. Relating to connecting multiple small low voltage connections with limited network analysis

Company Directive STANDARD TECHNIQUE: SD5R/2. Earth Fault Loop Impedances and Phase to Neutral Loop Impedances at LV Installations

SPTS 1 - Ratings and General Requirements for Plant, Equipment and Apparatus for The ScottishPower System and Connection Points to it.

KENYA ELECTRICITY GENERATING COMPANY LTD

ELE-CMOS-E-2001 Electrical Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

Power Meter PQM (EnerSure Enkapsis) Guide Form Specification PART 1: GENERAL

VI 3 - i TABLE OF CONTENTS

Centrale de mesure Power Meter PM500 Merlin Gerin

Installation and Operating Instructions

Standard Prices for Generators 2010

EI HIGH VOLTAGE INSULATION TESTING POLICY

\NYISO REVENUE METERING REQUIREMENTS MANUAL

RELEVANT ELECTRICAL STANDARDS

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PMAC770 Multifunction Power Meter. Installation & Operation Manual V2.0 ZHUHAI PILOT TECHNOLOGY CO., LTD.

Energy Division

G81 PART 1 FRAMEWORK APPENDIX

ISSN: [IDSTM-18] Impact Factor: 5.164

Multimeter 500CVD21 RTU500 series

Alternative Testing Techniques for Current Transformers. Dinesh Chhajer, PE Technical Support Group MEGGER

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

DM-III Multitest & DM-III Multitest F Power Quality Recorders

NIC Project Medium Voltage Direct Current Link Technical Specification

ENGLISH 3 Phase Multi-function Power Meter 1/5A MID MID

EASTRON SDM630MCT-RJV / SDM630MCT-RJA User Manual V1.1. Three phase multifunction din rail energy meter

Low Voltage Products. Enclosed Third Harmonic Filter THF and THF star Enclosed units. Brochure THFS1GB 03_04 1SCC330003C0201

ELECTRICAL NETWORKS SPECIFICATION TECHNICAL SPECIFICATION FOR A 230V/110V AND 400V/110V TRANSFORMER

Licensed Electricians Practical Assessment (LEP)

ECP HV METERING EQUIPMENT COMMISSIONING PROCEDURE

Revision Control. 0 18/07/2012 Initial Document Creation. STAKEHOLDERS The following positions shall be consulted if an update or review is required:

Powered by technology...driven by service CURRENT TRANSFORMERS. Multifunction Meters. Transducers & Isolators. Temperature Controllers

Energy Meters for DIN Rail Mounting Electric energy meter WS0101, WS0102,WS1102 WS0301, WS0302,WS1302

Contents. Introduction and description Package contents Device identification PM Options... 80

DESIGN PRACTICE NOTE DESIGN/REVIEW REQUIREMENTS FOR TRACTION BONDING PLAN

RISH Master 3430 DIGITAL MULTI-FUNCTION TRANSDUCER. Electro-Meters

Power Meter Series PM9

Technical Data Sheet

Licensed Electricians Practical Assessment (LEP)

SYSTEM MONITORING FAULT RECORDING

Balancing and Settlement Code. Code of Practice Five

OBICON. Perfect Harmony. Short overview. ROBICON Perfect Harmony. System Overview. The Topology. The System. ProToPS. Motors.

Meters. Ampere Meter. Volt Meter. Watt Meter. Var. Meter. Power Factor Meter. Frequency Meter. Demand Meter. Meter Relay.

