Subsea system readiness level assessment

Size: px
Start display at page:

Download "Subsea system readiness level assessment"

Transcription

1 doi: /ut International Journal of the Society for Underwater Technology, Vol 31, No 2, pp 77 92, 2013 Subsea system readiness level assessment Sirous Yasseri Safe Sight Technology, London, UK Technical Paper Abstract Both the American Petroleum Institute (API) 17N: 2009 and Det Norske Veritas (DNV) RP-A203 (2011) recommend that the technologies inserted into subsea installations should be assessed during design and manufacturing using a technology readiness level (TRL) scale. This should be used as a measure of maturity of all the individual technologies, for qualification and readiness assurance. This paper proposes the creation of a system-based approach for managing the development of subsea systems and making effective decisions to ensure the efficient progress of the project. It recommends complementing TRL with an integration readiness level (IRL) scale, to address IRL between the inserted technologies, along with a system readiness level (SRL) scale to assess the overall project status. It also presents a method for combining the current TRL scale and the proposed new IRL scale to determine an estimate of SRL at all stages of a subsea system development. This provides a composite metric for determining the system readiness level for project delivery. The application of the new proposed scales is demonstrated using a case example. Keywords: system readiness level (SRL), technology readiness level (TRL), integration readiness level (IRL), subsea technology qualification, subsea production technical risk Acronym list BoD basis of design: This is the system s engineering requirements. DP dynamic positioning DSM design structure matrix FAT factory acceptance test IRL integration readiness level Integration is the combining of separate components into a seamless unit. This is an integration-specific metric, to determine the integration readiness between two or more components, and/or subsystems (hardware and/or software). SRL system readiness level This is a metric that incorporates the maturity level of the integrated system, as well as the interoperability of the entire system. SRLest system readiness level estimate This is the SRL estimate at a review stage, which determines the current state of the system readiness. It is a derived metric, which aggregates TRL and IRL of all components of a system that may be at various levels of development at a given time. TRL technology readiness level This is a metric for determining technology maturity before incorporating into a system. address: sirous.yasseri@gmail.com 1. Introduction Technology readiness levels (TRLs) were first used by NASA in the 1980s as part of an overall technology risk management process. By the early 1990s, TRLs were routinely used within NASA to support technology maturity assessments and consistent comparisons of the maturity between different technologies (Mankins, 2002). The US Department of Defense (USDOD) adopted TRL for risk assessments in 1999 (USDOD, 1998). Current USDOD guidance (2008; 2009) requires the use of TRL (or an equivalent methodology) as part of an overall system technical risk assessment. These TRLs range from 1 to 9, with 9 signifying the highest degree of readiness and 1 the lowest. In the UK the Ministry of Defence (MOD) adopted TRL to improve technology management to reduce the project delay. In 2007, the UK MOD updated its TRLs section to bring more focus to the importance of project and sub-project interaction when conducting a TRL assessment (MOD, 2008). The MOD replaced NASA s broad generic terms with definitions aligned to specific milestones (MOD, 2011). Because of the success of TRL, a variety of other maturity metrics have been proposed as decision support tools (Bilbro, 2007), such as design readiness level; manufacturing readiness level; software readiness level; operational readiness level; human readiness levels; habitation readiness level; and capability readiness levels. Many industries have embraced the concept of TRL as a metric for measuring technology maturity. The American Petroleum Institute (API) RP 17N (2009) adopted TRL methodology for subsea equipment qualification and Det Norske Veritas (DNV) RP-A203 (2011) followed later. Bureau Veritas (2010) addresses the same issue using a risk-based approach. The API recommended practice is now written into major petroleum companies procedures as a tool to assess the level of progress of subsea design, fabrication and components qualification. Such policies require contractors to hold design and manufacturing reviews using TRL. Examples of TRL application to the offshore oil and gas can be found in US Mineral Management Service (MMS, 2010) and Millheim et al. (2011). 77

2 Yasseri. Subsea system readiness level assessment Undoubtedly, TRL is a useful tool for determining a technology s maturity before inserting it into a system. However, TRL was not intended to assess the integration of technologies and hence the readiness of the complete system comprising them. It was originally used by NASA and later by the USDOD as a tool for tracking contractors progress (Gove et al., 2007; Sauser et al., 2008a). Therefore, expecting that TRL will be able to monitor the readiness of a system comprising a collection of technologies, which are individually assessed against TRL, is optimistic. If the integration of two pieces of technology follows the same maturation path, just as the technologies do, then TLR can provide an assessment of integration readiness, which is true towards the high maturity end of TRL scale. However, TRL is not always capable of capturing the many small errors that can occur when two different components of software and/or hardware are brought tighter to exchange data. The need to explicitly address the integration of technology is evident from failures of high profile projects. For example, in NASA s Mars Climate Orbiter, the failure of two independently evaluated technologies to use the same units (i.e. metric versus imperial) contributed to the loss of the spacecraft (Sauser et al., 2008b). Discovering that different components designed and fabricated by different vendors do not match or were designed for a different set of conditions is not rare. The problem of integration becomes more acute when there are a feed-back and feed-forward loops between vendors, as changes in one part affect the other, and hence several iterations may be required to resolve the interdependent design issues, even though each design, on its own, looks complete. TRL, as used, determines where the readiness of a module or component lies on the scale, and integration readiness between modules or the entire system with the environment is only implied or is not assessed. This paper presents the new concept of an integration readiness level (IRL) scale. Just as a TRL has been used to assess the risk associated with developing components, an IRL is designed to assess the risk associated with integrating these components. The introduction of an IRL to the assessment process not only provides a check as to where the technology is on an integration readiness scale, but also presents a direction for improving integration with other technologies. Obviously, at a given review stage components may not be at the same level of readiness. A methodology is proposed to combine TRL and IRL into one composite index, termed SRL est, which is an estimate of a third scale termed the system readiness level (SRL), a third scale. The resultant SRL est can provide an assessment of overall system development and identify problem areas that require management attention. The following section introduces a methodology to map a subsea system, and section 3 discusses the current TRL for the subsea component readiness. The paper then introduces the new IRL concept in section 4 and describes the new concept of SRL in section 5. The case example in section 6 demonstrates how a composite scale can be derived and used in conjunction with the SRL table to determine what has been accomplished to date. Section 7 discusses issues of the subsea system readiness and section 8 summarises the conclusions of the paper. 2. Mapping the subsea system architecture The system architecture is a relationship map, which shows the position of components and/or modules and their relationship with each other (Yassine et al., 2003; Yassine and Braha, 2003; Danilovic and Browning, 2007). Components can implement one or more functions, and interfaces between components (i.e. linkages) must be well defined. A component is a hardware (or a software) object with clearly defined interfaces, which embodies specific functionality and interacts with other components and/or with the environment to enable the overall system to function. In this paper technologies and components are used interchangeably, and it also takes readiness and maturity to be the same entity and uses interchangeably. An effective method of understanding a complex system is to: identify the system boundaries, i.e. the terminal points and where the system integrates with its environment (or neighbours); break it down into components (and/or modules), which are easier to understand; and identify the interfaces (i.e. dependencies or relationships) between the components (or modules) that enable the system to function as a single entity (Sharman and Yassine, 2004). Subsea systems are generally modularised for ease of installation and parallel engineering. Modularising requires specifying the architecture and interfaces governing the modules interactions. In a modularised design the system components are spilt up and assigned to various modules according to a formal architectural plan (Eppinger, 1991). Modules are distinct parts of a larger system; although designed and produced separately they must function together. Modularisation enables managing complexity and parallel work, such as sourcing from different 78

3 Vol 31, No 2, 2013 suppliers and accommodating future expansion. Good architecture enables each individual module and its interfaces to be changed out without undermining the functionality of the system. A failed module can be retrieved and repaired or replaced. Although in theory modules can be organised in such a way to minimise the number of interfaces, the manufacturer s specialisation largely determines the subsea modules and their interfaces. This does not undermine the concept of modularisation, as the linear (sequential) nature of the subsea production system determines the line-up of components into natural modules. Fig 1 shows the block diagram of a simple system consisting of ten components grouped into two modules at an advanced stage of development. There are interfaces between components of each module and between components of the two modules. Interfaces between two components are shown by a double-headed arrow, implying that the readiness of two components to be integrated is interdependent. The arrow is not intended to indicate the direction of flow, but to show dependency. This paper assumes dependency and interface to be the same entity. The system matrix is a simple representation of a system architecture, which captures the relationship between different components. This is also a suitable tool for system modelling and analyses, especially for the purposes of decomposition and integration. Matrix-based approaches are used for managing complex systems and interactions of their elements (Steward, 1981). The DSM (Simon, 1962), which is a square matrix, has been used in modelling of a variety of products, processes and organisational structures in the past (Browning, 2001; Browning and Eppinger, 2002). DSM models can incorporate the concepts of hierarchy (Eppinger and Browning, 2012), direction of information flow and dependency. In this paper, a variation of DSM is tailored, for representing the subsea architecture and is used as a visual aid for decomposition and housekeeping when combining TRL and IRL into a single index. However, it has a wider application in grouping together components forming modules for enhancing manufacturing flexibility by reducing the number of interfaces (Eppinger and Browning, 2012). The block diagram of Fig 1 is mapped into design structure matrix (DSM) as shown in Fig 2. The DSM maps the elements of a system to each other (like a two-way table), enabling concise representation and integration analysis. One reads across a row of the matrix to see where the element in that row sends its outputs and reads down a column to see from where the element in that column receives its inputs (Browning, 2001). For example, the element E provides an output to elements A, D, F and J (reading across row 6) and receives an input from element A, D, F and J (reading down column 6). Hence a component location is known by its column and row. Information about dependency or interface is added by using a marker in the cells to represent relationships (x in Fig 2). An off-diagonal x signifies the A to F IRL=6 A to E E F ENV=5 A TRL=6 C IRL=4 IRL=6 B D TRL=6 D to E D to H IRL=6 G H IRL=4 IRL=4 IRL=4 I TRL=6 J ENV=5 C to J Fig 1: The block diagram for a system with two modules and 10 components (A to J). The double arrows indicate the interfaces between connected components 79

