Western Isles HVDC Link Consultation

Similar documents
Shetland HVDC Link Project. Consultation, August 2016

BAY OF SKAILL SUBSTATION - ORKNEY CAITHNESS CONNECTION

ORKNEY CAITHNESS CONNECTION

Scottish Hydro Electric Transmission Plc

PROPOSALS FOR AQUIND INTERCONNECTOR

PROPOSALS FOR AQUIND INTERCONNECTOR

Who we are. What is the difference between Transmission and Distribution? Overview of Transmission projects. Our responsibilities

East Anglia TWO and East Anglia ONE North. Summary and Approach to Site Selection

Caithness Moray HVDC Link Offshore Installation Public Engagement Event

The Kendoon to Tongland 132kV Reinforcement Project. Underground Cable Study: Our Approach

ENVIRONMENTAL ASSESSMENT (EA) PROCESS

National Grid s commitments when undertaking works in the UK. Our stakeholder, community and amenity policy

Orkney Electricity Network Reinforcement Stakeholder Consultation Response. August 2014

The offshore wind puzzle getting the pieces right

Neart na Gaoithe Offshore Wind Farm. Project Update 2018

Draft Myanmar Environmental Impact Assessment (EIA) Procedures: Comments 1 on aspects relevant to Offshore Oil and Gas Exploration and Production

Proposed Marwick Head Wave Farm Request for a Scoping Opinion December 2012

Marine Knowledge Infrastructure

Vattenfall in Norfolk

ABERDEEN HARBOUR EXPANSION PROJECT November Volume 2: Environmental Statement

An Introduction to KIS-ORCA

Falmouth Bay Short Term Test Site for Marine Energy Converters

Offshore Wind Supply Chain Opportunities with Innogy Renewables UK Ltd

Vattenfall Wind Power Ltd. Thanet Extension Offshore Wind Farm Preliminary Environmental Information Report Volume 1 Chapter 1: Introduction

Minutes of the 1 st Thematic Working Group Environment and Society of the Baltic InteGrid project

Kinsale Area Gas Fields Decommissioning Project Information Leaflet

Cable Details and Grid Connection Statement

BASELINE SURVEY, VISUAL - STANDARD

Offshore Cable Installation. November 2010 John Davies Global Marine Systems Limited

Annex C. DEA Pre-Application Meeting Records

FORT CUMBERLAND, EASTNEY, PORTSMOUTH PO4 9LD Telephone Facsimile

WHITE ROSE OILFIELD COMPREHENSIVE STUDY REPORT SUBMITTED BY:

Galloper Wind Farm Limited

Emerging Subsea Networks

Research Activities Plan. Appendix K Magnetic Fields from Submarine Cables

Marine Scotland Science: Oil and gas survey work. Peter Hayes Offshore Energy Environmental Advice Group

Founding Manifesto Friends of Floating Offshore Wind 18 May 2016

Onshore & Offshore Engineering and Management of Subsea Cables and Pipelines

AN OVERVIEW OF THE STATE OF MARINE SPATIAL PLANNING IN THE MEDITERRANEAN COUNTRIES MALTA REPORT

Westray South. SSE Renewables the offshore developer. Our core purpose is to provide the energy people need in a reliable and sustainable way.

Galloper Wind Farm Limited. Galloper Wind Farm Project Environmental Statement Chapter 1 Introduction October 2011 Document Reference 5.2.

