Modelling Parameters. Affect on DER Impact Study Results

Similar documents
POWER QUALITY IMPACTS AND MITIGATION OF DISTRIBUTED SOLAR POWER

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

IEEE 1547: Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces

IEEE sion/1547revision_index.html

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs

Phase-phase/phase-neutral: 24/13.8 kv star, 13.8 kv delta, 12/6.9 kv star.

Harmonics Issues that Limit Solar Photovoltaic Generation on Distribution Circuits

Embedded Generation Connection Application Form

Protective Relaying for DER

ECE 528 Understanding Power Quality

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW

Babak Enayati National Grid Thursday, April 17

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods

Revised IEEE 1547 Standard for Interconnecting Distributed Energy Resources with Electric Power Systems- National Grid Solar Program

Southern Company Interconnection Requirements for Inverter-Based Generation

Information and Technical Requirements For the Interconnection of Distributed Energy Resources (DER)

FACILITY RATINGS METHOD TABLE OF CONTENTS

Embedded Generation Connection Application Form

The Connecticut Light and Power Company

Impact of High PV Penetration on Grid Operation. Yahia Baghzouz Professor of Electrical engineering University of Nevada Las Vegas

Distributed Solar Integration Experiences

Experiences in Integrating PV and Other DG to the Power System

Wind Power Facility Technical Requirements CHANGE HISTORY

Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application

Impacts of the Renewable Energy Resources on the Power System Protection by: Brent M. Fedele, P.E., National Grid for: 11 th Annual CNY Engineering

Impact Assessment Generator Form

IEEE sion/1547revision_index.html

Utility Interconnection and System Protection

Table of Contents. Introduction... 1

TECHNICAL GUIDELINE FOR THE INTERCONNECTION OF DISTRIBUTED ENERGY RESOURCES TO EPCOR DISTRIBUTION AND TRANSMISSION INC. S DISTRIBUTION SYSTEM

Connection Impact Assessment Application

Transmission Facilities Rating Methodology for Florida

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

Focused Directional Overcurrent Elements (67P, Q and N) for DER Interconnection Protection

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

TechSurveillance. Revision of IEEE Standard New Reactive Power and Voltage Regulation Capability Requirements. Business & Technology Strategies

Transmission Facilities Rating Methodology

ESB National Grid Transmission Planning Criteria

Transmission Interconnection Requirements for Inverter-Based Generation

GENERATOR INTERCONNECTION APPLICATION Category 3 For All Projects with Aggregate Generator Output of More Than 150 kw but Less Than or Equal to 550 kw

Substation Testing and Commissioning: Power Transformer Through Fault Test

POWER FACTOR CORRECTION. HARMONIC FILTERING. MEDIUM AND HIGH VOLTAGE SOLUTIONS.

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Course 11 Distribution Transformer Applications Instructor: David R. Smith, PE Due: April 24, 2017 (EV), April 25, 2017 (LC)

BED INTERCONNECTION TECHNICAL REQUIREMENTS

TABLE OF CONTENT

MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

Embedded Generation Connection Application Form

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

Distribution System Development & Preliminary Studies

Form B. Connection Impact Assessment Application Form Distribution System

Need for grounding Codes and Standards for grounding Wind Turbine Generator grounding design Foundation + Horizontal Electrode grounding design

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

Notes 1: Introduction to Distribution Systems

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

Renewable Interconnection Standard & Experimental Tests. Yahia Baghzouz UNLV Las Vegas, NV, USA

E N G I N E E R I N G M A N U A L

1 INTRODUCTION 1.1 PRODUCT DESCRIPTION

Kansas City Power & Light Company. Transmission Facility Rating Methodology

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

MidAmerican Energy Company 69 kv Facility Ratings Methodology

GridLiance Reliability Criteria

OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS

MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology

A Tutorial on the Application and Setting of Collector Feeder Overcurrent Relays at Wind Electric Plants

Generation and Load Interconnection Standard

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning

ADVANCED CONTROLS FOR MITIGATION OF FLICKER USING DOUBLY-FED ASYNCHRONOUS WIND TURBINE-GENERATORS

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

Differential Protection for Microgrids with Embedded Generations

The Analysis of Voltage Increase Phenomena in a Distribution Network with High Penetration of Distributed Generation