4 Yasseri. Subsea system readiness level assessment A B C D E F G H I J ENV A A B B C C D D E E F F G G H H I I J J ENV Fig 2: DSM for the system shown in Fig 1. Components A to J are mapped along the diagonal and interfaces are indicated by a maker dependency (interface) of one component on another. The numerical values of X in Fig 2 are the IRL of the interacting components; they may be different and thus no symmetry is implied. Fig 2 shows that C and B are going to be connected. The readiness of C to be integrated with B is noted at the intersection of column 3 and row 4, and the readiness of B to be integrated with C is noted at the intersection of column 4 and row 3, which are not necessarily equal. Matrix-based tools provide some insight into the internal relationship of a complex system (i.e. a dependency map and their complexity); however, they do not expose the logic behind these dependencies. That is, if component A is shown to relate to component F, it is not clear why and how this relationship exists and where it originates from. Such information can be represented on block diagrams. The value of the relationship maps is to be able to show/capture that element A is dependent on F through some characteristic of A. In doing so, the analyst would understand better the complexity of a system and, in turn, has more information to manage dependencies and leverage them to improve system performance and mange interfaces between elements (Eppinger and Browning, 2012). The block diagram of Fig 1 offers an alternative method to expand the relationship maps. 3. Technology readiness level Metrics are an integral part of management activities for performance measurement, risk management, quality control and assurance, and maturity level assessment. Most organisations successfully employ various metrics in project management and system engineering. The primary purposes of any metric are: identify critical parameters; establish milestones to assess progress; provide direction for risk management/ mitigation; establish a common understanding of progress; and establish entry and exit criteria for major milestones. TRL satisfies all the requirements listed above. Given the pragmatic benefits of TRL concept, API (2009) adopted a similar scale. API s TRL has 8 levels, starting at 0 being unproven idea and ending with 7 as the highest level of maturity, which is proven in the field. Table 1 is an adaptation of API s TRL, where 0 to 6 (more or less) follows 1 to 7 the NASA s TRL, and API s 7 combines NASA s 8 and 9. The dependencies between modules and the dependency of the system to its environment are not explicitly addressed by API s TRL. TRL does not completely capture the risk involved in the adopting a new technology, since it does not address the architectural needs related to integration. Various studies (Mankins, 2002; Shishko et al., 2003; Valerdi and Kohl, 2004; Dowling and Pardoe, 2005; Smith, 2005) have discussed the inadequacy of TRL to address the technology integration issues. They have also stressed the need for metrics and 80

5 Vol 31, No 2, 2013 Table 1: TRL for subsea technology readiness level assessment (API, 2009) Phase TRL Development stage Development stage definition System validation 7 Field proven Production system field proven 6 System installed Production system installed and tested Technology validation 5 System tested Production system interface tested 4 Environment tested Preproduction system environment tested 3 Prototype tested System function, performance and reliability tested Concept validation 2 Validated concept Experimental proof of concept using physical model tests 1 Demonstrated concept Proof of concept as desk study or R&D experimentation 0 Unproven concept Basic research and development (R&D) in papers Production unit integrated into intended operating system, installed and operating in the same environment and operating conditions for more than 10% of its design life with acceptable reliability, demonstrating low risk of early life failures. Complies with all requirements of TRL 5. Production unit or full-scale prototype built and integrated into intended operating system. Full interface and functional test programme performed in intended or closely simulated environment and operated for less than three years. New technology equipment may require additional support for first 12 to 18 months of operation. Complies with all requirements of TRL 4. Designed and built as production unit or full-scale prototype and integrated into intended operating system with full interface and functional test, but not usually in intended field environment. Complies with all requirements of TRL 3. Designed and built as a production unit or full-scale prototype and put through qualification programme in simulated environment (e.g. hyperbaric chamber to simulate pressure) or actual intended environment (e.g. subsea environment) but not installed or operating. Reliability testing is limited to demonstrating that prototype function and performance criteria can be complied within the intended operating condition and external environment. Prototype built and put through generic functional and performance tests. Reliability tests are performed in relevant laboratory testing environment, including reliability growth tests, accelerated life tests and robust design development test programme. Tests are performed without integration into broader system. The extent of application compliance requirements are assessed and potential benefits and risks are demonstrated. Concept design or novel features of design validated by physical model, system mock-up or dummy, and functionally tested in laboratory environment. No design history. No environmental tests. Materials testing and reliability testing performed on key parts or components in testing laboratory prior to prototype construction. No design history. Essentially desk study not involving physical models but may include R&D experimentation. Technology concept and/or application formulated. Concept and functionality proven by analysis or reference to features common with/to existing technology. Basic scientific/engineering principles observed and reported in papers. No analysis or testing completed available. No design history. 81

6 Yasseri. Subsea system readiness level assessment methodology for the coupling and measuring the maturity of multiple technologies within systems. 4. Integration readiness level Integration is the process of assembling the system from its components (Buede, 2000). This seems to imply that putting together a system from its components entails no complication, since components are built from specifications, which are recognisable to any system engineer. However, integration can be a complex process containing multiple overlapping and iterative tasks to create a delivery system, built to the user requirements and that will function in the marine environment. The need for a reliable method becomes more imperative as a system s complexity increases and components are sourced from diffident manufacturers. Water depth and availability of installation vessel (the deck space for assembling components) and crane capacity could demand a specific interface type and hence add to complexity. A technology can only be successfully inserted into a system if its functionality, maturity and compatibility allow it to integrate with the rest of the system. The integration should not pose a problem if the technology and system evolve along similar maturation paths. However, the core technology components of a system receive more attention than the linkages between them. Inadequately conceived linkages can cause the integration of components from different suppliers to be problematic. The application of metrics to support integration has been extensively used in the computer industry to define coupling of components (Orme et al., 2006; 2007). Mankins (2002) proposes an integrated technology analysis methodology to estimate an integrated technology index and used it for a comparative ranking of competing systems. Mankins highlights the difficulty of using the TRL index when choosing between alternatives. The USDOD and MOD developed a technology insertion metric that includes an integration maturity level (Dowling and Pardoe, 2005). Gove et al. (2007) created an IRL to measure integration maturity on a scale similar to TRL. An IRL metric should be able to: determine the integration maturity between two or more components and/or modules; provide a means to reduce the uncertainty in integrating new technology into a system; meet the system requirements in terms of delivery time and functionality; and provide a common platform for tracking the system development and maturity assessment (Sauser et al., 2008a). For a metric to be useful (Dowling and Pardoe, 2005), it must be: unambiguous; understood by stakeholders with little effort; adequately measure the integration maturity; mirror the TRL for ease of implementation; and simple to apply. By drawing upon these studies, this paper extends the same concept to the subsea technology integration. Table 2 shows the proposed metric to measure the subsea IRL, which moves in parallel with TRL. IRL, as TRL, consists of three stages: (1) concept validation; (2) technology validation; and (3) system validation (see Table 2). Concept validation is about deciding if a number of technologies can be brought together to perform a function. Clarity and differentiation are important factors at this stage. Thus IRL 0 2 are considered fundamental to describing the three principles of integration, namely interface, interaction and compatibility. The next stage is technology validation, which is defined as a conformance to rules. Thus IRLs 3 5 are about assurance that an integration solution is in compliance with specifications. The final stage is system validation, which relates to practical considerations. IRLs 6 and 7 are about the assurance afforded by integration testing (in-place testing and actual performance in service). There are also three aspects to the readiness measure: (1) readiness of components to be integrated into a module; (2) readiness of modules to be connected together to make an assembly; and (3) the readiness of the assembly to be integrated into the marine environment. Both components and modules are tested at the factory for compliance. The factory acceptance test (FAT) qualifies a module as ready to be transported to the site (i.e. IRL exceed 4). The assemblies of a few modules are leak-tested at the site to assure their interface readiness for deployment. IRL must be 5 before it can be installed. Now that both the technologies and integration elements can be assessed and mapped along a numerical scale, the next challenge is to develop a metric that aggregates TRL and IRL. 5. Systems readiness level The application of an IRL in the assessment process provides a check as to where the technology maturity is on an integration readiness scale. Just as a TRL has been used to assess the risk associated with developing technologies, an IRL is designed to assess the risk associated with integrating these 82