Norfolk Vanguard & Norfolk Boreas Offshore Wind Farms. Wind Power for a Climate Smarter Future

Publishing date: 23/07/2015 Document title: We appreciate your feedback. Share this document

Commercial Fishing and Offshore Wind in Maine For more information: Josh Plourde (207) March 16, 2018

Dutch offshore wind energy policy an overview. Mark Stuurman Policy advisor

The potential for windpower in the Baltic Sea

Marine Renewable-energy Application

Post Consent Monitoring What is happening? Jim Mckie Marine Scotland, Marine Laboratory, Aberdeen

Introductory remarks

RENEWABLE ENERGY SOLUTIONS. oceaneering.com

Coastal Virginia Offshore Wind partnership with Orsted. February 2018 Update

Goal: Effective Decision Making

Empire Wind Offshore Wind Farm OCS-A 0512

EIA FOR EXPLORATION DRILLING WITHIN BLOCK ER236, OFFSHORE OF THE EAST COAST OF SOUTH AFRICA. Background Information Document. Purpose of this Document

Seagreen Wind Energy Limited C/o SSE Renewables 1 Waterloo Street Glasgow G2 6AY

Aedán Smith Head of Planning, RSPB Scotland

PORT OF POOLE DEVELOPING FOR THE FUTURE

Marine Management Organisation Marine Licence 1 Introduction

BROWSE BASIN NORTH-WEST AUSTRALIA

Non-Technical Summary of the SEA Report Draft on the Spatial Offshore Grid Plan for the German Exclusive Economic Zone of the North Sea 2016/2017


SEA CLIFFS SANDY BEACHES. The energy environment

Continuous Monitoring on the SSE Networks Transmission System

The Marine Plan for the Isle of Man. Dr Peter McEvoy Marine Spatial Planning Project Officer Isle of Man Government

Repsol E&P T&T Ltd is one of the upstream Repsol YPF Group of companies currently operating in more than 20 countries around the world.

Jørn Scharling Holm DONG Energy

The future of offshore wind in the US

Offshore Renewables Institute

Brae Area Pre Decommissioning MARATHON BRAE. Brae Area Decommissioning Programme. June Revision 1.0

Offshore Wind Risks - Issues and Mitigations

Developing the MAREMAP Toolbox to allow the Marine Renewable Energy sector to access NERC data. September 2013

RURAL ECONOMY AND CONNECTIVITY COMMITTEE SALMON FARMING IN SCOTLAND SUBMISSION FROM ANNE-MICHELLE SLATER. School of Law, University of Aberdeen

RENEWABLE ENERGY TECHNOLOGY ACCELERATOR (RETA) PROJECT

Contents: Part 1 Response to questions about the draft Marine Plans Part 2 Response to questions about the Sustainability Appraisal exercise

The South West Makes Waves In Scotland

Possible new marine Special Areas of Conservation and Special Protection Areas in Wales

Otway Gas Development Seabed Assessment and Drilling Program

Environmental Audit Committee Inquiry on 25 Year Environment Plan

SUBMARINE CABLES, RESOURCE USE, AND ENVIRONMENTAL PROTECTION. Ambassador Satya Nandan

Maritime Link Transmission Project. Qalipu Business Forum Thursday, February 28, 2013

Tidal Energy. Transmission & Distribution Network. Wind Energy. Offshore Substation. Onshore Substation. Tidal Stream Energy.

Rampion Offshore Wind Farm Meet The Buyer Event

Electromagnetic Fields emitted by High Voltage Alternating Current Offshore Wind Power Cables and interactions with marine organisms

Katherine Taaffe - Senior Manager, Network Infrastructure Assessment, OFGEM. Networking Refreshment Break

-PILOT & Industry development -Decommissioning. Audrey Banner Head of Offshore Decommissioning Unit, DECC

Guidance for UK Fire and Rescue Services. Dealing with incidents on or near National Grid high voltage overhead lines

tides waves tapping The case for marine energy Lauren Smith Jorge Seaman Siah Hwee Ang

Environmental and non-technical impacts of lean principles applied to offshore wind farms

Kingfisher Bulletin News That Saves Lives

An Overview of the Role and Work of the European Subsea Cables Association (ESCA)

Fishing Safely in UK Waters: Kingfisher Charts and FishSAFE

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES

Wind Turbine Decommissioning in the UK Offshore Zone

Bats and the Law An overview for planning, building and maintenance works

Sponsored by. Created and produced by

THE OFFSHORE PETROLEUM PRODUCTION AND PIPE-LINES (ASSESSMENT OF ENVIRONMENTAL EFFECTS) REGULATIONS 1999 (AS AMENDED) PETROLEUM OPERATIONS NOTICE No.

