1 PROVINCE.OF BRITISH COLUMBIA ORDER OF THE LIEUTENANfelOVERNOR IN COUNCIL Order in Council No Approved and Oidered a cieuisvunigott3mor Executive Council Chambers, Victoria On the recommendation of the undersigned, the Lieutenant Governor, by and with the advice and consent of the Executive Council, orders that, effective September I, 1995, (a) (b) B.C. Reg. 452/90, the B.C. Electrical Code Regulation, is repealed, and the Canadian Electrical Code, Part I, Seventeenth Edition, Safety Standard for Electrical Installations, Canadian Standards Association standard C , as available in printed form, including the Errata dated August 25, 1994, is adopted in whole as the B.C. Electrical Code Regulation, subject to the variations set out in the Schedule attached to this order. Minister Muntcpa/ Atkins Pnisiding Member ol Ort Eres:utive Council (Pus pare is for nuntstrunye purposes only and is not part of Ow Order ) Authority under which Order Is made: Act and section:- Other (specify1:- April 3, 1995 Electrical Safety A It, section 16 (2.1) a/ s /94/3.7/sas
2 SCHEDULE Interpretation 1. In this Schedule, "electrical code" means the Canadian Electrical Code, Part I. 17th Edition, Canadian Standards Association Standard C Amendments 2. Section 0 of the electrical code is amended (a) by striking out the definition of "Electrical contractor" and substituting the following: Electrical contractor includes a person, not being the worker of the contractor, who does electrical work for another person, and includes a utility corporation that does electrical work for another person;, (b) by striking out the definition of "Electrical equipment" and substituting the following: Electrical equipment includes any machinery, plant, works, wires, pipes, poles, conduits, apparatus, appliance and equipment used or designed or intended for use for or in connection with the generation, transmission, supply, distribution, or use of electrical energy for any purpose;, (c) by striking out the definition of "Inspection department" and substituting the following: Inspection department means the regulatory authority;, (d) by striking out the definition of "Inspector" and substituting the following: Inspector means an invector as defined in the Electrical Safety Act;, and (e) by adding after the definition of "Multi-wire branch circuit" the following definition: National Building Code of Canada means the British Columbia Building Code and local building bylaws..3. Section 2 is amended by striking out Rules 2-000, 2-004, 2.006, 2-008, 2-012, 2-020, and Section 6 is amended in Rule (2) by striking out paragraph (c) and substituting the following:
3 (c) Locating the service box inside a separate building, room or enclosure, provided that in multiple occupancy buildings a main disconnecting means is provided at each occupancy panelboard. switchboard or distribution centre. 5. Section 8 is amended in Rule (2) (a) by striking out "Subtitle ( I )" and substituting "Subrule (1) (a)". 6. Section 20 is amended in Rule (2) by striking out "masonry" in the first line. 7. Section 26 is amended (a) by striking out Rule and substituting the following: Protection for Power and Distribution Transformers Rated Over 750 V (I) Where short circuit protection or overload protection, or both, is required by these rules, it shall be provided in each phase of the system. (2) Subject to Subrule (8), each transformer shall be protected by an individual short circuit device on the primary side consisting of: (a) A fuse with a continuous current rating of not more than 250% of the primary current of the transformer; or (b) A circuit breaker with a trip setting of not more than 250% of the primary current of the transformer. (3) Where transformers are connected in parallel or series to form a transformer hank operating as a unit, each transformer shall be protected individually. (4) If the maximum fuse size required by Subrule (3) cannot withstand the inrush current, then a circuit breaker with overcurrent relays shall be used. (5) When a primary short circuit device is part of the service entrance equipment, its rating shall be acceptable to the supply authority. (6) Each transformer located within a bu ;ding shall be protected by an overioad protection device capable of opening all ungrounded primary or secondary conductors. (7) The overload device prescribed by Subrule (6) shall consist of: (a) A device that will cause the circuit to open after the transformer has operated at a current greater than 135% of its rated full current load for a period of not more than 10 minutes; or (b) A temperature sensing device in the transformer that will cause the circuit to open when the hot spot temperature of the winding 2
4 exceeds 105% of the maximum design hot spot temperature in accordance with CSA Standard C9 and ANSI Standard C57. (8) Where two or more transformers are operated in parallel, and each of them has secondary overload devices referred to in Subrule (7), they shall not be required to have individual short circuit devices on the primary side if the primal)/ feeder short circuit device will open the circuit before damage would occur in any of those transformers in the event of a short circuit., (b) in Rule by adding after Subrule (13) the following: (14) Where a receptacle, other than a ground fault circuit interrupter receptacle, is connected to a circuit that serves other outlets, the receptacle shall be installed in a manner that will permit it to be disconnected from the circuit conductors without interrupting their continuity., and (c) In Rule (19) by striking out "single" in the first line. 8. Section 30 is amended in Rule by striking out Subrule (2) and substituting the following: (2) In industrial and commercial establishments where a trained and qualified electrical maintenance staff is available, the voltage shall be permitted to exceed 150 volts-to-ground, but shall not exceed the voltage-to-ground of a nominal system voltage of 347/600Y. 9. Section 32 is amended in Rule by adding after Subrule (5) the following: (6) Overhead conductors between buildings shall be installed in accordance with the rules of Section Section 34 is amended by adding after Rule the following: Outdoor Portable Signs Location. A portable outdoor sigr shall be permitted to be situated less than 2.2 m above grade if the location would normally prevent vehicles from coming into contact with either the sign or its connecting cord Power Supply. A receptacle supplying a portable outdoor sign shall be: (a) A Class A ground fault circuit interrupter type; or (b) If installed on a building be either a Class A ground fault circuit interrupter type or be on a circuit protected by a Class A ground fault circuit interrupter. 3