7 Vol 31, No 2, 2013 Table 2: IRL for subsea technology readiness level assessment Phase IRL Development stage Development stage definition System validation Technology validation Concept validation 7 Integration is field proven through successful operations 6 Integration is completed and qualified through sufficient and rigorous testing in the marine environment 5 The integration has been verified and validated with sufficient detail for the system to be deployable 4 There is sufficient details to assure interoperability between technologies necessary to establish, manage and assure the integration 3 There is sufficient detail in the control and assurance of the integration between technologies to deliver the required functionality 2 There is sufficient evidence of compatibility between technologies within the system, namely they will work together and can be integrated with ease 1 There is some level of specificity to the system functionality to allow identification of linkage between technologies 0 The interface, i.e. the linkage, between technologies can be identified/ characterised with sufficient clarity The integrated subsea system is in production and is in compliance with all its functionality requirements. Inserted components are fully integrated and comply with all performance requirements decided at the outset. All components are maturing to TRL 7. The integrated subsea system is operating successfully with sufficient reliability for more than 10% of its service life. All interfaces meet and exceed all requirements of IRL 5 and below. The entire system is installed and tested both at component level and at system level. The interfaces of assemblies are proven to be reliable. Interfaces compatibility are assured by testing in the marine environment. The installed system is being commissioned and its functionality tested. The subsea system s integration meets all requirements of IRL 4 and below. Various parts of the subsea system are tested and interactions between interfaces are verified through testing in the factory and on the site. Installation contactor s procedures and tooling are in place and verified. Special tools and connectors are on the site and seabed is ready to host. The interfaces of all inserted technologies meet all requirements of IRL 3. Partly assembled system is tested on the site and the compatibility of interfaces is verified for the full design specifications. All integration issues and problems with interactions between various technologies have been teased out. Interface requirements are documented and interface management is in place to coordinate the flow of information between contactors. Quality control and assurance are in place. All requirements of IRL 2 are complied with. The system performance requirements are developed and translated into specifications for interfacing components, modules and assemblies. The specifications include performance requirements, functionality, environment and interface with other systems already in production. Technologies to be inserted into system are demonstrated to work together, either by previous filed proven records or by isolated factory tests. It can be shown that the constituent components can work together and realistically can perform the required function, but may need future work. An interoperability check is made on the components of the system to assure their compatibility. Either similar assembly is already in use, or proven in qualifying test. All likely problems can be solved. Special tools and connectors are identified. Interdependencies of components are identified and the channels for two-way flow of information/data are determined. Special needs are known by now. The concept has taken shape and refined to a point where the basic dimension, materials, technology need, interfaces between them etc. have been developed. It is judged that all needed technologies can be made into a seamless system. The concept or concepts may not meet all requirements, but there is a promise to meet all functionality requirements by additional efforts. The linkage between components and modules have been characterised and are judged as achievable. The description of functionality and interfaces is general without reference to specific performance. The concept has been advanced to a level that the physical principles can be communicated though reports and sketches. 83

8 Yasseri. Subsea system readiness level assessment technologies. Table 3 defines a SRL scale that incorporates the maturity level of components and the interoperability of the entire subsea system. Sauser et al. (2008a) proposed a method to combine the TRLs and IRLs for a system under development, which involves matrix operation. In the appendix, a simpler methodology is outlined to aggregate TRL and IRL into a single metric, termed SRL est. This methodology requires all components to be assessed using TRL (Table 1), as well as their readiness for integration with each other and the environment to be assessed using IRL (Table 2). The method combines TRLs and IRLs into a single composite metric, yielding a numerical value between 0 and 7. The estimated SRL est is used in Table 3 to judge what the system readiness is (compared with what it should be) at the time of assessment. Building a spreadsheet (see the case example in section 6) will enable the user to regularly review the state of system readiness and track the project s progress. 6. Case example Fig 3 shows a block diagram of a system with ten components (A to J) arranged in two modules. The TRL of each component is judged using Table 1 and is noted on its node. The IRL between two components is shown by a double-headed arrow. The IRLs of components with dependencies are judged using Table 2 and are shown on the double arrows. In this example some components of the first module have interface with components of the second module. Modules are transported to the site after completion of the FAT, which is a strength test (hydrotested at ~1.5 times of the design pressure). Its primary focus is the weld quality. At the site, a few of these modules are assembled and hydro-tested at ~1.25 times of the design pressure tested to detect interface leaks. These two tests determine if a module is ready for integration into the marine environment. Finally, the entire subsea system is hydro-tested at 1.1 times the design pressure. The intention is to assure no leakage at the assembly interfaces. These are the three minimum hydro-tests, with the relevant load factors as specified in applicable codes. Some codes, e.g. API 17N or ASME B31.8 (2010), replace the third test with three separate hydro tests, known as post installation test, integration test and operational test. In addition, sometimes a shallow water test is also performed by immersing a module into the water to ensure the centres of gravity and of buoyancy are correct. The components of this system are mapped onto a DSM as shown in Fig 4. The system matrix is extended horizontally to show the calculation details. Columns and rows are numbered for the ease of referencing. The off-diagonal numerical entries are IRL, corresponding to an interface readiness between two components. Not every component of the system interacts with every other component, but all of the component interactions that do exist are essential to achieve desired functionality. IRLs are taken from Fig 3 and entered into DSM of Fig 4. For example, 6 at the intersection of components A (row 3) and F (column 9) is the IRL of their interface; the same value is entered at the intersection of components F (row 8) and A (column 4), but do not need to be the same value. The matrix diagonal represents integration of a component with itself, which is left blank, assuming readiness of a component to be integrated with itself is judged by TRL (column 2). Assuring correct integration of components into modules, and then modules into assemblies, satisfies the concept and technology validation stages of integration. For the system validation, these assemblies must work together when inserted into the marine environment, and hence the interaction and compatibility of the entire system with its environment should be assured. The environmental readiness is somewhat qualified during the design phase by proper choice of material, corrosion protection, installation procedure, etc. Similarly, it is assured during the first two stages of interfacing, namely concept validation and technology validation, by complying with engineering specifications. However, without the strength test at the factory and the leak tests, environmental readiness remains subjective. This paper does not introduce another scale for the environmental readiness, but assumes that it matures along the same timeline as modules and hence can be measured using the same scale of 0 to 7. A single value for each module is entered in the last column of Fig 4 to indicate the module s environmental readiness level. In most cases the environment must be prepared (e.g. pre-sweep, seabed remediation, sand bag markers, foundation) to host the subsea modules, which is performed just before installation, when the system reaches maturity level 4. Note that in Fig 4, the part of the seabed where a module occupies is not part of the module, but the module is superimposed on the environment, and the column 14 represents the environment. The alternative is to add the associated seabed as a component to the module. For this case example, it is assumed that two interfacing components could be at different 84

9 Vol 31, No 2, 2013 Table 3: SRL for subsea system readiness level assessment Phase SRL Development stage Development stage definition System validation 7 Field proven operational system 6 The system is installed tested and commissioning in progress Technology validation 5 Manufacturing and installation in progress 4 Detail design and final procurement 3 Front end engineering, sourcing long lead items Concept validation 2 Concept selection, where an optimal concept has emerged 1 Concept refinement Two or more competing concept being considered 0 Concept definition, where various ideas are being considered or discounted The subsea system is in production and it is in compliance with all its functionality requirements. The subsea system is operating successfully with sufficient reliability for more than 10% of its service life. Assure the operation support will meet all of its expected functions. The entire subsea system is installed and tested both at component level and at the system level, and it is ready for its intended operation condition. The subsea system is being commissioned with operation support. Any remaining problems being rectified. The Health and Safety Executive (HSE) policy is monitored. The system with all inserted assemblies will meet all requirements of SRL4 and below. Partly assembled/installed system is tested and compliance verified for the full design specifications. Operational support availability is identified and assured. HSE, pre-commissioning and handover policy are established. Operation support needs are established. The chosen concept is detailed. Procurement date for long lead items is assured. Installation and commissioning contactors are ready. Integration and manufacturing risk are reduced. Procurement is advanced. Seabed is being prepared to host the system. The first choice and the competing option are moved forward to a level that the difference between them becomes obvious. Vendors, installation and commissioning contactors are selected and appointed, and assurance that they can meet the delivery dates is made. Possible integration problems are checked. Logistics are considered. The concept is in compliance with the demands by the marine environment. Seabed is being surveyed. Two or more options which best satisfy all requirements are identified. Technology risk is reduced. Aspect of technologies to be used is clarified. The most promising option is selected. The project schedule is determined. Promising concept is refined to an adequate level of maturity. The concepts are priced and ranked according to their desirability. Technologies that are needed are researched to see if they can be procured and at what price. The available infrastructure, means of transportation and installation contactors availability are studied. Operational requirements are considered. Fabrication, transportation and installation are considered. The influence of the marine environment on the system is studied and written into the basis of design. Reservoir data, geotechnical data, drilling requirements, distances and existing infrastructure information is collected. Concepts are developed. Economically or technically unfeasible concepts are screened out. The schedules are established and checked if they are realistic. Finance is considered. 85

10 Yasseri. Subsea system readiness level assessment Previous Module A TRL=6 A to E E B A to F IRL=6 F ENV=5 IRL=6 C D to E G IRL=4 ENV=5 IRL=4 IRL=4 D TRL=6 H D to H IRL=6 IRL=4 Next Module I TRL=6 C to J J Fig 3: A simple system consisting of 10 components arranged in two modules. Interfaces are shown by double headed arrow TRL, but their IRLs are the same and equal to the less ready component (because of mutual dependency), hence yielding a symmetric matrix. In general, if two components have to come together to create a connection, there may be different degrees of integration readiness for each component and therefore the matrix is not symmetric. Symmetry assumption is not necessary for the success of the method and can be dropped, if it is believed that retaining two different IRL for interfacing components would yield useful information. The distance between the furthest off-diagonal terms to the diagonal is known as the bandwidth of the matrix. A narrow bandwidth is an indication of a good system line-up (modularisation). A high bandwidth, as in this example, signifies that too many components from different modules are dependent on each other, which adds to the cost of managing the interface and will probably lead to delays. There are algorithms to collect components into modules in order to reduce the bandwidth and lower the dependencies. Each row of column 15 of Fig 4 is the average IRL for the row, determined by summing up of IRLs of all interfaces across the row and dividing it by the number of interfaces e.g. ( )/4 = 5.5. Column 16 gives the results of multiplication of the component s TRL by the average of its IRLs, e.g. in row 3, it is = 33. The square root of column 16 is given in column 17, giving a composite component readiness index. Column 18 is the square root of mean of squares noted in column 16, which is the sum of all squares in column 16 divided by the number of components in the module. 86

