Lean Aircraft Initiative Plenary Workshop. Program Instability
|
|
- Antonia Wells
- 5 years ago
- Views:
Transcription
1 Lean Aircraft Initiative Plenary Workshop Policy and External Environment Program Instability October 16, 1996 Presented by: Eric S. Rebentisch MIT
2 Outline Research overview Progress update SPO survey Contractor survey Recent findings Cost of instability Influence of technical advance Impact of specific practices Summary PE Massachusetts Institute of Technology
3 Near-term Research Strategy (CY 96) Continue analysis of SPO survey data. Program/technology characteristics. HR issues. Management strategies. Integrate Contractor survey data into program instability database and analysis process. Validate current findings through interactions with practitioners. Continued population of the LEM with findings. PE Massachusetts Institute of Technology
4 SPO Survey Update 145 responses to date: Air Force: 118 Army 16% 3% Navy Army: 23 Navy: 4 81% Air Force PE Massachusetts Institute of Technology
5 Size: Mean total program budget $3.7B (median $237M). Mean program length to IOC 7.75 years (median 6.4 years). Survey Sample Demographics ACAT Designation: 14% ACAT IV ACAT III 35% 41% ACAT I ACAT II 10% Source: 1996 Government PM survey. PE Massachusetts Institute of Technology
6 Survey Sample Demographics (cont.) Program Phase: Sustainment 12% 11% Other 5% Concept Exploration Production 29% 7% DEM/VAL 36% EMD Source: 1996 Government PM survey. PE Massachusetts Institute of Technology
7 Survey Sample Demographics (cont.) System Types (sectors represented) Other 13% 14% Electronics Engines 6% 12% Airframe Software 16% 14% Missiles/Munitions 25% Avionics Source: 1996 Government PM survey. PE Massachusetts Institute of Technology
8 Contractor Survey ~320 surveys distributed. 76 responses (~%24 response rate) to date 1 Sept. deadline. Follow-up underway. No analysis performed yet First looks by CY97. PE Massachusetts Institute of Technology
9 Cost of Instability Update Cost growth (average annual*): Budget changes: 2.4% Changes in user requirements: 2.7% Technical difficulties: 2.6% Total: 7.8% Budget and requirements changes account for 66% of average annual program cost growth. * Mean baseline period 60 months; median 43 months Source: 1996 Government PM survey. PE Massachusetts Institute of Technology
10 Cost of Instability Update (cont.) Schedule slip (total program): Budget changes: 9.1% Changes in user requirements: 11.9% Technical difficulties: 9.4% Total: 34.3% Budget and requirements changes account for 61% of total program schedule slip. Source: 1996 Government PM survey. PE Massachusetts Institute of Technology
11 Cost of Instability in Perspective Program Cost (Change from Baseline) 30% 20% 10% 0-10% -20% Average cost growth due to funding and requirements changes Traditional program baseline } Estimated range of savings from the use of lean practices Time (Years) -30% Source: 1996 Government PM survey, JSF MADP report. PE Massachusetts Institute of Technology
12 The Role of Uncertainty A fundamental tenet of leanness: Reduce uncertainty (uncontrolled variance) where possible. Problem: Aggressive technological advance introduces uncertainty into program planning and programming. Excess uncertainty may inhibit successful overall movement towards leanness. PE Massachusetts Institute of Technology
13 Types of Cost Growth Associated with System-level Technical Advance 12 Annual Program Cost Growth (%) Revolutionary New Concept Technical Problems Budget Instability Requirements Changes New Generation Architecture Incremental Improvement Little Change Source: 1996 Government PM survey. PE Massachusetts Institute of Technology
14 Subsystem-Level Technical Advance Level of Technical Advance Required in Critical System Components: All New Development All Non- Developmental 1 Lowest Quartile Cost Growth Median Quartiles Cost Growth Highest Quartile Cost Growth Source: 1996 Government PM survey. PE Massachusetts Institute of Technology
15 Non-Developmental Content 100 OTS / NDI Value Content (%) Lowest Quartile Cost Growth Median Quartiles Cost Growth Highest Quartile Cost Growth Source: 1996 Government PM survey. PE Massachusetts Institute of Technology
16 Military-Unique Characteristics Response to the statement: The technologies used in this program have more demanding requirements than commercial technologies and therefore this system should take longer to develop and field. Strongly Agree Strongly Disagree 1 Lowest Quartile Cost Growth Median Quartiles Cost Growth Highest Quartile Cost Growth Source: 1996 Government PM survey. PE Massachusetts Institute of Technology
17 Summary Unplanned cost growth from aggressive technological advance suggests: uncertainty associated with very advanced products presents significant challenges to the current planning/budgeting process. use of buffers to compensate for uncertainty (which is inconsistent with lean paradigm). overall levels of uncertainty in the system may have to be traded against goals for attaining leanness. PE Massachusetts Institute of Technology