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS

Subsea infrastructure in MRE ICOE November 6, By Don Bryan, BSc, MBA General Manager Pacific Northwest Operations

THE FISHSAFE INFORMATION PROJECT -

Esso offshore projects

Transcription:

Western Isles HVDC Link Consultation

Western Isles HVDC Link Consultation Who we are We are Scottish and Southern Electricity Networks, operating under licence as Scottish Hydro Electric Transmission Plc for the transmission of electricity in the north of Scotland. What is the difference between Transmission and Distribution? Electricity Transmission is the transportation of electricity from generating plants to where it is required at centres of demand. The Electricity Transmission network, or grid, transports electricity at very high voltages through overhead wires, underground cables and subsea cables. The transmission network connects large scale generation, primarily renewables, to central and southern Scotland and the rest of Great Britain. It also helps secure supply by providing reliable connection to the wider network of generation plans. The Electricity Distribution network is connected into the Transmission network but the voltage is lowered by transformers at electricity substations, and the power is then distributed to homes and businesses through overhead lines or underground cables. Overview of Transmission projects In total we maintain about 5,000km of overhead lines and underground cables easily enough to stretch across the Atlantic from John O Groats all the way to Boston in the USA. Our network crosses some of the UK s most challenging terrain including circuits that are buried under the seabed, are located over 750m above sea level and up to 250km long. The landscape and environment that contribute to the challenges we face also give the area a rich resource for renewable energy generation. There is a high demand to connect from new wind, hydro and marine generators which rely on Scottish and Southern Electricity Networks to provide a physical link between the new sources of power and electricity users. Scottish and Southern Electricity Networks is delivering a major programme of investment to ensure that the network is ready to meet the needs of our customers in the future. Our responsibilities We have a licence for the transmission of electricity in the north of Scotland and we are closely regulated by the energy regulator Ofgem. Our licence stipulates that we must develop and maintain an efficient, co-ordinated and economical system of electricity transmission. 02

Welcome Welcome to this statutory pre-application consultation event in relation to Scottish Hydro Electric Transmission plc (SHE Transmission) upcoming plans to submit a Marine Licence application to Scottish Ministers for the subsea element of their proposed Western Isles Connection (the Project) between Arnish and Dundonnell. The exhibition provides: Project Need SHE Transmission, as part of a much larger project, is proposing to construct and commission a subsea High Voltage Direct Current (HVDC) Link, which will be approximately 81km in length and with a capacity of 600MW between Arnish and Dundonnell. Project Overview Project Timeline Subsea Route Selection Subsea Routing Considerations Landfall Locations The Consenting Process Project Need At present the existing Western Isles system operates with a restricted 132kV connection to the Scottish mainland. The Western Isles possess attractive renewable resources which have been targeted by developers seeking to invest in onshore wind and marine generation projects. On Lewis and Harris today, a total of 380MW of generation is either connected or contracted to connect in the future. There are further interests from Developers of renewable energy projects in excess of 200MW; a mix of onshore wind, pump storage hydro and solar energy projects. Map 1: Proposed Western Isles Connection There is no spare capacity on the existing Western Isles network to connect additional generation. As a consequence, a higher capacity link to the Scottish mainland is proposed to facilitate export into the Great Britain Main Interconnected Transmission System (GB MITS). SHE Transmission has detailed plans to construct a 158km 600MW HVDC link of which 81km are subsea and 77km are underground cable between Beauly on the Scottish mainland (located North West of Inverness) and Arnish on the east coast of the Isle of Lewis via Dundonnell on the west coast of Scotland. Image: Example of Cable float in Western Isles HVDC Link Consultation 03

