1 Contacts: CubeSat Test Pod User s Guide Revision IV June, 2005 Cal Poly, San Luis Obispo Stanford University Prof. Jordi Puig-Suari Prof. Bob Twiggs, Director Aerospace Engineering Dept. Space Systems Development Lab. (SSDL) (805) Dept. of Aeronautics and Astronautics (805) fax (650) jpuigsua@calpoly.edu (650) fax btwiggs@leland.stanford.edu CubeSat Student Lead: Armen Toorian atoorian@calpoly.edu Official Website:

2 1.0 INTRODUCTION The Test Pod in Figure 1.1 is to be used by CubeSat developers as an environmental simulation of the P-Pod deployer shown in Figure 1.2, this will allow validation of the structural integrity of CubeSats under launch loads. The Test Pod interior is designed to simulate the environment inside the P-Pod deployer. The Test Pod allows CubeSat developers to test their satellites to the environment inside the P-POD deployer rather than designing to the launch vehicle loads. Top Panel Spring Plungers Load Plate Figure 1.1 Test Pod

3 Figure 1.2 P-POD CubeSat Deployer The Test Pod is not a fit check. CubeSats that do not meet the CubeSat Specifications (See Attached) may still fit in the Test Pod. The developers are responsible for meeting the engineering specifications. 2.0 DESCRIPTION The Test Pod interface control drawing is shown in Figure 2.1, this provides the necessary dimensions for adapting to your head plate. A Test Pod axis convention is also included in Figure 2.1, this will allow CubeSat developers to document and share results in a common format.

4 Figure 2.1 Test Pod Interface Control Drawing During the Z-Axis sine sweep test, the fundamental resonance was detected at roughly 600 Hz. Sine sweep tests repeatedly produced the fundamental frequencies shown below in Table 5.1. Fundamental Frequencies (Hz) X-AXIS Z-AXIS Test Pod Table 2.1 Natural Frequencies for 2 axes of the Test Pod

5 The intent is for CubeSat developers to share information learned during testing. Cal Poly will do its best to make all results available in future updates of this document. 3.0 ENVIRONMENTS 3.1 Sine Sweep The sine sweep test is recommended to include all available frequencies up to 2kHz. 3.2 Random A random vibration profile is not provided since a launch vehicle is not currently secured. CubeSat developers can obtain random vibration spectral densities to input to their shake table controller by referencing launch vehicle users guides. Some guides can be found on web sites such as: Future revisions of this document will include a worst-case spectral density based on launch vehicles that have been investigated by CubeSat.

6 4.0 PROCEDURES The following is a recommended procedure based on vibration tests performed at Cal Poly using a horizontal shake table. Individual circumstances will require the customer to amend these procedures. 1) Remove the top panel from the test pod assembly 2) Measure the thickness of the top plate and the load plate (see Figure 4.1) 3) Insert the load plate 4) Replace the top panel and start all top panel fasteners by hand 5) Lightly tighten the screws so that the panel is correctly aligned 6) Torque the screws until they are flush 7) Adjust spring plungers to the proper height: Height = Total Test Pod Height Satellite Height (at each rail) Pusher Plate Thickness Top Plate Thickness H = A B C D See Figure 4.1 for dimension labels.

7 Figure 4.1 Test Pod and Mass Model Dimensions Note that dimension B needs to be measured four times, once for each rail. The pitch of the spring plungers is 20 threads per inch. Therefore, to achieve the correct height, insert the spring plungers while keeping track of the number of full rotations. One rotation is a 20th of an inch. Starting from when the spring plungers grab the threads, use this information to calculate how many turns are required to reach the desired height. 8) Take precaution in mounting the Test Pod to the interface (head) plate as well as mounting the interface (head) plate to the test platform 9) Be sure to check all fasteners and data lines between tests to ensure a safe operating environment and accurate results 10) Mount the Test Pod to the interface (head) plate for testing 11) Orient Test Pod properly for testing of z-axis. Refer to Figure ) Check all fasteners and accelerometers are securely fastened 13) Input sine-sweep parameters for z-axis into controller and run 14) Inspect all fasteners and accelerometers for loosening or damage 15) Input random vibration parameters for z-axis into controller and run

8 16) Inspect all fasteners and accelerometers for loosening or damage 17) Confirm your requirements are met 18) Reorient Test Pod to test x-axis. Refer to Figure ) Input sine-sweep parameters for x-axis into controller and run 20) Inspect all fasteners and accelerometers for loosening or damage 21) Input random vibration parameters for x-axis into Controller and run 22) Inspect all fasteners and accelerometers for loosening or damage 23) Confirm requirements are met 24) Remove CubeSat and reorient in order to test the y-axis or mount the Test Pod accordingly and repeat steps 2-7

Test Pod User s Guide

Test Pod User s Guide Document Classification X Public Domain ITAR Controlled Internal Only Test Pod User s Guide Revision Date Author Change Log 6 11/6/2006 Jonathan Brown Moved to standard document format 1 of 6 1 Introduction

More information

CubeSat Design Specification

CubeSat Design Specification Document Classification X Public Domain ITAR Controlled Internal Only CubeSat Design Specification (CDS) Revision Date Author Change Log 8 N/A Simon Lee N/A 8.1 5/26/05 Amy Hutputanasin Formatting updated.

