ADVANCEMENT IN STATE GRASPING METHOD OF MV DISTRIBUTION NETWORK FOR SHORT-TERM AND MID-TERM PLANNING

Similar documents
NEW APPROACH TO REGULATE LOW VOLTAGE DISTRIBUTION NETWORK

VOLTAGE CONTROL IN MEDIUM VOLTAGE LINES WITH HIGH PENETRATION OF DISTRIBUTED GENERATION

D-UPFC Application as the Series Power Device in the Massive Roof-top PVs and Domestic Loads

European Utility Week 2014 Amsterdam. Case Study Power Network 2030 Stettlen

INVESTIGATING THE BENEFITS OF MESHING REAL UK LV NETWORKS

Network Monitoring and Visibility Summary

Modeling and Validation of an Unbalanced LV Network Using Smart Meter and SCADA Inputs

CHIL and PHIL Simulation for Active Distribution Networks

Efficient Integration of Distributed Generation in Electricity Distribution Networks

Modelling Parameters. Affect on DER Impact Study Results

Embedded Generation Connection Application Form

GRID CODE COMPATIBLE PROTECTION SCHEME FOR SMART GRIDS

Distributed generation on 11kV voltage constrained feeders

Master of Science thesis

Determination of Smart Inverter Power Factor Control Settings for Distributed Energy Resources

CHAPTER 8 Effect of HT Distribution Feeder Voltage on Distribution Transformer Losses

Table of Contents. Introduction... 1

BENEFITS OF PHASOR MEASUREMENT UNITS FOR DISTRIBUTION GRID STATE ESTIMATION : PRACTICAL EXPERIENCE FROM AN URBAN DEMONSTRATOR

Landis+Gyr S650 Smart Grid Terminal. a smart grid innovation

Embedded Generation Connection Application Form

VOLTAGE CONTROL STRATEGY IN WEAK DISTRIBUTION NETWORKS WITH HYBRIDS GENERATION SYSTEMS

Aggregated Rooftop PV Sizing in Distribution Feeder Considering Harmonic Distortion Limit

Embedded Generation Connection Application Form

Hybrid Power Quality Compensator for Traction Power System with Photovoltaic Array

VOLTAGE QUALITY PROVISION IN LOW VOLTAGE NETWORKS WITH HIGH PENETRATION OF RENEWABLE PRODUCTION

Company Directive POLICY DOCUMENT: SD4/7. Relating to 11kV and 6.6kV System Design

SOFT SENSOR FOR DISTRIBUTION TRANSFORMERS: THERMAL AND ELECTRICAL MODELS

Notes 1: Introduction to Distribution Systems

SOLID-STATE TRANSFORMERS

Monitoring Locations in Smart Grids 14PESGM2391

SAFETY ISSUES RELATED TO THE CONNECTION OF MV AND HV GROUNDING

Aalborg Universitet. Published in: PowerTech, 2015 IEEE Eindhoven. DOI (link to publication from Publisher): /PTC.2015.

DG TRANSFER CONNECTION SCHEME IN ACTIVE DISTRIBUTION NETWORKS

th International Conference on Harmonics and Quality of Power (ICHQP 2016)

DISTRIBUTION SYSTEM ANALYSIS

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV)

Voltage Level Management of Low Voltage Radial Distribution Networks with High Penetration of Rooftop PV Systems

Maximum Allowable PV Penetration by Feeder Reconfiguration Considering Harmonic Distortion Limits

Distribution Network Voltage Unbalance Control under High Penetration of Single-Phase Photovoltaic Microgeneration

Energex Smart Network Trials

INCREASING NETWORK CAPACITY BY OPTIMISING VOLTAGE REGULATION ON MEDIUM AND LOW VOLTAGE FEEDERS

Hamdy Faramawy Senior Application Specialist ABB Sweden

EH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström

PRAOGEN, A TOOL FOR STUDYING CONNECTION OF GENERATING PLANT ONTO THE MEDIUM- VOLTAGE NETWORK

GSGF White Paper: Status and Insights on Microgrids. From Pilot to Commercial Deployment

Danish German Exchange Arnsberg. The Required Toolbox For DSO 2.0. Sebastian Winter, BDEW.