5 Cord Connection. The flexible cord used to connect from the receptacle to the sign plug cap attachment shall be of a type suitable for extra hard usage in wet locations as specified in Table I I. 11. Section 38 is amended (a) by striking out the title of the section and substituting the following: Section 38 - Elevating Devices (b) by striking out Rule and substituting the following: Scope. This section applies to the installation of electrical equipment for elevating devices and is supplementary to, or amendatory of, the general requirements of this Code., (c) by adding a new Rule : Special Terminology. In this section the following definition shall apply: Elevating Device means a device meeting the definition of an elevating device in the Elevating Devices Safety Act, and includes passenger and freight elevators, dumbwaiters and escalators., (d) in Rule (3) by striking out "elevator", and (e) in Rule (i) in Subrule (1) (a) by striking out "elevator, dumbwaiter, and escalator" and substituting "elevating device", (ii) in Subrule (1) (b) by striking out "elevators, dumbwaiters, or escalators" and. ubstituting "elevating devices", and (iii) in Subrule (1) (c) by striking out "elevator" and substituting "elevating device". 12. Section 54 is amended by striking out Rule Section 56 is amended by striking out Rule Section 60 is amended (a) by striking out Rule , (h) in Rule (4) by striking out "900 tn" and substituting "900 mm", and (c) in Rule by striking out paragraph (a). 4
6 15. Section 62 is amended (a) in Rule , by renumbering the present rule as Subrule (1) and by adding the following: (2) Manually operable controls for electric heaters in bathrooms shall be located at least I m from the bathtub or shower stall, this distance being measured horizontally between the control and the bathtub or shower stall, without piercing a wall, partition, or similar obstacle., and (b) in Rule by adding after Subrule (2) the following: (3) Each central unit shall be provided with a disconnecting means connected on the line side of the controller and unit, located within sight of and within 9 m of the controller and unit, provided that the disconnecting means shall be permitted to be omitted where the central unit is located in a dwelling unit and fed from within that dwelling unit. 16. Section 66 is amended by striking out the section and substituting tht following: Scope Section 66 - Amusement Parks, Midways, Carnivals, Film Sets, T. V. Remotes and Travelling Shows Scope and Application ( I ) This Section applies to the installation of electrical equipment utilizing any source of power, including generator sets, used for amusement parks, midways, carnivals and other events of a temporary nature held indoors or outdoors, such as film sets, T. V. remotes, home shows, live theatre, travelling shows and tent meetings and is supplementary to, or amendatory of, the general requirements of this Code. (2) The installation of electrical equipment fonning part of an amusement ride shall comply with CSA Standard Z267-M1983, Safety Code for Amusement Rides Special Terminology. In this Section the following definitions appi Amusement ride means a device or combination of devices designated or intended to entertain or amuse people by physically moving them. Amusement park means a tract of land used as a temporary or permanent location for amusement rides and structures. Concession means a structure, or a combination of structures erected for the purpose of entertaining or amusing people with games or shows or for the dispensing of food, souvenirs and tickets by sale or for any other purpose. 5
7 General Supporting of Conductors (I) Only decorative lighting, signal, communication, and control circuits shall be supported on structures that support amusement rides. (2) The decorative lighting and control circuits of one amusement ride shall not be installed on a supporting structure of another ride. (3) Overhead conductors shall have a vertical clearance to finished grade of not less than the following: (a) Across highways, streets, lanes and alleys 5.5 m; (b) Across areas accessible to vehicles 5 m; (c) Across areas accessible to pedestrians 3.5 m Protection of Electrical Equipment. Mechanical protection of electrical equipment shall be acceptable for the conditions of use for the particular location. Grounding Grounding. The service and electrical distribution shall be grounded in accordance with Section 10 of this Code Equipment Bonding (I) Exposed lion-current-carrying metal parts of fixed electrical equipment such as motor frames, starters and switch boxes; parts of rides, conces sions and ticket booths and moving electrically operated equipment shall be bonded to ground by: (a) Means of the bonding conductor in the supply cord, or (b) Connection to a separate insulated flexible copper bonding conductor, sized in accordance with Table 16, and connected to the grounded circuit conductor at the service disconnect. (2) Cord connected operator controlled remote stations shall be bonded to ground Service Equipment Services and Distribution ( I ) Service equipment shall be of a size suitable for the connected load. (2) Where accessible to unauthorized persons enclosures for service equipment shall be lockable. (3) Generators shall not be accessible to unauthorized persons. 6
8 Mounting of Service Equipment. Service equipment shall be mounted on a solid backing and: (a) Be located so as to be protected from the weather; or (b) Be installed in a weatherproof enclosure; or (c) Be of weatherproof construction Distribution Equipment (I) Each concession and ride shall be provided with a fused disconnect switch or circuit breaker. (2) Where accessible to unauthorized persons, enclosures for switches, panelboards and splitters shall be lockable. Wiring Methods and Equipment Wiring Methods (I) Except as permitted in Rules to , wiring methods shall be in accordance with Section 12 and suitable for the condition of use. (2) Cords, cables, conduits and other electrical equipment shall be protected from physical damage. (3) Flexible supply cords shall be of the extra hard usage type and: (a) Provided with strain relief where they enter into enclosures and connectors; and (b) If exposed to the weather, be of a type suitable for outdoor use. (4) Terminations and connections for both multiconductor and singleconductor cables shall: (a) Be made using approved connectors and receptacles; and (b) Be rated in amperes and designed so that differently rated devices cannot be connected together; and (c) Have the female half attached to the load end of the power supply cord or cable; and (d) if ac iiiulticonductor, be polarized. (5) Notwithstanding Paragraph (4) (c), with special permission the grounded conductor and the bonding conductor shall be permitted to have the female half connected to the supply end of the power supply cord or cable. (6) With the exception of amusement parks, midways, carnivals, home shows, and tent meetings, receptacles rated 15 Amp, conforming to CSA configuration 5- I 5R rated 120 Volt, hospital grade and protected by a fuse or circuit breaker 7