Končar TMS - Bushing monitoring

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

DIRIS A40 DIRIS A41. Functions. Conformity to standards. Applications. Energy management DIRIS A40. Network analysis

Advanced Test Equipment Rentals ATEC (2832) CP RC. Resonance circuit for GIS testing

Technical Data Sheet AMIK 300 / 301

DM-III MULTITEST Power Quality Recorder

Substation Preventive Maintenance

Low Voltage Power Factor Correction Equipment Specifications Automatic, Automatic Detuned, Automatic Tuned

N30P DIGITAL PANEL METER

HAWK5000 Operators Manual


Electrical Theory. Power Principles and Phase Angle. PJM State & Member Training Dept. PJM /22/2018

Protection of Electrical Networks. Christophe Prévé

(240 ) Measurement of DC currents and DC voltages. Size (mm): Q48 Q144 Q72 Q144 Q48 Q144

N. TEST TEST DESCRIPTION

SUBJECT HEADING: Switching Programmes ISSUE: 18

UNIVERSAL MEASURING INSTRUMENTS. TNM 34xx. TNM 3410 / 3420 / 3430 / 3440 Universal measuring instrument 1/49

FACILITY RATINGS METHOD TABLE OF CONTENTS

Technical Data Sheet. x1000. kwh R Y B

EDS FAULT LEVELS

Measuring centers MC3x0 series Energy Meters with Power Display Energy Meter WQ0217 & WQ1217 Energy Meter with analogue pointer WQ0207 & WQ2207

Transcription:

Company Directive STANDARD TECHNIQUE: TP6F/1 Power Measurement Conventions Summary This document specifies the conventions that are used for the direction of Power Flow within Western Power Distribution s Network. NOTE: The current version of this document is stored in the WPD Corporate Information Database. Any other copy in electronic or printed format may be out of date. Copyright 2017 Western Power Distribution ST:TP6F/1 July 2017-1 of 13 -

IMPLEMENTATION PLAN Introduction This document specifies the conventions for the direction of power flow within Western power Distribution s network. Main Changes Section 2.1 has been modified to allow greater flexibility regarding the convention for the direction of power flow. Impact of Changes The changes will have minimal impact. Implementation Managers shall ensure all relevant staff are familiar with and comply with the requirements of this document. In accordance with the original issue of the document, retrospective action is required to: Check the calibration and directionality of active power and reactive power measurements in PowerOn. Add dynamic arrows to PowerOn indicating the direction of active power and reactive power and also a static arrow that specifies the direction of positive power flow. Implementation Timescale This document shall be implemented on issue. Checks on existing active / reactive power transducers, power factor transducers, and power meters shall be carried out as part of the next protection maintenance. The person carrying out these checks shall send their results to the PowerOn Team who will update PowerOn, adding dynamic and static arrows. This work shall be completed by the end of February 2020 (in accordance with the requirements of the original issue of this document). ST:TP6F/1 July 2017-2 of 13 -

REISION HISTORY DOCUMENT REISION & REIEW TABLE Date Comments Author July 2017 Section 2.1 has been modified to allow additional flexibility regarding the convention for power flow direction. A reference to ENA TS 41-15, Standard Schematic Diagrams for Equipment in 132k Substations, has been added. Andy Hood February 2016 New Document Andy Hood ST:TP6F/1 July 2017-3 of 13 -

1.0 INTRODUCTION With increasing levels of generation connected to Western Power Distribution s networks it is essential that the magnitude and direction of power flow within Western Power Distribution s networks is measured accurately and displayed in a consistent manner in PowerOn. This document specifies the conventions that are used for these measurements. Where any difficulty is encountered in the application of this document the author should be contacted who will determine whether a variation is appropriate. 2.0 REQUIREMENTS 2.1 Power Flow Conventions 2.1.1 Analogue measurements such as current, voltage, active power and reactive power are either provided by meters, transducers or by protection / tap-change control relays. Going forward it is expected that the majority of analogue readings will be derived from protection relays. Given this, the convention for the direction of active power and reactive power must align with convention used for protection relays. 2.1.2 These meters, transducers and relays measure phase to phase voltage (via Ts) and line current (via CTs) and use this data to determine the active power and reactive power. 2.1.3 The convention for the direction of directional protection relays and hence the convention for analogue measurements shall be in accordance with Western Power Distribution s protection standards and standard schematics. These in turn are based upon ENA EREC 5 and ENA TS 41-15. 2.1.4 In general for circuits (both incoming and outgoing) the positive direction is away from the busbars and towards the circuit / equipment to be protected. Typical examples are given in Figure 1 to 3, below. 2.1.5 For other applications the positive direction will depend on site specific requirements. 2.1.6 Where guidance is needed for new installations this is provided by Engineering Design. For existing installations, the asset owner should be able to determine the existing CT / T connections, check any relay / transducer settings and, where necessary carry out on load checks to determine the positive direction. ST:TP6F/1 July 2017-4 of 13 -