Western Isles HVDC Link Consultation Project Overview As the HVDC cable leaves land and enters the sea, it will either be routed via ducts that are created using a Horizontal Directional Drill or through a traditionally excavated trench. Once offshore the HVDC cable will be buried. If the sub sea cable cannot be buried it will be protected by alternative methods, for example High Density Polyethylene (HDPE) duct or rock placement. In addition to the subsea HVDC cables, the other key elements of the Western Isles HVDC Link include: HVDC Converter station at Beauly and associated Civil works HVDC Converter station at Arnish and associated Civil works AC Substation at Arnish 77km of underground land cable from Dundonnell to Beauly Proposed marine works The subsea cable installation comprises: Pre-lay survey Boulder clearance Cable trenching Cable laying Cable burial Rock placement (where required) Concrete mattressing (where required) Armour cable (where required) Post installation surveys Existing Network Convertor Station & Underground Cable Subsea Cable Convertor Station & Underground Cable Existing Network Arnish Sub Station 81km Sub Sea 77km Underground Cable Beauly Sub Station AC Electricity HVDC Electricity AC Electricity 04

Project Timeline Nov 17 Submission of report to Marine Scotland to ensure agreement of topics to be included in the supporting environmental information. Statutory consultation undertaken by Marine Scotland as part of this process. Sept 17 Mar 18 Preparation of Environmental Report to support the Marine Licence and Marine Works applications. 2018 Feb: Receipt of scoping opinion report from Marine Scotland to confirm the requirements for the Environmental Report. Mar: Pre-Application Consultation with the public on the preferred cable route corridor. Mar: Consider and reflect on feedback from the consultation on the content of the Environmental Report. Apr: Submission of Marine Licence application to Marine Scotland and Marine Works applications to Stornoway Port Authority. Apr/May: Statutory Consultation Marine Scotland will undertake statutory consultation following submission during which representations can be made directly to the relevant authority. July/Aug: Determination of the Marine Licence and Marine Works applications. 2020 Subject to consents, commencement of construction works. 2023 Completion of construction works. Western Isles HVDC Link Consultation 05

Western Isles HVDC Link Consultation Subsea Route Selection SHE Transmission have developed the subsea cable route in a manner which balances economic, technical and environmental considerations, a route which is economically viable, technically feasible and capable of being granted consent. Economic How the HVDC cable is installed and the route it takes are key factors informing the cost of the Western Isles HVDC Link. A straight-line route theoretically presents the cheapest option; however, the technical challenges and costs of transitioning the cable across multiple seabed and land features would mean that this is not a viable solution. SHE Transmission s preferred installation method for HVDC subsea cables is to bury them on the seabed. This method is the most common installation technique and is a proven method for protecting cables. In areas with thin sediment cover, or additional sea bed constraint, alternative means of protecting the cable on the seabed will be necessary. Covering cables with concrete mattressing is possible; however, due to the precise design requirements it is deemed to be relatively expensive, unsuitable for extensive lengths and subsequent maintenance of the cable can be complex. SHE Transmission is also considering placement of rocks to cover the cable. The placement is more economically efficient than installation of concrete mattresses and provides a high degree of protection. The final technique being considered, especially in sensitive marine habitats, is cable armouring where cables will be encased in a polymer casing and laid on the seabed. This option is costly; however, it reduces the requirement for burying, rock placement or laying of concrete mattresses. Environmental SHE Transmission recognise that a major infrastructure project like the Western Isles HVDC Link can impact the environment, therefore careful design and planning is required at every stage. Through careful evaluation, SHE Transmission will deliver effective protection measures within sensitive areas. A key example includes how the Wester Ross Marine Protected Area (MPA) will be protected. SHE Transmission has considered the physical disturbance to the designated habitats within the MPA, changes in temperature in the immediate vicinity of the cable and effects of smothering communities on the seabed. Given the available information, SHE Transmission intends using cable armouring in this area to minimise the impact on this sensitive marine environment. Additionally, the cable route has been moved slightly to the north to avoid the Shiant Banks Marine Protected Area (MPA). SHE Transmission is looking at all options of cable protection along different sections of the cable route. Final decisions will be taken once detailed engineering design studies have been completed. It is recognised that the sea area through which the proposed cable route passes is considered important for a variety of commercial fisheries activities, including shellfish (e.g. nephrops and scallop) and aquaculture. SHE Transmission is working with the relevant fishing organisations to ensure that possible disruption to fishermen operating in these areas is limited as far as practical. Technical There is a wide range of technical considerations; from cable size and capacity; connection to existing transmission infrastructure; to the method of installation which inform the routing process, with associated economic and environmental implications. Technical considerations include cable installation and protection methods, which are more achievable in softer sediment. Avoidance of undulating seabed topography is preferred to minimise the possibility of free spans, where the cable is suspended above the seabed, which can lead to seabed scouring. It is also necessary to take account of the access to existing infrastructure at either end of the cable route. Map 2: Environmental designations along the proposed cable route. 06

