Efficient Tactics of Project Management

Size: px
Start display at page:

Download "Efficient Tactics of Project Management"

Transcription

1 Ohio Structure Steel & Architectural Metals Association Efficient Tactics of Project Management Friday, June 23, 2017

2 Mark V. Holland, P.E. Chief Engineer Paxton & Veirling Steel Co.

3 How to get paid. This presentation will not discuss how to get paid or collect from your invoices. However At the end I will share some of my thoughts on this issue.

4 Code of Standard Practice ANSI / AISC Code of Standard Practice for Steel Buildings and Bridges Free download from AISC.org

5 What we will cover 1. Know what you sold your customer. 2. Set up meeting ~ or ~ learn from your mistakes. 3. Make sure the shop knows what is excepted of them. 4. Get and stay organized. 5. Use the schedule as a to do list. 6. Know how to talk to you customer. 7. Getting paid. 8. Keep the guy on site happy. 9. Be anonymous.

6 The Beginning Getting Started

7 Know what you sold your customer. The proposal. What is the proposal based on? Who is responsible for what? What is the scope? Who is your customer? The schedule. What was the price based on? When are things supposed to happen? The to do list. Cause and effect.

8 The proposal What is the proposal based on? Responsibility for Identifying Contract Documents. (AISC Section 1.4) (AISC Section 1.5) List of the design drawings. List of specifications. If model based ~ what version of the model.

9 AISC Section 1.4

10 AISC Section 1.5

11 The proposal Who is responsible for what? Responsible for design of the structure. ( Section 1.6) Responsible for connection design. ( Section 3.1.1)

12 AISC Section 1.6

13 The proposal What is the scope? The list of the design drawing, addendum, RFIs, etc... Should define the scope of work. Definition of Structural Steel ~ Other Steel, Iron or Metal Items. ( Section 2.1 ~ Section 2.2) Architectural, Electrical and Mechanical Design Documents and Specifications. ( Section 3.2)

14 AISC Section 3.2

15 The Schedule What was the price based on? Have a schedule at bid. The Bid Schedule shows the plan the price is based on. Without a Bid Schedule you will have a harder time proving entitlement when something changes.

16 The Schedule Use a CPM scheduling tool.

17 The Schedule ~ Sections of the Schedule Design Information IFC RFIs Addendum EtcA Material Procurement ABM Approval drawings

18 The Schedule ~ Sections of the Schedule Engineering Submittal Cycle Approval Cycle Release for Fabrication Fabrication Process Material Fit / weld Paint load Shipping

19 The Schedule Show when tasks need to start and finish.

20 The Schedule Organization the tasks.

21 The Schedule Acts as a to do list. Identify your baseline agreement. Show the cause and effect of changes. (Assuming you are using a CMP application.) Identify when resources are needed. Help you see a problem coming.

22 Starting the Project Get ready Get set Go

23 The Kick Off Meeting Step one of a Kick Off Meeting. Have one!

24 The Kick Off Meeting Learn from your mistakes. If I knew now when I didn t know then! At the end of your project hold a meeting and write down what went wrong. Make a list of the questions you wish you had asked at the start of the project. Turn that list into an agenda for the kicking off of the next project.

25 The Kick Off Meeting

26 The Kick Off Meeting 1. Basic Project Information. 2. Schedule Information. 3. Engineering and Detailing. 4. Buy Outs. 5. Shop Information. 6. Quality Information. 7. Billing and Contract Information. 8. Other items.

27 The Kick Off Meeting Basic Project Information. Do you have a contract or signed P.O.? What type of work (Industrial, commercial, etca)? What name for the project will you use? Who will be the project manager? the contract manager? What is in the proposal? Are you clear on your scope of work?

28 The Kick Off Meeting Basic Project Information. List of the customer contacts and their roles. Information about the size of the project (tons, man-hours, etca). Was there a schedule and who has it / who made it? What is the shipping address? Do we have to furnish a bond? (Type and paid by whom)

29 The Kick Off Meeting Basic Project Information. Will there be a customer kick off meeting? If so who will go and why? Is there an agenda for the meeting? (He who takes the notes controls the history.) What kind of reporting is required and when? Does the project have Liquidated or Actual Damages?

30 The Kick Off Meeting Schedule Information. Was there a schedule at bid and how does it fit into the shop load? Do you have the Issued For Construction drawings? Who will be responsible for the schedule? Has the project been sequenced? What are the delivery dates by sequence?

31 The Kick Off Meeting Engineering and Detailing. What is the budget for detailing? P.O. to a detailer? Is there a specific requirement for the type of application the project has to use to detail the steel? Has the detailer agreed to a submittal schedule? Is there an established project numbering system? Does the detailer have the pay categories?

32 The Kick Off Meeting Engineering and Detailing. Will engineering calculation be required? If so do they required a stamp, what state? (AISC Section 3.1.1) What is the bolt type? (Bearing, Slip Critical, TC, galvanized, DTIs, etca) What drawings does the detailer have and how did they get them? (Structural, Architectural, Mechanical, etca)

33 The Kick Off Meeting Buy Outs. Has the ABM been created? (Connection material?) Subcontract fabricators needed? Do they provide their own material? Submittals from them ~ drawings to them? List ALLthe buy outs not matter how minor. Are there any long lead time or odd buy outs?