More information

Development of Random Vibration Profiles for Test Deployers to Simulate the Dynamic Environment in the Poly-Picosatellite Orbital Deployer

Development of Random Vibration Profiles for Test Deployers to Simulate the Dynamic Environment in the Poly-Picosatellite Orbital Deployer Development of Random Vibration Profiles for Test Deployers to Simulate the Dynamic Environment in the Poly-Picosatellite Orbital Deployer Steve Furger California Polytechnic State University, San Luis

More information

Poly Picosatellite Orbital Deployer Mk. III Rev. E User Guide

Poly Picosatellite Orbital Deployer Mk. III Rev. E User Guide The CubeSat Program California Polytechnic State University San Luis Obispo, CA 93407 X Document Classification Public Domain ITAR Controlled Internal Only Poly Picosatellite Orbital Deployer Mk. III Rev.

More information

CUBESAT P-Pod Deployer Requirements

CUBESAT P-Pod Deployer Requirements CUBESAT P-Pod Deployer Requirements May 2002 Authors: Isaac Nason Michelle Creedon Nick Johansen Introduction The CubeSat program is a joint effort between Cal Poly and Stanford Universities to develop

More information

Revision C June 5, Author: Ryan Connolly

Revision C June 5, Author: Ryan Connolly The P-POD Payload Planner s Guide Revision C June 5, 2000 Author: Ryan Connolly P-POD Payload Planner s Guide: Revision B 5/15/00 2 of 19 1. INTRODUCTION The Space Development, Manufacturing & Integration

More information

Making it Small. April 22-24, 24, Cal Poly Developers Workshop California State Polytechnic University San Luis Obispo, CA

Making it Small. April 22-24, 24, Cal Poly Developers Workshop California State Polytechnic University San Luis Obispo, CA Making it Small April 22-24, 24, 2009 2009 Cal Poly Developers Workshop California State Polytechnic University San Luis Obispo, CA Prof. Bob Twiggs Bob.Twiggs@Stanford.Edu What started the miniaturization

More information

Methods to predict fatigue in CubeSat structures and mechanisms

Methods to predict fatigue in CubeSat structures and mechanisms Methods to predict fatigue in CubeSat structures and mechanisms By Walter Holemans (PSC), Floyd Azure (PSC) and Ryan Hevner (PSC) 08-09 August 2015 12th Annual Summer CubeSat Developers' Workshop 08-09

More information

6U CubeSat Design Specification Revision 1.0

6U CubeSat Design Specification Revision 1.0 X Document Classification Public Domain 6U CubeSat Design Specification Revision 1.0 (CP-6UCDS-1.0) Page 1 CHANGE HISTORY LOG Effective Date Revision Description of Changes 04/20/16 X1 Provisional release

More information

Improving Launch Vibration Environments for CubeSats

Improving Launch Vibration Environments for CubeSats Improving Launch Vibration Environments for CubeSats Dave Pignatelli California Polytechnic State University, San Luis Obispo Small Satellite Conference, Logan, Utah August 8th, 2017 1 CubeSat Launch Environments

More information

CubeSats: From Launch to Deployment Necessity for a standard.

CubeSats: From Launch to Deployment Necessity for a standard. 1 Necessity for a standard. Creation of a standard to facilitate the design process of small satellites. Deployment system to support the standard. Safe and reliable. Efficient and cost effective. Versatile.

More information

The Future for CubeSats Present and Coming Launch Opportunities 18th Annual AIAA / USU Conference on Small Satellites CubeSat Workshop

The Future for CubeSats Present and Coming Launch Opportunities 18th Annual AIAA / USU Conference on Small Satellites CubeSat Workshop The Future for CubeSats Present and Coming Launch Opportunities 18th Annual AIAA / USU Conference on Small Satellites CubeSat Workshop Presented By: Armen Toorian California Polytechnic State University

More information

Grain Tank Cross Auger Trough Liner for John Deere 9400 / 9500 Combine

Grain Tank Cross Auger Trough Liner for John Deere 9400 / 9500 Combine www.polyskid.com P. O. Drawer 349, Monticello, GA. 31064 Phone: 800-542-7659, Fax: 706-468-2881 E-Mail: polytech@polyskid.com Grain Tank Cross Auger Trough Liner for John Deere 9400 / 9500 Combine FOR

More information

Assembly Manual for the 1.2m Quick-Deploy Antenna System

Assembly Manual for the 1.2m Quick-Deploy Antenna System 704 North Clark Street Albion, MI 49224 USA Phone +1 517 680 0125 Fax +1 517 680 0133 www.challengercommunications.com Challenger Communications Assembly Manual for the 1.2m Quick-Deploy Antenna System

More information

Coach Class to Orbit: the NPS CubeSat Launcher

Coach Class to Orbit: the NPS CubeSat Launcher Calhoun: The NPS Institutional Archive Faculty and Researcher Publications Faculty and Researcher Publications Collection 2009-08 Coach Class to Orbit: the NPS CubeSat Launcher Hicks, Christina http://hdl.handle.net/10945/37306

More information

USER MANUAL FOR HIGH POWER TEST FIXTURES AND CALIBRATION KITS (PRODUCT NOTE: B )

USER MANUAL FOR HIGH POWER TEST FIXTURES AND CALIBRATION KITS (PRODUCT NOTE: B ) The World Wide Authority in the Design and Manufacture of Microwave Test Fixtures USER MANUAL FOR HIGH POWER TEST FIXTURES AND CALIBRATION KITS (PRODUCT NOTE: B6141961) HIGH POWER TEST FIXTURE AND MIDSECTION

More information

Spindle Drive Belt - Tension Adjustment - Gates Sonic Meter

Spindle Drive Belt - Tension Adjustment - Gates Sonic Meter Spindle Drive Belt - Tension Adjustment - Gates Sonic Meter - Lathe LAST UPDATED: 09/19/2018 Spindle Drive Belt - Tension Adjustment - Gates Sonic Meter 1 Change the units to lbf, as follows: Hold [0]

More information

F-150 Structural Holding System

F-150 Structural Holding System F-150 Structural Holding System Users Manual December 2013 by Vehicle Service Group. All rights reserved. CO8812.2 502073 Rev. - 12/11/2013 CHIEF'S LIMITED ONE-YEAR WARRANTY & LIABILITY Chief Automotive

More information

Tactile Switch. Ordering Information. A Wide Range of Models: 6 x 6 mm, 12 x 12 mm, Vertical, and High-force.

