MEDIA TOUR P-8 8Programs Chuck Dabundo Boeing Vice President, P-8 Program Manager Rob Elliott Boeing BCA P-8 Program Manager June 8, 2011 Copyright 2011 Boeing. All rights reserved. 1
P-8A Poseidon The P-8A Poseidon is the U.S. Navy s longrange, persistent, maritime patrol aircraft that will provide superiority in both the open ocean and littoral environments. Copyright 2011 Boeing. All rights reserved. 2
Capabilities Next generation anti-submarine warfare (ASW) to counter subsurface threats Detect, locate, identify and track targets in the surface, subsurface and littoral battlespace; if required: deny, disrupt or destroy Conduct armed Intelligence, Surveillance and Reconnaissance (ISR) in maritime and littoral areas of operation Provide command, control and communications (C3) and serve as an interoperable C3 node Provide accurate stand-off targeting and strike support for naval, joint and multi-national operations Copyright 2011 Boeing. All rights reserved. 3
P-8A Maturity Common with B-737 Proven airframe Engine, APU Hydraulics Electrical, ECS Fire Protection Ice & Rain Protection Flight Systems Fuel Valving & Pumping Airframe Systems 41 Million Commercial Flight Hours To Date Systems Integration Completed - 24,000 hours of weapon system integration Full functionality in test aircraft OA event provided additional confidence in weapon systems maturity Mission Computer & Displays Radar Acoustics EO/IR Sonobuoy Rotary Launcher IFFI ESM EWSP Communications Systems Mission Systems COTS components Upgrade to P-3 APS-137 AAPS and P-3C ASU Upgrade to MX-20 on P-3, C-130, AFRL Italian Navy NH-90 UPX-40 on MH-60R, AWACS, CP140 Components from ICAP III and EA-18G Components in multiple military aircraft Components in multiple military aircraft No Uniquely Developed P-8A Mission Systems Summary P-8A aircraft and mission systems are mature and stable Meets or exceeds all key performance parameters (KPPs) Proven performance and reliability in civilian and military environments Milestone C complete LRIP-1 contract award High Fidelity WSIL Has Allowed for Significant Integration Effort to Occur On Track to Support 2013 IOC Copyright 2011 Boeing. All rights reserved. 4
State of the Art Capabilities Air Refuel Receptacle Stores Management System Acoustics INMARSAT Mission Set Anti-Submarine Warfare (ASW) EO/IR (MX-20HD) s Armed Intelligence, Surveillance and Reconnaissance (ISR) Anti-Surface Warfare (ASuW) Radar (APY-10) EWSP Sea control Targeting and strike support 5 Mission Stations CFM56-7B Engines ESM Command, control and communications Copyright 2011 Boeing. All rights reserved. 5
Platform Heritage Leverages production efficiencies and performance of the Boeing Next-Generation 737 5,756 orders for 133 diverse customers worldwide; 3,655 aircraft delivered d Proven track record Continuous innovation Industry-leading reliability and operating costs Copyright 2011 Boeing. All rights reserved. 6
In-Line Production Spirit AeroSystems P-8 fuselage Boeing (Renton Factory) Wings, empennage, aircraft assembly, engine installations Boeing (Boeing Field) Mission systems installation and checkout First in industry with in-line production process Copyright 2011 Boeing. All rights reserved. 7
Commercial Derivative Efficiencies Benefits of an established commercial production system Robust manpower/training certification program Industrial agility across supply chain Commercial support systems infrastructure Copyright 2011 Boeing. All rights reserved. 8
Performing to Plan T2 T5 T1 T3 T4 T6 2010 2011 New Production Facility Opens Static Testing Complete LRIP-1 Contract Award P-8I Final Assembly Copyright 2011 Boeing. All rights reserved. 9
Moving Into Production P-8A LRIP 1 P-8I Final assembly of first P-8A and P-8I production aircraft underway P-8A March 2011 P-8I May 2011 Copyright 2011 Boeing. All rights reserved. 10
