Scope of Work Temecula Valley Regional Water Reclamation Facility 23 MGD Expansion Engineering Services During Construction

Size: px
Start display at page:

Download "Scope of Work Temecula Valley Regional Water Reclamation Facility 23 MGD Expansion Engineering Services During Construction"

Transcription

1 CH2M HILL 6 Hutton Centre Drive Suite 700 Santa Ana, CA Phone: Fax: November 12, 2015 Mr. Erik Jorgensen, P.E. Eastern Municipal Water District 2270 Trumble Road Perris, CA Subject: Dear Mr. Jorgensen: Scope of Work Temecula Valley Regional Water Reclamation Facility 23 MGD Expansion Engineering Services During Construction We would like to thank you for the opportunity to continue working with the Eastern Municipal Water District (EMWD) on the Temecula Valley Regional Water Reclamation Facility (TVRWRF) 23 million gallons per day (mgd) expansion project. As requested by EMWD, we prepared the attached scope of work (SOW), level of effort, and fee estimate for the services during construction (SDC) for this project. It is our understanding that this work will be an amendment to the existing contract. This SOW and level of effort cover the tasks needed to support EMWD during the construction and start up phases of the TVRWRF 23 mgd expansion project. The team that will perform the engineering services during construction is the same as the project team involved in the project design. If you have any questions regarding the attached SOW, please contact Fred Soroushian at or Carmen Quan at We will be ready to begin work immediately upon receiving your written authorization. Sincerely, CH2M HILL Tom Price, P.E. Vice President WBG SCO

2 Scope of Work This Scope of Work (SOW) details CH2M HILL s services during construction (SDC) for the TVRWRF 23 million gallons per day (mgd) expansion project. The following tasks are proposed for this project: Task 1 Services During Construction Task 1.1 Conformed Set Document Task 1.2 Solar Power Project Task 1.3 Submittal Review Task 1.4 Reply to Requests for Information (RFI) Task 1.5 Change Order Review Task 1.6 Manufacturer Operations and Maintenance Manual Review Task 1.7 Document Processing Task 1.8 Project Meetings/Site Visits Task 1.9 Testing and Startup Support Task 1.10 Southern California Edison (SCE) Closed Transition, Permitting and Coordination Support Task 1.11 Record Drawings Preparation Task 2 Post Construction Assistance Task 3 Project Management Task 4 Electronics Operations and Maintenance Manual Task 5 Fiber Optics System Submittal Review Task 6 Additional Consulting Engineering Services Following is a detailed description of each task, proposed fees, and assumptions used to develop this SOW. Task 1 Services During Construction Task 1.1 Conformed Set Document CH2MHILL will incorporate the addenda information in the bid documents, prepare the conformed set of drawings and specifications, and submit to EMWD in electronic portable document format (PDF). Conformed drawings for the SCE design and fiber optics project will be prepared by the respective design engineers. Task 1.2 Solar Power Project EMWD is planning to construct a solar power system at TVRWRF through a separate construction contract. The construction of the solar power system would overlap with the construction of the TVRWRF 23 mgd expansion project. To identify interfaces with the TVRWRF 23 mgd expansion project with primary metering and facilities construction sequencing and layout areas, CH2M HILL will review the solar system concept proposed by the solar system provider. The focus of CH2M HILL s review will be project interfaces and compatibility with the TVRWRF Expansion Project. CH2M HILL will provide review comments to EMWD and participate in up to one review meeting with the solar system design engineer and system provider. CH2MHILL will revise the bid documents, if necessary, to show the areas available for contractor staging and layout areas, and to include the power, fiber optics and SCADA interface with the solar power project. CH2M HILL s level of effort and task budget presented herein assumes one iteration of bid document revisions. WBG SCO 1

3 Task 1.3 Submittal Review CH2M HILL will review and provide comments on up to 435 shop drawing submittals and up to 95 resubmittals. The review period for each submittal is expected to be up to 10 working days from the time received by CH2M HILL unless substantial level of effort is required. CH2M HILL will inform EMWD when a specific submittal requires additional review time. It is assumed that all comments will be communicated to EMWD via e mail using EMWD s standard shop drawings submittal review form. CH2M HILL will be provided with one copy of each submittal for filing (PDF format). It is assumed that the contractor s submittals will be reviewed for completeness by the construction manager prior to sending them to CH2M HILL and that CH2M HILL is not responsible for communicating with the contractor to address incomplete information in a submittal. The level of effort for submittal review is based on 10 hours per submittal and resubmittal (5,300 hours total). Task 1.4 Reply to Requests for Information CH2M HILL will respond to up to 540 Reply to Requests for Information (RFIs) from the contractor related to construction activities of the design performed by CH2M HILL. The expected response period for each RFI shall be up to 5 working days from the time received by CH2M HILL, unless substantial level of effort is required. If this is the case, CH2M HILL will inform EMWD when a specific RFI requires additional review time. It is assumed that all responses will be communicated to EMWD via e mail using EMWD s standard RFI response form. The level of effort for reply to RFIs is based on 4 hours per RFI (2,160 hours total). Task 1.5 Change Order Review CH2M HILL will evaluate the impact of change orders on design and compliance with the contract documents and provide comments for up to 48 change orders to EMWD. The change order cost evaluation will be performed by EMWD. The maximum review and response period for each change order review shall be up to 15 working days from the time received by CH2M HILL. CH2M HILL will inform EMWD when a specific change order requires additional review time. CH2M HILL will be provided with one copy of each approved change order request for filing. Task Manufacturer Operations and Maintenance Manual Review CH2MHILL will review manufacturers operations and maintenance manuals submitted by the contractor for completeness, compliance and conformance with the specifications. CH2M HILL will deliver written review comments. Task 1.7 Document Processing EMWD will receive, log, and forward the RFIs, submittals, and change orders to CH2MHILL. For internal tracking and review of documents, CH2MHILL will receive and log the RFIs, submittals, and change orders, and distribute them internally for review, and process and return the review comments to EMWD. CH2MHILL will maintain an internal log and an internal file with the documents (submittals, RFIs, change orders, and their corresponding comments and responses) received and sent by CH2M HILL. Task 1.8 Project Meetings/Site Visits CH2M HILL will attend up to 40 monthly project meetings (including the construction kickoff meeting) and up to 24 site visits, per EMWD s request, during the construction period for this project. One CH2M HILL staff member will attend each of project meetings and up to two CH2MHILL staff will attend the site visits to support EMWD in addressing construction and/or facility related issues. It is assumed that all meetings and site visits will be held at the TVRWRF or EMWD headquarters building. WBG SCO 2