9 rated not greater than 20 Amp, shall be permitted for temporary lighting installations within the scope of this Section of the Code, where the loads are of an intermittent nature and where the connected load is not greater than 2,000 Watts. (7) Refer to Rules , , and for temporary wiring for portable stage equipment Equipment (I) Lighting streamers shall be made up of extra hard usage outdoor flexible cord with pin type sockets or with pig tail sockets attached to the cord by acceptable means. (2) Fluorescent fixtures shall not be mounted end-to-end unless they are marked for that purpose. (3) Incandescent lampholders shall be of the screw base type. (4) Utilization equipment shall only be installed in locations for which it is approved, unless suitable precautions are taken to protect it from inclement weather. Single-Conductor Cables Single-Conductor Cables. Single-conductor cables shall be permitted in sizes No. 4 AWG and larger providing they are: (a) Of suitable voltage and of a type acceptable for this use; and (b) Of a matched set with the same length for all conductors of the circuit including the bonding conductor; and (c) Covered or guarded so as not to present a tripping hazard in pedestrian walkways or roadways Maximum Available Fault Current. Systems employing single-conductor cables shall have the available fault current limited to 10,000 Amps Free Air A m pacity (I) Single-conductor cables that are bundled or installed in close proximity to one another shall be rated as multi-conductor cables in accordance with Section 4. (2) Notwithstanding Subrule (1), for temporary installations free-airrated single-conductor cables of any one circuit shall be permitted to be installed without spacing if different circuits are separated by at least one cable bundle diameter. 8
10 Single-Conductor Cable Connections (1) Connections to single-conductor cables shall not be accessible to unqualified persons. (2) Plug-in connectors for single-conductor cables shall' (a) Incorporate a locking cam design; and (h) Incorporate a mechanical interlock to prevent wrong connections or be color coded. (3) Single-conductor cables shall not be connected in parallel except as a means of reducing voltage drop, and cables so connected shall have overcurrent protection sized to protect the cable s 'h the smallest ampacity as though it were used alone Bonding. Each circuit incorporating single-conductor cables shall include a bonding conductor which shall be nth with the circuit conductors. Motors Motors. Motors, including protection and control, shall be installed in accordance with Section Location. Motors shall be installed only in dry locations unless they are of a type specifically marked for the location Portable Motors. Connections to portable motors shall be permitted to be made with flexible cord that shall have a serviceability not less than Type SOW for outdoor use. 17. Section 68 is amended (a) in Rule by adding "and to pools and spas supplied by a common water circulating system" after "spas and hot tubs", and (b) in Rule by striking out Subrule (3). 18. Section 84 is amended by striking out Rule Table 50 is repealed. 20. Appendix B is amended by striking out the note for Rule
Article 225: Outside Branch Circuits And Feeders
Part C: Code Book Questions Article 225: Outside Branch Circuits And Feeders 1.! Open (individual) aerial overhead conductors shall be insulated or covered when within! feet of a building.! (a) 10! (c)
More informationMECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 9/8/10 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions
conduit? 9/8/10 ELECTRICAL CONSISTENCY MEETING Code Consistency Questions 1. Can branch circuits of different services be installed in the same Yes, see 300.3(C)(1) for conductors of different systems
More informationMECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 2/9/11 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions
MECKLENBURG COUNTY Land Use and Environmental Service Agency Code Enforcement 2/9/11 ELECTRICAL CONSISTENCY MEETING Code Consistency Questions 1. I have a 500 KVA generator, with no overcurrent protection
More informationNational Marine Manufacturers Association Compliance Specialist Examination A.C. Electrical (2018 Model Year) ABYC E-11 Supplement 56
1. Two Electrical Technicians are discussing markings that are required for AC wiring. Tech A says that AC conductors must be rated for 600 volts and must have their jackets and individual conductors marked
More informationNEC 2014 Code Changes
NEC 2014 Code Changes Articles 200-215.3 CHANGES FROM 2011 CODE ARE IN RED Chapter 2 - Wiring and Protection ARTICLE 200 Use and Identification of Grounded Conductors 200.2 General Grounded Conductors
More informationJourneyman's Practice Exam
Journeyman's Practice Exam [Time limit 4.0 hrs.] (The test is open book. I've started at the front of the Code Book and worked toward the back for instructional purposes. The real test will not be in order
More informationAmerican Electrical Institute
American Electrical Institute Oregon Electricians Continuing Education Grounding & Bonding (Article 250) 4 Hours American Electrical Institute PO Box 31131 Spokane, WA 99223 www.aeitraining.com Article
More informationChapter 1. Applied Grounding and Bonding. Applied Grounding and Bonding 9/18/2011. Introduction. Introduction. Paul Dobrowsky Member NEC Panel 5
Applied Grounding and Bonding Paul Dobrowsky Member NEC Panel 5 1 Introduction This presentation is a representative sample from the following Chapters of Applied Grounding and Bonding. Chapter 1, Introduction
More informationCHAPTER 2 Wiring and Protection. Article 200 Use and Identification of Grounded Conductors
ARTICLE 200 USE AND IDENTIFICATION OF GROUNDED CONDUCTORS 70 35 CHAPTER 2 Wiring and Protection Article 200 Use and Identification of Grounded Conductors 200-1. Scope. This article provides requirements
More informationPart VIII Electrical GENERAL REQUIREMENTS CHAPTER 33
Part VIII Electrical CHAPTER 33 GENERAL REQUIREMENTS < SECTION E3301 GENERAL E3301.1 Scope. The installation of electrical systems, equipment and components indoors and outdoors that are within the scope
More informationNOTICE OF RULE MAKING PROCEEDINGS AND PUBLIC HEARING
1 1 1 1 1 NOTICE OF RULE MAKING PROCEEDINGS AND PUBLIC HEARING NORTH CAROLINA BUILDING CODE COUNCIL Notice of Rule-making Proceedings is hereby given by NC Building Code Council in accordance with G.S.
