CHAPTER 10 MICHIGAN DESIGN MANUAL BRIDGE DESIGN (SI) SHOP DRAWING REVIEW TYPES OF SHOP DRAWINGS Structural Steel

Similar documents
SECTION STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION STRUCTURAL STEEL. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

Working Drawing Manual

A. Extent of structural precast concrete work is shown on drawings and in schedules.

Section Meetings Section Material and Equipment. None Required

SECTION SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION STEEL LIGHTING STANDARDS. 1. Electrical conduit and fittings; Section

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

Edgerail Aluminum Bridge Railing System Specification & Installation Instructions

Working Drawing Procedure

SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES

SECTION CONCRETE REINFORCEMENT FOR STEAM UTILITY DISTRIBUTION

2016 Specification Treads, Base, Stringers and other Amenities Wausau Tile Precast Epoxy Terrazzo

Proposal PROJECT MANUAL P R O P E R T Y M A N A G E M E N T F A L L O N C O U N T Y. Baker, MT P.O. Box 846

.1 Comply with the General Conditions of the Contract, Supplementary General Conditions and the requirements of Division 1.

SECTION SUBMITTAL PROCEDURES

SECTION METAL FABRICATIONS

UFGS (November 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS

Chapter 1 General Design Information

PART MATERIALS. Section Fencing Materials. Description

Construction Tolerances - The following tolerances apply to cast-in-place structures:

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Taylor County July 2011 SECTION SHOP DRAWINGS, WORKING DRAWINGS AND SAMPLES

RAIL PANEL AT TRANSITION SECTION PLAN - POST DETAIL PLAN - TUBE SPLICE. Colorado Department of Transportation. Staff Bridge Branch

3400 Tectura Designs Precast Concrete

SECTION CHAIN LINK FENCING AND GATES AND SOFTBALL BACKSTOP

EMMEGI ARCHITECTURAL FENCING MASTER SPECIFICATION SECTION METAL FENCING, GATES & RAILING SYSTEM PART 1 GENERAL

How to Estimate the Cost of a. Precast Concrete Parking Structure

24" B B Joint X501 Joint See MARKINGS Note PCB-RXX-350-TL3 " X501 Y301 (Typ.) " A PLAN (reinforced casting option shown) A " dia. Hinge Bar (Typ.) NOT

STRUCTURAL STEEL AND ALUMINUM PART 1 - GENERAL 1.01 SCOPE:

UNISTRUT CORPORATION 2. AREA DIRECTLY ABOVE THE SUPPORT TO BE FREE AND CLEAR OF ALL OBSTRUCTIONS. 3. EXISTING STRUCTURE TO BE CHECKED BY OTHERS.

PROCEDURE FOR PROCESSING WORKING DRAWINGS

Collins Engineers Palmetto Islands County Park Boardwalk Repairs 03/28/2014 SECTION ROUGH CARPENTRY

UNISTRUT CORPORATION 2. AREA DIRECTLY ABOVE THE SUPPORT TO BE FREE AND CLEAR OF ALL OBSTRUCTIONS. 3. EXISTING STRUCTURE TO BE CHECKED BY OTHERS.

AESS Documents prepared by CISC ad hoc committee

TENANT IMPROVEMENT 16 FEBRUARY WEST 27TH STREET, 4TH FLOOR 100% CD OWNER/BID ADD 1-03/08/2018

NITTERHOUSE CONCRETE PRODUCTS, INC Molly Pitcher Highway South Chambersburg, PA

Architecturally Exposed Structural Steelwork (AESS) Sample Specification (for Engineers)

.2 Accompany all submissions with a transmittal letter, in duplicate, containing:.4 Specification Section number for each submittal

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

GUIDELINE SPECIFICATIONS

SECTION CABLE TRAYS

712 - STRUCTURAL STEEL CONSTRUCTION SECTION 712 STRUCTURAL STEEL CONSTRUCTION

Section COUPLINGS AND COUPLING ADAPTERS. This Section covers couplings and coupling adapters for ductile iron and steel pipe.