4 Task 1.9 Testing and Startup Support CH2MHILL will review the testing and startup plan submitted by the contractor. CH2MHILL will provide up to 180 hours of assistance during the testing and startup of the facility. The construction manager will coordinate the testing and startup with the contractor and EMWD operations staff. CH2MHILL will be available to address field questions during testing and startup periods. Task 1.10 SCE Primary Power, Rule 21, Closed Transition, Permitting and Coordination Support Subtask AT EMWD s request, CH2M HILL will provide support for SCE coordination and support services (including new switchgear, new power connection to the existing,12 kv system equipment, and Rule 21), during the construction phase of the project. If a meeting is required, EMWD will schedule the meeting with the necessary participants. Up to 400 hours have been estimated for this task, including the effort to prepare information required for the coordination activities and meeting participation. Subtask At EMWD s request, CH2M HILL will provide support to coordinate with SCE regarding the testing and acceptance of the closed transition control scheme during the construction phase of this project. EMWD will coordinate and schedule the meetings with SCE and other participants regarding closed transition. Up to 200 hours have been estimated for this task, including the effort to prepare information required for the coordination activities and meeting participation. Task 1.11 Record Drawings Preparation CH2M HILL will prepare the record drawings for this project from the markups made on the bid set plan by the contractor and construction manager. The field markups will be verified by the construction manager. The TVRWRF 23 mgd expansion design drawings will be modified by adding the field markups verbatim to prepare the record drawings. It is assumed that up to four drawings of plan and profile sheets for yard piping will be provided by the contractor as record drawings and presented as Microstation files that will be incorporated as part of the record drawing set. The record drawings (including corresponding Mylars, CAD, and PDF files) for fiber optics, solar power, and the SCE system will be prepared by their respective design engineers. Deliverables will include two compact discs (CDs), each containing the record drawings in CAD and PDF formats, one half size set of prints (11 inches by 17 inches) and one full size set of Mylars (22 inches by 34 inches). It is assumed that EMWD s construction manager will conduct consistent and thorough reviews during the construction period to check the accuracy and legibility of the hand marked master drawing set updated daily by the contractor. CH2M HILL is not responsible for the information submitted by the contractor to EMWD and will only transfer the marks as shown on the master drawing set prepared by the contractor to the CAD files prepared by CH2M HILL. Task 2 Post Construction Assistance CH2MHILL will be available to address field questions during the warranty period for the facilities constructed under the TVRWRF 23 mgd expansion project. This includes the 180 day commissioning period for the membrane bioreactor system. It is assumed that up to 150 hours of assistance will be provided for this task. Task 3 Project Management CH2M HILL s project manager (Fred Soroushian) will manage and coordinate the CH2MHILL team activities during the bid, construction, startup, and post construction periods. The CH2MHILL project manager will prepare and submit up to 40 monthly invoices and progress reports. The CH2MHILL project manager will participate in monthly conference calls, if requested by EMWD. WBG SCO 3

5 Task 4 Electronic Operations and Maintenance Manual CH2M HILL will prepare the contents and upload the information for the treatment process facilities constructed under the TVRWRF 23 mgd Expansion to the District s existing electronic Operations and Maintenance (EOM) SharePoint site. EMWD s existing EOM Sharepoint site is arranged by facility and each facility consists of a series of chapters each with the folders for each of the systems under a chapter. Each of the system folders has a series of sections which include several areas, each with its own data sheet configuration. Each section include (if applicable) the following areas: How It Works Schematic, Theory of Operation and Process Control, Process Design Data, Equipment Descriptions, Instrument Descriptions, Equipment Controls, Alarm and Alarm Responses, Standard Operating Procedures, and Emergency Operating Procedures. CH2MHILL will prepare and submit an outline detailing the organization of the TVRWRF EOM chapters, system folders, sections and data sheets for the facilities built under the TVRWRF 23 mgd. EMWD will review the outline and attend a workshop with CH2M HILL to discuss the comments on the outline. The TVRWRF EOM will include the new EOM chapters for new Plant 3A unit processes (primary clarification, fine screens, biological treatment, and membrane system). For existing processes that are being upgraded (headworks, disinfection, tertiary effluent pump system, sludge thickening, digester gas compression), new folders will be added for the new facilities only. Under the disinfection chapter we will add a folder for the new chlorine contact tanks, a folder for the new chlorinators, and a folder for the out of compliance pumps. Under the Tertiary Effluent Pump System we will add a folder for the new tertiary effluent pumps and a folder for the surge system. Under the Headworks chapter, we will add a folder for the new mechanical bar screen. Under the chapter for Sludge Thickening we will add a folder for the new rotary drum thickener (RDT). Under the chapter for Digester Gas Compression we will add a folder for the gas purification system, a folder for the gas compression system, and a folder for the sump system.ch2m HILL will prepare the contents and upload the information that goes into the data sheets for the following areas for each of the sections under each system folder in each of the chapters described in the second paragraph of Task 4: How It Works Schematic, Theory of Operation and Process Control, Process Design Data, Equipment Controls, Alarm and Alarm Responses, Standard Operating Procedures, and Emergency Operating Procedures. CH2M HILL will upload the information provided by the Contractor in the data sheets for the following areas corresponding to the system folders created under Task 4: Equipment Descriptions, and Instrument Descriptions. The Contractor will provide the fully populated data sheets for these as part of the submittal for each equipment and instrument/device. CH2M HILL will be provided access to EMWD s EOM SharePoint site to use or create new chapters, system folders and populate the data sheets for the TVRWRF EOM.CH2MHILL will conduct one four hour workshop to demonstrate use of the TVRWRF 23 mgd facilities EOM and familiarize EMWD staff with the organization and navigation of the site. It is anticipated the EOM Workshop will coincide with final acceptance of construction, so that files are complete and final. It is assumed that up to 400 data sheets will be provided by the General Contractor as part of the submittal effort and that the information in these data sheets will be uploaded to the TVRWRF 23 mgd facilities EOM. In addition, a total of up to 600 links will be required to link the How It Works Schematics (modified P&IDs) to the different data sheets and that a total of up to 1000 data sheets (including 20 for the Theory of Operation and Process Control) will be prepared and uploaded for task 4. Up to 2,750 hours have been estimated for task 4. CH2M HILL will not create or update information in the EOM for any of the existing facilities at the TVRWRF. Chapters for supporting facilities such as the electrical system, control equipment, and solar power system are not required for the EOM. WBG SCO 4