Tactile Switch. Ordering Information. A Wide Range of Models: 6 x 6 mm, 12 x 12 mm, Vertical, and High-force. Tactile Switch A Wide Range of Models: 6 x 6 mm, 12 x 12 mm, Vertical, and High-force. A positive click action plus a long life equal to that of a no-contact switch. Radial models (taping specifications)

More information

Attitude Determination and Control Specifications

Attitude Determination and Control Specifications Attitude Determination and Control Specifications 1. SCOPE The attitude determination and control sub system will passively control the orientation of the two twin CubeSats. 1.1 General. This specification

More information

Flight Unit S/N 001 Environmental Vibration Test Report. Dwg. No

Flight Unit S/N 001 Environmental Vibration Test Report. Dwg. No Rev. ECO Description Author Approved Date 01 32-261 Initial Release M. Smith 12-6-07 Flight Unit S/N 001 Environmental Vibration Test Report Dwg. No. 32-06050.0101 Revision 01 December 8, 2007 32-0605.0101

More information

6U SUPERNOVA TM Structure Kit Owner s Manual

6U SUPERNOVA TM Structure Kit Owner s Manual 750 Naples Street San Francisco, CA 94112 (415) 584-6360 http://www.pumpkininc.com 6U SUPERNOVA TM Structure Kit Owner s Manual REV A0 10/2/2014 SJH Pumpkin, Inc. 2003-2014 src:supernova-rev00_20140925.doc

More information

Travel Trailer Latch With Dead Bolt Trailer Latch With Dead Bolt. U.S. Patent No. 5,927,773

Travel Trailer Latch With Dead Bolt Trailer Latch With Dead Bolt. U.S. Patent No. 5,927,773 60-250 Travel Trailer Latch With Dead Bolt 60-251 Trailer Latch With Dead Bolt Service Manual (Installation and Troubleshooting) U.S. Patent No. 5,927,773 CONTENTS 1. BASIC COMPONENTS 2. INSTALLATION OF

More information

INSTALLATION INSTRUCTIONS VENETIAN 84" SLIDING SHOWER DOOR SYSTEM (180º INSTALLATION)

INSTALLATION INSTRUCTIONS VENETIAN 84 SLIDING SHOWER DOOR SYSTEM (180º INSTALLATION) INSTALLATION INSTRUCTIONS VENETIAN 84" SLIDING SHOWER DO SYSTEM (180º INSTALLATION) 28539 Industry Drive, Valencia, CA 91355 Toll Free Phone: (877) 728-3874 Toll Free Fax: (888) 440-9567 Phone: (661) 775-1675

More information

NORMAN SHUTTERS INSTALLATION INSTRUCTIONS. Hang Strip. (Inside Mount 2 Panel) Getting Started

NORMAN SHUTTERS INSTALLATION INSTRUCTIONS. Hang Strip. (Inside Mount 2 Panel) Getting Started NORMAN SHUTTERS INSTALLATION INSTRUCTIONS Hang Strip (Inside Mount 2 Panel) Getting Started Recommended Tools: Nail Gun or Drill, Tape Measure, Torpedo Level, Box Knife, 6 Philips head driver Make sure

More information

A Failure Analysis of the ExoCube CubSat. 13 th Annual Cubesat Workshop San Luis Obispo, CA Wednesday, April 20 th, 2016

A Failure Analysis of the ExoCube CubSat. 13 th Annual Cubesat Workshop San Luis Obispo, CA Wednesday, April 20 th, 2016 A Failure Analysis of the ExoCube CubSat 13 th Annual Cubesat Workshop San Luis Obispo, CA Wednesday, April 20 th, 2016 1 Background To characterize Hydrogen, Helium, Nitrogen and Oxygen, ions and neutrals

More information

INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS INSTALLATION INSTRUCTIONS TOOLS REQUIRED Rechargeable, variable speed drill 3/8 diameter drill bit 3 Robertson bits #0, #1 and #2 Slot screwdriver Non marring hammer with 1 head Level Caulk or sealant

More information

ASSEMBLY INSTRUCTIONS

ASSEMBLY INSTRUCTIONS ASSEMBLY INSTRUCTIONS PRINTED IN USA Assembly Instructions Include: P/N: LL-04-5 Step : Site Preparation Step 0: Guard Rail Installation Step : Leg Assembly Step : Stairs Step 3-8: Setting the Stage Step

More information

45 CUTTING HEAD TILE SAW-BLADE ALIGNMENT PROCEDURE

45 CUTTING HEAD TILE SAW-BLADE ALIGNMENT PROCEDURE The of the MK-770 may become misaligned with the Cutting Head of the Tile Saw over time. Should misalignment occur, perform the following steps to realign the Tile Saw. NOTE: If alignment problems are

More information

XL-GC03 Sliding Door Lock Installation Manual PAT XL-GC06 Sliding Door Hanger Installation Manual XL-GC08 Sliding Door Lock Guide Installation Manual