SECTION G ESTIMATE OF QUANTITIES

ALUMINUM PIPE GUIDERAIL 01/01/

STEEL PIPE GUIDERAIL 01/01/

Section 914. JOINT AND WATERPROOFING MATERIALS

SPECIFICATIONS FOR THE MANUFACTURE AND DESIGN OF PRECAST THREE SIDED ARCH STRUCTURES, WINGWALLS AND HEADWALLS

BAE Systems Combat Vehicles Supplier Quality Assurance AS9102 Requirement

TABLE OF CONTENTS. 1.0 Scope. 2.0 References. 3.0 Definitions. 4.0 Submission and Design Requirements. 5.0 Materials 5.1 General 5.

What Are Submittals?

SECTION 58 PRECAST CONCRETE BOX CULVERT. This work consists of furnishing and installing Pre-cast Concrete Box Culverts.

A. This section specifies procedural requirements for Shop Drawings, product data, samples, and other miscellaneous Work-related submittals.

A. Action Submittals: Written and graphic information that requires Architect's responsive action.

SECTION PRECAST CONCRETE SECTIONAL MANHOLES

SECTION PRECAST HOLLOW CORE PLANKS

1.1 RELATED DOCUMENTS

1. Architectural precast concrete cladding units.

James Luebke, PE Structural Development Engineer WisDOT Bureau of Structures

JVI Vector Connector

To: New York State Department of Transportation ENGINEERING INSTRUCTION. Approved:

FIRE STATION NO TH STREET NORTH ST. PETERSBURG, FL M-1 SCOPE OF WORK SYMBOL DESCRIPTION SYMBOL DESCRIPTION HVAC SYMBOL LEGEND

DRAFT UGANDA STANDARD

B. Installation Instructions. Provide installation instructions, including any special equipment, to address the following.

5/16" Flange nut. Bolt Keeper Plate (8" Sq. SYS.) (3) 1/2" x 3" Hex head connector zinc plated bolt w/ washers and nut. Anchor 3" sq. 7 Ga.

PIP STF05121 Anchor Fabrication and Installation Into Concrete

MISCELLANEOUS SIGN CONNECTION DETAILS TYPICAL ROUTE MARKER ASSEMBLIES SIGN TO POST MICHIGAN DEPARTMENT OF TRANSPORTATION

SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

(50 FT FT) MICHIGAN DEPARTMENT OF TRANSPORTATION 10-0" 7-6" 8-0" 6-0" Truss Depth. 3" sheets 5 & 6 of 10) DEPARTMENT DIRECTOR. Kirk T.

Scheduling, dimensioning, bending and cutting of steel reinforcement for concrete Specification

TECHNICAL INSTRUCTIONS: FOUNDRY. Page 1 of 8

TECHNICAL CORRECTION October Process Industry Practices Structural. PIP STF05121 Fabrication and Installation of Anchor Bolts

TYPE J (20 FT - 40 FT) MICHIGAN DEPARTMENT OF TRANSPORTATION 10-0" 7-6" NOTE: sheet 5 & 6 of 10) DEPARTMENT DIRECTOR. Kirk T.

SECTION SUBMITTAL PROCEDURES

PRECAST CONCRETE STRUCTURES

Standard Specifications

SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY 1234 MARKET STREET, PHILADELPHIA, PA 19107

SECTION SUBMITTALS PART 1 - GENERAL 1.01 RELATED DOCUMENTS

SECTION EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING

DIVISION 1 - GENERAL REQUIREMENTS SECTION SUBMITTALS

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

UNIFIED FACILITIES GUIDE SPECIFICATIONS

SECTION BULLET- RESISTANT DOORS

Precast Concrete Pavement

SECTION SUBMITTALS. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

A. Radius elbows with a construction radius of 1.5 the duct width are preferred to square elbows.

UCCS University Hall Fire Sprinkler System Upgrade March 1, 2011 RTA SECTION SUBMITTAL PROCEDURES PART 1 - GENERAL

SECTION SUBMITTAL PROCEDURES

UNIFIED FACILITIES GUIDE SPECIFICATIONS

SECTION CABLE TRAYS FOR ELECTRONIC SAFETY AND SECURITY

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

This specification describes the general requirements for Engineering Services provided to Vale.