6 Task 5 Fiber Optics System CH2M HILL will retain Carollo Engineers to prepare conformed drawings for fiber optics system, review and provide comments on shop drawing submittals and resubmittals, RFIs, change orders and preparation of record drawings for the fiber optics system (Appendix H of the bid documents). The review period for each submittal is expected to be up to 10 working days from the time received by Carollo unless substantial level of effort is required. CH2M HILL will inform EMWD when a specific submittal requires additional review time. It is assumed that all comments will be communicated to EMWD via e mail using EMWD s standard shop drawings submittal review form. CH2M HILL and Carollo will be provided with one copy of each submittal for filing (PDF format). It is assumed that the contractor s submittals will be reviewed for completeness by the construction manager prior to sending them to CH2M HILL and that CH2M HILL is not responsible for communicating with the contractor to address incomplete information in a submittal. Carollo will review RFIs and change orders related to Appendix H (the fiber optics system). The review period for RFIs is expected to be up to 5 working days and for change orders to be up to 15 days from the time received by Carollo unless substantial level of effort is required. In addition, Carollo will prepare the record drawings for the drawings in Appendix H and provide two compact discs (CDs), each containing the Appendix H record drawings in CAD and PDF formats, one half size set of prints (11 inches by 17 inches) and one full size set of Mylars (22 inches by 34 inches). Task 6 Additional Consulting Engineering Services Under this task CH2M HILL will provide additional engineering services to modify the existing design features in the existing TVRWRF 23 mgd Expansion documents. Task 6.1 Miscellaneous Services Some of support services include evaluation of Parkson Messner aeration panel system, preparation of a specification for Messner aeration panel system, preparing addendum number 4 (in addition to replying to contractor s questions), and preparing addendum number 5. Additional consulting and design services will be provided, if requested by EMWD. Task 6.2 Solids Handling Recycles Treatment Evaluation TVRWRF is currently required to meet 10 mg/l effluent total inorganic nitrogen (TIN) limits under the current NPDES permit requirements. Existing facilities at TVRWRF were designed to handle nitrogen loads according to the Basis of Design established at the time of Plant 1 and Plant 2 primary and secondary facilities design and construction. However, a review of the current influent loads indicate that the raw wastewater characteristics have changed over time and TVRWRF is experiencing an increased nitrogen load. As a result, the facility is experiencing challenges to meet TIN limits. Dewatering recycles contain a concentrated amount of nitrogen that correspond to about 20 to 25% of the plant influent typical load. Treatment of this sidestream can allow reduction in the overall nitrogen load for the whole plant and reduce effluent TIN levels and the tasks below focus on the developing alternatives for treating the sludge dewatering recycles Data Review and Study Basis Development CH2M will conduct a review of the influent and solids handling recycles water quality data. If recycles water quality data is not available, estimations will be made using the calibrated process model developed under the 23 mgd Expansion Project after necessary updates to the model. CH2M will prepare a summary of the review and establish study basis for review and approval of EMWD Alternatives Development and Evaluation CH2M will develop up to four alternatives to reduce nitrogen load in the dewatering recycles which will be suitable for phased implementation. Alternatives that can be readily implemented with minimal construction and can help reduce the current effluent TIN levels in accordance with the permit averaging cycle as well as alternatives that could be implemented as a longer term WBG SCO 5

7 solution will be evaluated. Use of existing process tankage will be evaluated as they fit into the identified alternatives. To review the facility modification needs, a site visit by up to two CH2M staff (e.g.; Mechanical Engineer, Process Engineer) will be conducted. Up to four alternatives will be further developed for budgetary construction cost estimating. For facility sizing, the process model developed under the 23 mgd Expansion project (baseline) will be used to develop whole plant process models for each alternative. By evaluating the alternatives as part of the whole plant, the evaluation will allow facilities sharing/redundancy and avoid costs that could be deferred/eliminated. Process control opportunities to better manage the key process parameters such as nitrogen (ammonia nitrate), dissolve oxygen, sludge retention time, etc. will be identified as applicable. A simplified site plan for each alternative will also be developed. Through review of monetary and non monetary criteria as well as implementation schedule, alternatives will be reviewed, and a recommendation will be developed. CH2M will develop a Class 4 opinion of construction cost for the selected alternative for budgetary planning purposes Study Report CH2M will develop a draft Technical Memorandum (TM) that presents a summary of the study findings and final recommendations. The draft TM will be submitted to EMWD electronically (.pdf or.doc format). EMD will provide one set of consolidated review comments which will be reconciled for developing the final TM. Final TM will be submitted in electronic format as a PDF file Project Workshops/Site Visits CH2M HILL will attend up to two project workshops. It is assumed that all meetings will be held at the EMWD Headquarters building. One workshop will be conducted at the midpoint of the study where alternatives could be reviewed. The second workshop will be conducted after the submission of the draft TM and will allow discussion of the EMWD comments and final direction regarding next steps for dewatering recycles treatment at TVRWRF. Level of Effort and Fee Estimate The level of effort and the fee presented in Table 1 is in addition to the fee in the current contract. The billing rates for this project are included in Table 2. The project will be managed to the total cost budget. The budget amount for Engineering Services During Construction is $3,598,938 CH2M will make reasonable efforts to complete the work within the budget and keep EMWD informed of progress so that the budget or work effort can be adjusted if found necessary. CH2M will inform EMWD in writing when 75 percent of the budget is spent. CH2M is not obligated to incur costs beyond the indicated budget, as may be adjusted, nor is EMWD obligated to pay CH2M beyond the budget limit. List of Assumptions 1. EMWD will provide construction management, inspection, administration, sampling and testing, and survey and geotechnical support for this project. 2. The total project schedule of 40 months including post construction assistance. 3. The project construction will start in 2016 and end in mid WBG SCO 6