XL-GC03 Sliding Door Lock Installation Manual PAT XL-GC06 Sliding Door Hanger Installation Manual XL-GC08 Sliding Door Lock Guide Installation Manual XL-GC0 Sliding Door Lock Installation Manual PAT XL-GC0 Sliding Door Hanger Installation Manual XL-GC0 Sliding Door Lock Guide Installation Manual Read all instructions carefully before installation. Before

More information

SPD 1004 QM Vibration Testing

SPD 1004 QM Vibration Testing SPD 1004 QM Vibration ing Document Author(s): Jehyuck Shin karamel_bro@khu.ac.kr Responsible Engineer(s): Seongwhan Lee Jungho Lee swhan@khu.ac.kr overthewater@khu.ac.kr Page 1/39 Revision History Revision

More information

BOB SLAY (assembly instructions)

BOB SLAY (assembly instructions) BOB SLAY (assembly instructions) Items included: 7 x Acrylic cutouts labeled A-G 1 x Acrylic IO Panel 1 x Acrylic locking plate of PCI cards 2 x Acrylic 5.25 spacers 2 x momentary switches (power/reset)

More information

Fig. 2 DORMA-Glas Stand/Issue 02/03 Seite/Page 1/7

Fig. 2 DORMA-Glas Stand/Issue 02/03 Seite/Page 1/7 FSW Installation instructions Track rail 75 x 72 mm 1. Ceiling substructure and installation of the track rail (Fig. 1): The track rail must be bolted over its entire length (including the stacking track

More information

Tools Required. * When installing on a fire door, please see instructions below. *

Tools Required. * When installing on a fire door, please see instructions below. * CL615 Tubular Mortice Latch with Code Free option CL615 Tubular Mortice Latch with Code Free option Number relating to picture Item 1 Front Plate and handle * 2 Back Plate and handle * 3 Neoprene seals

More information

Achievements in Developing an Advanced Standard for CubeSats

Achievements in Developing an Advanced Standard for CubeSats Achievements in Developing an Advanced Standard for CubeSats 10 th Annual CubeSat Workshop Ryan Williams, Engineer (presenting) Ryan Hevner, PSC 6U Canisterized Satellite Dispenser (CSD) Planetary Systems

More information

Custom Wood Frame Overlay for Glass Doors Installation Instructions

Custom Wood Frame Overlay for Glass Doors Installation Instructions MARVEL CUSTOM WOOD FRAME OVERLAY FOR GLASS DOORS Custom Wood Frame Overlay for Glass Doors Installation Instructions Wine Cellars 6SWC 6SWCE 61WC 61WCM 66SWC (2 required) 66SWCE (2 required) Beverage Centers

More information

HANDRAIL HEIGHT PER LOCAL CODE AUTHORITY. 6 3/8" [161.9mm]

HANDRAIL HEIGHT PER LOCAL CODE AUTHORITY. 6 3/8 [161.9mm] PLEASE READ PLEASE READ THESE INSTRUCTIONS THOROUGHLY PRIOR TO BEGINNING THE INSTALLATION! THIS INSTRUCTION SHEET IS INTENDED TO PROVIDE A SPECIFIC GUIDE TO FOLLOW FOR THE INSTALLATION OF THIS. CONTAINED

More information

TASK: Replace Control Mechanism/Drive End for G71 Supervue/Everglide Vertical headrail

TASK: Replace Control Mechanism/Drive End for G71 Supervue/Everglide Vertical headrail 1. Locate the clear plastic louver stems where louvers are attached. 2. Rotate louvers open. Slide a hard plastic card between the louver and the long side of the louver stem. Push the card and louver

More information

NanoRacks CubeSat Deployer (NRCSD) Interface Control Document

NanoRacks CubeSat Deployer (NRCSD) Interface Control Document NanoRacks CubeSat Deployer (NRCSD) Interface Control Document NanoRacks, LLC 18100 Upper Bay Road, Suite 150 Houston, TX 77058 (815) 425-8553 www.nanoracks.com Version Date Author Approved Details.1 5/7/13

More information

ASSEMBLY AND CARE INSTRUCTIONS JUST FOR KIDS 355

ASSEMBLY AND CARE INSTRUCTIONS JUST FOR KIDS 355 ASSEMBLY AND CARE INSTRUCTIONS VERSION: 8920100 (Revised 06/16) JUST FOR KIDS 355 SALES AND SERVICE spiethamerica.com Canada and International 135 Forestview Road, PO Box 40 Orillia, Ontario, Canada L3V

More information

Material Parameter Measurement (MPM)

Material Parameter Measurement (MPM) Material Parameter Measurement (MPM) C4 Software Module and Accessory of the KLIPPEL ANALYZER SYSTEM (Document Revision 1.3) FEATURES Measure E modulus and damping Evaluate raw materials Specify loudspeaker

More information

Model: SCD430 SCD640. Installation & Operation Guide P/N SCD640-95

Model: SCD430 SCD640. Installation & Operation Guide P/N SCD640-95 Model: SCD430 SCD640 Installation & Operation Guide P/N SCD640-95 Model SCD430 and SCD640 Kurt has two Self-Centering vises, a four-inch jaw width (SCD430) and a six-inch jaw width (SCD640). Jaw opening

More information

User Manual. Frame KIT VG-LFH15FWA VG-LFH20FWA VG-LFH25FWA

User Manual. Frame KIT VG-LFH15FWA VG-LFH20FWA VG-LFH25FWA User Manual Frame KIT VG-LFH15FWA VG-LFH20FWA VG-LFH25FWA The color and the appearance may differ depending on the product, and the specifications are subject to change without prior notice to improve