34 The Kick Off Meeting Shop Information. Break down of hours. First step processing. Fit / weld hours. Paint / load. Paint / coating system and any special requirements. (Back charges from on site paint repair is expensive!) Paint dry time?

35 The Kick Off Meeting Shop Information. Are there parts on the project that exceed the cranes capacity? Who will be responsible for taking picture in the shop? Does the project require seal welding?

36 The Kick Off Meeting Quality Information. What are the quality submittals? Is there any NDE that is in excess of Chapter N? Will the customer have surveillance in the shop? Is coating inspection greater than company standards? Are there quality records that are in excess of Chapter N or the company standards?

37 The Kick Off Meeting Billing and Contract Information. Are there flow-down provisions from the owner? Do they need to go to the subs? What are the Lean Rights? They very from state to state. How will the sales tax be handled? What is the payment cycle? Can you get paid for raw material?

38 The Kick Off Meeting Other Items. Do we have adequate insurance? Are we proceeding under our proposal terms? Did the contractor / owner accept them? Has Sales turned over all the files developed during the bid process? What is the warranty period for your scope?

39 The Kick Off Meeting From the meeting assign action and follow up on the questions.

40 The Kick Off Meeting One Final Question: What was said to the customer that is not written down?

41 Project Information Have some form / way to pull all the project information into one place. Keep this form up to date as the project evolves.

42 Project Information

43 Project Information Part One of a Project Information Sheet.

44 Project Information Part Two of a Project Information Sheet.

45 Project Information Part Three of a Project Information Sheet.

46 Project Information Part Four of a Project Information Sheet.

47 Project Information Have a standard filling system both electronic and hard copy.

48 Working the project Use the schedule as a to do list.

49 Next on the Schedule ~ Material Procurement ABM complete. P.O.s in place. Identify the balance of the material from the approval drawings. Track the receipt of the material.

50 Next on the Schedule ~ Material Procurement Track the receipt of material against the start of fabrication on the schedule. If the material is late how will it affect the start of fabrication? Report the affect of the late material to production and the customer. (The sooner you see the problem the easer the solutions.)

51 Next on the Schedule ~ Engineering / Detailing Start the detailer with clear directions. Stay in close contact with the detailer. Use RFIs or some written form for questions. (AISC Section 4.6 ~ The RFI Process (AISC Section ~ RFI is a design change) When a question / problem does not seem to have an answer call a meeting.

52 Next on the Schedule ~ Engineering / Detailing Parts of the Engineering / Detailing Cycle tracked. Submittals Cycle. Approval Cycle. Release approved drawings to the shop for fabrication.

53 Next on the Schedule ~ Engineering / Detailing Good detailing is the backbone of a successful project. Give the process the attention it needs.

54 Next on the Schedule ~ The Fabrication Cycle Make sure the shop knows what is expected of them. Hold some kind of meeting with the shop management and provide them with end dates by sequence. Make them aware of the hours estimated for the work and have a means of showing them how they are doing against these hours.

55 Next on the Schedule ~ The Fabrication Cycle Once you are sure the shop knows the scope of work and the required end dates ask these two questions: 1. Do you understand the scope and the required end dates? 2. What haven't I given you so you can make these dates? Then lessen to the answer to # 2 and get them what they need.

56 Next on the Schedule ~ The Fabrication Cycle Process the drawing to the shop. Material receipt. Approved shop drawings. Fabrication Cycle. Paint / Load / Ship.

57 Final Comment about Schedules You can t do this with a spreadsheet!

58 Communicating with the Customer

59 Communicating with the Customer By phone ~ one on one or in a conference call. A call has a more personal touch but there is not a record unless you document the call. When you get them on the phone you know they have the information or were asked the question. When you are on a conference call ~ know who else is on the call. (He who takes the notes controls the history.)

60 Communicating with the Customer By phone ~ one on one or in a conference call. If you have bad news, call your customer then send the or letter.

61 Communicating with the Customer By . Don t abuse . If you are at about the 5 th time around with the ~ call or go see them. Write your s like a letter. Make them understandable. is forever. Question: Is an contractually binding? Don t put anything in an you would not want your mom to read or you don t want on the news.

62 Communicating with the Customer By letter. Send a letter when you need to make the communication very formal. Always answer a letter with a letter. Have the last word. Don t be too wordy. The idea of the letter is to make your point not show how smart you are. Use plain English. You don t need to exercise the dictionary. Use a serialized numbering system.

63 Communicating with the Customer By net meetings. Great way of sharing a view of a model, drawing, document, etca No record unless some kind of recording is made. Notes are made to document the meeting. (He who takes the notes controls the history.)

64 Communicating with the Customer In person. Sometimes you just have to be there. Make a site trip. It will be worth the money spent to travel. There is no record of the visit unless you take the notes. (He who takes the notes controls the history.)