8 Table 1 Level of Effort and Fee for the Engineering SDC for the TVRWRF 23 mgd Expansion Project Task Description Labor Hours Labor Cost Expenses Subconsultants Total Cost Task 1 - Services During Construction 12,067 $2,512,212 $31,100 $164,062 $2,707,374 Task 1.1 Conformed Set Document 380 $56,328 $500 $12,155 $68,983 Task Solar Power Project 102 $19,232 $500 $0 $19,732 Task 1.3 Submittal Review 5,300 $1,135,474 $6,000 $76,312 $1,217,786 Task 1.4 Reply to Requests for Information (RFI) 2,160 $490,403 $0 $28,658 $519,061 Task 1.5 Change Order Review 768 $165,399 $0 $11,286 $176,685 Task Manufacturer Operations and Maintenance Manual Review 280 $60,780 $0 $0 $60,780 Task 1.7 Document Processing 893 $120,696 $200 $3,300 $124,196 Task 1.8 Project Meetings/Site Visits 704 $163,120 $5,400 $18,216 $186,736 Task 1.9 Testing and Startup Support 180 $42,520 $3,500 $0 $46,020 Task 1.10 Southern California Edison (SCE) Primary, Power, Rule 21, Closed Transition, Permitting and Coordination Support 600 $142,160 $1,000 $0 $143,160 Task 1.11 Record Drawings Preparation 700 $116,100 $14,000 $14,135 $144,235 Task 2 Post Construction Assistance 150 $37,900 $1,000 $0 $38,900 Task 3 Project Management 1,010 $193,975 $500 $17,996 $212,471 Subtotal Tasks 1 through 3 13,227 $2,744,087 $32,600 $182,058 $2,958,745 Task 4 Electronic Operations & Maintenance Manual 2,740 $437,330 $1,460 $0 $438,790 Task 5 Fiber Optics System 30 $4,745 $500 $54,825 $60,070 Task 6 Additional Consulting Engineering Services 755 $136,343 $700 $4,290 $141,333 Total Tasks 1 through 6 16,752 $3,322,505 $35,260 $241,173 $3,598,938 WBG SCO 7

9 Table 2 - CH2M HILL 2015 Hourly Charge Rates for Professionals and Technicians Classification 2015 Hourly Charge Rates Principal-In-Charge/Principal Program Manager $255 Principal Project Manager/Principal Consultant/Program Manager $240 Senior Project Manager/Senior Technologist $221 Project Manager/Senior Engineer/Scientist $202 Task Manager/Project Engineer/Assistant Project Manager $189 Associate Engineer/Scientist/Planner $162 Staff Engineer/Scientist/Planner $134 Senior Contracts/Procurement $188 Staff Contracts/Procurement $134 Senior Technician II $156 Senior Technician I $143 Staff Technician/Technical Editor $122 Junior Technician $98 Administration/Accounting $98 EXPENSES Expense Type Estimating Method Rate Health & Safety Assessment* Service Center $1.75 Auto Mileage Travel Current IRS Rate ($0.55/mile) + 10% Auto Rental Travel Actual + 10% Other Travel (FTR Guidelines) Travel Actual + 10% Equipment Rental Operating Expense Actual + 10% Postage/Freight Operating Expense Actual + 10% Reprographics Outside Service Actual + 10% Subcontractors Outside Service Actual + 10% * Assessment applies to all Health & Safety trained individuals Rates subject to change on January 1, 2016 WBG SCO 8

CITY OF BAYTOWN CENTRAL DISTRICT WASTEWATER TREATMENT PLANT GRIT, SECURITY, AND SCADA IMPROVEMENTS SCOPE OF SERVICES

CITY OF BAYTOWN CENTRAL DISTRICT WASTEWATER TREATMENT PLANT GRIT, SECURITY, AND SCADA IMPROVEMENTS SCOPE OF SERVICES CITY OF BAYTOWN CENTRAL DISTRICT WASTEWATER TREATMENT PLANT GRIT, SECURITY, AND SCADA IMPROVEMENTS SCOPE OF SERVICES FINAL DESIGN, BID PHASE, AND CONSTRUCTION SERVICES BACKGROUND ARCADIS U.S., Inc. (ARCADIS)

More information

CONVEYANCE PIPELINE AND PUMP STATION

CONVEYANCE PIPELINE AND PUMP STATION SCOPE OF WORK CONVEYANCE PIPELINE AND PUMP STATION The purpose of this scope of work is to provide engineering services to revise and complete the design of the RUWAP pipeline and 5th Avenue Pump Station

More information

SECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS

SECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Record Documents. B. Operation and Maintenance Manuals. C. Warranties and bonds. 1.02 RELATED REQUIREMENTS SECTION 01 78 00 A. Section 01 30 00 - Administrative

More information

This specification describes the general requirements for Engineering Services provided to Vale.

This specification describes the general requirements for Engineering Services provided to Vale. 1/9 1.0 PURPOSE This specification describes the general requirements for Engineering Services provided to Vale. 2.0 GENERAL For the purposes of this document, the Engineering Consultant shall be referred

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 12/12/2018

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 12/12/2018 SECTION 01 7839 - PROJECT RECORD DOCUMENTS GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

A. Section includes administrative and procedural requirements for project record documents, including the following:

A. Section includes administrative and procedural requirements for project record documents, including the following: SECTION 017839 - PROJECT RECORD DOCUMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01

More information

Section XV - PER, Design, and Construction Submittal Requirements

Section XV - PER, Design, and Construction Submittal Requirements Section XV - PER, Design, and Construction Submittal Requirements A. Introduction - In an effort to reduce paper and to further implement the Oracle Unifier Project Management System, the Engineering Department

More information

Presented by: Brent Bode, P.E., Tetra Tech, Inc. Low Energy, Non Shear WAS Thickening Alternatives and Design for Grand Rapids, MI WWTP

Presented by: Brent Bode, P.E., Tetra Tech, Inc. Low Energy, Non Shear WAS Thickening Alternatives and Design for Grand Rapids, MI WWTP Presented by: Brent Bode, P.E., Tetra Tech, Inc. Low Energy, Non Shear WAS Thickening Alternatives and Design for Grand Rapids, MI WWTP PRESENTATION AGENDA Project Background and Goals for GR WWTP WAS

More information

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals. SECTION 01300 PART 1 GENERAL 1.1 SECTION INCLUDES A. Description of Requirements B. Submittal Procedures C. Specific Submittal Requirements D. Action on Submittals E. Repetitive Review 1.2 DESCRIPTION

More information

Construction Phase Project Management and Documentation

Construction Phase Project Management and Documentation Construction Phase Project Management and Documentation Bill Mason CDM Smith Outline Design Bidding Construction Start-up & Closeout 2 DESIGN Design Preliminary Engineering Report Plans Specifications