More information

Z-Axis Assembly Replacement / Adjustment

Z-Axis Assembly Replacement / Adjustment Z-Axis Assembly Replacement / Adjustment TOOLS NEEDED: 1 Set of L-Shaped Allen Wrenches 3 blocks of wood, plastic, or acrylic cut to approximately 2 inches by 3 inches Household grade White Lithium grease

More information

Interplanetary CubeSat Launch Opportunities and Payload Accommodations

Interplanetary CubeSat Launch Opportunities and Payload Accommodations Interplanetary CubeSat Launch Opportunities and Payload Accommodations Roland Coelho, VP Launch Services Tyvak Nano-Satellite Systems Inc. +1(805) 704-9756 roland@tyvak.com Partnered with California Polytechnic

More information

Solidstep GEN 2 OEM INSTALL MANUAL. Rev: Page 1

Solidstep GEN 2 OEM INSTALL MANUAL. Rev: Page 1 Solidstep GEN 2 OEM INSTLL MNUL Rev: 03.23.2017 Page 1 TBLE OF CONTENTS System Information 2 Safety Information 2 Resources Required 3 Installation 3 Solidstep 3 Leg Extension djustment 5 System Information

More information

Innovative Uses of the Canisterized Satellite Dispenser (CSD)

Innovative Uses of the Canisterized Satellite Dispenser (CSD) Innovative Uses of the Canisterized Satellite Dispenser (CSD) By Walter Holemans (PSC), Ryan Williams (PSC), Andrew Kalman (Pumpkin), Robert Twiggs (Moorehead State University), Rex Ridenoure (Ecliptic

More information

RAILING. Installation Guide

RAILING. Installation Guide RAILING Installation Guide THE BEST CHOICE FOR STRONG & DURABLE RAILING SYSTEMS Our exclusive manufacturing process ensures our vinyl railing will provide superior strength plus it is virtually maintenance

More information

SolidStep 3.0 OEM INSTALLATION MANUAL

SolidStep 3.0 OEM INSTALLATION MANUAL SolidStep 3.0 OEM INSTLLTION MNUL TBLE OF CONTENTS Information 2 Safety 2 Preparation 2 Resources Required 2 Prior to Installation 3 Installation 3 Place ssembly Inside Doorframe 3 djust Transport Lock

More information

Flight Unit S/N 002 Environmental Vibration Test Report. Dwg. No

Flight Unit S/N 002 Environmental Vibration Test Report. Dwg. No Rev. ECO Description Author Approved Date 01 32-261 Initial Release M. Smith 12-6-07 Flight Unit S/N 002 Environmental Vibration Test Report Dwg. No. 32-06050.0102 Revision 01 November 26, 2007 32-0605.0102

More information

TOYOTA TUNDRA CARGO DIVIDER Preparation. Part Number: PT

TOYOTA TUNDRA CARGO DIVIDER Preparation. Part Number: PT Preparation Part Number: PT767-34070 Kit Contents 1 1 Divider Screen 2 1 LH Bracket with Warning Label 3 1 RH Bracket without Warning Label NOTE: Part number of this accessory may not be the same as the

More information

Cal Poly Coordination of Multiple CubeSats on the DNEPR Launch Vehicle. Authors: Simon Lee, Armen Toorian, Nash Clemens, Jordi Puig-Suari

Cal Poly Coordination of Multiple CubeSats on the DNEPR Launch Vehicle. Authors: Simon Lee, Armen Toorian, Nash Clemens, Jordi Puig-Suari Cal Poly Coordination of Multiple CubeSats on the DNEPR Launch Vehicle Authors: Simon Lee, Armen Toorian, Nash Clemens, Jordi Puig-Suari California Polytechnic State University Aerospace Engineering Department

More information

Congratulations! You are now on your way to enriching your life with!

Congratulations! You are now on your way to enriching your life with! C) Using the base point as your reference, measure up 8-1/32 and mark a horizontal line. Measure in from the edge of the door the distance of your backset and mark where the two lines cross. This will

More information

John Deere 9570STS, 9650STS, 9660STS, and 9750STS Grain Tank Cross Auger Trough Liner EXOPLATE INSTRUCTION MANUAL

John Deere 9570STS, 9650STS, 9660STS, and 9750STS Grain Tank Cross Auger Trough Liner EXOPLATE INSTRUCTION MANUAL PLEASE READ THE ENTIRE INSTRUCTION SHEET BEFORE STARTING INSTALLATION. PLEASE REFER TO THE OPERATORS MANUAL FOR YOUR SPECIFIC COMBINE FOR PERTINENT SAFETY PRECAUTIONS THE TERMS. LEFT, RIGHT, FRONT, & REAR

More information

INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS INSTALLATION INSTRUCTIONS ANSI/BHMA - A156.2 BOX CONTENTS CHECK THAT THE CONTENTS OF YOUR BOX ARE CORRECT ACCORDING TO THE MODEL Model 600/605 Model 610/615 Model 620/625 1 Front plate and handle 2 Back

More information

ABSTRACT INTRODUCTION

ABSTRACT INTRODUCTION COMPASS-1 PICOSATELLITE: STRUCTURES & MECHANISMS Marco Hammer, Robert Klotz, Ali Aydinlioglu Astronautical Department University of Applied Sciences Aachen Hohenstaufenallee 6, 52064 Aachen, Germany Phone:

More information

Strategies for Successful CubeSat Development. Jordi Puig-Suari Aerospace Engineering Department Cal Poly, San Luis Obispo CEDAR Workshop July, 2009