Discussion on the Deterministic Approaches for Evaluating the Voltage Deviation due to Distributed Generation

TEAMS Competition 2014

VOLTAGE MANAGEMENT BY THE APPORTIONMENT OF TOTAL VOLTAGE DROP IN THE PLANNING AND OPERATION OF COMBINED MEDIUM AND LOW VOLTAGE DISTRIBUTION SYSTEMS

How to maximize reliability using an alternative distribution system for critical loads

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS

POWER QUALITY AND STABILITY ISSUES IN MODERN DISTRIBUTION GRIDS: IDENTIFICATION AND MITIGATION

Modelling and Analysis of Practical Options to Improve the Hosting Capacity of Low Voltage Networks for Embedded Photo-Voltaic Generation

From: Roger Clayton Re: Notes from FERC DER Technical Conference, April Panel 4 Collection and availability of data on DER installations

Research Article Voltage Control on LV Distribution Network: Local Regulation Strategies for DG Exploitation

IEEE JOURNAL ON SELECTED AREAS IN COMMUNICATIONS, VOL. 32, NO. 7, JULY

POWER QUALITY IMPACTS AND MITIGATION OF DISTRIBUTED SOLAR POWER

LS-SVM-based On-Load Tap Changer Control for Distribution Networks with Rooftop PV s

II. SC SYSTEM. A. Configuration of SC system Fig. 1 shows a circuit configuration of SC system. This

Harmonic impact of photovoltaic inverter systems on low and medium voltage distribution systems

Variable Shunt Reactors. Johann Griebichler I EM TR LPT GTC

The Upgradabilty of Conventional Three Phase Delta/Star Networks

MODELING THE EFFECTIVENESS OF POWER ELECTRONICS BASED VOLTAGE REGULATORS ON DISTRIBUTION VOLTAGE DISTURBANCES

ENERGISING INRUSH CURRENT TRANSIENTS IN PARALLEL-CONNECTED TRANSFORMERS

G. KOEPPL Koeppl Power Experts Switzerland

A new Volt / var local control strategy in low-voltage grids in the context of the LINK-based holistic architecture

Lead Beneficiary: INESC Porto

VOLTAGE UNBALANCE DUE TO SINGLE-PHASE PHOTOVOLTAIC INVERTERS

THE NEED FOR ZERO SEQUENCE VOLTAGE PROTECTION IN MV NETWORKS WITH HIGH LEVELS OF DISTRIBUTED GENERATION

Suppression of Voltage Violation in PV Connected Distribution System via Cooperation of Battery Energy Storage System and SVR

ENEDIS FIELD EXPERIENCE OF AUGMENTED AND VIRTUAL REALITY TECHNOLOGIES AT THE SERVICE OF NETWORK OPERATORS

Company Directive STANDARD TECHNIQUE: SD1E/2. Technical Requirements for Customer Export Limiting Schemes

DG DEMONET - FINAL RESULTS OF FIELD TRIAL VALIDATION OF COORDINATED VOLT/VAR CONTROL

Wind Power Facility Technical Requirements CHANGE HISTORY

Medium-voltage in-phase regulator system Energy Management

Voltage Unbalance Reduction in Low Voltage Feeders by Dynamic Switching of Residential Customers among Three Phases

Problems connected with Commissioning of Power Transformers

A Practical Application of Low Voltage DC Distribution Network Within Buildings

MMC (Modular Multilevel Converter)

Impact of Distributed Generation on Voltage Regulation by ULTC Transformer using Various Existing Methods

Identifying Long Term Voltage Stability Caused by Distribution Systems vs Transmission Systems

ENG52 WP1 status and plans TU Eindhoven Project meeting, Glasgow, Vladimir Ćuk, Fei Ni,

Feeder Protection Challenges with High Penetration of Inverter Based Distributed Generation

