ELECTRIC TRANSMISSION (ET) Guideline G0104

Similar documents
Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Module 10. Initiation Code RELIABILITY ACCOUNTABILITY

GridLiance Reliability Criteria

A New Use for Fault Indicators SEL Revolutionizes Distribution System Protection. Steve T. Watt, Shankar V. Achanta, and Peter Selejan

Notes 1: Introduction to Distribution Systems

E N G I N E E R I N G M A N U A L

Transmission Availability Data Systems Frequently Asked Questions

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

I WP Asset # I ~:2 3. I Review Annual. ~c~~ Date: 'l/j(j/! ZL>IJ,...

Arc Flash Analysis Training

Transmission Interconnection Requirements for Inverter-Based Generation

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

EH27401 Communication and Control in Electric Power Systems Lecture 2. Lars Nordström

Module 9. Fault Type Form 4.X RELIABILITY ACCOUNTABILITY

BED INTERCONNECTION TECHNICAL REQUIREMENTS

SWITCHING SAFETY & RELIABILITY CONFERENCE

Generation Interconnection Requirements at Voltages 34.5 kv and Below

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0

HOOSIER ENERGY REC, INC. Requirements for Connection of Non Generation Facilities

Customer Requirements RF Antenna Installations

Table of Contents. Introduction... 1

VACUUM INTERRUPTER APPLICATION NOTES Filename: VIAN X-Rays and Vacuum Interrupters Revision: 0 PAGE 1

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

Module 11a. Initiating Cause Code Form 4.X RELIABILITY ACCOUNTABILITY

Wind Power Facility Technical Requirements CHANGE HISTORY

NOVEL PROTECTION SYSTEMS FOR ARC FURNACE TRANSFORMERS

Fault Locating at Pacific Gas and Electric Company

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning

University of Central Florida Main Campus. Electric. Service and Meter Installations Requirements. Issued January 26 th, 2017.

SUBJECT HEADING: Switching Programmes ISSUE: 18

Transmission Availability Data System Definitions

Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering

Overvoltage Protection

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section SCADA Technical and Operating Requirements

FACILITY CONNECTION REQUIREMENTS

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

POWER QUALITY A N D Y O U R B U S I N E S S THE CENTRE FOR ENERGY ADVANCEMENT THROUGH TECHNOLOGICAL I NNOVATION

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS

Electricity Networks Access Code 2004 Services Standard Performance Report for the year ended 30 June September 2018

Technical Requirements For Generation Connected to The ODEC System

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

ESB National Grid Transmission Planning Criteria

60 kv to 500 kv Technical Interconnection Requirements For Power Generators

EH2741 Communication and Control in Electric Power Systems Lecture 2

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T-18

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS

Single Line Diagram of Substations

Technical Interconnection Requirements For Transmission Voltage Customers for Service at 60,000 to 287,000 Volts R XX

Voltage and Reactive Procedures CMP-VAR-01

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. April 2009 Version 2

Earthing of Electrical Devices and Safety

Southern Company Interconnection Requirements for Inverter-Based Generation

OPERATING PROCEDURE. Table of Contents

Section 16621A - AUTOMATIC TRANSFER SWITCH. Part 1 General

Fault Localization using Wavelet Transforms in 132kV Transmission Lines

6B.6 Substation Grounding

This section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor.

The Many Uses of Transmission Line Arresters

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Utility Interconnection and System Protection

MANITOBA HYDRO TRANSMISSION SYSTEM INTERCONNECTION REQUIREMENTS. July 2016 Version 4

No. SSIEC-PRC SHINSUNG. Polymer Recloser SIREC SERIES 15kV, 27kV, 38kV 400A, 630A, 800A

Generation and Load Interconnection Standard

Generation and Load Interconnection Standard

II Design Criteria for Electrical Facilities Connected to the PJM 765 kv, 500 kv, 345 kv, 230 kv, 138 kv, 115 kv, & 69 kv Transmission Systems

Arizona Public Service Company and the Transmission Partnership for National Electric Power Company of Jordan

Modern transformer relays include a comprehensive set of protective elements to protect transformers from faults and abnormal operating conditions

Unit 2. Single Line Diagram of Substations

MV ELECTRICAL TRANSMISSION DESIGN AND CONSTRUCTION STANDARD. PART 1: GENERAL 1.01 Transformer

Company Directive POLICY DOCUMENT: SD4/7. Relating to 11kV and 6.6kV System Design

THE STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION PREPARED TESTIMONY OF RUSSEL D. JOHNSON

Education & Training

INTRODUCTION. General Design Criteria o (include charts from Section 2 of TSS) Functional Criteria o (from TSS section 3) Accessibility and Layout

Embedded Generation Connection Application Form

Electrical Equipment Condition Assessment

Guide and Requirements for Service. at 69,000 to 287,000 Volts R 0.2

Information and Technical Requirements For the Interconnection of Distributed Energy Resources (DER)

GUIDE FOR GENERATOR INTERCONNECTION THE WIRES OWNER DISTRIBUTION SYSTEM

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 7T-30A. NORTH COAST INTERCONNECTION: SKEENA BOB QUINN SUBSYSTEM Supersedes OO 7T-30A dated 07 July 2014

PREFACE ********************************************************** IT IS NOT INTENDED THAT THESE STANDARDS BE COPIED AND USED AS A SPECIFICATION!