65 Getting Paid

66 Getting Paid As much as you may love this business it is still a business and you need to be paid for what you do. Don t be afraid to ask for something you feel you have earned. Getting paid for change orders. You have to establish entitlement first. Then work on the value.

67 Final Thoughts If you keep the guy on site happy you will get paid. Be anonymous.

68 Reference Book

69 Time for Questions Question & Thanks

SAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT FORMAL INVITATION FOR BIDS ANNUAL CONTRACT FOR WELL MAINTENANCE SERVICES ADDENDUM NO.

SAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT FORMAL INVITATION FOR BIDS ANNUAL CONTRACT FOR WELL MAINTENANCE SERVICES ADDENDUM NO. SAN ANTONIO WATER SYSTEM PURCHASING DEPARTMENT Issued By: D. Anthony Rubin Date Issued: May 21, 2015 BID NO.: 15-7031 FORMAL INVITATION FOR BIDS ANNUAL CONTRACT FOR WELL MAINTENANCE SERVICES ADDENDUM NO.

More information

REQUEST FOR QUOTATION INVITATION

REQUEST FOR QUOTATION INVITATION REQUEST FOR QUOTATION INVITATION DATE: July 15, 2010 DPS: REQUIREMENT: SUBJECT: Patricia Farina DPS Contract Administrator Email: Patricia.Farina@cityofchicago.org Telephone: 312-744-7660 Silver Halide

More information

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

A. Action Submittals: Written and graphic information that requires Architect's responsive action. SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

A. Action Submittals: Written and graphic information that requires Engineer's responsive action.

A. Action Submittals: Written and graphic information that requires Engineer's responsive action. SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS DIVISION 1 - GENERAL REQUIREMENTS SECTION 01300 - SUBMITTALS PART 1 - GENERAL 1.1 STIPULATIONS A. The section "Special Requirements" forms a part of this section by this reference thereto and shall have

More information

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia BULLETIN NO. 6 TO THE PLANS AND SPECIFICATIONS FOR JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia EwingCole Architects.Engineers.Interior Designers.Planners

More information

Answer: Qualification statement should be provided with the bid.

Answer: Qualification statement should be provided with the bid. Little Diversified Architectural Consulting, Inc. 5815 Westpark Drive Charlotte, North Carolina 28217 Phone: 704-525-6350 Fax: 704-561-8700 Lincoln County Probation Renovation 208 N. Government Street

More information

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration SECTION 01 340 - SHOP DRAWINGS, PRODUCT DATA AND SAMPLES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals. SECTION 01300 PART 1 GENERAL 1.1 SECTION INCLUDES A. Description of Requirements B. Submittal Procedures C. Specific Submittal Requirements D. Action on Submittals E. Repetitive Review 1.2 DESCRIPTION

More information

East Central College

East Central College SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Section Meetings Section Material and Equipment. None Required

Section Meetings Section Material and Equipment. None Required January 2000 Page 1 of 8 PART 1 GENERAL 1.01 OTHER CONTRACT DOCUMENTS 1.02 DESCRIPTION OF WORK 1.03 RELATED WORK PART 2 PRODUCTS The General Conditions of the Contract, General Requirements and Supplemental

More information

SECTION STEEL LIGHTING STANDARDS. 1. Electrical conduit and fittings; Section

SECTION STEEL LIGHTING STANDARDS. 1. Electrical conduit and fittings; Section 02760-1 of 5 SECTION 02760 STEEL LIGHTING STANDARDS 02760.01 GENERAL A. Description Steel lighting standards shall include, but not necessarily be limited to, furnishing and installing steel lighting poles,

More information

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01334 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.01 SUMMARY A. Submit to the ENGINEER for review, such working drawings, shop drawings, test reports and data on materials and equipment

More information

Construction Phase Project Management and Documentation

Construction Phase Project Management and Documentation Construction Phase Project Management and Documentation Bill Mason CDM Smith Outline Design Bidding Construction Start-up & Closeout 2 DESIGN Design Preliminary Engineering Report Plans Specifications

More information

CHAPTER 10 MICHIGAN DESIGN MANUAL BRIDGE DESIGN (SI) SHOP DRAWING REVIEW TYPES OF SHOP DRAWINGS Structural Steel

CHAPTER 10 MICHIGAN DESIGN MANUAL BRIDGE DESIGN (SI) SHOP DRAWING REVIEW TYPES OF SHOP DRAWINGS Structural Steel CHAPTER 10 SHOP DRAWING REVIEW 10.01 TYPES OF SHOP DRAWINGS 10.01.01 Structural Steel 10.01.02 Prestressed Concrete 10.01.03 Bearings 10.01.04 Metal Stay - In - Place Forms () 10.01.05 Expansion Joints

More information

Proposal PROJECT MANUAL P R O P E R T Y M A N A G E M E N T F A L L O N C O U N T Y. Baker, MT P.O. Box 846

Proposal PROJECT MANUAL P R O P E R T Y M A N A G E M E N T F A L L O N C O U N T Y. Baker, MT P.O. Box 846 PROJECT MANUAL P R O P E R T Y M A N A G E M E N T F A L L O N C O U N T Y Proposal P.O. Box 846 Baker, MT 59313 P R E C A S T R E I N F O R C E D C O N C R E T E B O X C U L V E R T F O R W E S T M O