Flight Test Progress Entered Test Program 4Q09 3Q10 3Q10 Significant Clean/stores GVT Acoustic subsystem testing Radar system testing Accomplishments Flutter Envelope expansion Fuel system verification Comm system testing ASW testing Stores release testing Copyright 2011 Boeing. All rights reserved. 11
Major Program Events June 2004 Systems Development and Demonstration contract award December 2004 High-speed wind tunnel tests November 2005 Preliminary Design Review June 2007 Critical Design Review Fourth quarter 2009 Flight test start August 2010 Milestone C approval First quarter 2011 Static testing complete First quarter 2011 LRIP-1 contract award 2012 IOT&E 2013 Initial Operational Capability 2015 Increment 2 fleet introduction Copyright 2011 Boeing. All rights reserved. 12
Comprehensive Support System Service Engineering Chief Mechanic Service Engineering Fleet Support Center Supply Support Leverage commercial commonality Synergy with P-8A Technical Publications Leverage Commercial and P-8A Operator / Maintenance Manuals Commercial Formats and Revision i Schedules PHS&T Commercial Best Practices Training Pilot Mission Operator Maintenance Computing Resources Access to Technical Data GHMS S/W Support System Manpower and Planning On-Site Field Service Rep. Manpower/Personnel Guidance Operational Support Plan Guidance Maintenance Planning Two level O & D Maintenance Scheduled Maintenance Plan Maintenance Planning Document Ground Support Equipment Commercial Commonality Facilities Copyright 2011 Boeing. All rights reserved. 13
Integrated P-8A Training System Pilot, Aircrew & Maintenance Training High fidelity training Maximize readiness training performed in ground-based training systems Realistic and repetitive Training system concurrency Training solution designed to maintain P-8A training device concurrency with aircraft by using P-8A flight and mission software Reduced P-8A total ownership costs Reduce flight hours and expendables by training in ground based training system 70% P-8A Simulator Based Training Continuum Copyright 2011 Boeing. All rights reserved. 14 153783-10.ppt TSS Hello Brief 14
P-8A Capability Roadmap NEXT PHASE OF CAPABILITY: Multi-static Active Coherent (MAC) Automatic Identification System (AIS) Aircraft Rapid Capability Insertion (ARCI) Tactical Operations Center updates High Altitude ASW FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 P-8 Integration AAS Future Series Modification (TBD) NR implementation, ASuW Weapon, A4 Arch Upgrade Development / Integration System Test Integrated Test MAC, AIS, ARCI, TOC, High Alt ASW Increment 1 IOT&E FOT&E FOT&E FOT&E P-8 Baseline P-8 Fleet Configuration Copyright 2011 Boeing. All rights reserved. 15
Long-Range Maritime Patrol International Market Sales potential for an additional 100 aircraft Norway Canada U.K. Germany Spain Portugal Italy Greece Korea Japan Saudi Arabia India Taiwan Thailand Brazil Chile Argentina South Africa Australia New Zealand Copyright 2011 Boeing. All rights reserved. 16
P-8I Boeing to provide 8 P-8I aircraft to Indian Navy Contract includes provisions for additional 4 aircraft Significant accomplishments: July 2010 - FDR completed Dec 2010-1 st aircraft build initiated May 2011 - Final assembly underway Copyright 2011 Boeing. All rights reserved. 17
P-8 Australia Australia signed MOU with U.S. Navy to collaborate in Increment 2 Joint Program Office established at NAS Pax River Currently in discussions for follow on development and product support Copyright 2011 Boeing. All rights reserved. 18
Facilitized for the Future A TOWER Portable Offices PCA PCA Test Support Static Test Fatigue Test ASAT 7 S & I ASAT 8 Barge LR Shipside Barge Final Assembly Barge Barge Clear Zone for AP Moves Stores Tool Room Copyright 2011 Boeing. All rights reserved. 19
The Team Copyright 2011 Boeing. All rights reserved. 20
MEDIA TOUR Copyright 2010 Boeing. All rights reserved. Author, Filename.ppt 21