City of San José, California CITY COUNCIL POLICY

Rajasthan Technical University, Kota

Dairyland Power Cooperative June Transmission to Transmission (T-T) Interconnection Guidelines

The Connecticut Light and Power Company

Distribution/Substation Transformer

Bulk Electric System Definition Reference Document

Sub Regional RTEP Committee Mid-Atlantic - PSEG Solution Meeting

GREAT RIVER ENERGY GREAT RIVER ENERGY GENERATION INTERCONNECTION GUIDELINES. Revision 4

Field Instruction. Induced voltages can occur in overhead lines, underground cables, or in switchyards.

Voltage Sags Evaluating Methods, Power Quality and Voltage Sags Assessment regarding Voltage Dip Immunity of Equipment

TN, TT & IT Earthing Arrangements

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

Transmission to Distribution/ End-User Interconnection Guidelines for the Dairyland Power Cooperative Transmission System

First Draft Language

Great Northern Transmission Line: Behind the (Electrical) Design

Transcription:

ELECTRIC TRANSMISSION (ET) ISSUING DEPARTMENT: ETM x ETEC ETPO ETTS EFFECTIVE DATE: 06-01-1997 DEPARTMENTS AFFECTED: ETM ETEC ETPO x ETTS REVIEW DATE: 01-01-1998 DEPARTMENT GROUP: ALL All All x All P E PL T L C TOC S SCO U EMS TOPIC: PAGE NO.: 1 of 5 TITLE: Purpose The purpose of this guideline is to: (1) ensure service availability can be maintained to singletapped customers, (2) ensure system-wide consistency in the installation of selector switches on transmission lines, and (3) provide a clear understanding of the associated cost responsibilities wherever transmission lines are single-tapped. Implementation The Managers of Transmission Planning and System Operation are responsible for approving, revising, and distributing this guideline. Definition of Selector Switches Line Selector Switches are installed on one or both sides of a single-tap in order to provide operational flexibility in providing service to customers on the tap line. Selector switches are operated to avoid customer outages for planned maintenance in the main line and to restore service in the case of an unplanned interruption of the main line (see Figure 1). Selector switches do not reduce the number of outages to the customer, but they do provide a relatively inexpensive way of reducing the duration of a sustained outage [1] to the customer by allowing the transmission line to be sectionalized. Selector switches cannot reduce the frequency of maintenance or unplanned outages on the single-tap line to the customer. Applicability Effective immediately, selector switches are a standard service requirement for all new singletap interconnections to PG&E s transmission system. This is applicable where a single-tap configuration is to be used to interconnect a new load or generation customer to a PG&E-owned transmission line (60 kv and above) or when a change in service is requested by an existing load or generation customer. This guideline will also be incorporated into PG&E s transmission interconnection requirements. At PG&E s discretion, a selector switch may not be required should the distance from the new single-tap interconnection to either end of the transmission line or to an existing selector switch on the line be approximately one mile or less, and have minimal exposure to causes of outages trees, traffic, etc.). Refer to Attachment 1 for a list of criteria in determining the need for selector switches. [1] A sustained outage is an outage to a customer extending more than two minutes.

PAGE NO.: 2 of 5 Single-Tap Configuration For standard transmission tap interconnection to a customer-owned substation, a single-tap is provided from the most feasible transmission line to the customer s facility. With standard service, the customer will experience interruptions to their facility during a transmission line outage unless the customer has adequate on-site back-up generation. The installation of selector switches reduces the duration of a sustained outage, but it does not eliminate momentary outages to a customer. For a sustained outage on the transmission line, service to the customer will be interrupted for the duration of time [2] it takes PG&E to open the appropriate selector switch to isolate the faulted line section and close the breaker on the nonfaulted line section. As an example, for a sustained outage between Station B and the tap point, selector switch B would be opened to isolate the problem and service to the customer would be restored by closing the circuit breaker at Station A. Station "A" Selector Sw itch (Normally Closed) Selector Switch "B" (Normally Closed) Station "B" A B Tap Point REVENUE METER Customer Transformer Figure 1. Typical Single-Tap Configuration with Selector Switches Ownership & Accessibility PG&E shall own, operate and maintain all selector switches in the system to serve customerowned substations or customer load. PG&E s personnel must be able to access all selector switches installation 24 hours a day. [2] Duration of time refers to the time it takes a PG&E operator to manually operate the selector switches from the time PG&E was notified of an outage. This time could vary from about a half hour to several hours depending on the nature of the outage. Should the outage be such that the customer could be energized from one end of the transmission line, the appropriate selector switch would be opened.