A. Action Submittals: Written and graphic information that requires Engineer's responsive action.

StormTrap Guide Specification. StormTrap SingleTrap on Pad Foundation Groundwater BELOW Invert Revised 11/21/18

East Central College

C. Samples for Initial Selection: Manufacturer's color charts showing the full range of colors available.

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNION COUNTY VOCATIONAL-TECHNICAL SCHOOLS West Hall Addition Project Raritan Road, Scotch Plains, NJ

SECTION ARCHITECTURAL PRECAST CONCRETE PART 1 - GENERAL

Transcription:

CHAPTER 10 SHOP DRAWING REVIEW 10.01 TYPES OF SHOP DRAWINGS 10.01.01 Structural Steel 10.01.02 Prestressed Concrete 10.01.03 Bearings 10.01.04 Metal Stay - In - Place Forms () 10.01.05 Expansion Joints 10.01.06 Mechanical Equipment 10.01.07 Electrical Equipment and Circuitry 10.01.08 Water Mains 10.02 SHOP DRAWING PRODUCTION 10.02.01 Shop Drawing Submittal 10.02.02 Shop Drawing Review 10.02.03 Shop Drawing Distribution 10.03 SHOP DRAWINGS FOR RAILROAD STRUCTURES 10.03.01 Review Time 10.03.02 Prints Required 10.04 SHOP DRAWINGS FOR CONSULTANT-DESIGNED JOBS 10.04.01 Review Time 10.04.02 Prints Required 10.04.03 Shop Drawing Review (9-1-88) 10.04.04 Shop Drawing Distribution (9-1-88) 10.04.05 Structural Steel and Other Pay Weights ()

CHAPTER 10 SHOP DRAWING REVIEW 10.00 SHOP DRAWING REVIEW When reviewing shop drawings, it is not necessary to check the exact dimensions. It is the responsibility of MDOT to ascertain that the fabricator is supplying the items specified, while it is the contractor's responsibility that all items are fabricated to the correct dimensions. See Subsection 104.02 of the Standard Specifications for Construction. 10.01 TYPES OF SHOP DRAWINGS Shop drawings for the following construction items require the review and approval by MDOT prior to authorizing fabrication: A. Structural Steel B. Prestressed Concrete Beams C. Bearings D. Metal Stay-In-Place forms () E. Expansion Joints (If not pre-approved.) F. Mechanical Equipment G. Electrical Equipment and Circuitry H. Water Mains 10.01.01 Structural Steel Structural steel shop drawings shall be reviewed for the following items: A. Erection Diagram, showing general layout of the steel and marking scheme for identifying members. B. The number and the size of all members. C. The details of all splices, showing the number, size, and type of bolts, the type, size, and length of all welds and a section showing the size of all splice materials. D. The details of all field connections, showing number, size and type of bolts, and the locations where reaming is required. E. The number, size and spacing of shear developers. The use of shop welded shear developers is acceptable. (8-6-92) F. The amount and location of camber and the permissible tolerances. G. The ASTM designation of the steel to be fabricated. H. The steel surface preparation and the type of shop painting to be applied. I. All notes that appear on the design plans must be reflected on the shop drawings. J. Structural steel weights (shop bills) must be checked and should include weight adjustments cited in the Standard Specifications for Construction. K. Blocking and lifting diagrams.