18 The Role of Responsiveness Another tenet of leanness: Increase responsiveness (adaptability) where possible. Compensate for uncertainty. PE Massachusetts Institute of Technology
19 Management Practices to Overcome Instability Data collected: Use of various practices to avoid the onset and mitigate the negative impact of program instability. Uncertainty reducing Responsiveness enhancing Program plan sensitivity to unplanned budget changes. PE Massachusetts Institute of Technology
20 Tolerance to Budget Variability Use the following practices? Contractor involved in requirements generation High-risk developments off critical path Schedule interdependent activities in same budget year Designs validated using prototypes Use staff from other offices No Yes Design based on incremental technology steps Short cycle time Tolerable Variance in Budget (%) Source: 1996 Government PM survey. PE Massachusetts Institute of Technology
21 Cost Impacts of Requirements Changes Use the following practices? No Yes Use CAM Use TEMs Personnel as Needed Use Flexible Assembly Major Subsystems Managed in Different SPOs Multi-year Procurement Annual Cost Growth Due to Requirements Changes (%) Source: 1996 Government PM survey. PE Massachusetts Institute of Technology
22 Influence of OTS / NDI Content Use the following practices? Aggressively Advocate Support for your Program No Yes Designs Validated Using Prototypes Design Validated Using Simulation and Modeling Design Based on Incremental Technology Steps High-risk Developments Scheduled off Critical Path Use CAM Use Flexible Assembly Use 3-D Modeling OTS / NDI Content Value (%) Source: 1996 Government PM survey. PE Massachusetts Institute of Technology
23 Summary Increasing responsiveness to change: Tolerance to budget variance improved by reducing dependence on critical technologies or resources (risk management) and increasing responsiveness. Practices that increase program responsiveness decrease the premium paid for changing requirements. A Tradeoff: Use of risk management, responsiveness practices an apparent substitute for using more OTS / NDI technologies. PE Massachusetts Institute of Technology
24 Observations Program instability factors account for the major part of both program cost growth and schedule slip. Magnitude of the cost of program instability may equal or exceed that of expected cost savings from lean. PE Massachusetts Institute of Technology
25 Observations (cont.) Increased uncertainty associated with high levels of technical advance a potential barrier to realizing the full benefits of leanness: Tradeoff between accepting cost of uncertainty or developing increased responsiveness to unplanned changes. Support PD/SR investigation of benefits of modular/platform-based product development concepts. PE Massachusetts Institute of Technology
26 Next Steps Validate findings through discussions with practitioners. Integrate contractor data into on-going analysis of SPO data. Continued population of the LEM with findings. PE Massachusetts Institute of Technology
27 Other Policy Focus Team Activities Economic incentives: Two case studies well underway. Two more case study sites under negotiation. Use of commercial practices: Research begun to catalogue lessons learned from commercial practice pathfinder and pilot programs. Focus team defining additional research topic. Modeling the acquisition process: Model development progressing. Role of Lean User in requirements generation: White paper written. PE Massachusetts Institute of Technology
Lean Aircraft Initiative Plenary Workshop. Program Director Welcome
Lean Aircraft Initiative Plenary Workshop Program Director Welcome October 8, 1997 Presented By: Earll Murman MIT Today s Introduction Phase II Vision Vision Statement Workshop Theme Recent Significant
More informationJerome Tzau TARDEC System Engineering Group. UNCLASSIFIED: Distribution Statement A. Approved for public release. 14 th Annual NDIA SE Conf Oct 2011
LESSONS LEARNED IN PERFORMING TECHNOLOGY READINESS ASSESSMENT (TRA) FOR THE MILESTONE (MS) B REVIEW OF AN ACQUISITION CATEGORY (ACAT)1D VEHICLE PROGRAM Jerome Tzau TARDEC System Engineering Group UNCLASSIFIED:
More informationA New Way to Start Acquisition Programs
A New Way to Start Acquisition Programs DoD Instruction 5000.02 and the Weapon Systems Acquisition Reform Act of 2009 William R. Fast In their March 30, 2009, assessment of major defense acquisition programs,
More informationLean Aerospace Initiative Plenary Workshop. Key Characteristic Maturity Model
Plenary Workshop Key Characteristic Maturity Model March 31- April 1, 1998 Presented By: Basak Ertan MIT Research Sponsored By Lean Aerospace Presentation Outline Key Characteristic(KC) Overview Benchmarking
More informationManufacturing Readiness Assessment Overview
Manufacturing Readiness Assessment Overview Integrity Service Excellence Jim Morgan AFRL/RXMS Air Force Research Lab 1 Overview What is a Manufacturing Readiness Assessment (MRA)? Why Manufacturing Readiness?
More informationDEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers
Outcomes and Enablers 1 From an engineering leadership perspective, the student will describe elements of DoD systems engineering policy and process across the Defense acquisition life-cycle in accordance
More informationLean Enablers for Managing Engineering Programs
Lean Enablers for Managing Engineering Programs Presentation to the INCOSE Enchantment Chapter June 13 2012 Josef Oehmen http://lean.mit.edu 2012 Massachusetts Institute of Technology, Josef Oehmen, oehmen@mit.edu
More informationIntermediate Systems Acquisition Course. Lesson 2.2 Selecting the Best Technical Alternative. Selecting the Best Technical Alternative
Selecting the Best Technical Alternative Science and technology (S&T) play a critical role in protecting our nation from terrorist attacks and natural disasters, as well as recovering from those catastrophic
More informationManufacturing Readiness Levels (MRLs) Manufacturing Readiness Assessments (MRAs) In an S&T Environment
Manufacturing Readiness Levels (MRLs) Manufacturing Readiness Assessments (MRAs) In an S&T Environment Jim Morgan Manufacturing Technology Division Phone # 937-904-4600 Jim.Morgan@wpafb.af.mil Why MRLs?
More informationTRLs and MRLs: Supporting NextFlex PC 2.0
TRLs and MRLs: Supporting NextFlex PC 2.0 Mark A. Gordon Mfg Strategy, Inc. mark.gordon@mfgstrategy.org 1 1 TRLs and MRLs: Supporting NextFlex PC 2.0 Outline Purpose and Scope of Webinar Readiness Levels:
More informationManufacturing Readiness Levels (MRLs) and Manufacturing Readiness Assessments (MRAs)
Manufacturing Readiness Levels (MRLs) and Manufacturing Readiness Assessments (MRAs) Jim Morgan Manufacturing Technology Division Phone # 937-904-4600 Jim.Morgan@wpafb.af.mil Report Documentation Page
More informationOther Transaction Authority (OTA)
Other Transaction Authority (OTA) Col Christopher Wegner SMC/PK 15 March 2017 Overview OTA Legal Basis Appropriate Use SMC Space Enterprise Consortium Q&A Special Topic. 2 Other Transactions Authority
More informationOur Acquisition Challenges Moving Forward
Presented to: NDIA Space and Missile Defense Working Group Our Acquisition Challenges Moving Forward This information product has been reviewed and approved for public release. The views and opinions expressed
More informationLean Aerospace Initiative Plenary Workshop. Looking Forward to Phase III. March 23, 1999 Presented By: Cliff Harris MIT
Plenary Workshop Looking Forward to Phase III March 23, 1999 Presented By: Cliff Harris MIT Three Related Messages The Lean Industrial Model is evolving Phase III is refocused to the broader model If you
More informationAn Assessment of Acquisition Outcomes and Potential Impact of Legislative and Policy Changes
An Assessment of Acquisition Outcomes and Potential Impact of Legislative and Policy Changes Presentation by Travis Masters, Sr. Defense Analyst Acquisition & Sourcing Management Team U.S. Government Accountability
More informationIntegrated Transition Solutions
Vickie Williams Technology Transition Manager NSWC Crane Vickie.williams@navy.mil 2 Technology Transfer Partnership Between Government & Industry Technology Developed by One Entity Use by the Other Developer
More informationU.S. Combat Aircraft Industry, : Structure, Competition, Innovation
SUMMARY A RAND research effort sponsored by the Office of the Secretary of Defense examined the future of the U.S. fixed-wing military aircraft industrial base. Its focus was the retention of competition
More informationWhittard of Chelsea. Gender Pay Gap Reporting 2017
Whittard of Chelsea Gender Pay Gap Reporting 2017 Gender Pay Gap Introduction At Whittard we aim to be a great place to work and want our employees to be happy and proud to work for us. We have a clear
More informationAdoption and diffusion of cloud computing in the public sector A case study of Zambia. Shuller Habeenzu ITMC/RIA Focal Point-Lusaka
Adoption and diffusion of cloud computing in the public sector A case study of Zambia Shuller Habeenzu ITMC/RIA Focal Point-Lusaka Zambia : A brief Overview Rapid and youthful population growth Poverty
More informationSERC Technical Overview: First-Year Results and Future Directions. Barry Boehm, USC Rich Turner, Stevens. 15 October 2009
SERC Technical Overview: First-Year Results and Future Directions Barry Boehm, USC Rich Turner, Stevens 15 October 2009 Outline General context First year objectives Show ability to herd academic cats
More informationDefense Microelectronics Activity (DMEA) Advanced Technology Support Program IV (ATSP4) Organizational Perspective and Technical Requirements
Defense Microelectronics Activity (DMEA) Advanced Technology Support Program IV (ATSP4) Organizational Perspective and Technical Requirements DMEA/MED 5 March 2015 03/05/2015 Page-1 DMEA ATSP4 Requirements
More informationTECHNICAL RISK ASSESSMENT: INCREASING THE VALUE OF TECHNOLOGY READINESS ASSESSMENT (TRA)
TECHNICAL RISK ASSESSMENT: INCREASING THE VALUE OF TECHNOLOGY READINESS ASSESSMENT (TRA) Rebecca Addis Systems Engineering Tank Automotive Research, Development, and Engineering Center (TARDEC) Warren,
More informationTechnology & Manufacturing Readiness RMS
Technology & Manufacturing Readiness Assessments @ RMS Dale Iverson April 17, 2008 Copyright 2007 Raytheon Company. All rights reserved. Customer Success Is Our Mission is a trademark of Raytheon Company.