More information

SECTION STRUCTURAL STEEL. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION STRUCTURAL STEEL. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 051200 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

SECTION PROJECT MANAGEMENT AND COORDINATION

SECTION PROJECT MANAGEMENT AND COORDINATION SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

SUGGESTIONS FOR IMPROVING THE STRUCTURAL STEEL SHOP DRAWING PROCESS

SUGGESTIONS FOR IMPROVING THE STRUCTURAL STEEL SHOP DRAWING PROCESS SUGGESTIONS FOR IMPROVING THE STRUCTURAL STEEL SHOP DRAWING PROCESS SEAC/ RMSCA Steel Liaison Committee May 17, 2006 Disclaimer SEAC, RMSCA, nor its committees, writers, editors and individuals who have

More information

MINUTES OF MEETING. The following Questions were asked and answers were provided accordingly:

MINUTES OF MEETING. The following Questions were asked and answers were provided accordingly: MINUTES OF MEETING Meeting Date : July 15, 2014 Place : Greenwood Shop Main Conference Room Contract Title : Supply of Reworked T1 Trip Switch Brackets Proposal No. : T31BG14139 Present : TTC - A. Mckay

More information

CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT

CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT ADDENDUM NO. 1 TO REQUEST FOR PROPOSALS For EQUIPMENT FOR THE 2014 CITY OF MORRO BAY / CAYUCOS SANITARY DISTRICT WASTEWATER TREATMENT PLANT IMPROVEMENT PROJECT:

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 013300 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply

More information

SUBMITTAL PROCEDURES

SUBMITTAL PROCEDURES SUBMITTAL PROCEDURES PART 1 GENERAL The ASPA Project Engineer (APE) may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective

More information

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 01 33 00 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

B. Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form.

B. Bidders shall acknowledge receipt of this Addendum in writing on his Proposal Form. McKee and Associates Architecture and Interior Design Addendum No. THREE Date: 12.11.17 Project: A NEW BUILDING FOR THE GREATER LIMESTONE COUNTY CHAMBER OF COMMERCE ATHENS, ALABAMA A3.1 GENERAL PROJECT

More information

WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO Job No.:

WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO Job No.: WATER MAIN ALONG ENTRANCE TO ENCINO PS / HWY 281 TO ENCINO TANK Solicitation Number: CO-00111 Job No.: 16-7003 To Respondent of Record: ADDENDUM 2 July 5, 2017 This addendum, applicable to work referenced

More information

STATE OF TEXAS Agreement of Sale COUNTY OF TARRANT

STATE OF TEXAS Agreement of Sale COUNTY OF TARRANT STATE OF TEXAS Agreement of Sale COUNTY OF TARRANT This agreement is made and entered into by and between MORREL STUDIOS INC., ( Artist or Studios ), a New York corporation and the CITY OF ARLINGTON, TEXAS

More information

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES SECTION 01340 SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDED A. Contractor shall submit to the Architect/Engineer for review and exception, if any, such working

More information

INDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS:

INDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS: INDEX OF SPECIFICATIONS SECTION F SPECIAL CONDITIONS DIVISION 1 - GENERAL REQUIREMENTS: 013300 SUBMITTAL PROCEDURES 018116 CONSTRUCTION WASTE MANAGEMENT DIVISION 2 EXISTING CONDITIONS: 023000 EARTHWORK

More information

SQS Supplement A. Bridge Fabricators and Minor Structural. Component Manufacturers. MnDOT Supplier Qualification Standard

SQS Supplement A. Bridge Fabricators and Minor Structural. Component Manufacturers. MnDOT Supplier Qualification Standard SQS Supplement A MnDOT Supplier Qualification Standard Bridge Fabricators and Minor Structural Component Manufacturers Standard supports the Department s Approved Supplier Program for Structural Metals

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01330 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification

More information

Fabrication and Supply of Cable Tray. CTI Agartala, Aligarh, Gorakhpur, Muzaffarpur, Patna

Fabrication and Supply of Cable Tray. CTI Agartala, Aligarh, Gorakhpur, Muzaffarpur, Patna Fabrication and Supply of Cable Tray at CTI Agartala, Aligarh, Gorakhpur, Muzaffarpur, Patna BROADCAST ENGINEERING CONSULTANTS INDIALIMITED 14-B, I. P. Estate, Ring Road, New Delhi CONTENTS Sr. No Title

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

BAE Systems Combat Vehicles Supplier Quality Assurance AS9102 Requirement

BAE Systems Combat Vehicles Supplier Quality Assurance AS9102 Requirement 1 BAE Systems Combat Vehicles Supplier Quality Assurance AS9102 Requirement February 27, 2019 2 Scope The intent of this document is to provide an understanding, and clarification as to what BAE Systems

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01330 SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide submittals in accordance with the General Conditions as modified by the Supplementary Conditions,

More information

SPECIAL PROVISION Description of Project, Scope of Contract and Sequence of Work

SPECIAL PROVISION Description of Project, Scope of Contract and Sequence of Work 2004 Specifications CSJ 0110-04-166 SPECIAL PROVISION 000--363 Description of Project, Scope of Contract and Sequence of Work 1. General. The work to be performed on this project consists of furnishing,

More information

Anticipated schedule, Page 2. Change the Contract Term from 635 Days to be 1,127 Days.

