Consequential BSC changes resulting from the Smart Programme

Similar documents
P292 Amending Supplier & Meter Operator Agent responsibilities for smart Meter Technical Details

Engineering Recommendation M30 Issue Standard Electricity Network Operator Electricity Smart Meter Configurations

Intimate Communications Hub Interface Specification Report to Secretary of State

Wind. Farms. Purpose. recording Offshore. wind farms. the Transmission. the flows of voltages. the onshore. measuree and record. Agents.

G1 Capacity Market Metering

Overview of Metering Assurance in the Capacity Market

WP197 Capacity Market Metering Test

G20 Capacity Market Metering Statement

Capacity Market Prequalification

Herts Valleys Clinical Commissioning Group. Review of NHS Herts Valleys CCG Constitution

Smart Metering Implementation Programme: Prospectus 27 July 2010

Calculating and compensating for power transformer and cable (or line) losses - standard methods

The Namibian Grid Code

Balancing and Settlement Code. Code of Practice Two

Balancing and Settlement Code. Code of Practice Five

Balancing and Settlement Code. Code of Practice Five

PROJECT BRIEF PROJECT NEXUS. Development of Requirements FINAL DRAFT V1.0. Project Nexus Development of Requirements Project Brief.

European Workgroup. 7th May 2015

Office for Nuclear Regulation

Balancing and Settlement Code. Code of Practice One

Revision of the Public Law Outline

Conclusions on DCC s Consultation on the proposed changes to the SEC Subsidiary Documents that define DCC s SMETS1 Services

European Charter for Access to Research Infrastructures - DRAFT

Further Consultation on the Release of the / MHz Sub-band

Balancing and Settlement Code. Code of Practice One

European Update. 3 rd December 2015

Orkney Electricity Network Reinforcement Stakeholder Consultation Response. August 2014

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules. 45-day Formal Comment Period with Initial Ballot June July 2014

SATELLITE NETWORK NOTIFICATION AND COORDINATION REGULATIONS 2007 BR 94/2007

Consultation on Proposed National Rollout of Electricity and Gas Smart Metering

ECC. Doc. ECC(08)038 CEPT. 20 th Meeting Kristiansand, June Date issued: 23 rd May Subject: Password protection required?

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

CAR Part IX Regulations for srpas Manufacturers. Presented by RPAS TF Eng to Industry, Jan. 24, 2019

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

CMP298. Updating the Statement of Works process to facilitate aggregated assessment of relevant and collectively relevant embedded generation.

CHIEF ENGINEER PROCEDURE MANAGEMENT OF OVERLAPPING DESIGN AGREEMENT

BROADCASTING (RADIO MULTIPLEX SERVICES) BILL EXPLANATORY NOTES

EUROPEAN COMPLIANCE PROCESSES (post RfG Implementation) CONTENTS. (This contents page does not form part of the Grid Code) Paragraph No/Title

South African Distribution Code

25 th Workshop of the EURORDIS Round Table of Companies (ERTC)

Energy Networks Association

ESEA Flexibility. Guidance for Renewal Process. November 13, 2014

Serial Numbering Of Smart Type Electricity Meters From January 2013

UK Shared Business Services Ltd

Given FELA s specific expertise, FELA s submissions are largely focussed on policy and law issues related to inshore fisheries.

National Grid Gas Transmission (NGGT) Gas Quality Consultation Questions - Draft

Shell s Journey to Mobility

Government Policy Statement on Gas Governance

DNVGL-CG-0214 Edition September 2016

European Update. 5 th May 2016

ENGINEERING DRAWINGS MANAGEMENT POLICY (IFC/AS BUILTS)

II. The mandates, activities and outputs of the Technology Executive Committee

THE UNIVERSITY OF AUCKLAND INTELLECTUAL PROPERTY CREATED BY STAFF AND STUDENTS POLICY Organisation & Governance

Fact Sheet IP specificities in research for the benefit of SMEs

Company Directive STANDARD TECHNIQUE: TP14C. Distribution Business Provided Metering Facilities

NORTHERN IRELAND FIRE & RESCUE SERVICE BOARD MINUTES OF A MEETING 26 MARCH PM

AS/NZS 1200:2000 AS/NZS

Personal Medical Services (PMS) Contract Review Update

EUROPEAN COMPLIANCE PROCESSES (post RfG Implementation) CONTENTS. (This contents page does not form part of the Grid Code) Paragraph No/Title