11 Vol 31, No 2, TRL A B C D E F G H I J ENV Ave. TRL*Ave SQRT IRL _IRL (Col16) 3 6 A B C D E F G H I J Fig 4: DSM for the example case The readiness for the first module is calculated as: M1 R = = 5.31 (1) The denominator of 4 is the number of components of the first module. Similarly for the second module, the readiness is calculated as: M 2 R = 6 = 4.95 (2) Therefore, the readiness of each module to be integrated into its environment is judged to be 5 for both modules of the case example using Table 3. Hence, the aggregate system readiness index (SRI) is: SRI = 2 2 (5.31) 5 + (4.95) 5 = (3) The denominator of 7 is the highest IRL in Table 2; this number is used to normalise the environmental integration readiness level, namely 5/7, which is the same for both modules in the example. From a metric point of view, SRL est and SRL are meant to measure the same things on the same scale. However, SRL is defined (Table 3), while SRL est is derived by aggregation of attributes of all components, which may be at different levels of TRL and IRL. If all components mature simultaneously along the same path, then SRL est reduces to SRL. Entering Table 3 with 4.34, the system must be at assembly and installation stage; if the project schedule requires a different level then this must be justified. This index informs the management when and where to intervene if the system readiness is lagging behind the schedules. The markers in each row identify which other components must be ready for the integration to become complete; hence interfaces must be adequately managed. A tightly controlled project ensures that TRL, IRL and SRL closely follow each other. The derived system readiness index of 4.34 indicates that some components are not maturing within the desired time frame. In this hypothetical example, components with TRL or IRL lower than 4.34 need to be scrutinised. While this case example is simple, the underlying methodology is important. It demonstrates how to use DSM to combine TRL and IRL into a new metric, which indicates the readiness of the system. In addition to this housekeeping advantage, DSM provides a visual aid to present the system audit results to the senior managers. The advantage becomes more evident when dealing with more than 200 components manufactures in various locations that must mate and work together when assembled. 7. Discussion Measuring technology and system maturity is a multidimensional process that cannot be performed adequately by a one-dimensional metric such as TRL. Although TRL has been employed by many industries, it captures only a part of the information needed to support stakeholders decisions. TRL was not designed to assess the quality of the system architecture, design or integration, but only to measure the readiness of system components based on what has been accomplished at the time of assessment. IRL addresses this shortcoming, but it must be aggregated with TRL into a single composite index to be useful. In turn, there is a need for a scale to be used with this composite index. It is also proposed to use DSM as a visual aid to bring together all three elements of system maturation metrics. Readiness of components to be integrated into a module, or modules to be connected together, may be assessed by engineering judgment in formal reviews, assisted by measurements, specifications, codes and procedures. 87

12 Yasseri. Subsea system readiness level assessment This paper has also introduced the concept of environmental integration readiness level (i.e. module/ assemblies-to-marine-environment) for assemblies consisting of several modules that are large/heavy enough to be installed in a single operation. The readiness of all components cannot be assured until the factory acceptance tests, the leak tests at the site and in-place operational tests are performed. It should be kept in mind that by IRL = 5, all of the technical integration issues must be resolved. Once it reaches this level, the focus should be on confirmations of integration by more testing and the actual performance. In the context of this work, the integration readiness of modules-tomarine-environment may be judged using the available physical evidences, e.g. tests and compliance with rules, specifications and codes. The root mean square (RMS) method was used for determining SRL est (see for example Bissell and Chapman, 1992). This estimated value incorporates not only the current maturation of all components, but also the physical properties of interfaces, integrations requirements, interaction, compatibility, reliability, quality and performance when assemblies are brought together to deliver a specific functionality. The dependency of the system on the seabed is generally studied at the concept phase, and the demand of environment, such as geohazards, corrosion, unstable and uneven seabed are identified and written into the basis of design (BOD). The compliance of the design with the BOD is reviewed at all stages of the system development. Thus, the manufactured modules are expected to withstand the demand of its environment when installed. However, the readiness of environment to host the system is considered when the subsea system is ready to be installed. Early seabed surveys help to identify suitable positions for the subsea system. However, the major part of making the seabed ready for receiving the subsea system takes place before installation, when the modules and assemblies readiness exceed level 4. The major activities for the installation preparation are: acquisition of the permit (permission) for the vessel to enter the area; deployment of ship s transponder on the seabed; deepwater trials to assure redundancy of the deepwater system and also drift off tests; as-found survey looking for anomalies, debris and variation of the seabed; installation of transponders array to obtain a frame of reference for poisoning; seabed corrections and remediation, involving removal of debris, possibly dredging and shoring up; and accurate positioning/laying down buoyancy markers ballasted with sand bags. These markers act as visual aids for installation, by for example, identifying the corner locations for structures. The linear asset (e.g. pipelines, flowlines) follows a similar path, but is not necessarily in sync with the major equipment. Some post installation interventions, e.g. trenching of pipelines and piling of subsea structures, may be required to secure the asset. The subsea architecture is represented by a component-component (N-square) matrix the DSM which can describe a system structure with respect to the relationships between its components. The DSM is an effective representation tool for mapping subsea equipment and its linkages. DSM provides a platform for communicating about quality and alternative architecture, and managing interfaces. Its use can improve understanding of the project progress and communicating this to the senior managers. Simply building the DSM helps to increase overall awareness and understanding the relationship between components in the system. Integration analysis using a DSM promotes transparency by showing all metrics in one picture. DSMs can also address the following types of questions: Should the components be organised differently to improve interface management and delivery? How should those modules requiring too many interfaces be reconfigured? Where and which integrative mechanisms might be prudent? Are the current choices of integrative mechanisms well balanced? Are the interactions as shown in DSM correct and sufficient for the interface management? Interfaces between components of one module do not require the same level of management time as interfaces between components of two or more modules supplied by different vendors. The goal of DSM is to analyse the components within a system, and it allows one to re-sequence these in order to minimise interface between modules. DSM identifies bottlenecks during design, fabrication and installation. The diagonal entries of the matrix do not have any interpretation in describing the system; they are either left blank, or filled in with the component labels. This is done to separate the upper and lower triangles of the matrix and to 88

13 Vol 31, No 2, 2013 show the interfaces more clearly. The number of markers in a row determines dependencies, as well as the level of demand on the interface management and the criticality of the component. DSM can become the foundation for the optimal resource allocation, monitoring and evaluation tool. It can also be a basis for common measurement and language for delivery managers to improve the system development and acquisition process. The complexity of the interfaces is not shown on the Fig 4, but it can be indicated by colour coding of the relevant cell using a five level designation: none, minor, moderate, high and very high. No colour implies that there is no specific interface requirement or, if there is one, that its complexity is negligible. An alternative is to use a scale of 1 to 5 with 5 being the highest. The methodology that is described here is simple enough to be usable in practice, and yet adequately captures all relevant data and gives a clear picture of the entire system. It provides, with little effort from the user, a view of the system that is valuable especially during ongoing development. The concepts described here complement the practice of TRL and offers a vision of the system readiness that is compatible with the intuition of practicing engineers. 8. Concluding remarks This paper presents a system-based approach for managing subsea system development and making effective and efficient decisions for hardware and software, acquisition and their integration. This provides system engineers, delivery managers, quality control managers and project managers a common metric that can aid them in making effective and timely decisions during all phases of a subsea system development. This should help reduce both a project s technical risk and schedule risk. The new IRL scale, which parallels the current TRL scale, is necessary because when components are procured from different sources, integration could pose a problem if not properly managed. The proposed IRL mimics the value of the TRL by being simple to understand and use. A new SRL is also introduced as a scale for measuring the maturation of the entire subsea system. To tie up these three matrices, a methodology is described that combines TRLs and IRLs at the time of evaluation, into a single composite index termed SRL est. This composite index is an estimate of the system readiness level. By applying Table 3 and this index, the stage of advancement of the project can be determined. This paper also introduces the DSM for mapping the subsea architecture, namely all components and their linkages, into a single table (matrix) as a visual aid. DSM shows interdependencies between components and the need for information flow for the interface management. Consequently, DSM shows TRL and IRL in a single table. These metrics can identify critical parameters, establish milestones to assess progress, offer direction for risk management/mitigation and identify hot spots requiring management intervention. In summary, this paper provides a basis for: collective evaluation of component integration and system readiness to reduce schedule and technical risks; a dynamic assessment tool for tracking the progress of design, manufacturing and installation; and developing contingency, multiple-sourcing and sparing policy through the comparative analysis of multiple technologies. References American Petroleum Institute (API). (2009). AP RP 17N Recommended practice for subsea production system reliability and technical risk management. Washington DC: API. Bilbro JW. (2007). A suite of tools for technology assessment. Presented at: Technology maturity conference: multi-dimensional assessment of technology maturity. Virginia Beach, VA, September. Available at last accessed <10 October 2012>. Bissell C and Chapman D. (1992). Digital Signal Transmission. Cambridge University Press. UK. Browning TR. (2001). Applying the Design Structure Matrix to System Decomposition and Integration Problems: A Review and New Directions. IEEE Transactions on Engineering Management 48: Browning TR and Eppinger S. (2002). Modelling Impacts of Process Architecture on Cost and Schedule Risk in Product Development. IEEE Transactions on Engineering Management 49: Buede DM. (2000). The engineering design of systems: Models and methods. New York: Wiley. Bureau Veritas (BV). (2010). BV NI525:2010 Risk based qualification of new technology methodological guidelines. Neuilly-sur-Seine, France: BV, 20pp. Danilovic M and Browning RT. (2007). Managing complex product development projects with design structure matrices and domain mapping matrices. International Journal of Project Management 25: Det Norske Veritas (DNV). (2011). DNV-RP-A203 Recommended practice: Qualification of new technology. Oslo, Norway. Dowling T and Pardoe T. (2005). TIMPA Technology insertion metrics, volume 1. London: Ministry of Defence, QinetiQ. Eppinger SD. (1991). Model-based approaches to managing concurrent engineering. Journal of Engineering Design 2:

Jerome Tzau TARDEC System Engineering Group. UNCLASSIFIED: Distribution Statement A. Approved for public release. 14 th Annual NDIA SE Conf Oct 2011

Jerome Tzau TARDEC System Engineering Group. UNCLASSIFIED: Distribution Statement A. Approved for public release. 14 th Annual NDIA SE Conf Oct 2011 LESSONS LEARNED IN PERFORMING TECHNOLOGY READINESS ASSESSMENT (TRA) FOR THE MILESTONE (MS) B REVIEW OF AN ACQUISITION CATEGORY (ACAT)1D VEHICLE PROGRAM Jerome Tzau TARDEC System Engineering Group UNCLASSIFIED:

More information

Technology qualification management and verification

Technology qualification management and verification SERVICE SPECIFICATION DNVGL-SE-0160 Edition December 2015 Technology qualification management and verification The electronic pdf version of this document found through http://www.dnvgl.com is the officially

More information

A System Maturity Index for Decision Support in Life Cycle Acquisition

A System Maturity Index for Decision Support in Life Cycle Acquisition Over the next 5 years, many of the programs in our assessment plan to hold design reviews or make a production decisions without demonstrating the level of technology maturity that should have been there

More information

in the New Zealand Curriculum

in the New Zealand Curriculum Technology in the New Zealand Curriculum We ve revised the Technology learning area to strengthen the positioning of digital technologies in the New Zealand Curriculum. The goal of this change is to ensure

More information

Onshore & Offshore Engineering and Management of Subsea Cables and Pipelines

Onshore & Offshore Engineering and Management of Subsea Cables and Pipelines Established in 1997, Primo Marine is an independent specialist with a wealth of experience in subsea cable engineering, from landfalls to subsea marine infrastructures. With an extensive track record,

More information

TECHNOLOGY QUALIFICATION MANAGEMENT

TECHNOLOGY QUALIFICATION MANAGEMENT OFFSHORE SERVICE SPECIFICATION DNV-OSS-401 TECHNOLOGY QUALIFICATION MANAGEMENT OCTOBER 2010 FOREWORD (DNV) is an autonomous and independent foundation with the objectives of safeguarding life, property

More information

SPE A Systematic Approach to Well Integrity Management Alex Annandale, Marathon Oil UK; Simon Copping, Expro

SPE A Systematic Approach to Well Integrity Management Alex Annandale, Marathon Oil UK; Simon Copping, Expro SPE 123201 A Systematic Approach to Well Integrity Management Alex Annandale, Marathon Oil UK; Simon Copping, Expro Copyright 2009, Society of Petroleum Engineers This paper was prepared for presentation

More information

SUBSEA 7 AND GRANHERNE ALLIANCE. Engaging Early to Deliver Value

SUBSEA 7 AND GRANHERNE ALLIANCE. Engaging Early to Deliver Value SUBSEA 7 AND GRANHERNE ALLIANCE Viable Solutions Operators are seeking novel and reliable concepts to overcome industry challenges such as complex reservoirs, cost, growth and schedule creep and to optimise

More information

Offshore Wind Risks - Issues and Mitigations

Offshore Wind Risks - Issues and Mitigations DNV Offshore Wind Soren Karkov DNV an independent foundation Our Purpose To safeguard life, property and the environment Our Vision Global impact for a safe and sustainable future 2 More than 145 Years

More information

How it works and Stakeholder Benefits

How it works and Stakeholder Benefits UNFC 2009 - Applications in Uranium and Thorium Resources: Focus on Comprehensive Extraction How it works and Stakeholder Benefits David MacDonald Santiago 9-12 July 2013 Stakeholders of our reported resources

More information

Systems. Professor Vaughan Pomeroy. The LRET Research Collegium Southampton, 11 July 2 September 2011

Systems. Professor Vaughan Pomeroy. The LRET Research Collegium Southampton, 11 July 2 September 2011 Systems by Professor Vaughan Pomeroy The LRET Research Collegium Southampton, 11 July 2 September 2011 1 Systems Professor Vaughan Pomeroy December 2010 Icebreaker Think of a system that you are familiar

More information

OBSERVATORY SERVICING AND MAINTENANCE

OBSERVATORY SERVICING AND MAINTENANCE OBSERVATORY SERVICING AND MAINTENANCE How to deploy and maintain a network of observatories around Europe? We don t built what we cannot maintain! Jean-François DROGOU IFREMER Steve ETCHEMENDY M.B.A.R.I

More information

Keywords: DSM, Social Network Analysis, Product Architecture, Organizational Design.

Keywords: DSM, Social Network Analysis, Product Architecture, Organizational Design. 9 TH INTERNATIONAL DESIGN STRUCTURE MATRIX CONFERENCE, DSM 07 16 18 OCTOBER 2007, MUNICH, GERMANY SOCIAL NETWORK TECHNIQUES APPLIED TO DESIGN STRUCTURE MATRIX ANALYSIS. THE CASE OF A NEW ENGINE DEVELOPMENT

More information

TECHNICAL RISK ASSESSMENT: INCREASING THE VALUE OF TECHNOLOGY READINESS ASSESSMENT (TRA)

TECHNICAL RISK ASSESSMENT: INCREASING THE VALUE OF TECHNOLOGY READINESS ASSESSMENT (TRA) TECHNICAL RISK ASSESSMENT: INCREASING THE VALUE OF TECHNOLOGY READINESS ASSESSMENT (TRA) Rebecca Addis Systems Engineering Tank Automotive Research, Development, and Engineering Center (TARDEC) Warren,

More information

UNIT VIII SYSTEM METHODOLOGY 2014

UNIT VIII SYSTEM METHODOLOGY 2014 SYSTEM METHODOLOGY: UNIT VIII SYSTEM METHODOLOGY 2014 The need for a Systems Methodology was perceived in the second half of the 20th Century, to show how and why systems engineering worked and was so

More information

NURTURING OFFSHORE WIND MARKETS GOOD PRACTICES FOR INTERNATIONAL STANDARDISATION

NURTURING OFFSHORE WIND MARKETS GOOD PRACTICES FOR INTERNATIONAL STANDARDISATION NURTURING OFFSHORE WIND MARKETS GOOD PRACTICES FOR INTERNATIONAL STANDARDISATION Summary for POLICY MAKERS SUMMARY FOR POLICY MAKERS The fast pace of offshore wind development has resulted in remarkable

More information

Concurrent Increment Sequencing and Synchronization with Design Structure Matrices in Software- Intensive System Development

Concurrent Increment Sequencing and Synchronization with Design Structure Matrices in Software- Intensive System Development Concurrent Increment Sequencing and Synchronization with Design Structure Matrices in Software- Intensive System Development Dr. Peter Hantos The Aerospace Corporation NDIA Systems Engineering Conference

More information

Subsea Pipeline IMR. PT Hallin Marine June 18 th, 2014!

Subsea Pipeline IMR. PT Hallin Marine June 18 th, 2014! PT Hallin Marine June 18 th, 2014! Introduction Issues and Risks Inspection, Maintenance & Repair Case Study Conclusions and Recommendations 2 Introduction Subsea Pipeline IMR q Obtain data to assess the

More information

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015

Well Control Contingency Plan Guidance Note (version 2) 02 December 2015 Well Control Contingency Plan Guidance Note (version 2) 02 December 2015 Prepared by Maritime NZ Contents Introduction... 3 Purpose... 3 Definitions... 4 Contents of a Well Control Contingency Plan (WCCP)...

More information

Model Based Systems Engineering (MBSE) Business Case Considerations An Enabler of Risk Reduction

Model Based Systems Engineering (MBSE) Business Case Considerations An Enabler of Risk Reduction Model Based Systems Engineering (MBSE) Business Case Considerations An Enabler of Risk Reduction Prepared for: National Defense Industrial Association (NDIA) 26 October 2011 Peter Lierni & Amar Zabarah

More information

VIRTUS CONNECTION SYSTEMS Advanced Diverless Connection Solutions for any Subsea Field Application

VIRTUS CONNECTION SYSTEMS Advanced Diverless Connection Solutions for any Subsea Field Application VIRTUS CONNECTION SYSTEMS Advanced Diverless Connection Solutions for any Subsea Field Application 2 Virtus Subsea Connectors Delivering Long-Lasting Reliability at Each Subsea Connection Subsea production

More information

Subsea Boosting. November 2015 John Friedemann

Subsea Boosting. November 2015 John Friedemann Subsea Boosting John Friedemann GE Oil & Gas Land Pipelines ipigs Offshore LNG Liquefied Natural Gas Compression Trains Refinery Subsea A little History 969 OTC 94 97 SPE 463 985 OTC 7438 3 Topics Why?