10.01.02 Prestressed Concrete 10.01.03 Bearings Shop drawings for prestressed concrete elements shall be reviewed for the following items: A. Erection Diagram, showing the general layout of the concrete elements. B. The number and size of all members. C. The number, size, and type of prestressing strands or rods, and the forces in these prestressing elements. D. Bearing details showing size, type, and materials. E. The location and the details of lifting devices and of support points if the beam does not rest on its bearings while being transported. F. The location and type of any inserts required for attachments. Shop drawings for fabricator designed bearings shall be reviewed for the following items: A. Location Diagram, showing the general layout of the structure and the locations of the bearings. B. The number, size, and types of all bearings. C. The details of the bearings, showing all materials, dimensions, and welding. D. The steel surface preparation and shop coating details. E. Notes listing the material specifications for all parts of the bearings, and the design and specifications used for the design of the bearings. G. The layout of the casting bed to be used for casting the prestressed beams. This should show the location of hold-down devices for any draped strands. H. The location and length of any bondbreaker. I. The details and type of the reinforcing steel. J. All notes that appear on the design plans must be reflected on the shop drawings.

10.01.04 10.01.06 Metal Stay-In-Place Forms () Shop drawings for fabricator designed metal stay-in-place forms shall be reviewed for the following items: A. That all criteria listed in the Special Provision have been adhered to. B. Voids are filled or not filled with concrete based upon original design. C. Deck depth has not been compromised (increased or decreased) as result of using forms. D. All materials are galvanized. E. Support angles do not protrude into deck depth. F. Caulk or grout is applied along longitudinal seam between support angles and beam. G. Gauge(thickness) of metal deck form. Generally 19 or 22 gauge is acceptable. H. Welding criteria or procedures for metal forms and steel beams. 10.01.05 Mechanical Equipment Shop drawings for mechanical equipment must be reviewed for general conformance with the design specifications and plan details. The Contractor may submit copies of catalogue cuts, parts lists, operating procedures, etc., for review. 10.01.07 Electrical Equipment and Circuitry Shop drawings for electrical equipment and circuitry must be reviewed for general conformance with the design specifications and plan details. The Contractor may submit copies of catalogue cuts, parts lists, operating procedures, etc., for review. 10.01.08 Water Mains Shop drawings for water mains must be reviewed for general conformance with the design specifications and plan details. The drawings shall, as a minimum, show the plan and profile of the water mains, the type and quantity of material, all details for special connectors and fittings, and a listing of all specialty items. Expansion Joints Shop drawings are not required for proprietary expansion joints installed in bridge decks where the maximum opening is 100 mm, and where standard shop drawings have been preapproved by MDOT. The Contractor may select any joint that satisfies the design requirements from a number of joints listed on the plans and in the supplemental specifications. Copies of the standard shop drawings of the devices selected will be provided to the Project Engineer by the Design Division. When the maximum opening in the bridge deck is larger than 100 mm, a modular expansion joint is required and shop drawings for these joints shall be handled as the shop drawings for structural steel in Section 10.01.01.

10.02 10.02.02 SHOP DRAWING PRODUCTION The Contractor shall make arrangements to permit MDOT to deal directly with the fabricator or supplier for the following or similar items: A. Fabricated Structural Elements B. Mechanical Equipment C. Electrical Equipment and Circuitry D. Water Mains 10.02.01 Shop Drawing Submittal The fabricator shall submit four(4) sets of drawings to MDOT, for highway and pedestrian bridges designed by MDOT. For structures carrying railroads over highways and for projects designed by consultants, submittals should be according to Subsections 10.03.02 and 10.04.02 respectively. Shop Drawing Review The Design Division, the Bridge Fabrication Engineer of the Construction and Technology Division, and any Railroad or consultant involved shall review the drawings. Normally, the Bridge Fabrication Engineer will review only shop drawings for structural steel, prestressed concrete beams, and fabricator designed bearings and metal stay-in-place forms. The Design Division shall stamp all drawings either "Approved" or "Approved Subject to Correction." The drawings will also be stamped with the signature of the Engineer of Bridge Design. One(1) set will be returned to the fabricator. The shop bills for structural steel weights letter of transmittal shall show the fabricators's weight, the Design Division's checked weight, and the contract weight. 10.02.03 Shop Drawing Distribution After the necessary corrections have been made by the fabricator, he/she shall submit eleven(11) sets of shop drawings to the Design Division for distribution. All sets must be stamped "Approved" and must be stamped with the signature of the Engineer of Bridge Design. The Design Division will distribute the eleven(11) sets as follows: one(1) set to Design Files, three(3) sets returned to fabricator or supplier and five(5) sets to the Project Engineer, and two(2) sets to the Construction and Technology Division together with two(2) sets of prints of the sheets of contract plans which show prestressed concrete beam details. For shop bills for steel items the fabricator shall submit four(4) sets to the Design Division. Sets will be stamped as noted above. One(1) set will be returned to fabricator, two(2) sets will be sent to the Project Engineer and one(1) set will go to the Design Files. ()