More information

***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014)

***************************************************************************** DRAFT UFGS- 01 XX XX (FEB 2014) DRAFT UFGS- 01 XX XX (FEB 2014) ------------------------ Drafting Activity: USACE UNIFIED FACILITIES GUIDE SPECIFICATION SECTION TABLE OF CONTENTS DIVISION 01 GENERAL REQUIREMENTS SECTION 01 XX XX (FEB

More information

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01340 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Shop drawings, manufacturer's catalog cuts, product data, samples, and attached Shop Drawing/ Catalog

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO Job No.:

WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO Job No.: WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO-00111 Job No.: 16-7003 To Respondent of Record: ADDENDUM 2 July 5, 2017 This addendum, applicable to work referenced

More information

NOTICE OF BOARD MEETING & WORKSHOP

NOTICE OF BOARD MEETING & WORKSHOP NOTICE OF BOARD MEETING & WORKSHOP OF THE BOARD OF DIRECTORS OF THE A MUNICIPAl WATER DISTRICT WILL BE HELD ON WEDNESDAY, NOVEMBER 5, 2014 10:00 A.M. AT THE OFFICE OF THE AGENCY 6075 KIMBALL A VENUE, BUILDING

More information

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017 NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP 697-16-016 July 28, 2017 Reference is made to the Request for Proposal (RFP) to Service Providers for Nevada Shared Radio Replacement Project, upon

More information

Answer: Qualification statement should be provided with the bid.

Answer: Qualification statement should be provided with the bid. Little Diversified Architectural Consulting, Inc. 5815 Westpark Drive Charlotte, North Carolina 28217 Phone: 704-525-6350 Fax: 704-561-8700 Lincoln County Probation Renovation 208 N. Government Street

More information

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01334 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.01 SUMMARY A. Submit to the ENGINEER for review, such working drawings, shop drawings, test reports and data on materials and equipment

More information

TOBERMORY SEWAGE LAGOON

TOBERMORY SEWAGE LAGOON TOBERMORY SEWAGE LAGOON Annual Report January 1 to December 31, 2014 Prepared by: Cherie Young Process & Compliance Technician Ontario Clean Water Agency West Highlands Hub March 31, 2015 Ministry of the

More information

CITY OF RICHMOND SUBDIVISION PLAT AND PUBLIC INFRASTRUCTURE SUBMITTAL, REVIEW AND APPROVAL PROCEDURES

CITY OF RICHMOND SUBDIVISION PLAT AND PUBLIC INFRASTRUCTURE SUBMITTAL, REVIEW AND APPROVAL PROCEDURES SUBDIVISION PLAT AND PUBLIC INFRASTRUCTURE SUBMITTAL, REVIEW AND APPROVAL PROCEDURES CITY OF RICHMOND 112 JACKSON STREET RICHMOND, TEXAS 77469 PHONE: 281-232-6871 FAX: 281-238-1215 CITY OF RICHMOND PUBLIC

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01330 SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide submittals in accordance with the General Conditions as modified by the Supplementary Conditions,

More information

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES SECTION 01340 SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDED A. Contractor shall submit to the Architect/Engineer for review and exception, if any, such working

More information

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER.

SECTION CONTRACTOR SUBMITTALS. A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER. SECTION 01300 - PART 1 - GENERAL 1.1 GENERAL A. All submittals by the CONTRACTOR shall be submitted to the ENGINEER. B. Unless otherwise noted, within 14 days after the date of commencement as stated in

More information

[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards]

[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards] SECTION 01 78 23 - OPERATION AND MAINTENANCE DATA PART I - GENERAL 1.1 SUMMARY A. Operation and Maintenance Data shall be submitted in appropriately-sized binders, with dividers, and organized by each

More information

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA If project is not administered in PRISM, coordinate use of Exhibit 6 submittal schedule with this section. SECTION 01 33 23 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDED

More information

ADDENDUM NO. 1 REQUEST FOR QUALIFICATIONS (RFQ) AND REQUEST FOR PROPOSALS (RFP) FOR. RFQ/RFP No. 15P40. Campus Center East HVAC Unit Replacement

ADDENDUM NO. 1 REQUEST FOR QUALIFICATIONS (RFQ) AND REQUEST FOR PROPOSALS (RFP) FOR. RFQ/RFP No. 15P40. Campus Center East HVAC Unit Replacement ADDENDUM NO. 1 REQUEST FOR QUALIFICATIONS (RFQ) AND REQUEST FOR PROPOSALS (RFP) FOR RFQ/RFP 15P40 Campus Center East HVAC Unit Replacement CHAFFEY COMMUNITY COLLEGE DISTRICT February 26, 2015 CHAFFEY COMMUNITY

More information

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.1 DESCRIPTION A. This specification defines the general requirements and procedures for submittals. A submittal is information

More information

Scope of Services. Project management tasks are estimated based upon anticipated project duration of 52 weeks.

Scope of Services. Project management tasks are estimated based upon anticipated project duration of 52 weeks. Scope of Services Project Understanding The City of Sparks (City) has also requested the HDR Engineering, Inc. (HDR) provided limited shop drawing review and periodic observation during construction and

More information

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia BULLETIN NO. 6 TO THE PLANS AND SPECIFICATIONS FOR JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia EwingCole Architects.Engineers.Interior Designers.Planners

More information

Jacksonville District Master

Jacksonville District Master -01 33 00 (April 2006) From USACE / NAVFAC / AFCESA UFGS UNIFIED FACILITIES GUIDE SPECIFICATIONS Revised thoughout - changes not indicated by CHG tags SECTION TABLE OF CONTENTS DIVISION 01 - GENERAL REQUIREMENTS

More information

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration SECTION 01 340 - SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

Cloud Based Plan Review Process (Applicant)

Cloud Based Plan Review Process (Applicant) 1 Cloud Based Plan Review Process (Applicant) Organize Documentation Process Overview Upload Documents To Mercer Island FTP Site No Initial Submittal? Yes Intake Screening Approved? CST will inform you

More information

Exhibit A Project Identification. Exhibit B Project Charter / Project Intent. Exhibit C Project Scope. Exhibit C Project Schedule

Exhibit A Project Identification. Exhibit B Project Charter / Project Intent. Exhibit C Project Scope. Exhibit C Project Schedule Exhibit A Project Identification Exhibit B Project Charter / Project Intent Exhibit C Project Scope Exhibit C Project Schedule Exhibit D Project Budget Exhibit E Owner Supplied Documents Exhibit F Sample

More information

Dewatering Case Study Rotary Press Versus Screw Press

Dewatering Case Study Rotary Press Versus Screw Press Dewatering Case Study Rotary Press Versus Screw Press OWEA 2012 Annual Conference June 20, 2012 Kyle Novak, P.E. Presentation Overview Project Background Onsite Dewatering Consideration Case Study: Rotary

More information

Section Meetings Section Material and Equipment. None Required

Section Meetings Section Material and Equipment. None Required January 2000 Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK PART 2 PRODUCTS The General Conditions of the Contract, General Requirements and Supplemental

More information

SECTION PROJECT MANAGEMENT AND COORDINATION

SECTION PROJECT MANAGEMENT AND COORDINATION SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Coordination. B. Preconstruction meeting. C. Progress meetings. D. Preinstallation conferences. E. Requests for information (RFI). F. Coordination drawings.