EH2741 Communication and Control in Electric Power Systems Lecture 2

Network Equilibrium Balancing Act Conference Thursday 8th September 2016

FLC based AVC Relay with Newton Raphson Load Flow for Voltage Control in Distribution Network

UNBALANCED CURRENT BASED TARRIF

NEQUAL -WEB-BASED VOLTAGE QUALITY MONITORING IN SWITZERLAND

Power Factor and Power Factor Correction

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

Experiences of a microgrid research laboratory and lessons learned for future smart grids

THE IMPACT OF NETWORK SPLITTING ON FAULT LEVELS AND OTHER PERFORMANCE MEASURES

Advanced Pulse WattNode - Option PV (Photovoltaic)

LOAD BALANCING IN PRIMARY DISTRIBUTION FEEDERS BY COMBINATION OF RENEWABLE ENERGY SOURCE AND VOLTAGE SOURCE INVERTER

I. KEPCO Introduction

DC current interruption tests with HV mechanical DC circuit breaker

APPARENT POWER DEPENDENT VOLTAGE CONTROL IN THE LV GRIDS WITH DISTRIBUTED GENERATION USING ON-LOAD TAP CHANGING TRANSFORMER

CHAPTER 3 DEVELOPMENT OF DISTRIBUTION SIMULATION PACKAGE FOR LOAD ANALYSIS OF LV NETWORK

DISTRIBUTION LINE STRUCTURE AND GENERATION EFFICIENCY IMPROVEMENT: A CLUSTERED RESIDENTIAL GRID-INTERCONNECTED PV

Transcription:

PV capacity [GW] ADVANCEMENT IN STATE GRASPING METHOD OF MV DISTRIBUTION NETWORK FOR SHORT-TERM AND MID-TERM PLANNING Hiroyuki ISHIKAWA Ishikawa.Hiroyuki@chuden.co.jp Takukan YAMADA Yamada.Takukan@chuden.co.jp Kouji SADA Sada.Kouji@chuden.co.jp Tomihiro TAKANO Mitsubishi Electric Corp. Japan Takano.Tomihiro@df.MitsubishiElectric.co.jp Nobuhiko ITAYA Mitsubishi Electric Corp. Japan Itaya.Nobuhiko@ct.MitsubishiElectric.co.jp Hideya OHTSU Mitsubishi Electric Information Network Corp. Japan Ohtsu.Hideya@mind.co.jp ABSTRACT This paper describes the advancement in state grasping method of MV distribution networks. This is aimed to improve accuracy in grasping voltages and line currents of a MV distribution network with high penetration of renewable energy sources (RES), which is mostly photovoltaic generators (PV) in Japan. Advancement in grasping method is crucial for distribution system operators (DSOs) in many ways: Controlling on-load tap changers (OLTC) according to the exactly-estimated voltages contributes for maintaining voltages into the restricted ranges with less number of OLTCs. Investment for distribution network can be optimized by making components fit in with the exactlyestimated line currents. Proposed method will be realized by utilizing measured data from sensor-equipped automated switchgears and smart meters. Verification was carried out through computational simulation. Accuracy of the estimation was confirmed to be high enough for applying to short-term and mid-term planning, which is generally derived from the results of power flow calculation based on the grasped network conditions. INTRODUCTION In Japan, peak demand of electricity consumption is starting to saturate due to the divergence in the lifestyle of electricity consumers, which includes introduction of highly efficient electric appliances and Energy Management Systems (EMSs). This trend may accelerate due to the continuing decline in population nationwide. In this context, it is crucial to avoid excessive investment in distribution networks when replacing aged facilities and when connecting new loads or generators. On the other hand, capacity of PV installed to the power grid has been growing rapidly since feed-in-tariff scheme for RES started in 2012 in Japan. Chubu Electric Power Company Inc. (CEPCO), which is one of the utilities located at the central area of Japan, has hosted as much as 5.8GW of PV already at the end of FY2015 [1]. Most of the PVs are installed to MV and LV distribution networks causing voltage rise, and for minimizing investment, it is important to manage these voltage rise with least number of regulators. They will be realized by advancing short-term and midterm planning based on detailed modelling of network conditions, which can only be started from grasping the actual state of them. This paper describes how we are advancing state grasping method of MV distribution networks. 8 6 4 2 1.13 1.53 2.64 4.16 5.77 0 FY2011 FY2012 FY2013 FY2014 FY2015 Figure 1: Hosted capacity of PV in CEPCO [1]. CONVENTIONAL METHOD OF STATE GRASPING Methodology Conventionally, estimation of the state of a MV distribution network; i.e. line current and network voltage, which is the basis of the modelling for network planning, starts with the measuring of single-phase line current at the feeder circuit breaker (FCB) of substation. Secondly, the measured line current will be distributed to each nodes of the network according to their proportion of total contract capacities or peak demands. Thirdly, line current are calculated by aggregating these node currents. Power factor for calculating network voltage is also an estimated value derived through sampling research. They are assumed as constant value throughout the network. After all, network voltage will be calculated from the line current, line impedance and the constant power factor. Schematic diagram of the conventional method is shown in Figure 2. CIRED 2017 1/5

