PNWA 2013 SUMMER CONFERENCE: USACE PORTLAND DISTRICT UPDATE Michael E. Ott, P.E., PMP, USACE Portland District June 24-26, 2013 La Conner, WA US Army Corps of Engineers
Agenda Inland Navigation System Goal & Process Columbia-Snake River System (CSRS) Coordination Objectives The MCR Jetties Update Lower Columbia River Status Willamette River Deepening Status Alternative Financing
Our Goal Prioritized System Approach Integrated Process: Annual Budget Development Dam Safety & Readiness Program Communications Strategy Early & robust stakeholder coordination Tentative Extended NavLock outage: after 2016 Target: 2017, subject to funding availability
CSRS Requirements Prioritization Risk-informed decision process System reliability considerations Requirements list: Portland/Walla Walla Districts & Northwestern Division Periodic team meetings to review the list Reprioritized with new information/condition changes Addition of new or deletion of completed projects
The Columbia-Snake Inland Navigation Bonneville Miter Gates The Dalles Downstream gate NavLock Controls Upstream Gate
2011: New Gate Issues during break-in The Dalles Downstream Navigation Lock Gate Gudgeon bushing failures, gate vibration. 2012: Temporary repair for gudgeon bushing 1 replaced in December 2012 emergency lock outage Remaining 3 replaced during March 2013 lock outage 2013: Design Documentation Report Determine permanent gudgeon bushing repair Investigate gate vibration Determine corrosion control system Investigate gudgeon anchor replacement
Bonneville Downstream Navigation Lock Gate 2011: D/S Miter Gate inspection Skin plate/stiffener: quoin cracks Emergency repairs to strengthen pintle Gate no longer miters until fully loaded 2012: Gate fully instrumented Inspection: no further pintle corner cracking Resolving Remote monitoring challenges 2013: ROV inspection Corner stiffening seems to be performing well
Coordination Objectives CSRS maintenance/recapitalization with available funds Integrate into NWD budgeting process Coordination with PNWA & other stakeholders Use Inland Marine Transportation Improvement Report
Mouth of the Columbia River (MCR) Jetties Sand Island pile dikes 1930-1935 Columbia River Estuary Jetty A 1.6 miles long, 1938-39 Clatsop Spit Peacock Spit North Jetty 2 miles long, 1914-1917 Pacific Ocean South Jetty 6 miles long 1885-1913
BUILDING STRONG
FY 13: South Jetty (O&M) Dune Stabilization South Jetty Root & Trestle Bay: $5.5M Detailed Design Report, P&S, dynamic cobblestone revetment construction
South Jetty Dune Stabilization FY 13 milestones 28 June Contract Award 12 July Notice to Proceed 29 July Begin construction 11 October Complete construction
FY 14 PBUD: Jetty A Major Rehab (CG) - $1M Detailed Design Report, initiate P&S, Mitigation Plan, and physical modeling for head stabilization Based on Major Rehabilitation Report approved June 2012 Jetty A, Oct. 2012
MCR North Jetty FY 14 Capability (O&M) Two separate actions supported by the Major Maintenance Report: (1) Lagoon Fill: $10.32M (2) Critical Repairs: $13.25M Critical Repairs STA 86-99 Lagoon Fill
North Jetty Lagoon Fill (O&M, $10.32M capability) Redirects overland flow away from the jetty structure Dissipates flow into a constructed sump Places gravel, sand and quarry stone on the landward side of the jetty to eliminate the tidal flow through the jetty All three actions will stabilize the North Jetty Root and its foundation Stabilization Areas Oct. 2012
MCR Jetties Future work beyond FY 14 Jetty A, North Jetty, and South Jetty rehabilitation (CG funding) Seven-year construction plan developed in the FY 12 Major Rehabilitation Report supporting $257.2M in jetty repairs (Approximately $31M for Jetty A, $79.8M for the North Jetty and $146.4M for the South Jetty Major Rehab Report actions support measures that will prevent frequent and costly emergency repairs in the future.