Anticipated schedule, Page 2. Change the Contract Term from 635 Days to be 1,127 Days. This addendum is hereby made part of the Request for Bid for the above-named project and shall be taken into consideration by all firms preparing a submittal on this project. Acknowledge receipt of this

More information

This specification describes the general requirements for Engineering Services provided to Vale.

This specification describes the general requirements for Engineering Services provided to Vale. 1/9 1.0 PURPOSE This specification describes the general requirements for Engineering Services provided to Vale. 2.0 GENERAL For the purposes of this document, the Engineering Consultant shall be referred

More information

Merrick Pet Care New Distribution Center Hereford, Texas

Merrick Pet Care New Distribution Center Hereford, Texas Merrick Pet Care New Distribution Center Hereford, Texas DATE: March 16, 2015 ARCHITECTURAL/ELECTRICAL ADDENDUM #6 FROM: TO: PROJECT: Lavin Associates, Architects Plan Holders of Record Merrick Pet Care,

More information

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

39 Years of Learning the Hard Way. Mark A Etrheim, Mastercraft Homes Inc

39 Years of Learning the Hard Way. Mark A Etrheim, Mastercraft Homes Inc 39 Years of Learning the Hard Way Mark A Etrheim, Mastercraft Homes Inc Marketing- You need to tell the world how good you are! Clear and consistent message. What makes you unique? Sales- You must be able

More information

SECTION STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 05 12 00 - STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 3300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 General

More information

Artist Application to Consign in the Artist s Den Gallery

Artist Application to Consign in the Artist s Den Gallery Please complete the following application: Artist Application to Consign in the Artist s Den Gallery Artist Name: Address: Contact Phone: Email: Website (if applicable): Please provide a brief artist statement/biography.

More information

Your Guide To Renting or Owning a Mobile Home in Alaska

Your Guide To Renting or Owning a Mobile Home in Alaska Your Guide To Renting or Owning a Mobile Home in Alaska Provided as a Service by Alaska Legal Services Corporation Introduction Congratulations on your decision to rent or buy a mobile home! Having a place

More information

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following: SECTION 01 31 00 PROJECT MANAGEMENT AND COORDINATION PART 1 GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division

More information

QuickBooks Services Offered by Jennifer A. Thieme

QuickBooks Services Offered by Jennifer A. Thieme QuickBooks Services Offered by Jennifer A. Thieme (760) 685-6233 qbhelper@jenniferthieme.com I know there are MANY people you could have contacted, so I appreciate your consideration. Before we discuss

More information

Guidelines to Consign in Artist s Den Gallery

Guidelines to Consign in Artist s Den Gallery Guidelines to Consign in Artist s Den Gallery 1. The Mayflower Arts Center is a family friendly gallery and studio. Any/all artists and artworks are subject to Mayflower Arts Center s owner selection and

More information

City Council Report 915 I Street, 1 st Floor Sacramento, CA

City Council Report 915 I Street, 1 st Floor Sacramento, CA City Council Report 915 I Street, 1 st Floor Sacramento, CA 95814 www.cityofsacramento.org File ID: 2018-00196 March 20, 2018 Consent Item 14 Title: Contract: Fort Natomas Shade Structure Location: District

More information

[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards]

[Note to PSC: Include these sections in the Contract Documents, even though some are not included in the U of I Facilities Standards] SECTION 01 78 23 - OPERATION AND MAINTENANCE DATA PART I - GENERAL 1.1 SUMMARY A. Operation and Maintenance Data shall be submitted in appropriately-sized binders, with dividers, and organized by each

More information

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 013300 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

City of Boynton Beach Art in Public Places Artwork by Artist Name Final Artwork Information

City of Boynton Beach Art in Public Places Artwork by Artist Name Final Artwork Information Art in Public Places Artwork by Artist Name Final Artwork Information Completed by Owner Building Name Building Permit Number Public Art Name Building Street Address Building Owner s Name Owner s Contact

More information

c» BALANCE C:» Financially Empowering You Money Management Podcast [Music plays] Katie:

c» BALANCE C:» Financially Empowering You Money Management Podcast [Music plays] Katie: Money Management Podcast [Music plays] Katie: You re listening to money management. Hi, I m Katie, your host for today s podcast. When it comes to planning for your future, there s nothing more crucial

More information

TABLE OF CONTENTS. 1.0 Scope. 2.0 References. 3.0 Definitions. 4.0 Submission and Design Requirements. 5.0 Materials 5.1 General 5.