Subsea Routing Considerations Route options Determining the most appropriate route for the HVDC cable has involved consideration of several options. Following determination of the most efficient points to connect to the existing transmission infrastructure on Lewis and the Scottish mainland, the focus of our investigation centred on the area between Arnish on Lewis and Dundonnell in Wester Ross. Overall four routes between Lewis and Wester Ross have been considered during the development process: 1. A northern route connecting Arnish to Dundonnell via Little Loch Broom (proposed option to be taken forward) 2. A southern subsea route connecting Arnish to Dundonnell via Little Loch Broom (discounted due to proximity to Shiant Banks MPA) 3. A route connecting Arnish to Mungasdale via the east of Gruinard Island, thus avoiding Little Loch Broom (discounted due to presence of maerl) 4. A route connecting Arnish with Mungasdale via the west of Gruinard Island, thus avoiding Little Loch Broom (discounted due to the presence of maerl) 5. Straight line route connecting Arnish to Dundonnell via Little Loch Broom. Sensitivity of Receptors Receptors could be considered as any aspect of the environment, both human and non-human which may be impacted upon (positively or negatively). Completion of a range of technical studies help us to establish what the most sensitive receptors are within the area, the likely impacts they may experience during the installation phases of the project and the extent of these impacts. Examples of the likely receptors which could be impacted upon include, but are not limited to: Seabed habitats and associated organisms Marine mammals Commercial fisheries and aquaculture Shipping and navigation Impacts on receptors and the most effective means of mitigation have been taken into consideration when selecting the most appropriate route for the subsea cable. Determining Suitability Defining the route that is best economically, most technically achievable and with the least environmental impacts has been done by considering the constraints associated with each. To understand these constraints, marine surveys have been undertaken to map the seafloor to provide a detailed understanding of the geology, seabed sediments and the flora and fauna it supports. This information has been combined with data on other marine factors including fishing, shipping and the suitability of the seabed sediments for cable burial. Map 3: Bathymetry along the proposed cable route. The combination of this information enables the development of the preferred subsea cable route. Map 4: Proposed cable routes Western Isles HVDC Link Consultation 07

Western Isles HVDC Link Consultation Landfall Locations - Dundonnell Key Considerations and Challenges The criteria used to identify a possible landfall location were: Geology of seabed and coastline Proximity to existing electrical infrastructure Suitability of near shore seabed conditions Level of any commercial fisheries activities Presence of areas of cultural heritage Presence of ecological features Current use of the landfall location and surrounding areas Ease of construction and operation Any anticipated licensing obstacles Dundonnell The proposed landfall location at Dundonnell has been selected, balancing a range of cost, technical and environmental factors. A key influence in determining this landfall was the proximity to the road network allowing for the cable to be undergrounded along the existing road from Dundonnell to the proposed converter station at Beauly, Inverness-shire. 08