Strategies for Successful CubeSat Development. Jordi Puig-Suari Aerospace Engineering Department Cal Poly, San Luis Obispo CEDAR Workshop July, 2009 Strategies for Successful CubeSat Development Jordi Puig-Suari Aerospace Engineering Department Cal Poly, San Luis Obispo CEDAR Workshop July, 2009 1 Some CubeSat Facts Over 100 Developers Worldwide Including

More information

Installation Manual FLUSH MOUNT - Shingle, Slate,etc. Questions? Call Us! +1 (800)

Installation Manual FLUSH MOUNT - Shingle, Slate,etc. Questions? Call Us! +1 (800) www.trasnowandsun.com S Installation Manual FLUSH MOUNT - Shingle, Slate,etc. At TRA Snow and Sun we engineer and layout each project upon request free of charge. Just give us the project details and we

More information

CubeSat Standard Updates

CubeSat Standard Updates CubeSat Standard Updates Justin Carnahan California Polytechnic State University April 25, 2013 CubeSat Developers Workshop Agenda The CubeSat Standard CDS Rev. 12 to Rev. 13 Changes The 6U CubeSat Design

More information

Assembly Instructions for model: VMPR1

Assembly Instructions for model: VMPR1 Assembly Instructions for model: VMPR1 Congratulations on your purchase! The VMPR1 ceiling mount provides a unique, simplified method of ceiling mounting inverted LCD/DLP projectors. Its low profile design

More information

Step by Step Installation Instructions. Poly Shutters. Customer Service or visit us online at smithandnoble.com

Step by Step Installation Instructions. Poly Shutters. Customer Service or visit us online at smithandnoble.com Step by Step Installation Instructions Poly Shutters Customer Service 800.248.8888 or visit us online at smithandnoble.com Thank you for purchasing from smith+noble. Your new window treatments have been

More information

MPA-9000 Universal Ceiling Projector Mount Kit

MPA-9000 Universal Ceiling Projector Mount Kit I N S T R U C T I O N M A N U A L Universal Ceiling Projector Mount Kit The Universal Ceiling Projector Mount provides a unique, simplified method of ceiling mounting your inverted projector. This low

More information

5 kn Flexure Fixture. The difference is measurable

5 kn Flexure Fixture. The difference is measurable 5 kn Flexure Fixture Reference Manual - Equipment M10-82810-11 Revision C The difference is measurable Electromagnetic Compatibility Where applicable, this equipment is designed to comply with International

More information

Installation Instructions

Installation Instructions Installation Instructions For 4 foot / 1.2m Diameter Ultra-high Performance Antenna Model ADxxG-4-T2 Before Installation, please read the instructions carefully. This instruction guide covers the installation

More information

1. TOOLS + MATERIALS REQUIRED

1. TOOLS + MATERIALS REQUIRED R INSTALLATION INSTRUCTIONS PRODUCT: BALDUR + ODEN CONFIGURATION: BI-PARTING DOOR MOUNT: TOP MOUNT Product is covered by U.S. patents. For more information visit www.krownlab.com. TOOLS + MATERIALS REQUIRED

More information

Sales & Service. JFK - Just For Kids. sasportonline.com. 135 Forestview Road 7879 Will Rogers Blvd.

Sales & Service. JFK - Just For Kids. sasportonline.com. 135 Forestview Road 7879 Will Rogers Blvd. Sales & Service sasportonline.com SA Sport (Canada) SA Sport (U.S.A.) 135 Forestview Road 7879 Will Rogers Blvd. P.O. Box 40 Fort Worth, Texas Orillia, Ontario USA 76140 Canada L3V 6H9 Telephone: (705)

More information

Modal Analysis and Vibration Test of NASA MSFC Shaker Table

Modal Analysis and Vibration Test of NASA MSFC Shaker Table Washington University in St. Louis Washington University Open Scholarship Mechanical Engineering and Materials Science Independent Study Mechanical Engineering & Materials Science 11-11-2018 Modal Analysis

More information

GATE INSTALLATION INSTRUCTIONS

GATE INSTALLATION INSTRUCTIONS GATE INSTALLATION INSTRUCTIONS 1) Ensure posts for gate are fully installed. Posts need to be securely fastened to decking or concrete such that they will not sag with weight of the gate. For a single

More information

FOLDING DOOR INSTRUCTIONS

FOLDING DOOR INSTRUCTIONS FOLDING DOOR INSTRUCTIONS Please read these instructions carefully and follow them step by step to insure a smooth installation. Most importantly DO NOT open hardware boxes and mix hardware up. Hardware

More information

CL4500 Installation Instructions

CL4500 Installation Instructions CL4500 Installation Instructions Box Contents Check the contents of the box are correct according to the model 4510 4520 1 Front Plate 2 Back Plate 3 Lever Handles 4 Gaskets 5 Sprung Spindle (x1) 6 Spring

More information

CRCODE-202. Mechanical Lock. Instruction and Programming Manual. Before Installing:

CRCODE-202. Mechanical Lock. Instruction and Programming Manual. Before Installing: CRCODE-202 Mechanical Lock Instruction and Programming Manual Before Installing: 1. Please read the instructions carefully to prevent missing important steps. *Note: Improper installations may result in

More information

Motorized Tower Raising System Manual

Motorized Tower Raising System Manual Motorized Tower Raising System Manual Introduction and Safety Guidelines Important! Read through the manual in its entirety prior to assembly and installation of the motorized tower raising system. WARNING:

More information

Menu Board Tilt or Fixed Mount Installation Instructions MDS1T-200, MDS1T-300, MDS1T-400 MDS2T-200, MDS2T-300, MDS2T-400 MDS3T-200, MDS3T-300, MDS3T-400 MDS4T-200, MDS4T-300, MDS4T-400 MDS5T-200, MDS5T-300,

More information

Product Information. AK ERM 2xx0 TTR ERM 2x00 Modular Angle Encoders with Magnetic Scanning and Mechanical Fault Exclusion

Product Information. AK ERM 2xx0 TTR ERM 2x00 Modular Angle Encoders with Magnetic Scanning and Mechanical Fault Exclusion Product Information AK ERM 2xx0 TTR ERM 2x00 Modular Angle Encoders with Magnetic Scanning and Mechanical Fault Exclusion February 2017 ERM 2200 series Consisting of AK ERM 2280 and TTR ERM 2200 or TTR

More information

CubeSat Proximity Operations Demonstration (CPOD) Mission Update Cal Poly CubeSat Workshop San Luis Obispo, CA

CubeSat Proximity Operations Demonstration (CPOD) Mission Update Cal Poly CubeSat Workshop San Luis Obispo, CA CubeSat Proximity Operations Demonstration (CPOD) Mission Update Cal Poly CubeSat Workshop San Luis Obispo, CA 04-22-2015 Austin Williams VP, Space Vehicles ConOps Overview - Designed to Maximize Mission

More information

Installation of the JD 900 Series Flex Grain Platform Auger Trough Liner Kit

Installation of the JD 900 Series Flex Grain Platform Auger Trough Liner Kit www.polyskid.com P. O. Drawer 349, Monticello, GA. 31064 Phone: 800-542-7659 Fax: 706-468-2881 E-Mail: polytech@polyskid.com Installation of the JD 900 Series Flex Grain Platform Auger Trough Liner Kit

More information

BHJ Products, Inc. Parts List & Instructions

BHJ Products, Inc. Parts List & Instructions Product Name: Lifter-Tru Kit for Ford Windsor & SVO Small Block V8 Page 1 of 5 Kit Contents: 2x End Plates 2x 5/8 Threaded Adjustment Sleeves 1x Front Angle Bracket 2x 5/8 Adjustment Sleeve Spacers * 1x

More information

Metroboard Pulley Replacement Procedure

Metroboard Pulley Replacement Procedure Metroboard Pulley Replacement Procedure 1) Remove the two transmission cover screws (1/8 allen driver). Then remove the transmission cover. Note there is a split lock washer and flat washer as well, so

More information

CIRRUS AIRPLANE MAINTENANCE MANUAL

CIRRUS AIRPLANE MAINTENANCE MANUAL FASTENER AND HARDWARE GENERAL REQUIREMENTS 1. DESCRIPTION This section contains general requirements for common hardware installation. Covered are selection and installation of cotter pins, installation

More information

27APR18 U.S. RACK, Inc Falcon Drive, Madera, CA

27APR18 U.S. RACK, Inc Falcon Drive, Madera, CA 27APR18 U.S. RACK, Inc. - 2850 Falcon Drive, Madera, CA 93637-559-661-3050 INSTRUCTIONS for FIFTH WHEEL RACK Model 2010-4ADC WARNING: Do NOT attempt to install or use this rack without following all instructions.

More information

Mounting a BalanceBox 400 to a brick wall

Mounting a BalanceBox 400 to a brick wall Unpack the BalanceBox 400 and remove the Wall frame cover and its bag of screws. Slide the cover out at the top. NOTE: the cover is NOT included with the BalanceBox 400H LOCK SCREW HOLE MOBILE STAND MOUNTING

More information

Thread protection accessories are installed at the MODIX production factory and delivered with couplers.

Thread protection accessories are installed at the MODIX production factory and delivered with couplers. Installation of MODIX Rebar Coupler Identification of the product The type of MODIX Rebar Coupler can be identified by the marking on the product. Size of the Coupler can be identified also according to

More information

Replacing the Reciprocator on an SWF Multi-head.

Replacing the Reciprocator on an SWF Multi-head. Replacing the Reciprocator on an SWF Multi-head. Follow the instructions below to replace the reciprocator in the SWF multi-head machines. The tools required are found in the tool kit that came with the

More information

Side DuraRac Installation Instructions

Side DuraRac Installation Instructions Side DuraRac Installation Instructions Ford Transit Low Roof 130 /148 WB Frame Kit Part #: CRC 22-1010-002 V1.0.08.10.18 IMPORTANT INSTALLATION STEPS ARE DENOTED USING A STOP SIGN. THESE STEPS MUST BE

More information

RAX: Lessons Learned in Our Spaceflight Endeavor

RAX: Lessons Learned in Our Spaceflight Endeavor RAX: Lessons Learned in Our Spaceflight Endeavor Matt Bennett University of Michigan CubeSat Workshop Cal Poly, San Luis Obispo April 21 st, 2010 Background Sponsored by National Science Foundation University

More information

CAPSULE CONTACT MECHANISM AND HIGH-CAPACITY CUTOFF COMPACT RELAY FEATURES

CAPSULE CONTACT MECHANISM AND HIGH-CAPACITY CUTOFF COMPACT RELAY FEATURES CAPSULE CONTACT MECHANISM AND HIGH-CAPACITY CUTOFF COMPACT RELAY EV RELAYS (AEV) 80A A 0A FEATURES. High-, high-current control possible 0 high- switching cutoff has been achieved thanks to a sealed construction