More informationTechnology Refresh A System Level Approach to managing Obsolescence
Technology Refresh A System Level Approach to managing Obsolescence Jeffrey Stavash Shanti Sharma Thaddeus Konicki Lead Member Principle Member Senior Member Lockheed Martin ATL Lockheed Martin ATL Lockheed
More informationDavid N Ford, Ph.D.,P.E. Zachry Department of Civil Engineering Texas A&M University. Military Acquisition. Research Project Descriptions
David N Ford, Ph.D.,P.E. Zachry Department of Civil Engineering Texas A&M University Military Acquisition Research Project Descriptions Index Angelis, D., Ford, DN, and Dillard, J. Real options in military
More informationDistribution Restriction Statement Approved for public release; distribution is unlimited.
CEMP-RA Engineer Regulation 200-1-1 Department of the Army U.S. Army Corps of Engineers Washington, DC 20314-1000 ER 200-1-1 30 May 2000 Environmental Quality POLICY AND GENERAL REQUIREMENTS FOR THE ENVIRONMENTAL
More informationTHE APPLICATION OF SYSTEMS ENGINEERING ON THE BUILDING DESIGN PROCESS
THE APPLICATION OF SYSTEMS ENGINEERING ON THE BUILDING DESIGN PROCESS A.Yahiaoui 1, G. Ulukavak Harputlugil 2, A.E.K Sahraoui 3 & J. Hensen 4 1 & 4 Center for Building & Systems TNO-TU/e, 5600 MB Eindhoven,
More informationContinuous Competition as an Approach to Maximize Performance
Approved for Public Release: 12-3233. Distribution Unlimited. The Limits of Competition in Defense Acquisition Keywords: acquisition, competition, contracting, down-select, source selection Continuous
More informationSYSTEMS ENGINEERING MANAGEMENT IN DOD ACQUISITION
Chapter 2 Systems Engineering Management in DoD Acquisition CHAPTER 2 SYSTEMS ENGINEERING MANAGEMENT IN DOD ACQUISITION 2.1 INTRODUCTION The DoD acquisition process has its foundation in federal policy
More informationDoDI and WSARA* Impacts on Early Systems Engineering
DoDI 5000.02 and WSARA* Impacts on Early Systems Engineering Sharon Vannucci Systems Engineering Directorate Office of the Director, Defense Research and Engineering 12th Annual NDIA Systems Engineering
More informationThe Role of Public Procurement in Low-carbon Innovation in Infrastructure
ROUND TABLE ON SUSTAINABLE DEVELOPMENT The Role of Public Procurement in Low-carbon Innovation in Infrastructure Summary of the Round Table on Sustainable Development 1 held at OECD Headquarters, Paris,
More information2016 Smart Cities Survey Summary Report of Survey Results
Introduction 2016 Smart Cities Survey Summary Report of Survey Results In 2016, the International City/County Management Association (ICMA) conducted a survey in partnership with the Smart Cities Council
More informationOptical Telescope Design Study Results
Optical Telescope Design Study Results 10 th International LISA Symposium Jeff Livas 20 May 2014 See also poster #19: Shannon Sankar UF and GSFC Telescope Design for a Space-based Gravitational-wave Mission
More informationInstrumentation and Control
Program Description Instrumentation and Control Program Overview Instrumentation and control (I&C) and information systems impact nuclear power plant reliability, efficiency, and operations and maintenance
More informationOther Transactions (OTs) for Prototypes and the Information Warfare Research Project (IWRP) Consortium OT
Other Transactions (OTs) for Prototypes and the Information Warfare Research Project (IWRP) Consortium OT Jacob Ward Head, Cyber and Science & Technology Contracts Support Branch SSC Pacific 17 July 2018
More informationTen Years of Progress in Lean Product Development. Dr. Hugh McManus Associate Director, Lean Advancement Initiative Educational Network
Ten Years of Progress in Lean Product Development Dr. Hugh McManus Associate Director, Lean Advancement Initiative Educational Network 10-15 Years Ago: Questions Does Lean apply to Product Development,
More informationUsing MIL-STD-882D w/change 1 For Hazardous Materials Management
Using MIL-STD-882D w/change 1 For Hazardous Materials Management Karen Gill NDIA Environment, Energy Security, and Sustainability Symposium, Denver, CO June 2010 1 Driver DoD requires each acquisition
More informationTechnology Transition Assessment in an Acquisition Risk Management Context
Transition Assessment in an Acquisition Risk Management Context Distribution A: Approved for Public Release Lance Flitter, Charles Lloyd, Timothy Schuler, Emily Novak NDIA 18 th Annual Systems Engineering
More informationStrategic Guidance. Quest for agility, innovation, and affordability. Distribution Statement A: Approved for Public Release