VAR Generator Operation for Maintaining Network Voltage Schedules

Collaboration Agreement

Before the FEDERAL COMMUNICATIONS COMMISSION Washington, D.C. ) ) ) ) )

LLOYDS BANKING GROUP MATTERS RESERVED TO THE BOARDS (LLOYDS BANKING GROUP PLC, LLOYDS BANK PLC, BANK OF SCOTLAND PLC & HBOS PLC)

Broadcasting Services Act 1992

Getting the evidence: Using research in policy making

Re-use & Decommissioning in The Netherlands: A Joint Effort

The following draft Agreement supplements, but does not replace, the MOU by and between the Bureau of Land Management (BLM) and the California

VAR Generator Operation for Maintaining Network Voltage Schedules

CHESS Release Business and Technical Overview Client Segregation Enhancements to CHESS

G81 PART 1 FRAMEWORK APPENDIX

VAR Generator Operation for Maintaining Network Voltage Schedules

Checklist. Please read Circular No (CR) before completing the checklist.

Sypris Solutions, Inc. Conflict Minerals Report For the Period Ending December 31, 2013

New approach for lighting Regulations

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 INNOVATION

Minutes from the Health and Well-Being Board Financial Planning Group Tuesday 15 December North London Business Park, F13 1pm 3pm

IR UK Interface Requirement 2083

Demand Side Response Methodology (DSR) for Use after a Gas Deficit Warning (GDW) Background. Draft Business Rules

Lambeth Clinical Commissioning Group

Tha Board O Ulster-Scotch 97th Board Meeting 31 March 2010 Ulster-Scots Agency Board Room Belfast

Guidance Notes for Power Park Developers

VAR Generator Operation for Maintaining Network Voltage Schedules

KKR Credit Advisors (Ireland) Unlimited Company PILLAR 3 DISCLOSURES

CHESS Release Business and Technical Overview Client Segregation Enhancements to CHESS

UNITED STATES SECURITIES AND EXCHANGE COMMISSION. Form 8-K BMC STOCK HOLDINGS, INC.

I. Introduction. Cover note. A. Mandate. B. Scope of the note. Technology Executive Committee. Fifteenth meeting. Bonn, Germany, September 2017

1 st MEETING OF THE IHO COUNCIL

MINISTRY OF HEALTH STAGE PROBITY REPORT. 26 July 2016

DNVGL-CP-0338 Edition October 2015

SECTION 13. ACQUISITIONS

NHS Vale of York CCG TURNAROUND ACTION PLAN

RELEVANT ELECTRICAL STANDARDS

Broadcasting Services Act 1992

Engineering Recommendation G22

Health & Safety Policy Statement

JRC Response to the Consultation on. More Radio Spectrum for the Internet of Things

Statement on variation of 900 MHz and 1800 MHz Wireless Telegraphy Act licences

Appointment of External Auditors

Route Planning & Cable Route Surveys

1. The Office of Communications (Ofcom) grants this wireless telegraphy licence ( the Licence ) to

Transcription:

139/13 Consequential BSC changes resulting from the Smart Programme Meeting Name Supplier Volume Allocation Group Meeting Date 4 September 2012 Purpose of paper Summary For Information This paper gives an overview of the consequential amendments to the BSC which are likely to be required to support DECC s Smart Metering ation Programme. 1. Overview 1.1 This paper gives ELEXON s view on what consequential BSC amendments are likely to be needed to support the Department of Energy and Climate Change s (DECC s) Smart Metering ation Programme (SMIP) between now and Q4 2014. We give a high-level overview of these amendments and a description of their possible timings and dependencies. 1.2 The new Smart regulatory regime will initially cover the Metering and data retrieval processes for domestic and elective-non-domestic customers. Transition will take a few years, during which time existing dumb Meters will continue to be governed by the BSC while Smart Meters will be increasingly governed by the new Smart Energy Code (SEC). SEC commencement is scheduled for Q2 2013, followed by an interim period during which additional SEC content will be incorporated. The final SEC will apply from Q4 2014 when the new Data and Communications Company (DCC) services go live and the DCC mass Smart Meter rollout begins. 1.3 Most of the consequential BSC amendments are relatively minor wording changes to the Code. As these changes are straightforward and are driven by DECC s Smart regulatory arrangements, we believe that the necessary Modification Proposals could be progressed quickly. More detailed development via Change Proposals will be required in the areas of Meter Technical Details and Codes of Practice compliance. Our expectation is that all the changes will be progressed under the normal Modification/CP processes, and that the Secretary of State will not use its powers to designate any changes to the BSC arrangements. 1.4 The information given in this paper represents our latest thinking, and may be subject to change as DECC s SMIP planning progresses. We welcome your views on our draft roadmap, which we will continue to update and share with you following any significant developments. Page 1 of 12 ELEXON 2012