More information2014 NEC Changes Part 1
www.garyklinka.com Page 1 of 8 Instructions: Fee $20 1. Print these pages. 2. Circle the correct answers and transfer them to the answer sheet. 3. Page down to the last page for the verification forms
More informationArticle 250 Grounding & Bonding
Article 250 Grounding & Bonding AMERICAN ELECTRICAL INSTITUTE N16 W23217 Stone Ridge Dr. Waukesha, WI 53188 855-780-5046 www.aeitraining.com DISCLAIMER NOTE: This course is APPROVED for continuing education
More informationAlternating Current Power
Chapter 4 Alternating Current Power MElec-Ch4-1 Overview What is Alternating Current AC Hazards AC Power Requirements Shoreside Utility System On-Board Generators MElec-Ch4-2 What is Alternating Current
More informationELPT 1429 RESIDENTIAL WIRING
SYLLABUS ELPT 1429 RESIDENTIAL WIRING INDUSTRIAL AND COMMERCIAL ELECTRICITY BRAZOSPORT COLLEGE LAKE JACKSON TEXAS PREPARED BY: Larry Grable DATE: September 13, 2005 INSTRUCTOR RECOMMENDED BY: RECOMMENDED
More informationMichigan State University Construction Standards SWITCHBOARDS, PANELBOARDS, AND CONTROL CENTERS PAGE
PAGE 262400-1 SECTION 262400 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationWisconsin Contractors Institute Continuing Education
IMPORTANT NOTE: You should have received an email from us with a link and password to take your final exam online. Please check your email for this link. Be sure to check your spam folder as well. If you
More informationa) Determine the smallest, standard-sized circuit breaker that should be used to protect this branch circuit.
ECET4520 Exam II Sample Exam Problems Instructions: This exam is closed book, except for the reference booklet provided by your instructor and one (8.5 x11 ) sheet of handwritten notes that may not contain
More informationWiring Methods, Components, and Equipment for General Use -- OSHA Standard
ABE285 Wiring Methods, Components, and Equipment for General Use -- OSHA Standard 1910.305 1 Carol J. Lehtola, Charles M. Brown, and William J. Becker 2 The Impact of Safety on Florida Agriculture Florida
More informationFINAL - IT 30 ELECTRICAL INSPECTOR EXAMINATION ANSWER SCHEDULE. Question 1 Marks Reference Marking notes. (2 marks) EA 2
FINAL - IT 30 ELECTRICAL INSPECTOR EXAMINATION ANSWER SCHEDULE Notes:1. (1 mark) means that the preceding statement/answer earns 1 mark. 2. This schedule sets out the expected answers to the examination
More information1 Exam Prep NFPA 70: National Electric Code 2011 Tabs and Highlights
1 Exam Prep NFPA 70: National Electric Code 2011 Tabs and Highlights These 1 Exam Prep Tabs are based on NFPA 70: National Electrical Code, 2011. Each 1 Exam Prep Tabs sheet has five rows of Tabs. Start
More informationElectrical Wiring: Commercial, Seventh Canadian Edition
Electrical Wiring Commercial Canadian 7th Edition Mullin SOLUTIONS MANUAL Full download at: https://testbankreal.com/download/electrical-wiring-commercialcanadian-7th-edition-mullin-solutions-manual/ Unit
More informationContinued from Part 1 Rules 1 25.
Continued from Part 1 Rules 1 25. 26 225.32 Disconnect Location The disconnecting means for a building or structure must be installed at a readily accessible location, either outside the building or structure
More information2017 NEC TABLE OF CONTENTS
Article 90 Introduction 90.1 Purpose (A) Practical Safeguarding (B) Adequacy (C) Relation to Other International Standards 90.2 Scope (A Covered (B) Not Covered (C) Special Permission 90.3 Code Arrangement
More informationUNION COUNTY ENGINEER DIVISION OF BUILDING REGULATIONS
UNION COUNTY ENGINEER DIVISION OF BUILDING REGULATIONS Residential Pool Permit Requirements FEES: A nonrefundable permit application fee of $25.25 and a nonrefundable plan review fee of $40.40 will be
More informationPREFACE ********************************************************** IT IS NOT INTENDED THAT THESE STANDARDS BE COPIED AND USED AS A SPECIFICATION!