Strategic Guidance Quest for agility, innovation, and affordability As we end today s wars and reshape our Armed Forces, we will ensure that our military is agile, flexible, and ready for the full range
More informationGender Pay Report 2017
Gender Pay Report 2017 Introduction The gender pay gap measures the difference between men and women s average earnings and is expressed as a percentage of men s pay. According to the Office of National
More informationGerald G. Boyd, Tom D. Anderson, David W. Geiser
THE ENVIRONMENTAL MANAGEMENT PROGRAM USES PERFORMANCE MEASURES FOR SCIENCE AND TECHNOLOGY TO: FOCUS INVESTMENTS ON ACHIEVING CLEANUP GOALS; IMPROVE THE MANAGEMENT OF SCIENCE AND TECHNOLOGY; AND, EVALUATE
More informationPrototyping: Accelerating the Adoption of Transformative Capabilities
Prototyping: Accelerating the Adoption of Transformative Capabilities Mr. Elmer Roman Director, Joint Capability Technology Demonstration (JCTD) DASD, Emerging Capability & Prototyping (EC&P) 10/27/2016
More informationComments of Deepwater Wind, LLC May 18, 2018
STATE OF NEW JERSEY BOARD OF PUBLIC UTILITIES Docket No. QX18040466 In the Matter of Offshore Wind Renewable Energy Certificate (OREC) Funding Mechanism Comments of Deepwater Wind, LLC May 18, 2018 Deepwater
More informationTransitioning Technology to Naval Ships. Dr. Norbert Doerry Technical Director, SEA 05 Technology Group SEA05TD
Transitioning Technology to Naval Ships Transportation Research Board Public Meeting National Academy of Sciences June 10, 2010 Dr. Norbert Technical Director, SEA 05 Technology Group SEA05TD Norbert.doerry@navy.mil
More informationUNCLASSIFIED. UNCLASSIFIED Office of Secretary Of Defense Page 1 of 5 R-1 Line #102
Exhibit R-2, RDT&E Budget Item Justification: PB 2015 Office of Secretary Of Defense Date: March 2014 0400: Research, Development, Test & Evaluation, Defense-Wide / BA 4: Advanced Component Development
More informationDesign Principles for Survivable System Architecture
Design Principles for Survivable System Architecture 1 st IEEE Systems Conference April 10, 2007 Matthew Richards Research Assistant, MIT Engineering Systems Division Daniel Hastings, Ph.D. Professor,
More informationCOLLECTIVE PROTECTION
Joint Program Executive Office for Chemical and Biological Defense Joint Science and Technology Office COLLECTIVE PROTECTION April 4, 2007 Advanced Planning Brief to Industry STANLEY A. ENATSKY, PE JPM
More informationEfficient Tactics of Project Management
Ohio Structure Steel & Architectural Metals Association Efficient Tactics of Project Management Friday, June 23, 2017 Mark V. Holland, P.E. Chief Engineer Paxton & Veirling Steel Co. How to get paid. This
More informationAircraft Structure Service Life Extension Program (SLEP) Planning, Development, and Implementation
Structures Bulletin AFLCMC/EZ Bldg. 28, 2145 Monohan Way WPAFB, OH 45433-7101 Phone 937-255-5312 Number: EZ-SB-16-001 Date: 3 February 2016 Subject: Aircraft Structure Service Life Extension Program (SLEP)
More informationInformation Warfare Research Project
SPACE AND NAVAL WARFARE COMMAND Information Warfare Research Project Charleston Defense Contractors Association 49th Small Business Industry Outreach Initiative 30 August 2018 Mr. Don Sallee SSC Atlantic
More informationEXPERT GROUP MEETING ON CONTEMPORARY PRACTICES IN CENSUS MAPPING AND USE OF GEOGRAPHICAL INFORMATION SYSTEMS New York, 29 May - 1 June 2007
EXPERT GROUP MEETING ON CONTEMPORARY PRACTICES IN CENSUS MAPPING AND USE OF GEOGRAPHICAL INFORMATION SYSTEMS New York, 29 May - 1 June 2007 STATEMENT OF DR. PAUL CHEUNG DIRECTOR OF THE UNITED NATIONS STATISTICS
More informationDemonstration System Development for Advanced Shipboard Desalination FNC
AMENDMENT NUMBER 0002 BAA 11-010 ENTITLED Demonstration System Development for Advanced Shipboard Desalination FNC The purpose of Amendment 0001 is to provide answers to following questions: Q1- Do you
More informationHuman System Integration: Challenges and Opportunities
Headquarters U.S. Air Force Human System Integration: Challenges and Opportunities Dr. Mica Endsley USAF Chief Scientist I n t e g r i t y - S e r v i c e - E x c e l l e n c e 1 Surveying the Science
More informationEngaging Innate Human Cognitive Capabilities to Coordinate Human Interruption in Human- Computer Interaction: The HAIL System
Engaging Innate Human Cognitive Capabilities to Coordinate Human Interruption in Human- Computer Interaction: The HAIL System Operator Console Cognitive System Components Weapon System HAIL Engine Dr.