HV/MV Voltage, V Line current, I (measured) FCB with sensor Power factor, cosθ Line impedance, R + jx R 1 + jx 1 R 2 + jx 2 V I 1 V I V 2 2 1 peak demand or contract capacity : P 1 [kw] P 2 [kw] line current (estimated) network voltage (estimated) P 1 : I 1 = I P 1 + P 2 P 2 : I 2 = I P 1 + P 2 : V [V] = V - 3 I ( Rcosθ + Xsinθ ) : V 1 [V] = V - 3 I 1 ( R 1 cosθ + X 1 sinθ ) : V 2 [V] = V - 3 I 2 ( R 2 cosθ + X 2 sinθ ) Figure 2: Schematic diagram of the conventional method. Single-line load current measured at the FCB is distributed to each nodes according to their peak demand or contract capacity. Voltage is calculated from constant power factor and line impedance. Issues Conventional method is available because loads with uniform characteristics are the major players in the distribution network. However, as the customers lifestyles are diverging related to the high interest in environmental issues, it may become difficult to estimate the state of the network with the conventional method. Additionally, reverse power flow from the vastly installed PVs make this more complicated, as the line current measured with the limited sensors mounted on the FCBs are mixture of power consumption of loads and generated power of PVs. They do not represent the actual electricity consumption nor the actual power generation, and so distributing them according to the contact capacities or peak demands of each nodes will result to an estimation that diverge much from true values. Overall, state grasping of a distribution network is becoming more and more difficult and is necessary to be upgraded for the usage of detailed network planning. PROPOSED METHOD Basic Concept There are some necessary specifications when upgrading the grasping method ; Specification 1: Actual load and actual PV output of each node is necessary to be grasped individually. As mentioned in the previous section, power flow (or line current) measured with the sensors mounted on FCBs cannot directly be utilized for plannning, as they are mixture of consumption and generation. It is necessary to split them into actual load and actual PV output, and to distribute them individually into each node of the network. This will be realized by appling sensors that can measure three-phase current, three-phase voltage and power factor to the exisiting automated switchgears. They are connected to the central systems by ad-hoc communication networks already, and so the measured data can easily be collected, transferred and stored at the central systems for utilization. Specification 2: Avoid increase in the number of sensing equipment. Automated switchgears are mounted on trunk lines, which means that their number is limited and is not enough for monitoring power flow of each branches in detail. Their measurements are also a mixture of generation and consumption, and is necessary to be splitted as well. These constraints may well be covered by increasing the number of sensors, though it is not acceptable for economic reasons. Thus, smart meters are chosen as available sensors for filling the gap that the minimum number of sensors cannot measure. Metered data are aggregated for splitting the measured power flow of trunk line into cosumption and generation, and also for distributing them individually into each nodes to monitor the condition of each branches. In CEPCO, deployment of smart meter has started from FY2014, and finally will be finished at the end of FY2022 with more than 10 million smart meters. Active power of LV meters, active/reactive power of MV meters can be collected every 30 minutes and be utilized for various purposes. Specification 3: Applicable with unknown connected phases for single-phase loads/pvs. More than 1.5 million pole-mounted MV/LV transformers are installed to the MV distribution network, and none of their connected phases are managed in CEPCO. In utilizing LV smart meters as sensors, it is necessary either to research and manage the connected phases of every pole-mounted transformers or to develop an available method of utilizing LV smart meter data without the information of MV/LV transformers connected phases. We have chosen the later idea, for it takes much more effort to research and manage topology of 1.5 million polemounted transformers. These specifications are to be satisfied by the following methodology in several steps. Methodology In order to meet the requirements of above specifications, following procedure is proposed. Schematic diagram of the proposed method is also shown on Figure 3. CIRED 2017 2/5