PREFACE This publication has been prepared as a guide for Architectural and Engineering (A&E) firms in the preparation of documents for the design and construction of new structures and the remodeling
More informationSECTION OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 05 73 OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY SPEC WRITER NOTE: Delete between // -- // if not applicable to project. Also, delete any other item or
More informationSOLAR PV MICROINVERTER/ACM STANDARD PLAN - COMPREHENSIVE Microinverter and ACM Systems for One- and Two- Family Dwellings
SOLAR MICROINVERTER/M STANDARD PLAN - COMPREHENSIVE Microinverter and M Systems for One- and Two- Family Dwellings SCOPE: Use this plan ONLY for systems using utility-interactive Microinverters or Modules
More information1. All electrical switches and outlets used shall be equal to Hubbell heavy duty, specification grade or equivalent quality.
PART 1: GENERAL 1.01 Wiring Devices A. This section of the standard includes design requirements for wiring connections, including receptacles and switches to equipment specified in other sections. 1.02
More informationGROUNDED ELECTRICAL POWER DISTRIBUTION. Excerpt from Inverter Charger Series Manual BY: VIJAY SHARMA ENGINEER
GROUNDED ELECTRICAL POWER DISTRIBUTION Excerpt from Inverter Charger Series Manual BY: VIJAY SHARMA ENGINEER .0 Conductors for Electrical Power Distribution For single-phase transmission of AC power or
More informationECET Fall 2017 Name: _ Lab Assignment #01
ECET 4520 - Fall 2017 Name: _ Lab Assignment #01 General Instructions: This assignment is to be completed individually. All answers/work required for each problem should be neatly written in the space
More informationSAFETY AND HEALTH STANDARD ELECTRICAL GROUNDING Effective Date: 07/17/10 Standard: Document Number: KUCSH0039 Rev: 4
SAFETY AND HEALTH STANDARD ELECTRICAL GROUNDING Effective Date: 07/17/10 Standard: 16.10 Document Number: KUCSH0039 Rev: 4 16.10.1 INTRODUCTION 16.10.1.1 The intent of this standard is to ensure that continuity
More informationElectrical IP Red Seal Practice Exam
Electrical IP Red Seal Practice Exam PRACTICE EXAM-3 1. What size 2 pole breaker must you use on a 3HP, 115V single phase motor? A. 40A B. 50A C. 80A. D. 100A. 2. An electrical equipment approved for use
More informationSECTION DISTRIBUTION SWITCHBOARDS
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 24 13 DISTRIBUTION SWITCHBOARDS SPEC WRITER NOTE: Delete between // -- // if not applicable to project. Also delete any other item or paragraph not applicable
More informationSECTION LOW-VOLTAGE ELECT. DIST. DESIGN AND CONSTRUCTION STANDARDS _ February 2015 PART I: GENERAL
PART I: GENERAL 1.01 Wiring Devices A. This section of the standard includes design requirements for wiring connections, including receptacles and switches to equipment specified in other sections. a.
More informationB. Manufacturers: Square-D, G.E. or Westinghosue.
SECTION 16470 - PANELBOARDS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. General: Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification
More informationCustomer Connection Guide Updates Effective May 2017
This document provides a list of the updates to the EPCOR Distribution and Transmission Inc. (EDTI) Customer Connection Guide. If you have any questions, please contact EDTI Customer Engineering Services
More informationINTELLIMETER REGISTER
INTELLIMETER REGISTER MODEL RG2 INSTALLATION AND CONNECTIONS INSTALLATION MANUAL WARNING: Any work on or near energized metering equipment can present a danger of electrical shock. All work on these products
More informationVI 3 - i TABLE OF CONTENTS
VI 3 - i TABLE OF CONTENTS 3 PROJECT SPECIFIC DATA... 1 3.1 DEFINITIONS... 1 3.1.1 Design Data, High and Medium Voltage... 1 3.1.2 Design Data, Low Voltage Equipment... 2 3.1.3 Phase Relationship... 3
More informationSECTION PANELBOARDS
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 24 16 PANELBOARDS SPEC WRITER NOTE: Delete between // --- // if not applicable to project. Also, delete any other item or paragraph not applicable in the section
More information2/15/2015. Current will always try to return to its source. In order for there to be current, there must be a complete circuit
Current will always try to return to its source In order for there to be current, there must be a complete circuit Current will take as many paths or circuits available to it to return to the source The
More informationFINAL - ER 70 Electrician Regulations Answer Schedule. Question 1 Marks Reference Marking notes
FINAL - ER 70 Electrician Regulations Answer Schedule Notes:1. (1 mark) means that the preceding statement/answer earns 1 mark. 2. This schedule sets out the expected answers to the examination questions.
More informationER 87 Electrician Regulations Answer Schedule. Question 1 Marks Reference Marking notes. (1 mark) ESR 27(2) (2 marks) ESR 74A(1AA)
ER 87 Electrician Regulations Answer Schedule Notes:1. (1 mark) means that the preceding statement/answer earns 1 mark. 2. This schedule sets out the expected answers to the examination questions. The
More informationFTTH ENGINEERING AND INSTALLATION INTRODUCTION
1 FTTH ENGINEERING AND INSTALLATION INTRODUCTION GROUNDING FTTH SYSTEMS AT THE HOME. By Dean Mischke, P.E., V.P. Grounding and bonding. Why are we worried about such an old school concept in the modern
More informationTABLE OF CONTENT
Page : 1 of 34 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia TABLE OF CONTENT SCOPE 3 REFERENCES
More informationS&C Series 2000 Circuit-Switchers Outdoor Transmission (69 kv through 230 kv)
Outdoor Transmission (69 kv through 230 kv) Detailed Functional Specification Guide 1.0 GENERAL 1.01 The circuit-switcher shall conform to the following specification. 1.02 The circuit-switcher shall be
More informationCONTINUING EDUC ATION
3 CONTINUING EDUC ATION FOR WISCONSIN ELECTRICIANS 2017 NEC Article 250 2 Hours WISCONSIN CONTRACTORS INSTITUTE N16 W23217 Stone Ridge Drive Suite 290 Waukesha, WI 53188 262-409-4282 www.wcitraining.com
More informationpower Knowledge The Hager Guide to current thinking on the regulations, protection and control of Klik lighting circuits.