Lower Columbia River Channel Cross Section by Quarter Last Year 23-Aug-12 15-Dec-12 15-Feb-13 A B C D Key Ports A B C D Key Ports A B C D LOWER DESDEMONA 46 48 49 47 46 48 50 51 42 44 44 42 UPPER DESDEMONA 43 44 45 43 42 44 45 43 41 45 44 35 FLAVEL BAR 39 42 43 36 Astoria 42 44 44 36 Astoria 41 43 45 42 UPPER SANDS 42 44 45 42 42 43 45 43 41 44 44 42 UPPER SANDS 42 44 44 42 42 44 44 41 39 42 43 42 TONGUE POINT CROSSING 40 45 46 44 39 43 44 44 40 42 41 37 TONGUE POINT CROSSING 40 42 43 37 41 44 44 39 43 45 46 44 MILLER SANDS 42 44 42 35 43 44 47 45 39 46 43 43 MILLER SANDS 37 44 41 31 38 45 44 43 45 44 43 42 MILLER SANDS 39 41 40 38 45 44 42 41 43 42 42 38 PILLAR ROCK RANGES 41 41 41 38 42 42 44 39 39 44 44 43 PILLAR ROCK RANGES 43 44 43 42 42 45 43 43 44 46 46 43 BROOKFIELD-WELCH IS 45 48 49 43 43 46 45 45 45 48 44 33 BROOKFIELD-WELCH IS 46 50 45 33 46 48 45 31 40 44 42 38 SKAMOKAWA BAR 41 40 39 35 39 43 43 40 47 44 45 43 SKAMOKAWA BAR 48 47 44 44 48 46 45 43 55 53 53 54 PUGET ISLAND BAR 51 52 54 48 50 51 52 48 44 43 42 39 PUGET ISLAND BAR 43 44 43 40 43 43 43 40 39 42 41 38 WAUNA & DRISCOLL RANGES 38 41 40 38 39 43 43 40 38 40 43 41 WAUNA & DRISCOLL RANGES 38 39 42 42 38 43 43 42 38 42 44 44 WESTPORT BAR 39 41 42 43 38 43 43 43 42 44 42 39 WESTPORT BAR 37 39 40 39 43 44 42 40 40 43 43 42 EUREKA BAR 35 37 40 40 43 43 43 42 46 46 47 45 EUREKA BAR 46 43 45 44 46 45 46 43 41 43 41 39 EUREKA BAR 41 41 38 40 42 42 43 40 44 43 43 42 GULL ISLAND BAR 42 43 44 42 43 44 44 42 50 44 45 38 GULL ISLAND BAR 48 44 42 35 50 47 44 38 47 48 46 41 STELLA-FISHER BAR 47 52 50 39 47 49 47 42 39 42 42 40 STELLA-FISHER BAR 37 41 41 39 40 43 43 42 42 43 44 41 WALKER ISLAND REACH 40 44 45 36 42 44 43 42 44 42 42 39 WALKER ISLAND REACH 40 42 39 35 42 42 43 41 47 47 47 45 WALKER ISLAND REACH 47 47 47 44 46 47 47 43 42 43 43 41 SLAUGHTERS BAR 42 41 40 42 42 42 42 42 42 42 44 42 SLAUGHTERS BAR 38 41 41 38 43 44 45 44 41 43 42 42 LOWER DOBELBOWER 37 43 43 40 42 44 41 44 47 45 46 42 LOWER DOBELBOWER 47 47 43 39 Longview 47 46 44 42 Longview 44 44 42 40 UPPER DOBELBOWER 42 43 42 38 44 44 42 40 41 42 44 43 UPPER DOBELBOWER 40 42 40 40 41 42 44 43 42 62 62 59 KALAMA BAR 43 69 59 60 45 56 61 58 41 46 45 33 KALAMA BAR 42 44 42 34 43 47 44 33 43 43 43 40 KALAMA BAR 41 43 42 40 Kalama 42 44 43 42 Kalama 39 44 44 39 LOWER MARTIN BAR 36 43 43 39 39 45 45 39 43 44 46 39 LOWER MARTIN BAR 42 41 43 39 40 44 44 42 43 44 43 38 LOWER MARTIN BAR 40 41 41 37 43 44 44 38 45 43 43 40 UPPER MARTIN BAR 49 44 42 39 48 45 41 41 41 43 43 41 UPPER MARTIN BAR 39 40 41 41 43 43 44 41 40 43 43 42 UPPER MARTIN BAR 39 40 40 39 40 43 43 42 40 44 41 38 ST. HELENS BAR 41 43 40 37 42 43 41 39 42 44 42 37 ST. HELENS BAR 35 39 40 37 42 45 42 39 51 52 48 45 WARRIOR ROCK BAR 49 50 47 44 50 51 48 44 41 43 42 43 WARRIOR ROCK BAR 40 41 42 40 41 43 43 41 39 43 43 43 WARRIOR ROCK BAR 37 42 44 45 42 43 43 44 40 43 42 40 HENRICI BAR 40 41 41 40 42 43 43 40 43 43 43 41 HENRICI BAR 42 41 41 39 44 44 43 41 43 43 42 40 WILLOW BAR 41 42 40 39 41 43 43 39 40 43 43 41 WILLOW BAR 40 43 41 40 Portland 41 43 44 40 Portland 42 42 44 44 MORGAN BAR 40 43 43 42 42 42 44 44 42 46 50 50 MORGAN BAR 41 46 48 50 42 46 48 50 44 44 44 43 MORGAN BAR 45 44 45 44 45 43 45 43 48 49 47 39 LOWER VANCOUVER 48 49 49 38 48 49 49 37 43 42 42 42 44 43 42 LOWER VANCOUVER 44 44 42 40 43 42 44 42 45 43 44 42 47 47 LOWER VANCOUVER 47 44 43 40 Vancouver 44 43 42 Vancouver
Equipment in 2013 Dredge Season for the Columbia System Essayons Oregon Stuyvesant Yaquina 18
Lower Columbia River Channel Cross Section by Quarter Currently
Lower Columbia River Channel Cross Section by Quarter Currently
Willamette Channel Deepening Funds in Pbud FY14 Review Sediment Data Prepare SAP Rock Coring Planning
Low Use Projects Alternative Financing: State of Oregon A formal MOA process has been initiated State Priorities are being discussed
Questions? Mike Ott 503-808-4345 michael.e.ott@usace.army.mil