= Convention for positive active power and reactive power Figure 1 Typical Power Flow Convention for Switchboards CTs in circuit breaker = Convention for positive active power and reactive power Figure 2 Typical Power Flow Convention for Transformers ST:TP6F/1 July 2017-5 of 13 -

WPD s Network WPD s Network Metering CB Metering CB WPD Customer WPD Dummy CB (provides Isolation / earthing facilities) Customer WPD s Network WPD s Network Metering CB Metering CB WPD WPD Customer Customer = Convention for positive active power and reactive power Figure 3 Typical Power Flow Convention for Metering Arrangements ST:TP6F/1 July 2017-6 of 13 -

2.2 PowerOn Fusion Facilities 2.2.1 Where power measurements are available in PowerOn the direction of active power and reactive power shall be displayed by dynamic arrows on the screen (one arrow for active power and one arrow for reactive power). In addition, when the user zooms in closely to the associated plant the convention for positive power flow shall be indicated by a static arrow. 2.2.2 It should be noted that voltage (), current (A) and apparent power (A) do not have a direction. 2.3 Data Logger 2.3.1 Data Logger shall provide positive and negative values of Active Power and Reactive Power. The convention for power flow direction shall be in accordance with the static arrow displayed in PowerOn. 2.4 Commissioning Requirements 2.4.1 Requirements for commissioning protection equipment are defined in the TP10 series of documents. Transducers and their associated CTs and T circuits shall be commissioned using the same techniques applied to protection relays and systems. The calibration and directional sensing of relays, meters and power transducers are critical to their operation and therefore the commissioning tests must verify these aspects. The following checks and tests are applicable: Inspection of secondary wiring and equipment. Insulation resistance (IR) tests on secondary wiring. Resistance tests. CT Tests. T Tests. Auxiliary supply tests (where applicable). Calibration tests. On load checks / tests to verify the correct magnitude of current, voltage, active power and reactive power etc. and also the directionality of active power and reactive power. ST:TP6F/1 July 2017-7 of 13 -

3.0 BACKGROUND 3.1 Types of Power Measurement Three different types of Power are applicable to A.C. systems, Apparent Power, Active Power and Reactive Power. (a) Apparent Power = oltage x Current and has units of olt-amperes (e.g. A, ka or MA). (b) Active Power = oltage x Current x COS Ѳ, where Ѳ is the angle between the oltage and Current waveforms. Active Power is expressed in Watts (e.g. W, kw or MW). (c) Reactive Power = oltage x Current x SIN Ѳ, where Ѳ is the angle between the oltage and Current waveforms. Reactive Power is expressed in ARs (e.g. Ar, kar or MAr) Note, COS Ѳ is known as the Power Factor 3.2 Direction of Power Flow AC current, voltage and apparent power are, by themselves, non-directional quantities and are therefore not assigned a direction. The direction of active and reactive power flow depends on the relationship (angle) between the voltage waveform and the current waveform. This relationship can be shown in two ways, as a diagram of voltage and current by angular displacement (as shown in Figure 4) or as a vector diagram (as shown in Figure 5). 3.2.1 Active Power If the current lags or leads the voltage by 90 o or less the active power is positive. If the current lags or leads the voltage by more than 90 o the flow of active power is negative. 3.2.2 Reactive Power If the current lags the voltage by less than 180 o the reactive power is positive. If the current leads the voltage by less than 180 o the flow of reactive power is negative. ST:TP6F/1 July 2017-8 of 13 -

oltage () / Current (A) 400 300 200 100 0-100 -200-300 -400 0 30 60 90 120 150 180 210 240 270 300 330 360 Angle (degrees) oltage Current Figure 4 Current & oltage Waveforms - Current lagging oltage by 30 o Note, A compete cycle (i.e. 360 o ) has a duration of 20ms where the frequency is 50Hz. oltage ( ph-n ) 30 o (lagging) Current (A) Figure 5 ector Diagram Current Lagging oltage by 30 o ST:TP6F/1 July 2017-9 of 13 -