Knowledge is power The Hager Guide to current thinking on the regulations, protection and control of Klik lighting circuits. Written by: Paul Sayer Technical Standards Manager for Hager Contents 2 Conductor
More informationELECTRIC GROUNDING AND WIRING REQUIREMENTS BOOTHS-METAL
BELL SYSTEM PRACTICES Plant Series SECTION 508-100-100 Issue 3, October 1970 AT&TCo Standard ELECTRIC GROUNDING AND WIRING REQUIREMENTS BOOTHS-METAL I. GENERAL 1.01 This section is reissued to: Revise
More informationUNITY/I TM. Installation Manual. UT3K, UT4K, UT5K and UT8K. Single-Phase Uninterruptible Power Systems
UNITY/I TM UT3K, UT4K, UT5K and UT8K Single-Phase Uninterruptible Power Systems Installation Manual MLS-0351C-OL Copyright 1994-1997 Best Power. All rights reserved. å IMPORTANT SAFETY INSTRUCTIONS! SAVE
More informationDepartment of Labor and Industry Electrical Licensing
Department of Labor and Industry Electrical Licensing License Examination Guide The information in this guide is provided by the Licensing Unit of the Department of Labor and Industry to ensure that applicants
More informationELECTRICIAN S THEORY EXAMINATION 17 November 2012 QUESTION AND ANSWER BOOKLET
Candidate Code No. ET43 For Board Use Only Result Date Int Result Date Int ELECTRICIAN S THEORY EXAMINATION 17 November 2012 QUESTION AND ANSWER BOOKLET INSTRUCTIONS READ CAREFULLY Time Allowed: Three
More information7 o/c4 - To meet the requirements of BS 7671, all fault current protective devices without back-up protection on the supply side must be capable of:
1 PAPER 5 Sample Questions A- C&G 2382 17th Edition Paper A 1 o/c1 BS 7671 does not apply to a equipment of aircraft b photovoltaic systems c marinas d fairgrounds. 2 o/c1 Where protection for persons
More informationWe have 3 ways to help you prepare
P a g e 2 Texas Electrical Excel is your source for obtaining your license state exam. Call us if you have questions regarding your applications, exam preparation, exam registration and more. We have reached
More informationNATIONAL RULES FOR ELECTRICAL INSTALLATIONS. Fourth Edition. Extracts from Amendment No.1: June 2011
NATIONAL RULES FOR ELECTRICAL INSTALLATIONS Fourth Edition ET 101:2008 Extracts from Amendment No.1:2011 22 June 2011 Page vi: Insert after 1 st Paragraph: Section 710: Medical Locations was prepared by
More informationCONSULTANT PROCEDURES & DESIGN GUIDELINES Liquid-Filled Utility Transformers UNIVERSITY OF MISSOURI
GENERAL: The scope of this document is to provide instruction for the installation and testing of Medium Voltage, 3 Phase, Pad Mounted Transformers installed at the University of Missouri. Preferred transformers
More informationLow Voltage Power Factor Correction Equipment Specifications Automatic, Automatic Detuned, Automatic Tuned
Low Voltage Power Factor Correction Equipment Specifications Automatic, Automatic Detuned, Automatic Tuned Part 1 - General Scope and Product Description 1.0 This specification contains the minimum design
More informationCapstone Turbine Corporation Nordhoff Street Chatsworth CA USA Phone: (818) Fax: (818) Web:
Phone: (818) 734-5300 Fax: (818) 734-5320 Web: www.capstoneturbine.com Technical Reference Capstone MicroTurbine Electrical Installation 410009 Rev F (October 2013) Page 1 of 31 Capstone Turbine Corporation
More informationLicensed Electricians Practical Assessment (LEP)
Licensed Electricians Practical Assessment (LEP) Surname: Given Names: Date: Time: Location: Assessment Time (includes reading and preparation time): At the end of this time you will be asked to stop.