More informationA QUALITY ASSURANCE STRATEGY IN MALAYSIA 2020 POPULATION AND HOUSING CENSUS
United Nations Regional Workshop on The 2020 World Programme on Population and Housing Censuses: International Standards and Contemporary Technologies SESSION 6: A QUALITY ASSURANCE IN POPULATION AND HOUSING
More informationHow the U.S. Naval Air Systems Command is transforming its engineering workforce with MIT s Architecture and Systems Engineering Online Program
For the past three years, the Department of Defense s Naval Air Systems Command (NAVAIR) organization has committed to a different kind of mission than any it has pursued before to transform their engineering
More informationNguyen Thi Thu Huong. Hanoi Open University, Hanoi, Vietnam. Introduction
Chinese Business Review, June 2016, Vol. 15, No. 6, 290-295 doi: 10.17265/1537-1506/2016.06.003 D DAVID PUBLISHING State Policy on the Environment in Vietnamese Handicraft Villages Nguyen Thi Thu Huong
More informationPerspectives on the Scientific and Technological Needs in DOE s Environmental Management Program
Perspectives on the Scientific and Technological Needs in DOE s Environmental Management Program National Academies of Sciences, Engineering, and Medicine Oak Ridge Public Meeting August 9 th, 2018 Statement
More informationChallenges and Innovations in Digital Systems Engineering
Challenges and Innovations in Digital Systems Engineering Dr. Ed Kraft Associate Executive Director for Research University of Tennessee Space Institute October 25, 2017 NDIA 20 th Annual Systems Engineering
More informationSoftware Failures. Dr. James A. Bednar. Dr. David Robertson
Software Failures Dr. James A. Bednar jbednar@inf.ed.ac.uk http://homepages.inf.ed.ac.uk/jbednar Dr. David Robertson dr@inf.ed.ac.uk http://www.inf.ed.ac.uk/ssp/members/dave.htm SEOC2 Spring 2005: Failures
More informationOVERVIEW: THE PROMISE OF CIVIL-MILITARY INTEGRATION (CMI)
Chapter One INTRODUCTION OVERVIEW: THE PROMISE OF CIVIL-MILITARY INTEGRATION (CMI) After World War II, the Pentagon s unique regulatory and oversight requirements, combined with its specialized and highly
More informationMichael Coughenour Lockheed Martin Rotary & Mission Systems (RMS) System Engineering Technologist
A Systems Engineering approach to applying Risk Management Framework (RMF) for a successful program and a secure system a case study RMF is Not a 4-Letter Word Craig Covak Lockheed Martin Rotary & Mission
More informationNational Academy of Sciences Committee on Naval Engineering in the 21 st Century
National Academy of Sciences Committee on Naval Engineering in the 21 st Century Workshop for Examining the Science and Technology Enterprise in Naval Engineering Session One: Future Needs for S&T Output
More informationTechnology Insertion: A Way Ahead
Obsolescence Challenges, Part 2 Technology Insertion: A Way Ahead Brent Hobson In the Summer 2008 issue of the Canadian Naval Review (Volume 4, No. 2), my article, Obsolescence Challenges and the Canadian
More informationROI of Technology Readiness Assessments Using Real Options: An Analysis of GAO Data from 62 U.S. DoD Programs by David F. Rico
ROI of Technology Readiness Assessments Using Real Options: An Analysis of GAO Data from 62 U.S. DoD Programs by David F. Rico Abstract Based on data from 62 U.S. DoD programs, a method is described for
More informationManufacturing Readiness Level (MRL) Deskbook Version 2016
Manufacturing Readiness Level (MRL) Deskbook Version 2016 Prepared by the OSD Manufacturing Technology Program In collaboration with The Joint Service/Industry MRL Working Group This document is not a
More informationElements in decision making / planning 4 Decision makers. QUESTIONS - stage A. A3.1. Who might be influenced - whose problem is it?