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

MOBILE SUBSTATIONS 2015 MINNESOTA POWER SYSTEMS CONFERENCE

IEEE Major Revision of Interconnection Standard

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

Transformer Protection

Maine Public Service Reliability Solutions Update

Network Monitoring and Visibility Summary

Determination of Smart Inverter Power Factor Control Settings for Distributed Energy Resources

Central East Voltage and Stability Analysis for Marcy FACTS Project Phase I

MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above

g GE POWER MANAGEMENT

Power Transformer Ratings' Calculation and Analysis - IEEE C

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 150 KW BUT LESS THAN OR EQUAL TO 550 KW

Differential Protection Optimal differential protection for phase shifter transformers and special transformers

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV)

ROCHESTER PUBLIC UTILITIES FACILITY RATINGS METHODOLOGY FOR TRANSMISSION, SUBSTATION, & GENERATION EQUIPMENT

NERC Protection Coordination Webinar Series July 15, Jon Gardell

UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS

Voltage-based limits on PV hosting capacity of distribution circuits

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

ANALYSIS OF LIGHTNING ARRESTER OVERLOADING IN FUTURE DISTRIBUTION SYSTEMS WITH DISTRIBUTED GENERATION. A Thesis JONATHAN MICHAEL SNODGRASS

IMPLEMENTATION OF ADVANCED DISTRIBUTION AUTOMATION IN U.S.A. UTILITIES

Transcription:

Modelling Parameters Affect on DER Impact Study Results

Agenda Distributed Energy Resources (DER) Impact Studies DER Challenge Study Steps Lessons Learned Modeling Reverse Power Transformer Configuration Regulator Current Transformer (CT) Voltage Flicker DER Interconnection Transformer

The Challenge Distributed energy resources (DER) are sources of electric power that are not directly connected to a bulk power transmission system The electric power system (EPS) was not designed to accommodate generation at the distribution voltage level IEEE 1547 Standard for Interconnecting Distributed Resources with Electric Power Systems DER interconnection impact studies determine potential issues and identify mitigation strategies that allow for successful integration of the proposed DER

Background DER can be thermal generation, renewable generation, and energy storage Point of Interconnection (POI) Point of Common Coupling (PCC)

DER Interconnection Impact Study Steps Screenings Reverse Power Evaluation Steady State (Voltage Drop): Thermal, Voltage, Regulation Voltage Flicker Risk of Islanding Evaluation Short Circuit Protection http://energy.leidos.com/blog/why-impact-studies-are-vital-for-successful-der-interconnections

LESSONS LEARNED

Model Scope Steady State Scenarios Minimum Load without Proposed DER Minimum Load with Proposed DER Peak Load without Proposed DER Peak Load with Proposed DER Chose Load Normal Load Solar Daytime Load: 8am-6pm, 10am-4pm Include DER Impact is Cumulative Existing Approved, including Mitigation Proposed Scope Substation or Feeder Contingencies Distributed Automation Substation Autotransfer Connection Direct Behind the Meter

Reverse Power Desktop Review Worst case analysis Substation Transformer Load (kw) Daytime Minimum Load 5,516 Approved DER Projects -3,666 Proposed DER Under Study -4,450 Total Forecasted Load -2,600 Reverse power is expected to be an issue Possible substation upgrades: regulator (LTC) controls, bidirectional meter May indicate need for transmission study or revised protection

Reverse Power Detailed Review Detailed Analysis: Hourly Substation Load and Forecasted Hourly Generation One Approved Solar Not Reach Nameplate Seven Hours Reverse Power at 1,266 kw Worst Case Proposed Solar At Nameplate 4 Hours https://pvwatts.nrel.gov/index.php

Transformer Parameters Our Model 69 kv Source 13.2 kv Feeder De-energized Tap Changer (DETC) Unknown Different Client 69 kv Source 12.47 kv Feeder 67 kv Transformer 68.8 kv DETC Tap 70.4 kv DETC Tap

Transformer Parameters Correct setup Model shows low voltage Transformer LTC: -5,-5,-5 (4) 13.2 kv Caps: One 1200 kvar

Transformer Parameters Incorrect setup Undervoltage not detected Transformer LTC: 2, 2, 2 1200 kvar : 1311 kvar

Transformer Parameters Assume a 67 13.8 kv transformer Compare breaker fault current center tap versus DETC Voltage Settings for Sources and Transformers with Off-Nominal Taps, Greg Shirek P.E., Milsoft, 2011