More information

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 013300 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

ADDENDUM #2 September 12, 2018

ADDENDUM #2 September 12, 2018 Physical Plant Services Project Management 1000 Rim Drive Phone: (970) 247-7523 Fax: (970) 247-7555 Project No. 2007-130P18 Whalen Gymnasium Expansion and Renovation for Exercise Science Request for Qualifications

More information

Construction Services Architect / Engineers Guidelines

Construction Services Architect / Engineers Guidelines Construction Services 2016 Architect / Engineers Guidelines TL Architect/Engineer Fee Proposal Format Fee proposals should be formatted in the following content order: Client Information: Project Name:

More information

TAB B-9 RECORD DRAWINGS

TAB B-9 RECORD DRAWINGS TAB B-9 RECORD DRAWINGS Project record drawings and shall be prepared for all University of Arizona projects. The concept Record Drawings shall replace what has previously been called As-Builts. During

More information

SECTION III SUBMITTALS AND APPROVALS

SECTION III SUBMITTALS AND APPROVALS SECTION III SUBMITTALS AND APPROVALS In order to expedite the approval process of new water distribution system and sanitary sewer collection system extensions, the Hilton Head No. 1 Public Service District

More information

Facility P&ID Drawings and why you need them!

Facility P&ID Drawings and why you need them! and why you need them! Graham Nasby City of Guelph Water Services Guelph, Ontario, Canada 2018 ISA Water/Wastewater & Automatic Controls Symposium (WWAC) 7-9 August 2018, Bethesda, Maryland, USA No part

More information

CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT

CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT ADDENDUM NO. 1 TO REQUEST FOR PROPOSALS For EQUIPMENT FOR THE 2014 CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT WASTEWATER TREATMENT PLANT IMPROVEMENT PROJECT:

More information

CITY OF LOMPOC DEVELOPMENT ASSISTANCE BROCHURE ENCROACHMENT PERMITS AND PUBLIC IMPROVEMENT PLANS

CITY OF LOMPOC DEVELOPMENT ASSISTANCE BROCHURE ENCROACHMENT PERMITS AND PUBLIC IMPROVEMENT PLANS CITY OF LOMPOC DEVELOPMENT ASSISTANCE BROCHURE E-10 ENCROACHMENT PERMITS AND PUBLIC IMPROVEMENT PLANS The City of Lompoc has determined that the Engineering Division should administer and issue Encroachment

More information

DIGITAL DATA SUBMISSION STANDARDS Procedures and Guidelines

DIGITAL DATA SUBMISSION STANDARDS Procedures and Guidelines DIGITAL DATA SUBMISSION STANDARDS Procedures and Guidelines 2014 Citizens Wastewater of Westfield - GIS Digital Standards Table of Contents Introduction... 3 Definitions and Terms... 3 Reference Documents...

More information

Design Deliverables. Summary. A. Expectations for Design Deliverables:

Design Deliverables. Summary. A. Expectations for Design Deliverables: Design Deliverables Summary A. Expectations for Design Deliverables: The Design Team is obligated to advance and deliver the project with a professional manner and standard of care that meets the expectations

More information

2017 CDM Smith All Rights Reserved November 2016 SECTION PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS)

2017 CDM Smith All Rights Reserved November 2016 SECTION PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS) ATTACHMENT 5, CONTRACT 13, ADDENDUM 3 2017 CDM Smith 14955-109447 SECTION 01725 PROJECT MANAGEMENT INFORMATION SYSTEM (PMIS) PART 1 GENERAL 1.01 DESCRIPTION A. The Owner and Contractor shall utilize the

More information

State College Area School District

State College Area School District State College Area School District The following is a guideline for project design submittals to the Facility Committee of the State College Area School District. During the design process the committee

More information

SECTION ADMINISTRATIVE REQUIREMENTS

SECTION ADMINISTRATIVE REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Electronic document submittal service. B. Preconstruction meeting. C. Progress meetings. D. Construction progress schedule. E. Coordination drawings. SECTION 013000

More information

Drawings or Data are Submitted: For Approval For Information B Training Plan Polymer Make Down Units 01820

Drawings or Data are Submitted: For Approval For Information B Training Plan Polymer Make Down Units 01820 Date: 2/1/18 P1-101 Submittal Transmittal Project Name: P1-101 Sludge Dewatering and Odor Control at Plant 1 To: Orange County Sanitation District 10844 Ellis Avenue Fountain Valley, CA 92708 Attn: Plant

More information

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following: SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

SECTION 2 GENERAL REQUIREMENTS

SECTION 2 GENERAL REQUIREMENTS SECTION 2 GENERAL REQUIREMENTS 2-1 ENGINEER REQUIRED: All plans and specifications for Improvements which are to be accepted for maintenance by the County and private, on-site drainage and grading shall

More information

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES

STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES STANDARD SPECIFICATIONS SECTION 01330 SUBMITTAL PROCEDURES PART 1 GENERAL 1.1 DESCRIPTION A. Section includes general requirements and procedures related to preparation and transmittal of Submittals to

More information

00-General Drawings. Doc. no.: NA-00-STS002

00-General Drawings. Doc. no.: NA-00-STS002 Gæðaskjal (GSK) GSK-1773 Date of issue: 24.11.2016 Revision no.:2.0 Responsible: Einar Friðgeir Björnsson Editor: Rafn Magnús Jónsson 00-General Drawings Doc. no.: NA-00-STS002 This standard technical

More information

SECTION SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum

SECTION SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum SECTION 013201 - SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum Pay Unit price breakdown) shall be developed and ultimately

More information

This Call for Qualifications does not require the preparation of a design proposal.