139/13 2. Changes 2.1 Appendix 1 shows our current roadmap for progressing the changes; specifically their timings and dependencies based on our assumptions regarding key SMIP milestones. The SMIP milestones are shown in italics and represent our best view/estimate, rather than actual planned dates from the DECC SMIP. A dashed activity boundary indicates that changes may not be required. 2.2 Appendix 2 gives more information on each change. 2.3 Changes 2, 3 and 4 (and possibly the Modification part of change 6) could potentially be packaged as a single Supplier Agent responsibilities Modification Proposal. Alternatively, changes 2 and 4 could be progressed as one Metering Modification Proposal. 3. Recommendations 3.1 We invite the SVG to: a) NOTE and DISCUSS the consequential changes to the BSC which may be required to support the Smart Metering ation Programme, and their likely timings and dependencies; and b) NOTE that we will continue to update you and seek your views on any further developments. List of Appendices: Appendix 1 Roadmap Appendix 2 Changes in more detail List of Attachments: None For more information, please contact: Kathryn Coffin and Jon Spence, Market Advisors, BSC Operations kathryn.coffin@elexon.co.uk / 020 7380 4030 jon.spence@elexon.co.uk / 020 7380 4313 Page 2 of 12 ELEXON 2012

139/13: Appendix 1 Activity / Milestone 2012 2013 2014 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 SEC Commencement Start of mass roll-out 1) BSC SEC change co-ordination 2) Meter Operator obligations: Communications Equipment 3) Data Collector obligations: Data retrieval Licence changes (incl. data ownership) approved 4) Ownership of Metering Data SMETS 2 consultation SMETS 2 EC notification period Secretary of State designation of SMETS v2 5) SMETS / BSC Code of Practice compliance Page 3 of 12 ELEXON 2012

139/13: Appendix 1 Activity / Milestone 2012 2013 2014 SMIP End-to-End Testing Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 6) Ownership/distribution of Meter Technical Details a) workshops b) pre-consultation on outline solution/options c) develop CPs for SVG approval d) participant system changes 7) Change of Supplier 8) Assurance 9) miscellaneous changes (see Appendix 2) Page 4 of 12 ELEXON 2012

Subject High-level description Type BSC CSD 1 2 by 3 Outstanding dependencies & considerations 1 Change coordination between BSC & Smart Energy Code (SEC) SEC code administrator will need change co-ordination arrangements with other codes BSC already requires BSC Panel to have joint working arrangements (JWAs) with Core Industry Document Owners and System Operator-Transmission Owner Code (STC) Committee in practice, ELEXON administers these on Panel s behalf Possible mod Section F None None SEC commencement (Q2 2013) Q4 2014 to align with full SEC If SEC is a Core Industry Document, no BSC change needed if not, could add specific obligation as per STC Smart Metering Regulation Group (SMRG) Working Group (WG) 4 Consequential Changes is still considering whether JWAs or Priority Provisions (equivalent to those between BSC & Master Registration Agreement (MRA)) are needed We believe BSC-MRA Priority Provisions are unnecessary for SEC (e.g. no need for BSCCo to be a SEC Party) in practice, have never needed to use right to veto MRA changes so little different to normal JWAs ELEXON will develop arrangements with SEC administrator regardless of obligations so no risk if BSC change is after SEC commencement Could potentially be progressed as straightforward Modification Proposal at opportune time 1 Code Subsidiary Documents: e.g. Balancing and Settlement Code Procedures (BSCPs), Metering Codes of Practice (CoPs). 2 Earliest point at which change can be raised. 3 Backstop dates; in practice earlier implementation of some changes may be possible/appropriate. Page 5 of 12 ELEXON 2012