Step 1: First of all, output of net-metered PVs (P npv) are to be estimated as they cannot be metered directly by the smart meters. In order to split the net-metered data into load consumption and PV output, modelling method beyond the meters is applied [2]. Modelling is realized by time-series metered data of neighboring individually-metered PVs (P ipv), and P npv will be estimated from them. Step 2: Smart meter data of individually-metered PVs (P ipv) and estimated output of net-metered PVs (P npv) are aggregated, added to the active power (P T) of the trunk line measured with the sensors, for calculating actual active current of load consumption (I PL) and active current of power generation (I PG). Calculation is indicated as below, where I PT stands for measured active current of the trunk line. I PL = I PT P T + ( P ipv + P npv ) P T I PG = I PT I PL = I PT P ipv + P npv P T I PT, I PG and I PL are average values of three-phase current, in order to meet the requirement of Specification 3. Step 3: I PL and I PG is distributed to each node according to their power consumption (P L,a) or their PV output (P PV,a) calculated from the aggregated metered data. Active current originated from loads of node a (I PL,a) or from PVs of node a (I PG,a) is calculated as follows; P L,a I PL,a = I PL P T + ( P ipv + P npv ) P PV,a I PG,a = I PG P ipv + P npv Step 4: Reactive current of node a originated from loads (I QL,a) and PVs (I QG,a) is also calculated from similar procedure as Step 1 through Step 3. Step 5: Active and reactive line current can be calculated individually by aggregating node current derived from Step 3 and Step 4. Finally, network voltage is calculated from active and reactive line current, by multiplying line impedances to them. Smart meter Step 1 P ipv FCB Sensor-mounted Automated switchgear Solar farm P npv Step 3 I PL,a I PG,b Node a Node b HV/MV Active power, P T Line current, I PT (measured) Load current, I PL PV current, I PG ( = I PT - I PL ) Step 2 Step 3 Roof-top PV Figure 3: Schematic diagram of the proposed method. Three-phase line current and voltage, power factor is measured at the trunk line with switchgear. Smart meter data is combined with them for detailed monitoring of branch lines. VERIFICATION To verify the proposed method, computational simulation was carried out. Simulation Model Existing 6.6kV distribution line of CEPCO with certain characteristics was chosen and modelled; 1) Feeder with various kinds of loads, residential and non-residential to verify the influence of load characteristics. 2) Feeder with high rate of unbalance (>2% in voltage) to verify the influence of unbalance. MV and LV loads of each nodes were modelled from sampled load curves of similar contract types and contract capacities. PV was also modelled from sampled output patterns of actual roof-top PVs. However, the existing feeder has no PVs installed, so the nodes with residential customers were chosen for hosting additional PVs. As the connected phases of each MV/LV pole-mounted transformers are unknown, their topologies were determined so that the simulated voltage unbalance fit the actual unbalance rate of the existing MV feeder. Single line diagram of the simulation model is indicated on Figure 4. As shown in Figure 4, node A and node B was chosen as the reference node for evaluating the simulated results. This was because they are the most difficult node to monitor line current or network voltage, with the lack of sensor-equipped switchgears. CIRED 2017 3/5