More informationAN EXAMPLE OF A STANDARD ARC FLASH PPE LABELING STRATEGY
The Electrical Power Engineers Qual-Tech Engineers, Inc. 201 Johnson Road Building #1 Suite 203 Houston, PA 15342-1300 Phone 724-873-9275 Fax 724-873-8910 www.qualtecheng.com AN EXAMPLE OF A STANDARD ARC
More informationEASQ ELECTRICAL APPLIANCE SERVICEPERSON (QUALIFIED) MARKING SCHEDULE. SECTION 1 Marks Reference Marking notes Qu 1 A 10 MΩ (2 marks)
EASQ ELECTRICAL APPLIANCE SERVICEPERSON (QUALIFIED) MARKING SCHEDULE Notes: 1. (1mark) means that the preceding statement/answer earns 1 mark. 2. This schedule sets out the expected answers to the examination
More informationGeneration Interconnection Requirements at Voltages 34.5 kv and Below
Generation Interconnection Requirements at Voltages 34.5 kv and Below 2005 March GENERATION INTERCONNECTION REQUIREMENTS AT 34.5 KV AND BELOW PAGE 1 OF 36 TABLE OF CONTENTS 1. INTRODUCTION 5 1.1. Intent
More informationLicensed Electricians Practical Assessment (LEP)
Licensed Electricians Practical Assessment (LEP) Surname: Date: Given Names: Time: Assessment Time (includes 10 minutes reading time): At the end of this time you will be asked to stop. 4 hours Have you
More informationPOWER SERVICE DETAILS
POWER SOURCE # POLE MOUNTED SERVICE TRANSFORMER BY POWER HANDHOLE 0/0V, -PHASE, SERVICE CONDUCTORS; -# AWG SERVICE CONDUCTOR AND -# AWG GROUNDED SERVICE CONDUCTOR (NEUTRAL) SERVICE XFMR SECONDARY. A 0V
More informationPage Electric Utility Service Specifications
T Y P I C A L U N D E R G R O U N D S E R V I C E R E Q U I R E M E N T S 200 Amps Maximum - UG-1 Sheet 1 of 3 87 T Y P I C A L U N D E R G R O U N D S E R V I C E R E Q U I R E M E N T S 200 Amps Maximum
More informationSERVICING & METERING SERVICING AND METERING SECTION 5 SEC5:
SECTION SERVICING AND METERING SECTION 1. SERVICING.... NST IMPEDANCE TESTING.... METERING... General Requirements.... CT METERING... 8 CT Metering General Requirements... 8 Existing Installation Alterations
More informationElectrical Occupations
Job Ready Assessment Blueprint Electrical Occupations Test Code: 3029 / Version: 01 Copyright 2011. All Rights Reserved. General Assessment Information Blueprint Contents General Assessment Information
More informationWiring of the Main Distribution Panelboard
Job Sheet 4 Wiring of the Main Distribution Panelboard OBJECTIVE To connect the service-entrance conductors. To ground the main distribution panelboard (MDP). To wire a branch circuit supplying a three-phase
More informationBulletin Voltage drop in single dwelling units Rule 8-102
Bulletin 8-6-0 Voltage drop in single dwelling units Rule 8-102 Scope Issued February 2014 (1) Background (2) Application of voltage drop for branch circuits in single dwelling units a) Determination of
More informationSTANDARD COMMENTS 2016 ELECTRICAL PLAN REVIEW CHECK LIST
STANDARD COMMENTS 2016 ELECTRICAL PLAN REVIEW CHECK LIST Item Comments 1. The electrical plan check is approved and ready to have the electrical permit issued, pending the building permit being issued.
More informationShort Circuit Current Calculations
Introduction Several sections of the National Electrical Code relate to proper overcurrent protection. Safe and reliable application of overcurrent protective devices based on these sections mandate that
More informationSECTION 5 TRANSFORMERS
SECTION 5 TRANSFORMERS Necessary transformers will be installed and maintained by The City of Aspen. The City of Aspen will not furnish transformers unless they are of standard size and voltage as established
More information3Ø Short-Circuit Calculations
3Ø Short-Circuit Calculations Why Short-Circuit Calculations Several sections of the National Electrical Code relate to proper overcurrent protection. Safe and reliable application of overcurrent protective
More informationUNIVERSITY OF MISSOURI Liquid-Filled Utility Transformers 2016 Q1
GENERAL: The scope of this document is to provide instruction for the installation and testing of Medium Voltage, 3 Phase, Pad Mounted Transformers installed at the University of Missouri. Preferred transformers
More informationSUPPLEMENTARY INSTALLATION INSTRUCTIONS Ventilating Fan (Contractor Pack)
SUPPLEMENTARY INSTALLATION INSTRUCTIONS Ventilating Fan (Contractor Pack) Model No. FV-08VSLA2 Contents Housing Can FV-08VSLA2 General Safety lnformation Unpacking Supplied Accessories Wiring Diagram lnstallation
More informationSECTION SHORT CIRCUIT, COMPONENT PROTECTION, FLASH HAZARD AND SELECTIVE COORDINATION STUDY
SECTION 16075 - SHORT CIRCUIT, COMPONENT PROTECTION, FLASH HAZARD AND SELECTIVE COORDINATION STUDY PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Provide a short-circuit, component protection, flash
More informationEDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS
ENGINEERING DESIGN STANDARD EDS 08-2109 LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS Network(s): Summary: EPN, LPN, SPN This standard provides guidance on the installation of
More informationModule 2 Unit 6, 7, 8
Module 2 Unit 6, 7, 8 1. What is the definition of an ideal conductor? Material that will carry the greatest current with the lowest temperature rise 2. How much does copper weigh compared to aluminum?