More information

Adjusting Ibanez SR405QM Truss Rod

Adjusting Ibanez SR405QM Truss Rod Adjusting Ibanez SR405QM Truss Rod High tension caused by the strings can cause the wood of the fret board to bow. This bowing can become so extreme it becomes difficult or impossible to play on due to

More information

PAM-200 Universal Projector Mount

PAM-200 Universal Projector Mount INSTALLATION MANUAL PAM-200 Universal Projector Mount Sony Electronics 16540 West Bernardo Drive San Diego, CA 92127 www.sony.com IN-PAM200.R0 Table of Contents Parts List...- 3 - Installation Tools...-

More information

INSTALLATION MANUAL H A

INSTALLATION MANUAL H A INSTALLATION MANUAL CABINET RACK CR-43-6 (4-UNIT SIZE) Be sure to read this installation manual thoroughly before installing this Cabinet Rack. For the mounting procedures of the components and the relevant

More information

(U) A Path Forward for Small Satellite Ground Architecture

(U) A Path Forward for Small Satellite Ground Architecture (U) A Path Forward for Small Satellite Ground Architecture LtCol Joseph Gueck: gueckjos@nro.mil MAJ Benjamin Seth Bowden: bowdenbe@msd.nro.mil Mr. David C. Williamson: willdavi@msd.nro.mil 2013 Ground

More information

Legacy Woodworking Machinery a division of Phantom Engineering. The Legacy CNC. Assembly Manual

Legacy Woodworking Machinery a division of Phantom Engineering. The Legacy CNC. Assembly Manual Legacy Woodworking Machinery a division of Phantom Engineering The Legacy CNC Assembly Manual New Orientation of the Legacy Step one: Re-orientation of the machine Remove the X-axis screw and supports.

More information

The ENDEVCO high-g shock triaxial accelerometer: A smaller, more cost-effective solution to making triaxial measurements. Endevco technical paper 334

The ENDEVCO high-g shock triaxial accelerometer: A smaller, more cost-effective solution to making triaxial measurements. Endevco technical paper 334 The ENDEVCO high-g shock triaxial accelerometer: A smaller, more cost-effective solution to making triaxial measurements Endevco technical paper 334 New VC accelerometer technology for flight test offers

More information

ICU TRACKLESS SLIDING DOOR

ICU TRACKLESS SLIDING DOOR Interior View 0 Installation Instructions Tools Required: Screwdrivers Small Straight (Flat Blade) - for Terminal Block wiring # Phillips (Crosspoint) - for various #8, #0, and #4 screws Wrenches / Sockets

More information

Door Hardware Installation Instructions. Version A No Interior on an Un-prepped Door Step 1 Select the Position of the Handleset

Door Hardware Installation Instructions. Version A No Interior on an Un-prepped Door Step 1 Select the Position of the Handleset For Assistance Call: 1-800-522-7336 8 am - 5 pm, Monday - Friday, MST or visit our Website at: www.grandeur-nw.com Door Hardware Installation Instructions Dummy Handleset Optional Rosette (Round) Interior

More information

incorrect use or handling that exceeds normal operating limits.

incorrect use or handling that exceeds normal operating limits. User s Manual Wall mount unit for projectors Model name HAS-WM06 Thank you for purchasing a wall mount unit specially designed for Hitachi projectors. Be sure to read this manual and the User s Manual

More information

EXPERIMENT 1 TO CHECK WHETHER THE MEASURING INSTRUMENTS ARE ACCURATE, PRECISE OR BOTH.

EXPERIMENT 1 TO CHECK WHETHER THE MEASURING INSTRUMENTS ARE ACCURATE, PRECISE OR BOTH. EXPERIMENT 1 TO CHECK WHETHER THE MEASURING INSTRUMENTS ARE ACCURATE, PRECISE OR BOTH. Aim 1: To check whether the given Vernier Caliper is accurate, precise or both. Objective: Students will be able to

More information

HANDRAIL HEIGHT PER LOCAL CODE AUTHORITY. 6 3/8" [161.9mm]

HANDRAIL HEIGHT PER LOCAL CODE AUTHORITY. 6 3/8 [161.9mm] P-RSS PLEASE READ PLEASE READ THESE INSTRUCTIONS THOROUGHLY PRIOR TO BEGINNING THE P-RSS INSTALLATION! THIS INSTRUCTION SHEET IS INTENDED TO PROVIDE A SPECIFIC GUIDE TO FOLLOW FOR THE INSTALLATION OF THIS

More information

Pole Mount Installation Guide

Pole Mount Installation Guide Pole Mount Installation Guide (No Fine Adjustment) 495R Billerica Ave. North Billerica, MA 01862 USA Tel (978)459-8800 fax (978)459-3310 / 8814 Email: sales@radiowaves.com www.radiowaves.com IMPORTANT!

More information

Global Educational Network for Satellite Operations (GENSO)

Global Educational Network for Satellite Operations (GENSO) Global Educational Network for Satellite Operations (GENSO) Kyle Leveque, Dr. Jordi Puig-Suari, Dr. Clark Turner California Polytechnic State University, SLO {kleveque, jpuigsua, csturner}@calpoly.edu

More information

INSTALLATION INSTRUCTIONS SMALL FLAT PANEL ADJUSTABLE PITCH WALL MOUNT Model: FTR Series

INSTALLATION INSTRUCTIONS SMALL FLAT PANEL ADJUSTABLE PITCH WALL MOUNT Model: FTR Series INSTALLATION INSTRUCTIONS SMALL FLAT PANEL ADJUSTABLE PITCH WALL MOUNT Model: FTR Series Specifications: Designed for installation on single wood studs or drywall (1/2" minimum thickness); either option

More information