More information

Systems Engineering Overview. Axel Claudio Alex Gonzalez

Systems Engineering Overview. Axel Claudio Alex Gonzalez Systems Engineering Overview Axel Claudio Alex Gonzalez Objectives Provide additional insights into Systems and into Systems Engineering Walkthrough the different phases of the product lifecycle Discuss

More information

Effective Implementation of Subsea Integrity Management

Effective Implementation of Subsea Integrity Management Effective Implementation of Subsea Integrity Management Himanshu Maheshwari Engineering Specialist 2H Offshore Inc Houston, TX, USA Peter Falconer Global Subsea IM Business Manager 2H Offshore Inc Houston,

More information

Technology Transition Assessment in an Acquisition Risk Management Context

Technology Transition Assessment in an Acquisition Risk Management Context Transition Assessment in an Acquisition Risk Management Context Distribution A: Approved for Public Release Lance Flitter, Charles Lloyd, Timothy Schuler, Emily Novak NDIA 18 th Annual Systems Engineering

More information

Focusing Software Education on Engineering

Focusing Software Education on Engineering Introduction Focusing Software Education on Engineering John C. Knight Department of Computer Science University of Virginia We must decide we want to be engineers not blacksmiths. Peter Amey, Praxis Critical

More information

Getting the evidence: Using research in policy making

Getting the evidence: Using research in policy making Getting the evidence: Using research in policy making REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 586-I Session 2002-2003: 16 April 2003 LONDON: The Stationery Office 14.00 Two volumes not to be sold

More information

Tuning-CALOHEE Assessment Frameworks for the Subject Area of CIVIL ENGINEERING The Tuning-CALOHEE Assessment Frameworks for Civil Engineering offers

Tuning-CALOHEE Assessment Frameworks for the Subject Area of CIVIL ENGINEERING The Tuning-CALOHEE Assessment Frameworks for Civil Engineering offers Tuning-CALOHEE Assessment Frameworks for the Subject Area of CIVIL ENGINEERING The Tuning-CALOHEE Assessment Frameworks for Civil Engineering offers an important and novel tool for understanding, defining

More information

Taking a broader view

Taking a broader view Taking a broader view A brief introduction to DNV GL 1 SAFER, SMARTER, GREENER We are a global classification, certification, technical assurance and advisory company 2 In a challenging world we make businesses

More information

learning progression diagrams

learning progression diagrams Technological literacy: implications for Teaching and learning learning progression diagrams The connections in these Learning Progression Diagrams show how learning progresses between the indicators within

More information

Quality Focused Risk Management Framework for Research and Development Programs

Quality Focused Risk Management Framework for Research and Development Programs Quality Focused Risk Management Framework for Research and Development Programs Carla Oliveira, Lila L. Carden & Jamison V. Kovach University of Houston Houston Regional Quality Conference November 13,

More information

Optime Subsea AS. Web: BIC/SWIFT: SPTRN022 IBAN: NO

Optime Subsea AS. Web:     BIC/SWIFT: SPTRN022 IBAN: NO ~Ä TABLE OF CONTENTS TABLE OF CONTENTS... 1 1 Introduction to Optime... 1 2 Products... 2 3 Services... 1 4 Quality, Health, Safety & Environment... 2 5 Partners & Supply chain... 2 1 Introduction to Optime,

More information

ARTES Competitiveness & Growth Full Proposal. Requirements for the Content of the Technical Proposal. Part 3B Product Development Plan

ARTES Competitiveness & Growth Full Proposal. Requirements for the Content of the Technical Proposal. Part 3B Product Development Plan ARTES Competitiveness & Growth Full Proposal Requirements for the Content of the Technical Proposal Part 3B Statement of Applicability and Proposal Submission Requirements Applicable Domain(s) Space Segment

More information

Offshore Support Vessels Located in the US Gulf of Mexico in March 2018

Offshore Support Vessels Located in the US Gulf of Mexico in March 2018 Offshore Support Vessels Located in the US Gulf of Mexico in March 18 IMCA March 1, 18 Prepared by IMCA The International Marine Contractors Association (IMCA) is the international trade association representing

More information

Recommended Practice for Wet and Dry Thermal Insulation of Subsea Flowlines and Equipment API RECOMMENDED PRACTICE 17U FIRST EDITION, FEBRUARY 2015

Recommended Practice for Wet and Dry Thermal Insulation of Subsea Flowlines and Equipment API RECOMMENDED PRACTICE 17U FIRST EDITION, FEBRUARY 2015 Recommended Practice for Wet and Dry Thermal Insulation of Subsea Flowlines and Equipment API RECOMMENDED PRACTICE 17U FIRST EDITION, FEBRUARY 2015 Special Notes API publications necessarily address problems

More information

Procurement Risk Management of Flexible Pipes and Umbilicals. Presented by Hanh Ha Kuala Lumpur Convention Centre 9 th June 2010

Procurement Risk Management of Flexible Pipes and Umbilicals. Presented by Hanh Ha Kuala Lumpur Convention Centre 9 th June 2010 Procurement Risk Management of Flexible Pipes and Umbilicals Presented by Hanh Ha Kuala Lumpur Convention Centre 9 th June 2010 Content Who are BPP-TECH? SURF Procurement What is it about. How and where

More information

OWA Floating LiDAR Roadmap Supplementary Guidance Note

OWA Floating LiDAR Roadmap Supplementary Guidance Note OWA Floating LiDAR Roadmap Supplementary Guidance Note List of abbreviations Abbreviation FLS IEA FL Recommended Practices KPI OEM OPDACA OSACA OWA OWA FL Roadmap Meaning Floating LiDAR System IEA Wind

More information

A FRAMEWORK FOR PERFORMING V&V WITHIN REUSE-BASED SOFTWARE ENGINEERING

A FRAMEWORK FOR PERFORMING V&V WITHIN REUSE-BASED SOFTWARE ENGINEERING A FRAMEWORK FOR PERFORMING V&V WITHIN REUSE-BASED SOFTWARE ENGINEERING Edward A. Addy eaddy@wvu.edu NASA/WVU Software Research Laboratory ABSTRACT Verification and validation (V&V) is performed during

More information

marine, construction, drilling, floating production, decommissioning and renewables industries.

marine, construction, drilling, floating production, decommissioning and renewables industries. Maritime Assurance & Consulting Ltd (MAC), a Bureau Veritas Group Company, is a UK-based company with a global reach, offering a comprehensive range of support services to the Dynamic Positioning Assurance

More information

4 Briefing. Responsible investor

4 Briefing. Responsible investor Issue Responsible investor 4 Briefing Wednesday 8 th February 2012 In 2010, we accepted all 26 recommendations made by the Bly Report our internal investigation into the Deepwater Horizon incident. BP

More information

GENERAL DESCRIPTION OF THE CMC SERVICES

GENERAL DESCRIPTION OF THE CMC SERVICES STANDARD FOR CERTIFICATION No.1.1 GENERAL DESCRIPTION OF THE CMC SERVICES MAY 2007 FOREWORD (DNV) is an autonomous and independent foundation with the objectives of safeguarding life, property and the

More information

Implementing FPSO Digital Twins in the Field. David Hartell Premier Oil

Implementing FPSO Digital Twins in the Field. David Hartell Premier Oil Implementing FPSO Digital Twins in the Field David Hartell Premier Oil Digital Twins A Digital Twin consists of several key elements and features: 1. A virtual, dynamic simulation model of an asset; 2.

More information

Summary of Changes and Current Document Status

Summary of Changes and Current Document Status DNV SERVICE DOCUMENTS Summary of Changes and Current Document Status FEBRUARY 2012 FOREWORD DET NORSKE VERITAS (DNV) is an autonomous and independent foundation with the objectives of safeguarding life,

More information

COMMERCIAL INDUSTRY RESEARCH AND DEVELOPMENT BEST PRACTICES Richard Van Atta

COMMERCIAL INDUSTRY RESEARCH AND DEVELOPMENT BEST PRACTICES Richard Van Atta COMMERCIAL INDUSTRY RESEARCH AND DEVELOPMENT BEST PRACTICES Richard Van Atta The Problem Global competition has led major U.S. companies to fundamentally rethink their research and development practices.

More information

ENGINEERING SERVICES CONSULTANCY

ENGINEERING SERVICES CONSULTANCY ENGINEERING SERVICES CONSULTANCY Managing complexity, unlocking value Petrofac Engineering & Production Services 02 03 Discover the difference Consultancy services Petrofac is an international service

More information

Opportunities and Challenges in Deepwater West Africa Projects

Opportunities and Challenges in Deepwater West Africa Projects Opportunities and Challenges in Deepwater West Africa Projects Finding Petroleum - Finding African Oil Mark Jones - INTECSEA (UK) Royal Society of Chemistry, London 28th January 2015 Opportunities and

More information

TYPE APPROVAL PROCEDURE

TYPE APPROVAL PROCEDURE Approval Amendment Record Approval Date Version Description 15/06/2012 1 Initial issue under MTM. Replaces Connex documents cml- 8.13-PR-002 & cml-8.21-po-168 30/11/2012 2 Document revised and updated

More information

Accuracy, Precision, Tolerance We understand the issues in this digital age?