More informationConstruction Electrician/Industrial Electrician/Power Electrician Common Core Level 2
Common Core Level 2 Unit: B1 Commercial Electrical Code Level: Two Duration: 60 hours Theory: Practical: 60 hours 0 hours Overview: This unit is designed to provide the apprentice with the knowledge about
More informationLIFE LINE PRODUCT SPECIFICATION FOR A 1 TO 3 KVA, SINGLE PHASE, POWER DISTRIBUTION SYSTEM WITH REGULATION AND CONDITIONING
LIFE LINE PRODUCT SPECIFICATION FOR A 1 TO 3 KVA, SINGLE PHASE, POWER DISTRIBUTION SYSTEM WITH REGULATION AND CONDITIONING 1.0 General This specification covers the electrical characteristics and general
More informationDIVISION 26 ELECTRICAL SECTION ELECTRICAL
DIVISION 26 ELECTRICAL SECTION 26 1000 ELECTRICAL PART 1 - GENERAL 1.1 WORK INCLUDED A. Furnish all labor, material and equipment necessary for the complete installation of the Electrical System as shown
More informationVariable Transformers Product Design & Engineering Data
Variable Transformers Product Design & Engineering Data Product Design & Engineering Data Type 1010B Cutaway General Information STACO ENERGY PRODUCTS CO. is a leading manufacturer of variable transformers,
More informationSECTION DISTRIBUTION SWITCHBOARDS
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 26 24 11 SPEC WRITER NOTES: Use this section only for NCA projects. Delete between // -- // if not applicable to project. Also delete any other item or paragraph
More informationResidential Construction Checklist Single and Two Family Construction
DATE: _ Building Inspection Submittal Requirements Residential Construction Checklist Single and Two Family Construction Submit a City of Big Spring Permit Application, checklist, and 3 complete hard copy
More informationHigh Frequency Sinewave Guardian TM Filter
High Frequency Sinewave Guardian TM Filter 380V 480V TECHNICAL REFERENCE MANUAL FORM: SHF-TRM-E REL. April 2015 REV. 001 2015 MTE Corporation Caution Prior to start up; confirm the drive operation mode
More informationLes Hampson Cert Ed FSCTE, Chairman CAI Technical Committee
Making the Bond Les Hampson Cert Ed FSCTE, Chairman CAI Technical Committee After many man hours of deliberation and consultation the Code of Practice Electrical Safety Requirements for Signal Reception
More informationThe Importance of the Neutral-Grounding Resistor. Presented by: Jeff Glenney, P.Eng. and Don Selkirk, E.I.T.
The Importance of the Neutral-Grounding Resistor Presented by: Jeff Glenney, P.Eng. and Don Selkirk, E.I.T. Presentation Preview What is high-resistance grounding (HRG)? What is the purpose of HRG? Why
More informationUniversity of Central Florida Main Campus. Electric. Service and Meter Installations Requirements. Issued January 26 th, 2017.
University of Central Florida Main Campus Electric Service and Meter Installations Requirements Issued January 26 th, 2017 1 P a g e Table of Contents 1. GENERAL INFORMATION... 3 2. DEFINITIONS... 3 3.
More informationBGE STRATEGIC CUSTOMER ENGINEERING
TABLE OF CONTENTS 1. GENERAL. 2 2. BGE SUPPLY FEEDER. 4 3. SWITCHGEAR ENCLOSURE AND ASSEMBLY. 5 4. CIRCUIT BREAKER. 9 5. SWITCHGEAR EQUIPMENT... 10 6. MAIN AND GROUND BUS.... 15 7. GROUND AND TEST DEVICE.
More informationChapter 25. Lighting Plans
Chapter 25 Lighting Plans The following are changes, additions or deletions to the January 2014, Topic #625-000-008, Plans Preparation Manual (PPM), for use on Turnpike projects only. 25.1 General Replace
More informationEducation & Training
Distribution System Operator Certificate This program provides you with a proficient working knowledge in modern electric power distribution systems. These four classes are designed to walk students through
More informationSAUDI STANDARD NO. SASO IEC : 2007 SWITCHES FOR HOUSEHOLD AND SIMILAR FIXED ELECTRICAL INSTALLATIONS
SAUDI STANDARD NO. SASO IEC 60669-2-2: 2007 SWITCHES FOR HOUSEHOLD AND SIMILAR FIXED ELECTRICAL INSTALLATIONS Part 2-2: Particular requirements Electromagnetic remote-control switches (RCS) SAUDI ARABIAN
More informationSECTION EQUIPMENT WIRING
PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 26 27 17 EQUIPMENT WIRING A. The Conditions of the Contract and applicable requirements of Divisions 0 and 1 and Section 26 00 01, Electrical General Provisions,
More information3.1 Overview of ATCO Electric s URD System Design
Page: 3-1 3.0 URD DESIGN GUIDELINES 3.1 Overview of ATCO Electric s URD System Design ATCO Electric s design for distribution power supply to URD areas is a primary looped supply system. This is generically
More informationSINGLE-PHASE VSV SWITCH
May 2006 Supercedes: March 2006 SINGLE-PHASE VSV SWITCH INSTALLATION AND OPERATING MANUAL Table of Content: Page I. General...2 II. Specifications...2 III. Installation...2 IV. Maintenance...4 V. VSV Power
More informationMinorWorks/Single Circuit Electrical Certificate
MinorWorks/Single Circuit Electrical Certificate Requirements for Electrical Installations BS767 [IET Wiring Regulations] Information for recipients : This safety Certificate for Minor Works/ Single Circuit
More informationECET 211 Electric Machines & Controls Lecture 3-1 (Part 1 of 2) Motor Transformers and Distribution Systems
ECET 211 Electric Machines & Controls Lecture 3-1 (Part 1 of 2) Motor Transformers and Distribution Systems Text Book: Electric Motors and Control Systems, by Frank D. Petruzella, published by McGraw Hill,
More informationElectrical Measurement Safety. Sponsored By:
Electrical Measurement Safety Sponsored By: About the Viewer Panel Slides: Go to the Links tab at the top and click on the link to download the PDF of the slides If you re watching the archive version,
More informationCanadian Standards Association Mississauga, Ontario To the Part I Committee
Canadian Standards Association Mississauga, Ontario To the Part I Committee Subject No. 3130 Chair: R. Leduc Date: December 24, 2003 Title: Receptacles in Residential Occupancies, Rules 26-710, 26-712,