10.03 SHOP DRAWINGS FOR RAILROAD STRUCTURES When a railroad crosses over a highway, the Railroad must review and approve shop drawings for that structure. 10.03.01 Review Time At the pre-construction meeting the Contractor must be made aware of the extra time required for review of the shop drawings by the Railroad. 10.03.02 Prints Required The fabricator shall transmit six(6) sets of shop drawings to MDOT for review and thirteen(13) sets for distribution. Two(2) sets are to be forwarded by MDOT to the Railroad for review and, after approval, for distribution.

10.04 SHOP DRAWINGS FOR CONSULTANT- DESIGNED JOBS When a structure has been designed by a consultant, shop drawing review will, in general, be a separate part of the Scope of Work defined in the Consultant Agreement. The review of shop drawings and structural steel pay weights shall be as described in sections 10.01-10.03. The consultant shall send copies of all correspondence to the MDOT Consultant Coordinator. () 10.04.01 Review Time Except for the time required for transmittal to and from the consultant, there will be no extra time allotted for the review of the shop drawings by the consultant. 10.04.02 Prints Required The consultant shall receive shop drawings from the fabricator for review. A copy of the transmittal letter from the fabricator to the consultant and one(1) set of prints shall also be sent to MDOT Consultant Coordinator. Two(2) sets of prints should be forwarded by the consultant to the Bridge Fabrication Engineer, Construction & Technology Division, for review. If a railroad crosses over a highway, the railroad company must also be sent two(2) sets of drawings for review and approval. () 10.04.03 Shop Drawing Review () After reviewing the details and receiving comments from other reviewing agencies, the consultant shall coordinate the comments on one(1) set of shop drawings and send them back to the fabricator. These plans shall be stamped approved or approved subject to correction. The approval stamp shall imprint APPROVED FOR MDOT By consultants name, along with the date. The consultant shall keep one copy of the drawings and comments to review the fabricators corrected drawings. 10.04.04 Shop Drawing Distribution () The consultant shall receive twelve(12) sets of corrected shop drawings from the fabricator for distribution (fourteen(14) sets if the job includes a railroad bridge over a highway). If all corrections have been made, the consultant shall stamp all the drawings approved. The consultant shall return three(3) sets of the drawings to the fabricator, send five(5) sets to the MDOT Construction Engineer, send two(2) sets to the Bridge Fabrication Engineer, send one(1) set to MDOT s Design Consultant Coordinator and keep one(1) set for the consultants files. If the job involves a railroad over a highway, two(2) sets shall be sent to the railroad company. 10.04.05 Structural Steel and Other Pay Weights ()The consultant shall review and approve the structural steel pay weights submitted by the fabricator. The fabricator shall submit five(5) sets to the consultant. Sets will be stamped as noted in section 10.04.03. One(1) set will be returned to fabricator, two(2) sets will be sent to the Construction Project Engineer, one(1) set will go to the consultant files and one(1) set will be sent to the MDOT Design Consultant Coordinator.