Subject High-level description Type BSC CSD by Outstanding dependencies & considerations 2 Meter Operator Agent (MOA) obligations: Communications Equipment BSC currently says MOA responsible for Metering Equipment (including, if applicable, Associated Communications Equipment) Existing BSC definition of Metering Equipment includes Associated Communications Equipment Existing BSC definition of Communications Equipment refers to transmission to a Data Collector for the purposes of Supplier Volume Allocation These obligations/definitions may not be appropriate for Smart Meters serviced by the Data Communications Company (DCC) Mod Sections J, L, S and X-1 (NB term Metering Equipment currently appears in BSC ~188 times!) None Meter Operation Code of Practice Agreement (MOCOPA)? SEC commencement (Q2 2013) DCC Go Live / start of mass Smart Meter rollout (Q4 2014) SMIP still to decide who will own Communications Equipment and be responsible for commissioning, testing and maintenance SMRG WG4 still discussing definition of Metering Equipment As straightforward Code-only change, can afford to wait for further clarity before raising Minimal risk if BSC changes made after SEC commencement can address through interim guidance, with SVG & Performance Assurance Board (PAB) involvement BSC s Metering Equipment commissioning and/or audit requirements may also need amending Page 6 of 12 ELEXON 2012

Subject High-level description Type BSC CSD by Outstanding dependencies & considerations 3 Data Collector (DC) obligations: Data retrieval BSC currently says Non Half Hourly (NHH) DC responsible for retrieving metered data, and requires Supplier to ensure DC has access to Meter Will need to change for Smart Meters where Suppliers retrieve readings via DCC May also need amending for opt-out non-domestic customers (if Smart Metering System Operator (SMSO) retrieves readings) and Half Hourly elective customers (if DCC responsible for reads) For DCC-serviced Smart Meters, may no longer be necessary to appoint same NHHDC where Outstation is used for both Import and Export Mod Sections J and S BSCP504 None SEC commencement (Q2 2013) DCC Go Live / start of mass Smart Meter rollout (Q4 2014) No dependencies and straightforward / light-touch change if responsibility is passed to Supplier for Smart Meters (Suppliers already potentially acting as data retrievers for existing Smart trials) If need/want to reference SMSOs or existing (pre-smart rollout) Advanced Metering for Domestics (AMD) Meters, will be dependency on SMIP/ Registration changes Have alerted DECC to this issue and await further clarity on SEC requirements before progressing Page 7 of 12 ELEXON 2012

Subject High-level description Type BSC CSD by Outstanding dependencies & considerations 4 Ownership of Metering Data BSC currently says Supplier owns customer s metered data (although gives customer rights of data access/use) Will not be true for Smart Meters, where customer will own metered data SEC will establish data access/use rights needed for Suppliers, Distributors and authorised third parties Mod Section L None Distribution Connection and Use of System Agreement (DCUSA)? When licence changes approved (Q3 2012?) DCC Go Live / start of mass Smart Meter rollout (Q4 2014) Wording of BSC changes will depend on final licence wording Need to understand if changes will apply to non-domestic customers as well as domestic, and how BSC will capture intent of licences while retaining necessary data access for BSC arrangements (e.g. for profiling) Have alerted DECC to this issue and await further clarity before progressing As licences take precedence, believe is no urgency to progress (will confirm with DECC) Page 8 of 12 ELEXON 2012

Subject High-level description Type BSC CSD by Outstanding dependencies & considerations 5 Smart Metering Equipment Technical Specification (SMETS) & compliance with BSC s Metering Codes of Practice (CoPs) BSC currently requires Metering Equipment to comply with CoPs However, Smart Meters which comply with SMETS will not additionally need to comply with NHH CoPs Mod + CP(s) Section L BSCP514 & CoP10? MOCOPA? Following Secretary of State s designation of SMETS v2 (Q2 2013) SMETS v2 to be sent to EC in Q4 2012 (currently out for consultation) Q4 2013 (target), to capture Foundation (pre-2014- rollout) Meters BSC change straightforward mod to amend Section L to require compliance with SMETS or CoPs CSD changes need more thought intend to progress separately via CP(s) Need to find a suitable home (e.g. BSCP514, MOCOPA) for Current Transformer (CT) requirements & any other requirements which are still needed but don t relate to Metering Equipment (e.g. sealing) Need to consider what becomes of CoP10 use for elective HH and NHH CT metering? Should security requirements (e.g. 3-tier passwords) change to allow SMETS-compliant Meters to be used for elective HH? Previously highlighted to SVG in Nov 2011 (paper 129/07) Ideally, BSC/CSD changes would be made in parallel with SMETS However, would not penalise any participants for CoPs noncompliance in interim providing comply with SMETS Page 9 of 12 ELEXON 2012