Accuracy, Precision, Tolerance We understand the issues in this digital age? Accuracy, Precision, Tolerance We understand the issues in this digital age? Abstract Survey4BIM has put a challenge down to the industry that geo-spatial accuracy is not properly defined in BIM systems.

More information

OTC seems to be able to afford to fix the problems associated with downtime due to an incomplete design.

OTC seems to be able to afford to fix the problems associated with downtime due to an incomplete design. OTC 15194 DEEPWATER BOP CONTROL SYSTEMS - A LOOK AT RELIABILITY ISSUES Earl Shanks, Transocean; Andrew Dykes, ABS Consulting; Marc Quilici, ABS Consulting; John Pruitt, ABS Consulting Copyright 2003, Offshore

More information

TIES: An Engineering Design Methodology and System

TIES: An Engineering Design Methodology and System From: IAAI-90 Proceedings. Copyright 1990, AAAI (www.aaai.org). All rights reserved. TIES: An Engineering Design Methodology and System Lakshmi S. Vora, Robert E. Veres, Philip C. Jackson, and Philip Klahr

More information

Offshore Renewables Institute

Offshore Renewables Institute Offshore Renewables Institute Introducing the Offshore Renewables Institute (ORI) About Us We bring together experts and expertise from across a broad university partnership: the University of Dundee;

More information

Stakeholder and process alignment in Navy installation technology transitions

Stakeholder and process alignment in Navy installation technology transitions Calhoun: The NPS Institutional Archive DSpace Repository Faculty and Researchers Faculty and Researchers Collection 2017 Stakeholder and process alignment in Navy installation technology transitions Regnier,

More information

Logic Solver for Tank Overfill Protection

Logic Solver for Tank Overfill Protection Introduction A growing level of attention has recently been given to the automated control of potentially hazardous processes such as the overpressure or containment of dangerous substances. Several independent

More information

Mid Term Exam SES 405 Exploration Systems Engineering 3 March Your Name

Mid Term Exam SES 405 Exploration Systems Engineering 3 March Your Name Mid Term Exam SES 405 Exploration Systems Engineering 3 March 2016 --------------------------------------------------------------------- Your Name Short Definitions (2 points each): Heuristics - refers

More information

Review of Technology Level 3 achievement and Level 3 and 4 unit standards. Graphics Design Graphic Communication

Review of Technology Level 3 achievement and Level 3 and 4 unit standards. Graphics Design Graphic Communication Page 1 of 18 Fields Engineering and and Sciences Review of Level 3 achievement and Level 3 and 4 unit standards Unit standards Field Subfield Domain ID Engineering and Design Design Computer 19355 Graphics

More information

Type Approval JANUARY The electronic pdf version of this document found through is the officially binding version

Type Approval JANUARY The electronic pdf version of this document found through  is the officially binding version STANDARD FOR CERTIFICATION No. 1.2 Type Approval JANUARY 2013 The electronic pdf version of this document found through http://www.dnv.com is the officially binding version The content of this service

More information

University of Massachusetts Amherst Libraries. Digital Preservation Policy, Version 1.3

University of Massachusetts Amherst Libraries. Digital Preservation Policy, Version 1.3 University of Massachusetts Amherst Libraries Digital Preservation Policy, Version 1.3 Purpose: The University of Massachusetts Amherst Libraries Digital Preservation Policy establishes a framework to

More information

87R14 PETROLEUMEXPLORATI

87R14 PETROLEUMEXPLORATI E 87R14 SA M PL COSTESTI MATECLASSI FI CATI ON SYSTEM-ASAPPLI EDFORTHE PETROLEUMEXPLORATI ONAND PRODUCTI ONI NDUSTRY AACE International Recommended Practice No. 87R-14 COST ESTIMATE CLASSIFICATION SYSTEM

More information

ARTES Competitiveness & Growth Full Proposal. Requirements for the Content of the Technical Proposal

ARTES Competitiveness & Growth Full Proposal. Requirements for the Content of the Technical Proposal ARTES Competitiveness & Growth Full Proposal Requirements for the Content of the Technical Proposal Part 3C (DDVP) Statement of Applicability and Proposal Submission Requirements Applicable Domain(s) Space

More information

Software-Intensive Systems Producibility

Software-Intensive Systems Producibility Pittsburgh, PA 15213-3890 Software-Intensive Systems Producibility Grady Campbell Sponsored by the U.S. Department of Defense 2006 by Carnegie Mellon University SSTC 2006. - page 1 Producibility

More information

SAUDI ARABIAN STANDARDS ORGANIZATION (SASO) TECHNICAL DIRECTIVE PART ONE: STANDARDIZATION AND RELATED ACTIVITIES GENERAL VOCABULARY

SAUDI ARABIAN STANDARDS ORGANIZATION (SASO) TECHNICAL DIRECTIVE PART ONE: STANDARDIZATION AND RELATED ACTIVITIES GENERAL VOCABULARY SAUDI ARABIAN STANDARDS ORGANIZATION (SASO) TECHNICAL DIRECTIVE PART ONE: STANDARDIZATION AND RELATED ACTIVITIES GENERAL VOCABULARY D8-19 7-2005 FOREWORD This Part of SASO s Technical Directives is Adopted

More information

Emerging Subsea Networks

Emerging Subsea Networks FIBRE-TO-PLATFORM CONNECTIVITY, WORKING IN THE 500m ZONE Andrew Lloyd (Global Marine Systems Limited) Email: andrew.lloyd@globalmarinesystems.com Global Marine Systems Ltd, New Saxon House, 1 Winsford

More information

The use of an integrated contract model (iepci) for Subsea developments

The use of an integrated contract model (iepci) for Subsea developments NH GRAND HOTEL KRASNAPOLSKY AMSTERDAM 3-5 APRIL 2017 The use of an integrated contract model (iepci) for Subsea developments Tim Crome 1991 1993 1995 1997 1999 2001 2003 2005 2007 2009 2011 MCE Deepwater

More information

Integrity Management of Offshore Assets

Integrity Management of Offshore Assets OIL & GAS Integrity Management of Offshore Assets Opening session Leif Collberg 05 May 2017 1 DNV GL 2015 05 May 2017 SAFER, SMARTER, GREENER How regulations can solve the challenge of being performance

More information

A NEW APPROACH FOR VERIFICATION OF SAFETY INTEGRITY LEVELS ABSTRACT

A NEW APPROACH FOR VERIFICATION OF SAFETY INTEGRITY LEVELS ABSTRACT A NEW APPROACH FOR VERIFICATION OF SAFETY INTEGRITY LEVELS E.B. Abrahamsen University of Stavanger, Norway e-mail: eirik.b.abrahamsen@uis.no W. Røed Proactima AS, Norway e-mail: wr@proactima.com ABSTRACT

More information

Integrity Monitoring? New thinking in the approach to Subsea IMMR. Dr Karl Woods, Snr Subsea Reliability Engineer 22/2/2017

Integrity Monitoring? New thinking in the approach to Subsea IMMR. Dr Karl Woods, Snr Subsea Reliability Engineer 22/2/2017 Integrity Monitoring? New thinking in the approach to Subsea IMMR Dr Karl Woods, Snr Subsea Reliability Engineer 22/2/2017 Disclaimer and important notice This presentation contains forward looking statements

More information

A Knowledge-Centric Approach for Complex Systems. Chris R. Powell 1/29/2015

A Knowledge-Centric Approach for Complex Systems. Chris R. Powell 1/29/2015 A Knowledge-Centric Approach for Complex Systems Chris R. Powell 1/29/2015 Dr. Chris R. Powell, MBA 31 years experience in systems, hardware, and software engineering 17 years in commercial development

More information

CONCURRENT ENGINEERING READINESS ASSESSMENT OF SUB-CONTRACTORS WITHIN THE UK CONSTRUCTION INDUSTRY

CONCURRENT ENGINEERING READINESS ASSESSMENT OF SUB-CONTRACTORS WITHIN THE UK CONSTRUCTION INDUSTRY CONCURRENT ENGINEERING READINESS ASSESSMENT OF SUB-CONTRACTORS WITHIN THE UK CONSTRUCTION INDUSTRY Malik M. A. Khalfan 1, Chimay J. Anumba 2, and Patricia M. Carrillo 3 Department of Civil & Building Engineering,

More information

LINKING PROCESS MAPPING AND TECHNOLOGY: A CASE STUDY OF TEAMWORK 2001

LINKING PROCESS MAPPING AND TECHNOLOGY: A CASE STUDY OF TEAMWORK 2001 LINKING PROCESS MAPPING AND TECHNOLOGY: A CASE STUDY OF TEAMWORK 2001 Isao T Matsumoto 1, Antony Thorpe 1, Andrew Baldwin 1 and Richard McWilliams 2 1 CICE, Department Civil and Building Engineering, Loughborough

More information

UNIT-III LIFE-CYCLE PHASES

UNIT-III LIFE-CYCLE PHASES INTRODUCTION: UNIT-III LIFE-CYCLE PHASES - If there is a well defined separation between research and development activities and production activities then the software is said to be in successful development

More information

Wave & Tidal Safety & Construction Guidelines

Wave & Tidal Safety & Construction Guidelines Wave & Tidal Safety & Construction Guidelines Malcolm Bowie Ltd All-Energy, Aberdeen, 24 th May 2012 Principal Challenges - Energetic environment with very unique construction risks. - Many new / radical

More information

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017

NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP July 28, 2017 NEVADA DEPARTMENT OF TRANSPORTATION Addendum 3 to RFP 697-16-016 July 28, 2017 Reference is made to the Request for Proposal (RFP) to Service Providers for Nevada Shared Radio Replacement Project, upon

More information

Technology Readiness for the Smart Grid

Technology Readiness for the Smart Grid CIGRE US National Committee 2013 Grid of the Future Symposium Technology Readiness for the Smart Grid Presented by Keith E. Lindsey President Lindsey Manufacturing Co. Outline What is Technology Readiness?