TABLE OF CONTENTS. 1.0 Scope. 2.0 References. 3.0 Definitions. 4.0 Submission and Design Requirements. 5.0 Materials 5.1 General 5. 1.0 Scope 2.0 References 3.0 Definitions 4.0 Submission and Design Requirements 5.0 Materials 5.1 General 5.2 Marking 6.0 Equipment 7.0 Production 7.1 Steel Octagonal Poles 7.2 Base Plate 7.3 Top Cap 7.4

More information

COMMERCIAL / INDUSTRIAL APPLICATION FOR PLAN EXAMINATION AND BUILDING PERMIT

COMMERCIAL / INDUSTRIAL APPLICATION FOR PLAN EXAMINATION AND BUILDING PERMIT Community Development 1050 W Romeo Rd, Romeoville, IL 60446-1530 (815) 886-7200 Fax #: (815) 886-2724 Email: buildinginspections@romeoville.org COMMERCIAL / INDUSTRIAL APPLICATION FOR PLAN EXAMINATION

More information

Cielito Lindo de Tubac Home Owners Association PAINTING POLICIES AND PROCEDURES

Cielito Lindo de Tubac Home Owners Association PAINTING POLICIES AND PROCEDURES Cielito Lindo de Tubac Home Owners Association PAINTING POLICIES AND PROCEDURES The CC&Rs for Cielito Lindo de Tubac HOA address exterior repainting only briefly under Article 3.1(A), (B) and (E). As this

More information

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES

DIVISION 1 GENERAL REQUIREMENTS SECTION SUBMITTAL PROCEDURES DIVISION 1 GENERAL REQUIREMENTS SECTION 01 33 00 PART 1 - GENERAL 1.1 SUMMARY A. This section includes administrative and procedural requirements for submittals required for performance of the work, including

More information

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.1 DESCRIPTION A. This specification defines the general requirements and procedures for submittals. A submittal is information

More information

The enclosed information is provided for consideration in the preparation of your response to the abovereferenced

The enclosed information is provided for consideration in the preparation of your response to the abovereferenced To: Prospective Vendor(s) Date: October 25, 2016 Subject: Solicitation Number: DHSMV-RFI-007-16 Cameras and Related Accessories Addendum No. 1 The enclosed information is provided for consideration in

More information

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES SECTION 01340 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Shop drawings, manufacturer's catalog cuts, product data, samples, and attached Shop Drawing/ Catalog

More information

Red Flags When Hiring a 5Pavement Contractor

Red Flags When Hiring a 5Pavement Contractor Red Flags When Hiring a 5Pavement Contractor Getting ready to replace your old driveway with paving stones? Looking to upgrade your pool deck or walkways? Adding paving stones is a great way to beautify

More information

SECTION BULLET- RESISTANT DOORS

SECTION BULLET- RESISTANT DOORS 1 SECTION 08 3950 BULLET- RESISTANT DOORS PART 1- GENERAL 1.01 SUMMARY A. This Section Includes: 1. Bullet- resistant steel door and frame systems. 2. Door hardware for bullet- resistant steel door and

More information

Elite Real Estate Flipping Advice: 7 Tips to Finding the Best Contractors for Rehabs

Elite Real Estate Flipping Advice: 7 Tips to Finding the Best Contractors for Rehabs Elite Real Estate Flipping Advice: 7 Tips to Finding the Best Contractors for Rehabs Out of all of the tasks associated with the business of real estate flipping, few are as essential to the success of

More information

Line 6 L I M I T E D R E F URBISH E D (B-ST O C K) W A RR ANT Y

Line 6 L I M I T E D R E F URBISH E D (B-ST O C K) W A RR ANT Y Line 6 L I M I T E D W A RR A N T Y PO L I C Y PLEASE READ THIS DOCUMENT CAREFULLY. IT CONTAINS IMPORTANT INFORMATION ABOUT YOUR RIGHTS AND OBLIGATIONS, AS WELL AS LIMITATIONS AND EXCLUSIONS THAT MAY APPLY

More information

Seven Things to Know Before Hiring a General Contractor

Seven Things to Know Before Hiring a General Contractor Seven Things to Know Before Hiring a General Contractor Seven Things to Know Before Hiring a General Contractor Copyright All Rights Reserved 1 Introduction The kitchen is outdated and looks like something

More information

Facility Services Subgroup Preface for Divisions 21` through 28

Facility Services Subgroup Preface for Divisions 21` through 28 Facility Services Subgroup Preface for Divisions 21` through 28 1.1 EXECUTIVE SUMMARY A. This document provides standards for the Consultants and Contractors producing mechanical and electrical design

More information

Pre-Filter. Brushless/ Sparkless Blower. HEPA Filter. Fluorescent Light

Pre-Filter. Brushless/ Sparkless Blower. HEPA Filter. Fluorescent Light A Pre-Filter Brushless/ Sparkless Blower HEPA Filter Fluorescent Light B TO: Nayan Patel Central Drugs Compounding Pharmacy 520 W. La Habra Blvd. La Habra, CA 90631 QUOTATION DATE: QUOTATION NO: PHONE

More information

SECTION WOOD AND PLASTIC DOORS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION WOOD AND PLASTIC DOORS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 081416 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

SECTION SUBMITTAL PROCEDURES

SECTION SUBMITTAL PROCEDURES SECTION 01 33 00 SUBMITTAL PROCEDURES PART 1 GENERAL 1.1 SUMMARY A. Section Includes. 1. Submittal procedures. 2. Product data. 3. Shop drawings. 4. Samples. 5. Design data. 6. Test reports. 7. Certificates.

