Commercial Fishing and Offshore Wind in Maine For more information: Josh Plourde (207) March 16, 2018

Similar documents
Western Isles HVDC Link Consultation

ENVIRONMENTAL ASSESSMENT (EA) PROCESS

U.S. Army Corps of Engineers Regulatory Program

RENEWABLE ENERGY SOLUTIONS. oceaneering.com

UNDERWATER NOISE, MARINE SPECIES PROTECTION, AND IMPLICATIONS FOR MARINE SURVEYS. Presenter: Denise Toombs Company: ERM

Research Activities Plan. Appendix K Magnetic Fields from Submarine Cables

Coastal Virginia Offshore Wind partnership with Orsted. February 2018 Update

TOPICS TO BE COVERED. 1) Planning Areas 2) Scoping 3) Public Meetings 4) DRAFT Release 5) Secondary Scoping 6) Final Designation

Environmental and non-technical impacts of lean principles applied to offshore wind farms

Offshore Cable Installation. November 2010 John Davies Global Marine Systems Limited

Empire Wind Offshore Wind Farm OCS-A 0512

Falmouth Bay Short Term Test Site for Marine Energy Converters

SUBMARINE CABLES, RESOURCE USE, AND ENVIRONMENTAL PROTECTION. Ambassador Satya Nandan

Testimony by. Before the. Boston, Mass. July 24, 2002

Emerging Subsea Networks

Don Shall. 3 Dave Wilson

Goal: Effective Decision Making

Offshore Drilling in the Atlantic January 2018

the future of electricity

Offshore Drilling Rigs

Southern Shrimp Alliance, Inc P.O. Box 1577 Tarpon Springs, FL Ph Fx

Marine Scotland Science: Oil and gas survey work. Peter Hayes Offshore Energy Environmental Advice Group

BAY OF SKAILL SUBSTATION - ORKNEY CAITHNESS CONNECTION

Written Comment: Sydney Basin and Orpheus Graben Areas

Introduction to the. Responsible Offshore Development Alliance

Deepwater Archaeology and Cultural Resource Management: Working with

Wildlife distributions and habitat use on the mid-atlantic Outer Continental Shelf

Engineering Solutions

NATIONAL POLICY ON OILED BIRDS AND OILED SPECIES AT RISK

The future of offshore wind in the US

Compensatory Mitigation Monitoring Report Aquatic Habitat Improvement City of Montrose Whitewater Park, Montrose County, Colorado March 6, 2014

Wind Turbine Decommissioning in the UK Offshore Zone

Non-Technical Summary of the SEA Report Draft on the Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the North Sea 2016/2017

DUGONGS IN ABU DHABI

Shetland HVDC Link Project. Consultation, August 2016

Marine Renewable-energy Application

PROPOSALS FOR AQUIND INTERCONNECTOR

Draft Potential Conditions

Old House Channel Bathymetric and Side Scan Survey

PROPOSALS FOR AQUIND INTERCONNECTOR

MARINE STUDIES (FISHERIES RESOURCE MANAGEMENT) MASTER S DEGREE (ONLINE)

Final Prospectus and Terms of Reference for an Independent Review of the New England Fishery Management Council 2/27/18

Offshore Pipelines. Capability & Experience

NAPA MARSHES RESTORATION Coastal Ecosystem Restoration Through Collaborative Partnerships

Spring-Summer Issue 66. The Great Egg Harbor Watershed Association s website has a new look. Check us out.

Technical Memorandum ECO-7

NEBA new Good Practice Guide Rob Holland, Technical Lead, OSRL. Copyright Oil Spill Response Limited.

Sea Duck Joint Venture Annual Project Summary for Endorsed Projects FY 2010 (October 1, 2009 to Sept 30, 2010)

Gulf of St Lawrence: Industry Challenges and Response

Licensed to kill: can we use quota markets to conserve seabirds? Sean Pascoe, Josh Donlan, Mary Turnipseed And others..