PAGE NO.: 3 of 5 Cost for New Single-Tap Interconnections [3] Effective immediately, with the exception allowed in Attachment 1, line selector switches are a PG&E requirement for all new single-tap interconnections to the transmission system as a means of providing adequate level of service availability. In accordance with PG&E s electric tariff, if line selector switches are considered special facilities, then the installation cost of the switches will be determined by the application of Electric Rules 2, 15 and 16 as appropriate [4]. For existing single-tap interconnections, refer to Attachment 2 for the need and installation cost responsibilities for line selector switches. Selector Switches Capability PG&E will determine on a case-by-case basis whether selector switches should be capable of line dropping and/or loop splitting and would specify the capabilities of the selector switches and any associated interrupting devices. PG&E will identify locations with access difficulties, such as mountainous terrain, and may recommend that the selector switches be motor operated and remotely controlled. Selector Switches Installation Selector switches must be located in close proximity (within one pole or tower structure) on either side of the single-tap on the transmission line. All structures used for mounting the selector switches will be determined and designed by PG&E. PETER Q. LAI Manager, Transmission Planning ROD J. MASLOWSKI Manager, System Operation References: Electric Rule 2 (Description of Service) Electric Rule 15 (Line Extensions) Electric Rule 16 (Service Extensions) PG&E Interconnection Handbook ET Standard ET-SL-S012 (115 kv Pole-Mount Switches) [3] New Single-Tap Interconnections: A customer requesting PG&E s service who is not currently interconnected to PG&E s transmission system. [4] With the unbundling of electric and transmission services starting in January 1998, the cost responsibilities may need to be revised at that time.

PAGE NO.: 4 of 5 ATTACHMENT 1 Criteria for Determining When One Or No Selector Switch Is Required Radial Transmission Line At PG&E s discretion, only one selector switch may be required on the non-source side of the tapped transmission line. When One Selector Switch Is Sufficient At PG&E s discretion, PG&E may elect to install only one selector switch on one side of the single-tap providing the line section without the selector switch is (a) approximately one mile or less from the tap point to the end of the transmission line and has minimal exposure to causes of outages (trees, traffic, etc.) or (b) approximately one mile or less from the interconnection tap point of another customer with line selector switches and has minimal exposure to causes of outages. When No Selector Switches Are Required At PG&E s discretion, selector switches may not be required on the transmission line if the distances on either side of the tap to the ends of the transmission line or other selector switches on the line are approximately one mile or less and has minimal exposure to causes of outages. Criteria for Determining When Selector Switches Are Required Length of Transmission Line Long transmission lines have more exposure and have a greater frequency of being forced out of service for maintenance. Long lines are also at greater risk of experiencing sustained faults due to increased exposure to adverse elements. Location and Route of Transmission Line Geographic and environmental conditions affect the total exposure of the line to adverse elements. For example, transmission lines that traverse mountainous areas are subject to greater number of outages due to exposure to trees and inclement weather. Multiple Customers on Transmission Line At PG&E s discretion, PG&E may require selector switches on a transmission line where multiple customers are tapped as a means of maintaining service availability.

ATTACHMENT 2 PAGE NO.: 5 of 5 Need and Installation Cost for Existing Single-Tap Interconnections This guideline is not intended for retroactive application to existing single-tap interconnections; however, the installation of line selector switches on existing single-tap interconnections will be considered on a case-by-case basis based on the following: 1. Existing Single-Tap Customer s Request for Selector Switches When an existing single-tap customer requests selector switches as a means of minimizing down time to his/her facility, then the selector switches will be treated as special facilities and paid for by the customer in accordance with Electric Rule 2 -- Description of Service. 2. PG&E Determines When Selector Switches Are Necessary When line selector switches are determined by PG&E to be needed for system benefits, the installed cost of the selector switches will be borne by PG&E. System benefits include but are not limited to: (a) minimizing sustained outages to multiple customers on a single-tap line, (b) avoiding difficult clearance coordination with multiple customers. Note: On existing single-tap interconnections, should the need for selector switches be identified, then the criteria outlined in Attachment 1 also applies.