This Call for Qualifications does not require the preparation of a design proposal. EDMS# 211137 I. Introduction This Call for Qualifications invites professional artists, or artist team, to participate in a two-stage selection process to develop an original, public art work for Port

More information

Detail Design For Pavement Rehabilitation on Trunk Highway 14 From Tracy to Revere

Detail Design For Pavement Rehabilitation on Trunk Highway 14 From Tracy to Revere Detail Design For Pavement Rehabilitation on Trunk Highway 14 From Tracy to Revere Section 1 Introduction and Intersection Information State Project (SP) 6401-37 on MN Highway 14 SP 6401-37 is a Bituminous

More information

SAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT FORMAL INVITATION FOR BIDS ANNUAL CONTRACT FOR WELL MAINTENANCE SERVICES ADDENDUM NO.

SAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT FORMAL INVITATION FOR BIDS ANNUAL CONTRACT FOR WELL MAINTENANCE SERVICES ADDENDUM NO. SAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT Issued By: D. Anthony Rubin Date Issued: May 21, 2015 BID NO.: 15-7031 FORMAL INVITATION FOR BIDS ANNUAL CONTRACT FOR WELL MAINTENANCE SERVICES ADDENDUM NO.

More information

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 01 33 00 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

STATEMENT OF WORK Environmental Assessment for the Red Cliffs/Long Valley Land Exchange in Washington County, Utah

STATEMENT OF WORK Environmental Assessment for the Red Cliffs/Long Valley Land Exchange in Washington County, Utah I. Introduction STATEMENT OF WORK Environmental Assessment for the Red Cliffs/Long Valley Land Exchange in Washington County, Utah The Bureau of Land Management s (BLM) St. George Field Office (SGFO) requires

More information

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS SECTION 01300 SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections,

More information

Working Drawing Manual

Working Drawing Manual Working Drawing Manual 2012 Table of Contents Section 1 Working Drawing Types... 1 1.1 General... 1 Section 2 Processing Steps... 1 2.1 Project Manager... 1 2.2 Engineering Document Unit... 2 2.3 Contractor...

More information

JOB DESCRIPTION. Coachella Valley Water District October 12, DEPARTMENT: Facilities and Maintenance REPORTING RELATIONSHIP:

JOB DESCRIPTION. Coachella Valley Water District October 12, DEPARTMENT: Facilities and Maintenance REPORTING RELATIONSHIP: Coachella Valley Water District October 12, 2017 TITLE: Electronic Technician II SECTION: Electronics Shop DEPARTMENT: Facilities and Maintenance REPORTING RELATIONSHIP: Reports to: Electronics Supervisor,

More information

Vanderbilt University Standard Specification Revised 2/6/08

Vanderbilt University Standard Specification Revised 2/6/08 SECTION 01 78 23 OPERATION AND MAINTENANCE DATA PART 1 GENERAL 1.01 RELATED SECTIONS A. Section 01 77 00 Closeout Procedures B. Section 01 78 39 Project Record Documents 1.02 SUMMARY A. This section provides

More information

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01 33 23 - SHOP DRAWINGS, PRODUCT DATA, AND PART 1 - GENERAL 1.1 SUMMARY A. Products include, but are not limited to, the following construction submittals: 1. Shop Drawings. 2. Product Data. 3.

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 013300 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply

More information

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES DIVISION 1 GENERAL REQUIREMENTS SECTION 01 33 00 PART 1 - GENERAL 1.1 SUMMARY A. This section includes administrative and procedural requirements for submittals required for performance of the work, including

More information

CHAPTER 11 PRELIMINARY SITE PLAN APPROVAL PROCESS

CHAPTER 11 PRELIMINARY SITE PLAN APPROVAL PROCESS CHAPTER 11 PRELIMINARY SITE PLAN APPROVAL PROCESS 11.01.00 Preliminary Site Plan Approval 11.01.01 Intent and Purpose 11.01.02 Review 11.01.03 Application 11.01.04 Development Site to be Unified 11.01.05

More information

SUGGESTIONS FOR IMPROVING THE STRUCTURAL STEEL SHOP DRAWING PROCESS

SUGGESTIONS FOR IMPROVING THE STRUCTURAL STEEL SHOP DRAWING PROCESS SUGGESTIONS FOR IMPROVING THE STRUCTURAL STEEL SHOP DRAWING PROCESS SEAC/ RMSCA Steel Liaison Committee May 17, 2006 Disclaimer SEAC, RMSCA, nor its committees, writers, editors and individuals who have

More information

ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030

ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030 ADDENDUM NO. 3 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO. 2018-008-COM.00030 To: Prospective Bidders of Record Date: January 8, 2019 The following changes, additions, revisions, and/or deletions

More information

MnDOT Contract Exhibit A - Scope of Services

MnDOT Contract Exhibit A - Scope of Services Introduction Information Introduction This Scope of Services represents work on two individual highway improvement projects as described below. The State intends to let two of the projects as separate

More information

Anticipated schedule, Page 2. Change the Contract Term from 635 Days to be 1,127 Days.

Anticipated schedule, Page 2. Change the Contract Term from 635 Days to be 1,127 Days. This addendum is hereby made part of the Request for Bid for the above-named project and shall be taken into consideration by all firms preparing a submittal on this project. Acknowledge receipt of this

More information

Working Drawing Procedure

Working Drawing Procedure Working Drawing Procedure June 2007 Prepared by Structural Engineering & Construction Services 1.0 Working Drawing Procedure 1.1 General There are two primary types of working drawings, those requiring

More information

Bid No. B14-02 Building 100 HVAC Improvements

Bid No. B14-02 Building 100 HVAC Improvements Bid No. B14-02 Building 100 HVAC Improvements Addendum No. 1 This Addendum No. 1 sets forth modifications to portions of the bid and contract documents for the above-referenced work described as: Building

More information

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

A. Action Submittals: Written and graphic information that requires Architect's responsive action. SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

A. Action Submittals: Written and graphic information that requires Engineer's responsive action.

A. Action Submittals: Written and graphic information that requires Engineer's responsive action. SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Electronic Document Review (EDR)

Electronic Document Review (EDR) Electronic Document Review (EDR) Submittal Requirements Table of Contents Introduction... 3 Electronic Document Review Submittals:... 4 Plans... 4 Plat... 4 Forms... 4 Correspondence... 5 Plan Revisions...