More information

Brad Luke. Director Peddle Thorp Auckland

Brad Luke. Director Peddle Thorp Auckland Brad Luke Director Peddle Thorp Auckland Site Observation and Practical Completion Preparation PEDDLE THORP Introduction Architects Agreement for Services. Observation Work Plans. Auckland Council Quality

More information

-and- (the Artist ) maquette means the drawing or model, prepared by the Artist, of the proposed Art Work;

-and- (the Artist ) maquette means the drawing or model, prepared by the Artist, of the proposed Art Work; THIS AGREEMENT made in triplicate this th day of, 200 BETWEEN: CITY OF OTTAWA (the City -and- (the Artist WHEREAS the Council of the former City of Ottawa, an old municipality as defined in the City of

More information

Pledge of Allegiance Staff Introduction Bid Package Submittal Sign-In Sheet and Project Scope Q&A Process Anticipated Date Sequence General Project

Pledge of Allegiance Staff Introduction Bid Package Submittal Sign-In Sheet and Project Scope Q&A Process Anticipated Date Sequence General Project Pledge of Allegiance Staff Introduction Bid Package Submittal Sign-In Sheet and Project Scope Q&A Process Anticipated Date Sequence General Project Overview Procedures, Protocol, and General Contract Requirements

More information

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS SECTION 01300 SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections,

More information

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS

KINGS COUNTY JAIL EXPANSION PHASE III COUNTY OF KINGS SECTION 01 3100 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

My current net worth By <insert day> <insert month> of <insert year> I will have increased my net worth by $ I will do this by:

My current net worth By <insert day> <insert month> of <insert year> I will have increased my net worth by $ I will do this by: Worksheet 1. Taking Control of your financial life My current net worth By of I will have increased my net worth by $ I will do this by: 1. 2. 3. My 90 Day Wealth

More information

AIA Continuing Education

AIA Continuing Education AIA Continuing Education Hall & Company is a Registered Provider with the American Institute of Architects Continuing Education Systems. Credit earned based on the completion of this program will be reported

More information

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS

SECTION ADMINISTRATIVE REQUIREMENTS SECTION ADMINISTRATIVE REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Coordination. B. Preconstruction meeting. C. Progress meetings. D. Preinstallation conferences. E. Requests for information (RFI). F. Coordination drawings.

More information

SECTION SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum

SECTION SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum SECTION 013201 - SCHEDULE OF VALUES PART 1 - GENERAL 1.1 THE REQUIREMENT A. This Section defines the process whereby the Schedule of Values (Lump Sum Pay Unit price breakdown) shall be developed and ultimately

More information

Section COUPLINGS AND COUPLING ADAPTERS. This Section covers couplings and coupling adapters for ductile iron and steel pipe.

Section COUPLINGS AND COUPLING ADAPTERS. This Section covers couplings and coupling adapters for ductile iron and steel pipe. PART 1 GENERAL 1.01 SUMMARY Section 15155 This Section covers couplings and coupling adapters for ductile iron and steel pipe. 1.02 MEASUREMENT AND PAYMENT A. No separate payment for Work performed under

More information

Recommended Practice PS-24 Tracking the Procurement Process (TCM Framework Reference 7.7)

Recommended Practice PS-24 Tracking the Procurement Process (TCM Framework Reference 7.7) Recommended Practice PS-24 Tracking the Procurement Process (TCM Framework Reference 7.7) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Final Revision 2 AACE International Recommended Practice PS-24 Tracking

More information

A REAL ESTATE INVESTOR S GUIDE TO MANAGING CONTRACTORS FROM START TO FINISH. LendingOne YOUR LOGO

A REAL ESTATE INVESTOR S GUIDE TO MANAGING CONTRACTORS FROM START TO FINISH. LendingOne YOUR LOGO A REAL ESTATE INVESTOR S GUIDE TO MANAGING CONTRACTORS FROM START TO FINISH LendingOne YOUR LOGO Contents Introduction.3 Stage 1: Research and Evaluation.4 Stage 2: Bidding Time..6 Stage 3: Contract for

More information

ADDENDUM NO. 2 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030

ADDENDUM NO. 2 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030 ADDENDUM NO. 2 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO. 2018-008-COM.00030 To: Prospective Bidders of Record Date: December 17, 2018 The following changes, additions, revisions, and/or deletions

More information

Pay-As-You-Go Guidance

Pay-As-You-Go Guidance Pay-As-You-Go Guidance Contents: 1. What is a Pay-As-You-Go meter? 1. What is a Pay-As-You-Go meter? 2. The benefits of having a Pay-As-You-Go meter 3. Reading your meter A Pay-As-You-Go meter (also known

More information

Working Drawing Manual

Working Drawing Manual Working Drawing Manual 2012 Table of Contents Section 1 Working Drawing Types... 1 1.1 General... 1 Section 2 Processing Steps... 1 2.1 Project Manager... 1 2.2 Engineering Document Unit... 2 2.3 Contractor...