A Describe the CONTEXT, setup the BASELINE, formulate PROBLEMS, identify NEEDS A.. What is the context, the baseline and are the key problems? A.. What are the urgent priorities herein? A.. How would you
More informationWorkshop on Census Data Processing Doha, Qatar 18-22/05/2008
Palestinian National Authority Palestinian Central Bureau of Statistics United Nations Statistics Division (UNSD) Economic and Social Commission for Western Asia (ESCWA) Workshop on Census Data Processing
More informationReport 2017 UK GENDER PAY GAP UK GENDER PAY GAP REPORT
Report 2017 UK GENDER PAY GAP UK GENDER PAY GAP REPORT 2017 1 INTRODUCTION DEE SAWYER Head of Human Resources At T. Rowe Price we are committed to diversity and inclusion. It is an integral part of our
More informationMinute /18. Exemptions. FOI Exemptions: Section Page 4, FOI Exemption Section 43. Section Page 4-5, FOI Exemption Section 22
Minute 2 2017/18 Exemptions FOI Exemptions: Section 4.6.3 Page 4, FOI Exemption Section 43 Section 4.6.5 Page 4-5, FOI Exemption Section 22 Section 5.2 Page 7, FOI Exemption Section 22 Section 5.3 Page
More informationTechnology Needs Assessments under GEF Enabling Activities Top Ups
National Communications Support Programme United Nations Development Programme Global Environment Facility Technology Needs Assessments under GEF Enabling Activities Top Ups UNFCCC/UNDP Expert Meeting
More informationErika Rivers MN DNR Mary Blickenderfer U of MN Extension
Erika Rivers MN DNR Mary Blickenderfer U of MN Extension MACPZA Conference October 8, 2009 Own Manage/ Regulate Educate/ Influence Own Most Minnesota shoreland is in private ownership. Statewide minimums
More informationOther Transaction Agreements. Chemical Biological Defense Acquisition Initiatives Forum
Other Transaction Agreements Chemical Biological Defense Acquisition Initiatives Forum John M. Eilenberger Jr. Chief of the Contracting Office U.S. Army Contracting Command - New Jersey Other Transaction
More informationTechnology Readiness Assessment of Department of Energy Waste Processing Facilities: When is a Technology Ready for Insertion?
Technology Readiness Assessment of Department of Energy Waste Processing Facilities: When is a Technology Ready for Insertion? Donald Alexander Department of Energy, Office of River Protection Richland,
More informationCollaborative Efforts in Engineering and Technology Education
Collaborative Efforts in Engineering and Technology Education R. Sterkenburg, D.L. Stanley & J. Lampe Purdue University Abstract - Over the last two years, Mechanical Engineering (ME) and Aviation Technology
More informationAcquisition Intrapreneur
The Pursuit of Acquisition Intrapeneurs Presented By Major Chris Forseth LAI Fellowship 20012002 March 25, 2003 Acquisition Intrapreneur Definition: Individuals within the acquisition profession who take
More informationSpiral Acquisition and the Integrated Command and Control System
Spiral Acquisition and the Integrated Command and Control System Thomas F. Saunders USC-SEI Spiral Workshop February 2000 Outline - 0 Different views of spiral 0 Spiral seems to work when... 0 Spiral stumbles
More informationCACI INTERNATIONAL INC /DE/
CACI INTERNATIONAL INC /DE/ FORM 8-K (Unscheduled Material Events) Filed 8/8/2005 For Period Ending 8/8/2005 Address 1100 N GLEBE ST ARLINGTON, Virginia 22201 Telephone 703-841-7800 CIK 0000016058 Industry
More informationNew Methods for Architecture Selection and Conceptual Design:
New Methods for Architecture Selection and Conceptual Design: Space Systems, Policy, and Architecture Research Consortium (SSPARC) Program Overview Hugh McManus, Joyce Warmkessel, and the SSPARC team For
More informationTechnology Transfer. When, Why, Issues and Advantages. David F. Sutter IREAP, U. of Maryland. Bruce P. Strauss U.S. Dept.
Technology Transfer When, Why, Issues and Advantages David F. Sutter IREAP, U. of Maryland Bruce P. Strauss U.S. Dept. of Energy PAC 07 June 25, 2007 Introduction Technology transfer is a big and very
More informationONR BAA Affordable Electronically Scanned Array Technology for Next Generation Naval Platforms. Questions & Answers 3/21/07
ONR BAA 07-010 Affordable Electronically Scanned Array Technology for Next Generation Naval Platforms Questions & Answers 3/21/07 NOTE: Questions and Answers in this document are considered. Final Versions
More informationSLOSS FURNACES PHOTOGRAPHY POLICY
SLOSS FURNACES PHOTOGRAPHY POLICY Sloss Furnaces National Historic Landmark is a museum and educational institution whose primary mission is to preserve and promote the site in order to educate and expose
More informationWorking conditions of dancers in the contemporary dance sector
Working conditions of dancers in the contemporary dance sector EDN workshop on dance production and funding in Europe Brussels, 17.10.2016 Delphine Hesters - Flanders Arts Institute Overview Observations
More informationA new approach to funding, accelerating, and commercializing fusion. R. Mumgaard CEO --Commonwealth Fusion Systems NAS comments, PPPL, April 12, 2018