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 3300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

September 6, 2018 CITY OF BERKELEY SHATTUCK RECONFIGURATION AND PEDESTRIAN SAFETY PROJECT SPECIFICATION NO C ADDENDUM NO.

September 6, 2018 CITY OF BERKELEY SHATTUCK RECONFIGURATION AND PEDESTRIAN SAFETY PROJECT SPECIFICATION NO C ADDENDUM NO. Department of Public Works Transportation Division September 6, 2018 CITY OF BERKELEY SHATTUCK RECONFIGURATION AND PEDESTRIAN SAFETY PROJECT SPECIFICATION NO. 17-11090-C ADDENDUM NO. 3 Dear Bidder: The

More information

Attachment C to Modification # 6 to VA HSMM. Schedule of Fees

Attachment C to Modification # 6 to VA HSMM. Schedule of Fees Task A. Perform radio asset inventory, needs assessment, and project expected growth. B. Document existing radio frequency authorizations. Devise a frequency reuse strategy. Determine the capacity of the

More information

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 General

More information

SUBMITTAL PROCEDURES

SUBMITTAL PROCEDURES SUBMITTAL PROCEDURES PART 1 GENERAL The ASPA Project Engineer (APE) may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective

More information

January, 2014 Page 1 of 5

January, 2014 Page 1 of 5 Part 1 General 1.1 General Instructions.1 These instructions add information to all articles of contracts with professionals..2 For each project, McGill University Facilities Operations and Development

More information

Controlling Changes Lessons Learned from Waste Management Facilities 8

Controlling Changes Lessons Learned from Waste Management Facilities 8 Controlling Changes Lessons Learned from Waste Management Facilities 8 B. M. Johnson, A. S. Koplow, F. E. Stoll, and W. D. Waetje Idaho National Engineering Laboratory EG&G Idaho, Inc. Introduction This

More information

SECTION 3 SUBMISSION REQUIREMENTS

SECTION 3 SUBMISSION REQUIREMENTS SECTION 3 SUBMISSION REQUIREMENTS Table of Contents Page No 3.1 GENERAL... 3 3.2 COORDINATION WITH OUTSIDE AGENCIES... 3 3.3 PRELIMINARY DESIGN... 4 3.4 FINAL DESIGN... 5 3.4.1 GENERAL... 5 3.4.2 PHASE

More information

PREPARATION GUIDELINES FOR UDFCD MAINTENANCE SITE PLAN

PREPARATION GUIDELINES FOR UDFCD MAINTENANCE SITE PLAN PREPARATION GUIDELINES FOR UDFCD MAINTENANCE SITE PLAN Overview The Urban Drainage and Flood Control District (District) is now requiring that a Maintenance Site Plan (Plan) be submitted for all pond projects

More information

Designer CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer

Designer CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer Designer CM/Owner s Rep Prime Contractor SubContractor Supplier Manufacturer Construction Documents 1.1 to 1.6 Create Submittal Log 1.1 Construction Docs Focus of this process is to transmit submittal

More information

Appendix-1. Project Design Matrix (PDM)

Appendix-1. Project Design Matrix (PDM) Appendix-1 Project Design Matrix (PDM) Appendix-I Project Design Matrix (PDM) Version 1 PDM: Electric Power Technical Standards Promotion Project in Vietnam Duration: 3 Years (March in 2010 to January

More information

Emergency responder radio coverage in new buildings. California Fire Code Section is hereby amended to read:

Emergency responder radio coverage in new buildings. California Fire Code Section is hereby amended to read: Sunnyvale 2013 Fire Code Section 510 16.52.510. Emergency responder radio coverage. (a) Emergency responder radio coverage in new buildings. California Fire Code Section 510.1 is hereby amended to read:

More information

APPLICATION FORM FOR INFRASTRUCTURE NOC

APPLICATION FORM FOR INFRASTRUCTURE NOC APPLICATION FORM FOR INFRASTRUCTURE NOC Submission Type New Resubmission (Previous Reference No): Arch. Str. HVAC EHS Others Revision /Amendment (Infrastructure NOC Reference No): Arch. Str. HVAC EHS Others

More information

SECTION OPERATION AND MAINTENANCE DATA

SECTION OPERATION AND MAINTENANCE DATA SECTION 01787 OPERATION AND MAINTENANCE DATA PART 1 GENERAL 1.01 SUMMARY A. Compile product data and related information appropriate for OWNER's maintenance and operation of products furnished under Contract.

More information

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION 01 3100 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

TOWN of LAKESHORE SITE PLAN CHECKLIST

TOWN of LAKESHORE SITE PLAN CHECKLIST TOWN of LAKESHORE SITE PLAN CHECKLIST Last Revised December 17, 2009 Project Name: Project Location: Date Submitted: Name Phone Number E-mail Address Owner: Contractor/ Engineer: ( ) ( ) Applicant: ( )

More information

Stanford University-Facilities Design Guideline SECTION Plans Review Submission Guidelines

Stanford University-Facilities Design Guideline SECTION Plans Review Submission Guidelines SECTION 01 33 00 Plans Review Submission Guidelines PART 1 GENERAL 1.01 OVERVIEW A. University Plans Review Process: 1. The process by which the Designer s schematic, design development, construction documents

More information

PROCEDURE FOR PROCESSING WORKING DRAWINGS

PROCEDURE FOR PROCESSING WORKING DRAWINGS PROCEDURE FOR PROCESSING WORKING DRAWINGS MAY 2005 Procedure for Processing Working Drawings GENERAL: The procedure for the review and processing of working drawings provide for two primary types of drawings,

More information

SECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents.

SECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents. SECTION 01 3000 PART 1 GENERAL 1.1 SECTION INCLUDES A. Electronic document submittal service. B. Preconstruction meeting. C. Submittals for review, information, and project closeout. D. Submittal procedures.

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-11 47 00 (August 2017) ----------------------------- Preparing Activity: USACE Superseding UFGS-11 47 00 (February 2009) UNIFIED FACILITIES GUIDE SPECIFICATIONS References

More information

Design Appendix: Throughout this document various supporting appendixes are referenced. These appendixes can be found at

Design Appendix: Throughout this document various supporting appendixes are referenced. These appendixes can be found at Aetna Information Services (AIS) http://ot.aetna.com March 16, 2016 Ver 21 Design Phase / Process This sequence of eight design weeks DW s leads the project team from project kickoff through to construction

More information