More information

Subsea Structural Engineering Services. Capability & Experience

Subsea Structural Engineering Services. Capability & Experience Subsea Structural Engineering Services Capability & Experience Capability Overview INTECSEA s subsea structural engineering team has a proven track record for providing solutions to problems in the implementation

More information

Techniques for Generating Sudoku Instances

Techniques for Generating Sudoku Instances Chapter Techniques for Generating Sudoku Instances Overview Sudoku puzzles become worldwide popular among many players in different intellectual levels. In this chapter, we are going to discuss different

More information

SIMON HINDLEY MENG, AMRINA MANAGING DIRECTOR, NAVAL ARCHITECT

SIMON HINDLEY MENG, AMRINA MANAGING DIRECTOR, NAVAL ARCHITECT SIMON HINDLEY MENG, AMRINA MANAGING DIRECTOR, NAVAL ARCHITECT University of Southampton, Master of Engineering (Hons) Ship Science 2007 Associate Member of Royal Institution of Naval Architects 2007 s.hindley@solis-marine.com

More information

Score grid for SBO projects with a societal finality version January 2018

Score grid for SBO projects with a societal finality version January 2018 Score grid for SBO projects with a societal finality version January 2018 Scientific dimension (S) Scientific dimension S S1.1 Scientific added value relative to the international state of the art and

More information

FOSS in Military Computing

FOSS in Military Computing FOSS in Military Computing Life-Cycle Support for FOSS-Based Information Systems By Robert Charpentier Richard Carbone R et D pour la défense Canada Defence R&D Canada Canada FOSS Project History Overview

More information

DNV GL Marine Renewables

DNV GL Marine Renewables ENERGY DNV GL Marine Renewables De-Risking Technologies, Insurance and Certification: The Certification Role Claudio Bittencourt Business Development Director Wave & Tidal Renewables Certification International

More information

Years 5 and 6 standard elaborations Australian Curriculum: Design and Technologies

Years 5 and 6 standard elaborations Australian Curriculum: Design and Technologies Purpose The standard elaborations (SEs) provide additional clarity when using the Australian Curriculum achievement standard to make judgments on a five-point scale. They can be used as a tool for: making

More information

SUBSEA SYSTEM ARCHITECTURE FOR CORAL SOUTH FLNG

SUBSEA SYSTEM ARCHITECTURE FOR CORAL SOUTH FLNG Introduction to Eni Our new mission: We are an energy company. We are working to build a future where everyone can access energy resources efficiently and sustainably. Our work is based on passion and

More information

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers Outcomes and Enablers 1 From an engineering leadership perspective, the student will describe elements of DoD systems engineering policy and process across the Defense acquisition life-cycle in accordance

More information

Offshore Pipelines. Capability & Experience

Offshore Pipelines. Capability & Experience Offshore Pipelines Capability & Experience Capability Overview INTECSEA is a leading engineering and project delivery company in the offshore oil and gas sector. It operates across the full project cycle

More information

Manufacturing Readiness Assessment Overview

Manufacturing Readiness Assessment Overview Manufacturing Readiness Assessment Overview Integrity Service Excellence Jim Morgan AFRL/RXMS Air Force Research Lab 1 Overview What is a Manufacturing Readiness Assessment (MRA)? Why Manufacturing Readiness?

More information

Technology and Manufacturing Readiness Levels [Draft]

Technology and Manufacturing Readiness Levels [Draft] MC-P-10-53 This paper provides a set of scales indicating the state of technological development of a technology and its readiness for manufacture, derived from similar scales in the military and aerospace

More information

Specification for Subsea Umbilicals

Specification for Subsea Umbilicals Specification for Subsea Umbilicals Upstream Segment ANSI/API SPECIFICATION 17E FOURTH EDITION, OCTOBER 2010 EFFECTIVE DATE: APRIL 1, 2011 ISO 13628-5:2009 (Identical), Petroleum and natural gas industries

More information

7 Briefing. Responsible investor

7 Briefing. Responsible investor Issue Responsible investor 7 Briefing Monday, 5 th October 202 In 200, we accepted all 26 recommendations made by the Bly Report our internal investigation into the Deepwater Horizon incident. BP has committed

More information

DNVGL-RP-A203 Edition June 2017

DNVGL-RP-A203 Edition June 2017 RECOMMENDED PRACTICE DNVGL-RP-A203 Edition June 2017 The electronic pdf version of this document, available free of charge from http://www.dnvgl.com, is the officially binding version. FOREWORD DNV GL

More information

Manufacturing Readiness Level Deskbook

Manufacturing Readiness Level Deskbook Manufacturing Readiness Level Deskbook 25 June 2010 Prepared by the OSD Manufacturing Technology Program In collaboration with The Joint Service/Industry MRL Working Group FORWARDING LETTER WILL GO HERE

More information

Intermediate Systems Acquisition Course. Lesson 2.2 Selecting the Best Technical Alternative. Selecting the Best Technical Alternative

Intermediate Systems Acquisition Course. Lesson 2.2 Selecting the Best Technical Alternative. Selecting the Best Technical Alternative Selecting the Best Technical Alternative Science and technology (S&T) play a critical role in protecting our nation from terrorist attacks and natural disasters, as well as recovering from those catastrophic

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the Board of Trustees. Description

More information

Costs of Achieving Software Technology Readiness

Costs of Achieving Software Technology Readiness Costs of Achieving Software Technology Readiness Arlene Minkiewicz Chief Scientist 17000 Commerce Parkway Mt. Laure, NJ 08054 arlene.minkiewicz@pricesystems.com 856-608-7222 Agenda Introduction Technology

More information

INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE

INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE INTEGRATED SERVICES AND PRODUCTS ACROSS THE FIELD LIFE CYCLE 4 What we do 6 Why choose us? 7 Service and product capabilities For more than 35 years, we have been providing clients with standalone and

More information

(R) Aerospace First Article Inspection Requirement FOREWORD

(R) Aerospace First Article Inspection Requirement FOREWORD AEROSPACE STANDARD AS9102 Technically equivalent to AECMA pren 9102 Issued 2000-08 Revised 2004-01 REV. A Supersedes AS9012 (R) Aerospace First Article Inspection Requirement FOREWORD In December 1998,

More information

Information & Communication Technology Strategy

Information & Communication Technology Strategy Information & Communication Technology Strategy 2012-18 Information & Communication Technology (ICT) 2 Our Vision To provide a contemporary and integrated technological environment, which sustains and

More information

SPICE: IS A CAPABILITY MATURITY MODEL APPLICABLE IN THE CONSTRUCTION INDUSTRY? Spice: A mature model

SPICE: IS A CAPABILITY MATURITY MODEL APPLICABLE IN THE CONSTRUCTION INDUSTRY? Spice: A mature model SPICE: IS A CAPABILITY MATURITY MODEL APPLICABLE IN THE CONSTRUCTION INDUSTRY? Spice: A mature model M. SARSHAR, M. FINNEMORE, R.HAIGH, J.GOULDING Department of Surveying, University of Salford, Salford,

More information

Guidance on TRL for renewable energy technologies

Guidance on TRL for renewable energy technologies Guidance on TRL for renewable energy technologies Guidance on TRL for renewable energy technologies - Ref: PP-03583-2015 Webinar for C-energy2020 project 16/11/2018 The presentation today Topic Discussion

More information

NZQA registered unit standard version 4 Page 1 of 5. Plan, construct, modify, and report on an electronic prototype

NZQA registered unit standard version 4 Page 1 of 5. Plan, construct, modify, and report on an electronic prototype Page 1 of 5 Title Plan, construct, modify, and report on an electronic prototype Level 3 Credits 6 Purpose This unit standard is intended for use in a senior secondary school environment, pre-employment

More information

FUTURE-PROOF INTERFACES: SYSTEMATIC IDENTIFICATION AND ANALYSIS

FUTURE-PROOF INTERFACES: SYSTEMATIC IDENTIFICATION AND ANALYSIS 13 TH INTERNATIONAL DEPENDENCY AND STRUCTURE MODELLING CONFERENCE, DSM 11 CAMBRIDGE, MASSACHUSETTS, USA, SEPTEMBER 14 15, 2011 FUTURE-PROOF INTERFACES: SYSTEMATIC IDENTIFICATION AND ANALYSIS Wolfgang Bauer

More information

Integrating Core Systems Engineering Design Concepts into Traditional Engineering

Integrating Core Systems Engineering Design Concepts into Traditional Engineering Paper ID #12537 Integrating Core Systems Engineering Design Concepts into Traditional Engineering Disciplines Rama N Reddy Prof. Kamran Iqbal, University of Arkansas, Little Rock Kamran Iqbal obtained

More information