Wendy Webber Regional Director Northeast Regional Office U.S. Fish and Wildlife Service 300 Westgate Center Drive Hadley, MA

Offshore Wind Floating Turbines

from ocean to cloud DUAL-CONDUCTOR CAPABILITIES IN WET PLANT DESIGN QUALIFICATION SEATRIALS

Annex C. DEA Pre-Application Meeting Records

Subsea infrastructure in MRE ICOE November 6, By Don Bryan, BSc, MBA General Manager Pacific Northwest Operations

Object Detection Using the HydroPACT 440 System


Dutch offshore wind energy policy an overview. Mark Stuurman Policy advisor

Subsea UK Neil Gordon Chief Executive Officer Championing the UK Subsea Sector Across the World

Using Norwegian competence from oil and gas subsea operations towards the development of ocean mining operations

In cooperation to Deep Sea Technology

Cat Island Chain Restoration Project Brown County Port & Resource Recovery Department

PORT OF POOLE DEVELOPING FOR THE FUTURE

The first Floating Wind Turbine in France (SEM-REV) I. Le Crom, ECN, EERA Deepwind 19/01/2018

Emerging Subsea Networks

This document is available on the Ministry for the Environment s website:

March 22, Ms. Diana Heyder, NEPA Division U.S. Department of Energy Golden Field Office Denver West Parkway Golden, CO 80401

ANY OTHER BUSINESS. Advancing international collaboration for quiet ship design and technologies to protect the marine environment

SET-PLAN IMPLEMENTATION

Canadian Ocean Science Priorities under the Galway Statement on Atlantic Ocean Cooperation

Aedán Smith Head of Planning, RSPB Scotland

SYSTEM 5900 SIDE SCAN SONAR

The Growing Offshore Wind Market: Massachusetts Example National Conference of State Legislatures

Sea Duck Joint Venture Annual Project Summary for Endorsed Projects FY08 (October 1, 2007 to September 30, 2008)

PRELIMINARIES. Generators and loads are connected together through transmission lines transporting electric power from one place to another.

Beaufort Sea Coastal Marine Program CCGS Nahidik Program

Oceans of Information

Kinsale Area Gas Fields Decommissioning Project Information Leaflet

The Marine Plan for the Isle of Man. Dr Peter McEvoy Marine Spatial Planning Project Officer Isle of Man Government

The Active Heave Compensation (AHC) system makes the raising, lowering and handling of loads on floating vessels much safer and easier.

Ecosse Subsea Systems. Subsea Springboard 2017 David Hunt

Memorandum. Application for Amendment to DNR Land Use Permit # LAS29209

Subsea Tooling Services UK Ltd Engineered Subsea Solutions

Opportunities for Offshore Wind Development in the U.S.

Enabling Array Cable Cost Reduction

Offshore Construction Management Services. Capability & Experience

RENEWABLE ENERGY TECHNOLOGY ACCELERATOR (RETA) PROJECT

UTOFIA System 1 test on a Unmanned Surface Vehicle

ROCHESTER CABLES ENGINEERED CABLE SOLUTIONS FOR HARSH ENVIRONMENTS

The USFWS is here to help you! An overview of the ESA process

Offshore Wind Risks - Issues and Mitigations

to BP Canada Energy Group ULC c/o Anita Perry, Regional Manager, Atlantic Canada

Sanctuary Background. Sanctuar y Background

WHITE ROSE OILFIELD COMPREHENSIVE STUDY REPORT SUBMITTED BY:

The potential for windpower in the Baltic Sea

Baltic Marine Environment Protection Commission

Annex I Content, format and structure of annual reports for exploration under contract for polymetallic nodules

Appendix D.21 Tseycum First Nation

Esso offshore projects

Record of the 12 th Scientific Working Group of the Preparatory Conference of the North Pacific Fisheries Commission Tokyo, Japan March 2014

Transcription:

Commercial Fishing and Offshore Wind in Maine For more information: Josh Plourde (207) 907-0069 jp@maine.edu March 16, 2018 Future Offshore Wind Development in Maine The University of Maine will not license its floating offshore wind turbine technology to any developer, or support any future offshore wind development in the Gulf of Maine, that does not constructively engage with the fishing community. Any future wind farms will be located in federal waters and under the jurisdiction of the Bureau of Ocean Energy Management (BOEM). While there is activity underway to develop offshore wind in southern New England and along the east coast, these states are at least 5-10 years ahead of Maine in terms of opening areas in federal waters for offshore wind development. BOEM has a prescribed process to determine potential wind energy areas, and requires significant public input over a 5-10 year period before an area can be bid on by a developer. Cable Installation and Fisheries Dr. Bob Steneck 1 of the UMaine Darling Marine Center has said: o No long-term impacts to the ecosystem are expected from cable installation. Short-term adverse effects of the disturbance itself, if any, are likely to be very local and temporary. o Focusing the installation schedule in winter months will reduce impacts because many of the shallow water dwelling lobsters will have moved to deep water. Nevertheless, some will be in the cable area. o It is highly unlikely that this project will impact scallops, oysters, or local lobster landings; many factors such as water temperatures play a much bigger role. We checked with local oyster growers and they know of no oysters being overwintered in the Damariscotta River south of the Fort Island constriction. o The impacts of scallop dragging are likely more than this operation. Dredges pose about the same risk to newly settled lobsters living in burrows as would the cable laying operation, however, the area dredged is much greater. 2 3 4 Impacts to American lobsters from cable burial would primarily be through the physical disturbance of habitat by plowing and the temporary increased suspended sediment and turbidity from construction methods. However, we expect this impact, if measurable, would be very temporary 5. Dragging for scallops and other species currently creates significant sediment disturbance, directly removes biogenic (sponges, hydrozoans, etc.) and sedimentary (sand waves, depressions) structures, and leads to reduction of habitat complexity which may lead to increased predation on juveniles of harvested species 6 such as lobster. UMaine has been a long-time significant partner to the lobster industry in Maine through the Lobster Institute, Darling Marine Center, etc., and will continue to do so. 1

Fishing has not been impacted by offshore wind projects such as Block Island in Rhode Island, and in fact, underwater videos from the Block Island project show a thriving ecosystem in a previously dead area 7. Independent and detailed studies have concluded that electrical cables do not pose a threat to marine life 8 Cable Installation The cable will be installed using a hydraulic jet plow, an industry standard. We will prioritize cable burying at 6 ft., although this level of burial will not be possible 100% of the way. Our research shows that the cable can be buried the majority of the way between the Test Site and the two potential landing locations. Where the cable can t be buried, we plan to mattress the cable with concrete or run the cable through protective conduit which would be resistant to snagging on nets. The cable and its protective conduit is smaller than rocks/boulders seen on ledges. This is standard practice for subsea cables throughout the U.S. and across the globe according to LS Cable, an international cable installer. This same cable installer and installation method was used to install a cable between Rockport and North Haven Island. The 9.9-mile cable is buried 6 deep in the mud of Penobscot Bay, 9 the same depth is what MAV will be doing where possible with its cable. We are aware of ledges/ridges running between the Test Site and East Boothbay. A subsea geophysical survey will determine its maximum burial ability on this proposed route. The cable will be installed using a hydraulic jet plow. This will temporarily result in an approximately 13 wide trough, and the cable will be installed simultaneously by the plow. The jet plow operates at a rate of about 100 meters/hour. Cable length from the Test Site to East Boothbay would be approximately 21.7 miles; from the Test Site to St. George would be about 22.7 miles. Bottom-disturbing activities associated with installation of the subsea cable could temporarily increase suspended sediments and turbidity in nearby habitats. The extent of these impacts will depend on local sediment type, current circulation patterns, and burial techniques used. Construction activities will be relatively short-term and localized with water quality conditions likely recovering completely without mitigation once construction is complete. Although individuals or populations may be affected by noise and activity from laying cable, these activities are temporary and will not have long-term impacts. 5 A recent study by Applied Sciences Associates, Inc., who studied the suspended sediment resulting from the installation of a proposed 77-mile, 1,000 MW cable (approximately 80 times the power capacity of the proposed MAV cable) in New York suggest that sediment returns to ambient conditions in as little as 24 hours after the jetting occurs 10. 2