I (A) () Ѳ Active Power = IxxCOSѲ (W) Apparent Power = Ix (A) Reactive Power = IxxSINѲ (Ar) Figure 6 Apparent Power, Active Power and Reactive Power 3.2.3 Figure 6 shows the relationship between apparent power, active power and reactive power. In this case both active power and reactive power are positive since the current is lagging the voltage by less than 90 o. 3.2.4 Figure 7 shows how the direction of power flow changes as the angle between the current and voltage varies. Four examples are provided: I1 lags the voltage by approximately 20 o and, in this case, the Active Power and Reactive Power are both positive. I2 leads the voltage by approximately 20 o and in this case the Active Power is positive and the Reactive Power is negative. I3 lags the voltage by approximately 160 o and so in this case the Active Power is negative and the Reactive Power is positive. I4 leads the voltage by approximately 160 o and so in this case both the Active Power and the Reactive Power are negative. ST:TP6F/1 July 2017-10 of 13 -

Lagging PF o +90 +120 o +60 o Leading PF I4 +150 o -ve P -ve Q +ve P -ve Q +30 o I2 180 o oltage ( ph-n ) I3-150 o -ve P +ve Q +ve P +ve Q -30 o I1 Leading PF -120 o -90 o -60 o Lagging PF P = Active Power (kw) Q = Reactive Power (kar) Figure 7 Four Quadrant Diagram - Direction of Power Flow 3.3 Power Transducer Requirements 3.3.1 Transducers shall satisfy the requirements of the relevant WPD switchgear and protection panel specifications, for example EE SPEC: 3 and EE SPEC: 87. 3.3.2 Figure 8 and 9 show the AC connection requirements for standard Power transducers and the direction of positive power that results from these connections. 3.3.3 At the time of writing, power transducers are connected using the 3 x voltage, 1 x current arrangement, shown in Figure 8, which is suitable for balanced three wire networks. Going forward, specifications and standard drawings will be modified so that transducers are connected using the 3 x voltage, 3 x current arrangement shown in Figure 9. This will allow additional data, including all three current values to be made available if the transducer is connected to the RTU by a communication interface (e.g. Modbus, DNP3.0 or IEC61850 protocol). 3.3.4 Where the transducer DC milliamp outputs are hardwired to an RTU the following parameters shall be monitored: 1 x line Current 1 x voltage (phase-phase) Active power (total) Reactive power (total) ST:TP6F/1 July 2017-11 of 13 -

L1 L2 L3 T Direction of positive (+ve) power 1 13 5 2 8 14 CT 3 I4MT 4U2 Transducer Figure 8 Standard Transducer Connections (1 Current, 3 oltage Arrangement) L1 L2 L3 T Direction of positive (+ve) power CTs 1 4 7 9 6 11 8 5 2 I4MT 4U2 Transducer 3 Figure 9 Standard Transducer Connections (3 Current, 3 oltage Arrangement) ST:TP6F/1 July 2017-12 of 13 -

APPENDIX A SUPERSEDED DOCUMENTATION ST:TP6F dated February 2016 APPENDIX B ANCILLARY DOCUMENTATION EE SPEC: 3 EE SPEC: 87 ENA EREC 5 ENA EREC 41-15 12k and 36k Indoor Circuit Breakers including associated Protection and Ancillary Electrical Equipment Protection and Control Cubicles for Outdoor 72k and 36k Circuit Breakers and Primary Substation Transformers Standard Schematic Diagrams Standard Schematic Diagrams for Equipment in 132k Substations APPENDIX C KEY WORDS Transducer, Power, Apparent Power, Active Power, Reactive Power, Power Factor, Current, oltage, Protection, Direction, Measurement. ST:TP6F/1 July 2017-13 of 13 -