Subject High-level description Type BSC CSD by Outstanding dependencies & considerations 6 MOA obligations: Meter Technical Details (MTDs) BSC currently places obligations on MOA to maintain MTDs, and to provide them to relevant HHDC or NHHDC so DC can read and process Meter data for Supplier Volume Allocation Joint BSC/MRA MTD workshops discussing how best to amend these for Smart Meters Mod + CP(s) Section S TBC may include BSCPs 504, 514, & 515 and PARMS 4 MRA Data Transfer Catalogue (DTC) Participant system changes Q4 2012 In time for SMIP s endto-end testing (mid- 2014) Participants may need 12-18 months between approval and implementation of BSCP drafting to make system changes Participants may need to complete system changes in time for SMIP s end-to-end testing in mid-2014 Proposed approach: Split into Mod and CP(s) Mod is minor self-evident change & can be progressed quickly Use existing MTD workgroup to develop/review detailed BSCP changes (including pre-consultation on options) in Sep-Oct 2012 before raising CP(s) Consult wider industry on BSCP changes under CP(s) towards end 2012 Bring CP(s) for SVG approval in Q1 2013 To speed progression, amend existing BSCPs as least-impact approach rather than create new Smart BSCP (could revisit in future if needed) Could provide guidance on where to find new Smart provisions in BSCPs Will need to align BSC and MRA DTC CPs 4 ELEXON s Performance Assurance Reporting and Monitoring System. Page 10 of 12 ELEXON 2012

Subject High-level description Type BSC CSD by Outstanding dependencies & considerations 7 Change of Supplier (CoS) MTDs/CoS workshops reviewed a potential enduring Smart CoS process, where old Supplier responsible for closing read and new Supplier responsible for opening read Would simplify data transfer processes on concurrent change of Supplier and agent(s) This change not required to support SMIP, but exploits benefits of Smart rollout Workshop receptive to possibility of such change, subject to mitigating risk of gaps/overlaps in the settled energy Ofgem has commenced a separate review of CoS process under its Smarter Markets work, and intends to issue an options/framework consultation in Q2 2013 Possible Mod + CP TBC TBC MRA TBC End 2014 Will progress minimum changes needed to make existing CoS process work for Smart (these will fall out of the other changes above) Will provide input into Ofgem s review, and any other discussions, on wider reforms to CoS process In meantime will continue to investigate industry appetite for separating old and new Supplier responsibilities for closing/opening readings (via MTD/CoS workshop preconsultation in Sep-Oct 2012), with view to implementing such a change by end 2014 Do not anticipate that any BSC changes needed to support CoS process for Foundation (pre-2014-rollout) Meters. Page 11 of 12 ELEXON 2012

Subject High-level description Type BSC CSD by Outstanding dependencies & considerations 8 Assurance SEC will include assurance regime need to ensure SEC and BSC assurance arrangements work together and that BSC obtains the necessary assurance from SEC May be potential synergies or conflicts (plus possibility of, or need for, collaborative activities) between the two codes Possible mod Section Z TBC TBC SEC commencement (Q2 2013) 2014 to align with full SEC Will keep a watching brief on discussions of following SMIP workgroups: Foundation Interim Operating Model (FIOM) workgroup Foundation Strategy Group (FSG) SEC workgroup (SMRG WG2) 9 Miscellaneous May include: Clarifying that remotely disabling Meter (i.e. disabling flows from system) doesn t equal deenergisation CPs None BSCPs MRA SEC commencement (Q2 2013) Q2 2014 (in time for DCC Smart Meter rollout) Subject to further discussion by workgroup Registration changes (Market Domain Data changes, e.g. new entities/roles, to support wider non-bsc registration changes) Reading types DC validation rules Frequency for processing readings from Smart Meters (as set out in BSCP504 4.20) Page 12 of 12 ELEXON 2012