A new approach to funding, accelerating, and commercializing fusion R. Mumgaard CEO --Commonwealth Fusion Systems NAS comments, PPPL, April 12, 2018 Your charge to me: 1. The capabilities and prospects
More informationStudent Guidance Notes 2019
Student Guidance Notes 2019 This guidance is here to help you complete our application form. Please read through this guidance carefully before you apply for our programmes. If you have any questions,
More informationFollow the Yellow Brick Road
NDCEE National Defense Center for Environmental Excellence National Defense Center for Environmental Excellence TRANSFERRING TECHNOLOGY SOLUTIONS Supporting Readiness, Sustainability, and Transformation
More informationGender Pay Gap Report 2017
Gender Pay Gap Report 2017 2 House of Lords Introduction The House of Lords Administration believes that transparent reporting and monitoring is an important step to tackling any inequality revealed through
More informationAir Force Institute of Technology. A Quantitative Analysis of the Benefits of Prototyping Fixed-Wing Aircraft
CONTENT APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED Air Force Institute of Technology E d u c a t i n g t h e W o r l d s B e s t A i r F o r c e A Quantitative Analysis of the Benefits of Prototyping
More informationTHE 2012 POPULATION AND HOUSING CENSUS AN OVERVIEW. NATIONAL BUREAU OF STATISTICS 4 th August, 2011 Dar es Salaam
1 THE 2012 POPULATION AND HOUSING CENSUS AN OVERVIEW NATIONAL BUREAU OF STATISTICS 4 th August, 2011 Dar es Salaam Outline of the Presentation 2 Background Information Census major phases Progress so far
More informationCOST GROWTH, ACQUISITION POLICY, AND BUDGET CLIMATE David L. McNicol
COST GROWTH, ACQUISITION POLICY, AND BUDGET CLIMATE David L. McNicol The Problem This article asks whether, taking account of funding climate, there is a statistically significant association between changes
More informationIntroduction Strategic Objectives of IT Operation for 2008 Census Constraints Conclusion
For Expert Group Meeting Opportunities and advantages of enhanced collaboration on statistical information management in Asia and the Pacific, 20-22 June 2011, Bangkok, Thailand Introduction Strategic
More informationA/AC.105/C.1/2006/NPS/CRP.7 16 February 2006
FOR PARTICIPANTS ONLY A/AC.105/C.1/2006/NPS/CRP.7 16 February 2006 Original: English COMMITTEE ON THE PEACEFUL USES OF OUTER SPACE Scientific and Technical Subcommittee Forty-third session Vienna, 20 February
More informationABSTRACT. Keywords: ESSP, Earth Venture, program management, NASA Science Mission Directorate, Class-D mission, Instrument-first 1.
SSC14-VI-10 Opportunities for Small Satellites in NASA s Earth System Science Pathfinder (ESSP) Program Frank Peri, Richard, C. Law, James E. Wells NASA Langley Research Center, 9 Langley Boulevard, Hampton,
More informationForward Looking Information
Innovation April 4, 2018 Kalev Ruberg, Vice President, Digital Systems and Chief Information Officer Greg Brouwer, General Manager, Technology and Innovation Forward Looking Information Both these slides
More informationMassachusetts Renewables/ Cape Wind Survey
Massachusetts Renewables/ Cape Wind Survey Prepared for Civil Society Institute (CSI) Prepared by June 7, 2006 Copyright 2006. Opinion Research Corporation. All rights reserved. Table of Contents Page
More informationModel Based Systems Engineering (MBSE) Business Case Considerations An Enabler of Risk Reduction
Model Based Systems Engineering (MBSE) Business Case Considerations An Enabler of Risk Reduction Prepared for: National Defense Industrial Association (NDIA) 26 October 2011 Peter Lierni & Amar Zabarah
More informationRAPID FIELDING A Path for Emerging Concept and Capability Prototyping
RAPID FIELDING A Path for Emerging Concept and Capability Prototyping Mr. Earl Wyatt Deputy Assistant Secretary of Defense, Rapid Fielding Office of the Assistant Secretary of Defense (Research and Engineering)
More informationTHE EM LEAD LABORATORY: PROVIDING THE RESOURCES AND FRAMEWORK FOR COMPLEXWIDE ENVIRONMENTAL CLEANUP-STEWARDSHIP ACTIVITIES
ABSTRACT THE EM LEAD LABORATORY: PROVIDING THE RESOURCES AND FRAMEWORK FOR COMPLEXWIDE ENVIRONMENTAL CLEANUP-STEWARDSHIP ACTIVITIES Greg B. Frandsen, Paul K. Kearns, and Raymond L. McKenzie Environmental
More informationInnovation Workshop. Creating Capability to Envision and Shift U.S. Air Force Mindset for a Very Different Future
Innovation Workshop Creating Capability to Envision and Shift U.S. Air Force Mindset for a Very Different Future Background Air Force Studies Board Division on Engineering & Physical Sciences Meeting March
More informationDUSD (S&T) Software Intensive Systems
DUSD (S&T) Software Intensive Systems 25 July 2000 Jack Ferguson (fergusj@acq.osd.mil) Director, Software Intensive Systems, ODUSD(S&T) Outline Role of Deputy Under Secretary of Defense for Science and
More information