Landfall Locations - Lewis Key Considerations and Challenges The criteria used to identify a possible landfall location were: Geology of seabed and coastline Proximity to existing electrical infrastructure Suitability of near shore seabed conditions Level of any commercial fisheries activities Presence of areas of cultural heritage Presence of ecological features Current use of the landfall location and surrounding areas Ease of construction and operation Any anticipated licensing obstacles Arnish The proposed landfall location at Arnish has been selected, balancing a range of cost, technical and environmental factors. A key factor in determining this landfall was the proximity to the wider electrical network and the location of the windfarm projects seeking connection to the grid. Western Isles HVDC Link Consultation 09

Western Isles HVDC Link Consultation The Consulting Process SHE Transmission will require a Marine Licence from the Scottish Government as well as a Marine Works Licence from the Stornoway Port Authority. As part of the licence application procedure, SHE Transmission is preparing supporting environmental information which will describe the characteristics of the project and provide information on the possible environmental effects of the connection and how they will be managed. When completed this information will be available on the projects dedicated webpage www.ssentransmission.co.uk/projects/western-isles. The licensing procedures also require SHE Transmission to consult on its proposals. This exhibition forms part of the consultation process. Scoping of the project has been undertaken with Marine Scotland. This ensures that focused and proportionate environmental information is produced to accompany the application, which addresses the specific requirements and potential effects. Following advice from Marine Scotland (and consultees), the possible effects of the installation and operation of the subsea cable will be considered along with the possibility for cumulative effects where there is potential for effects to overlap with other marine and coastal developments. The following topics will be covered as part of the supporting environmental information: Designated sites Benthic ecology Marine mammals Commercial fisheries and aquaculture Shipping and navigation Community Liaison Manager Lisa Marchi-Grey Information lisa.marchi@sse.com 07825 015 507 Lisa Marchi-Grey Scottish and Southern Electricity Networks, 10 Henderson Road, Inverness, IV1 1SN www.ssen-transmission.co.uk/projects western-isles Information will also be made available via the project web page and social media channels: Project Website: Find us on Facebook: SSEN Community Follow us on Twitter: @ssencommunity Comments made are not representations to the Scottish Ministers. If SHE Transmission plc submits an application for a marine licence to Scottish Ministers, an opportunity will be given for representations to be made to the Scottish Ministers on the application. 10

Your comments We are keen to receive your views and comments in regards to the following questions: Please complete in BLOCK CAPITALS. (Please tick one box per question only) Q1 Do you understand the need for the Western Isles HVDC Link project? Yes No Unsure Q2 Has the consultation information been clear and easy to understand? Yes No Unsure Q3 Do you have any comment on how the subsea cable route and landfall locations have been selected? Comment Q4 Do you understand the consenting process that SHE Transmission will follow for the Western Isles HVDC Link? Yes No Unsure Q5 Do you have comments on the proposed scope of the additional environmental information being prepared to accompany the marine licence application? Comments Western Isles HVDC Link Consultation 11

Q6 Do you have any other comments that SHE Transmission should consider as it progresses the Western Isles HVDC Link? Comments Please write in any further comments you would like to make about the engagement process as a whole. Full name Address Postcode Telephone Email If you would like to be kept informed of progress on the project please tick this box. If you would like your comments to remain anonymous please tick this box. Thank you for taking the time to complete this feedback form. Please hand your completed form in at the event or alternatively by one of the methods below: Post: Lisa Marchi-Grey, Scottish and Southern Electricity Networks, 10 Henderson Road, Inverness, IV1 1SN Email: lisa.marchi@sse.com Closing date for feedback is 16:00, Friday 30th March 2018 The feedback form and all information provided at the event can also be downloaded from the dedicated website: Any information given on the feedback form can be used and published anonymously as part of Scottish and Southern Electricity Networks consultation report. By completing this feedback form you consent to Scottish and Southern Electricity Networks using feedback for this purpose.