More information

Myth Bookkeeper SAMPLE MICHAEL E. GERBER. Why Most Bookkeeping Practices Don t Work and What to Do About It CHAPTER

Myth Bookkeeper SAMPLE MICHAEL E. GERBER. Why Most Bookkeeping Practices Don t Work and What to Do About It CHAPTER From the Best-Selling Author of The E-Myth SAMPLE CHAPTER Myth Bookkeeper Why Most Bookkeeping Practices Don t Work and What to Do About It MICHAEL E. GERBER C h a p t e r 6 The Bookkeeping Business Journey

More information

Mr. Ditmore s Yearbook Classroom Procedures & Syllabus

Mr. Ditmore s Yearbook Classroom Procedures & Syllabus Mr. Ditmore s Yearbook Classroom Procedures & Syllabus Course Description Welcome to Yearbook! Being in Yearbook at Water Valley is a very special opportunity to grow as a student that no other class allows

More information

C. Samples for Initial Selection: Manufacturer's color charts showing the full range of colors available.

C. Samples for Initial Selection: Manufacturer's color charts showing the full range of colors available. SECTION 105113 - METAL LOCKERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

CONVEYANCE PIPELINE AND PUMP STATION

CONVEYANCE PIPELINE AND PUMP STATION SCOPE OF WORK CONVEYANCE PIPELINE AND PUMP STATION The purpose of this scope of work is to provide engineering services to revise and complete the design of the RUWAP pipeline and 5th Avenue Pump Station

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS PROJECT: Painting of the Signal Poles, Mast Arms and Decorative Bases OWNER: City of Goose Creek, Department of Public Works RECEIPT OF PROPOSALS: Separate sealed proposals for the

More information

2016 Specification Treads, Base, Stringers and other Amenities Wausau Tile Precast Epoxy Terrazzo

2016 Specification Treads, Base, Stringers and other Amenities Wausau Tile Precast Epoxy Terrazzo 2016 Specification Treads, Base, Stringers and other Amenities 09400 Wausau Tile Precast Epoxy Terrazzo PART 1 - GENERAL 1.1 SUMMARY A. Perform all work required to complete, as indicated by the Contract

More information

10930 W. Sam Houston Parkway N., Suite 900

10930 W. Sam Houston Parkway N., Suite 900 ADDENDUM NO. 1 10930 W Sam Houston Pkwy. North Suite 900 Houston, Texas 77064 281.664.1900 281.664.1912 (f) www.salasobrien.com March 21, 2018 Project: Prepared by: Taylor Career Center Welding Labs Beaumont

More information

Architecturally Exposed Structural Steelwork (AESS) Sample Specification (for Engineers)

Architecturally Exposed Structural Steelwork (AESS) Sample Specification (for Engineers) Architecturally Exposed Structural Steelwork (AESS) Sample Specification (for Engineers) Sample Specification (for Engineers) Architecturally Exposed Structural Steel (AESS) PART 1 GENERAL 1.1. RELATED

More information

Chapter 1 General Design Information

Chapter 1 General Design Information Chapter 1 General Information Introduction The primary aim in both designing and checking is to produce a structure that will safely carry the anticipated loads. The design team, consisting of the designers,

More information

UFGS (November 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS

UFGS (November 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCESA / NASA UFGS-27 05 28.36 40 (August 2011) ----------------------------------- Preparing Activity: NASA Superseding UFGS-27 05 28.36 40 (November 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

SECTION ADMINISTRATIVE REQUIREMENTS

SECTION ADMINISTRATIVE REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Electronic document submittal service. B. Preconstruction meeting. C. Progress meetings. D. Construction progress schedule. E. Coordination drawings. SECTION 013000

More information

SECTION 025 INDUSTRIAL PAINTING

SECTION 025 INDUSTRIAL PAINTING SECTION 025 INDUSTRIL PINTING Industrial painting, including all necessary preparation and application, except as modified in this Section, shall conform to the recommendations of the manufacturer of the

More information

SPECIAL SPECIFICATION 6574 Low Power Wireless Modem

SPECIAL SPECIFICATION 6574 Low Power Wireless Modem 2004 Specifications CSJ 1068-04-126, etc. SPECIAL SPECIFICATION 6574 Low Power Wireless Modem 1. Description. This work shall consist of furnishing and supplying a Low Power Wireless Modem at the locations

More information

SECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents.

SECTION A. RFI: Request from Contractor seeking interpretation, information, or clarification of the Contract Documents. SECTION 01 3000 PART 1 GENERAL 1.1 SECTION INCLUDES A. Electronic document submittal service. B. Preconstruction meeting. C. Submittals for review, information, and project closeout. D. Submittal procedures.

More information

SECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS

SECTION CLOSEOUT SUBMITTALS SECTION CLOSEOUT SUBMITTALS PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Record Documents. B. Operation and Maintenance Manuals. C. Warranties and bonds. 1.02 RELATED REQUIREMENTS SECTION 01 78 00 A. Section 01 30 00 - Administrative