Cable Overview Typical jet plow and simultaneous cable installation. The cable is roughly 5.5 in diameter and will run from the Monhegan Island Test Site to the mainland connection either in East Boothbay or St. George. The cable has three-phase insulated conductors with an electrical shield and is mechanically protected by armor. The cable has multiple layers of electrical insulation and mechanical protection, including a double-layer of galvanized steel armor. The medium voltage cable is encased in conductive sheathing (armoring), which inhibits electromagnetic fields from entering the surrounding environment. The cable is sized for the two turbines; additional turbines cannot be added to the cable. The alternating current cable transmits power at 34.5 kv. Example of a subsea cable. Fiber optic strands can be seen in the center of the cable. The cable has a 5.5" outer diameter. There currently are many cables along the coast of Maine, and countless cables along the East coast. Electrical cables do not pose a threat to marine life, and this is supported by significant evidence in the U.S. and abroad. 8 The Project is obligated to submit a decommissioning plan as part of its permit application to the Maine Department of Environmental Protection. This decommissioning plan will be widely circulated and made available for public comment as part of the permit application process 11. 3

This figure shows seabed depth and gradient between the Monhegan Test Site and East Boothbay based on available data. A subsea cable survey will need to be conducted to fully understand the ocean floor between these two locations. 4

This figure shows seabed depth and gradient between the Monhegan Test Site and St. George based on available data. A subsea cable survey will need to be conducted to fully understand the ocean floor between these two locations. 5

Maine Aqua Ventus Overview There is a major international competition to develop floating wind hull technologies. UMaine s technology has successfully competed against 70 other projects since 2012. This project, hosted by Maine, is funded by the U.S. Department of Energy whose goal is to demonstrate that this cost-effectively technology can be used anywhere in the U.S. New England Aqua Ventus I is the only current project supported by the US government, making this project of critical national importance. So far, Aqua Ventus has been awarded $10.7M from the DOE to advance its designs and permitting efforts, and a milestone contract for and additional $40M. New England Aqua Ventus I is a 12 MW floating offshore wind research and development project. Project participants include Cianbro Corporation, the University of Maine, and Naval Energies. The floating offshore wind turbine platforms and column segments will be fabricated and assembled at an existing industrial facility adjacent to the Penobscot River in Brewer. Turbine components will be assembled on the hull in Searsport and subsequently towed to the UMaine Deepwater Offshore Wind Test Site at Monhegan Island. Electricity will be sold to Central Maine Power to help finance the research project; electricity will go to the nearest load point. References 1 Dr. Robert Steneck, University of Maine Darling Marine Center. 207.581.5315 https://umaine.edu/marine/faculty/robert-steneck/ 2 Caddy, J. F. (1973). Underwater observations on tracks of dredges and trawls and some effects of dredging on a scallop ground. Journal of the Fisheries Board of Canada, 30(2), 173-180. 3 Currie, David R., and Gregory D. Parry. "Impacts and efficiency of scallop dredging on different soft substrates." Canadian Journal of Fisheries and Aquatic Sciences 56, no. 4 (1999): 539-550. 4 Jenkins, S. R., B. D. Beukers-Stewart, and A. R. Brand. "Impact of scallop dredging on benthic megafauna: a comparison of damage levels in captured and non-captured organisms." Marine Ecology Progress Series 215 (2001): 297-301. 5 Offshore Wind Undersea Cable Impacts on Lobsters, Ecology & Environment Inc., February 2018. 6 Peter J. Auster, Richard J. Malatesta, Richard W. Langton, Les Watting, Page C. Valentine, Carol Lee S. Donaldson, Elizabeth W. Langton, Andrew N. Shepard & War G. Babb (2008) The impacts of mobile fishing gear on seafloor habitats in the gulf of Maine (Northwest Atlantic): Implications for conservation of fish populations, Reviews in Fisheries Science, 4:2, 185-202, DOI: 10.1080/10641269609388584 7 https://youtu.be/9bfa84lion0 8 Renewable Energy in situ Power Cable Observation Final Report, U.S. Bureau of Ocean Energy Management, 2016. https://www.boem.gov/2016-008/ 9 Fox Islands Electric Cooperative, Inc., http://www.foxislands.net/energy.html 10 https://www.nhsec.nh.gov/projects/2015-04/application/2015-04_2016-04- 12_app35_modeling_sediment_dispersion_cable_burial_srp_little_bay.pdf 11 See Section 3 (G) (1) - http://www.mainelegislature.org/legis/statutes/38/title38sec480-hh.html 6