Voltage drop [V] 77kV/6.6kV FCB 6.6kV distribution line Table 1: Simulated Conditions. Max. load Hosted PV capacity 0 3.5MW/ 6.5MW (= 2/3 of residential 1.3Mvar(lead) loads with 4kW of PVs each) Node A (reference for current) Figure 5: Three-phase average line current of every 30 minutes (Node A). Node B (reference for volt.) <Industrial Area> <Residential Area> Figure 4: Single line diagram of the simulation model. This is based on the existing MV feeder of CEPCO. The most difficult node to monitor was chosen as the reference nodes. Simulation Conditions Simulation conditions are shown on Table 1. Load was fixed to heavy load condition, and PV was simulated with various capacities. Three-phase average values of the reference nodes of every 30 minutes were compared for evaluating the grasping method. Figure 5 shows the line current of Node A. Peak load occurs around 19:30-20:30 for, when lighting demand of residential loads are high. For with high penetration of PVs, line current starts to decline from 6:00 when PV starts generation and reaches peak in 12:00. Figure 6 shows the voltage drop between Node B and FCB. Voltage drop reaches peak as with the line current. For, voltage rises in the day time, indicated as negative value in the figure. Figure 6: Three-phase average voltage drop from FCB of every 30 minutes (Node B). Results and Discussions a) Estimation with Conventional method Estimated result is shown in Figure 7 and Figure 8. Line current estimated with the conventional method fit well with the actual state for. Voltage drop is overestimated biasedly, due to misestimation of power factor as 95% (lagged), which is almost 100% in actual state. Estimation diverges much for line current and for network voltage when a large amount of PVs are hosted in. This is because the measured line current at the automated switchgear diverges from the actual power consumption, and also their distribution diverge as they are calculated according to the contract capacities. This misestimation may cause unexpected violation of thermal capacity or restricted voltages if short-term and mid-term planning was carried out based on the network condition estimated with the conventional method. CIRED 2017 4/5

Voltage drop [V] Voltage drop [V] 59A (estimated) (estimated) 11A (estimated) (estimated) Figure 7: Line current of Node A estimated with conventional method. Figure 9: Line current of Node A estimated with proposed method. 334V (estimated) (estimated) 27V (estimated) (estimated) Figure 8: Voltage drop from FCB at Node B estimated with Conventional method. (). b) Estimation with Proposed method Estimated result is shown in Figure 9 and Figure 10. By applying proposed method, estimation error of line current and network voltage declined to absolute error of 11 and 27[V] in maximum respectively for. These errors occur due to the unbalances in current and voltage, which is much lower than the simulated conditions for the majority of feeders in CEPCO. Thus, it is assumed that grasping errors appears to be much lower when applied in the real field, and is accurate enough for the practical usages. CONCLUSIONS This paper proposes a new method of grasping conditions of MV distribution network with various loads and large hosted capacities of PVs. Conventional state grasping method has some assumptions; passive loads with constant power factor are the only players in the network, which have been changing due to the divergence in lifestyles of customers and also by the hosted DER. These changes make it difficult to monitor the network conditions with the conventional method, and their advancement is inevitable. Advancement in state grasping is realized through replacing the automated switchgears to sensor-equipped Figure 10: Voltage drop from FCB at Node B estimated with proposed method. ones, and also combining metered data from smart meters. First of all, measured line current will be adjusted by metered data of PVs so that the actual load can be derived. Actual load current will then be distributed to each node of the network according to their aggregated smart meter data. Actual PV current will be distributed to each PV nodes according to their smart meter data as well. Finally, these node currents will be aggregated to obtain line current, and to calculate network voltage. Verification was carried out by computational simulation. Simulated results indicated that the proposed method can be applied for monitoring the network conditions with high accuracy. CEPCO is now developing related system of proposed method to advance the short-term and mid-term planning, which is planned to be completed in the end of FY2021. REFERENCES [1] Chubu Electric Power Company Inc., 2016, Chubu Electric Power Company Group Annual Report 2016, 39 [2] T. Yamada, 2016, "Utilization of smart meter data in modelling of PV output", Proceedings of CIGRE SESSION 2016, C6 contributions, PS2, Q2.5 CIRED 2017 5/5