Transformer Parameters kvar impacted by applied voltage Standard C37.010 substation transformer X/R ratio kvar = kv 2 * 1000 X c Nominal, nameplate, and tap voltages affect load flow and fault current results

Regulator Current Transformer (CT) CT primary rating (not the ratio) controls regulator output https://www.beckwithelectric.com/docs/app-notes/ appn-17.pdf V bus = V line + I load (R + jx) CT rating

Regulator CT ~ 100 A at 0.9 PF ~ 90 A real current Correct CT Rating 250 A V = 121 V + 90A/250A * 6 = 123.1 V Incorrect CT rating 100A V = 121 V + 90A/100A * 6 = 126.4 V

Regulator CT Substation LTC: CT on Nameplate Regulator: Typical CT Ratings http://www.cooperindustries.com/content/dam/public/ powersystems/resources/library/225_voltageregulators/ TD225011EN.pdf

Voltage Flicker A change in electric light source intensity due to variation in input voltage of the power supply GE Flicker Curve Maximum allowable percent voltage change at 2%, 2.7%, or 2.8% Once per day changes above 2.8% would be noticeable. Voltage change is more irritable when there are more dips per second.

Voltage Flicker Methodology utility dependent Generation changes - On: 100%, Off: 0%, 5%, or 20% Reduce generation on the whole feeder or just on part of the feeder near the POI All generation or just solar Study flicker whole feeder or just POI and substation Quasi time series analysis IEEE Std 1453 supplanted IEEE 519 and calls for short-term (Pst) and long-term (Plt) flicker indices

Voltage Flicker Voltage drop generation on Record all overhead and underground voltages Lock regulators and capacitors, and generation off Second voltage drop Record second set of voltages Compare percent voltage change using Excel Voltage violations? Set up for first voltage drop Set up for second voltage drop

Voltage Flicker Utility has Rooftop DER information available Proposed DER under study Lesson learned: smaller DER impacting results Model had 1-phase PV (3 to 20 kw) Added 20 kw PV in low voltage area POI checked for flicker 100% generation to 0% Criteria is 2%

Voltage Flicker Flicker 20 kw POI: Before (120V Base) Primary POI 20 kw After (120V Base) Percent Change Example 20 kw Assuming the flicker criteria is 2%, the approved and proposed projects are exacerbating a pre-existing flicker problem Check flicker at all locations Question rooftop nameplate generation Other Small DG PV Status Approved 2000 kw Proposed 1980 kw 115.9 113.9 1.8% On to Off On Off Off 115.9 112.6 2.8% On to Off On to Off Off Off 115.7 111.1 4.0% On to Off On to Off On to Off Off 116.0 110.1 5.1% On to Off On to Off On to Off On to Off

Interconnection Transformer Winding Interconnection transformer winding configuration affects POI fault current Available fault for unit under study ~ 108 A 13.2 kv Fault Model Actual Results POI Grounded Wye Grounded Wye Incorrect Results POI Grounded Wye Delta

Summing It All Up DER interconnection impact studies identify issues and mitigation to allow successful interconnection Studies range from simple screening to multiple steps Chose the model scope based on situation Studies depend on correctly choosing model parameters and reviewing lessons learned

QUESTIONS

Impacts of Interconnecting DER on a Utility Distribution System What are the issues associated with interconnecting DER to a distribution system? Reverse power flow Thermal loading Voltage regulation Voltage flicker Protection Risk of unintentional islanding DER interconnection impact studies determine potential issues and identify mitigation strategies that allow for successful integration of the proposed DER

Transformer Parameters Incorrect transformer secondary LTC not correct Transformer LTC: 2, 2, 2 (4) 13.2 kv Caps: One 1200 kvar

Transformer Parameters System short circuit limits (8kA, 10kA) 65k fuse rated 7.1 ka first fuse on OH Results by transformer setup

Voltage Flicker Results at Proposed POI Before (120V Base) Proposed POI 1980 kw After (120V Base) Percent Change PV Status 121.3 119.3 1.6% Proposed Off, All other DG 100% to 0% 122.4 118.4 3.3% Proposed and all other DG 100% to 0% Annual hourly PV forecast https://pvwatts.nrel.gov/index.php AC Size: 20 kw DC/AC Ratio: 1.15 Tilt: 30 o (7 in 12) Azimuth: 225 o Check flicker at all locations Monitor impact of smaller DER