Agenda Notes for 4 th Meeting of Sub Group in respect of Preparation of Reliability Standards for Protection System and Communication System

Similar documents
(Circuits Subject to Requirements R1 R5) Generator Owner with load-responsive phase protection systems as described in

Standard Development Timeline

Determination of Practical Transmission Relaying Loadability Settings Implementation Guidance for PRC System Protection and Control Subcommittee

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

1

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

Protection System Review Program

Standard Development Timeline

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

Transmission Line Protection Objective. General knowledge and familiarity with transmission protection schemes

Summary of Relaying Reviews Reporting

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell

Transmission Protection Overview

Standard Development Timeline

Final ballot January BOT adoption February 2015

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Introduction. Disclaimer

4.2.1 Generators Transformers Transmission lines. 5. Background:

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

ESB National Grid Transmission Planning Criteria

Relay Loadability Exceptions

Transmission System Phase Backup Protection

PROTECTION SIGNALLING

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

Effect of Series Capacitor on Line Protection - A Case Study

Implementation Plan Project Modifications to PRC Reliability Standard PRC-025-2

Modern transformer relays include a comprehensive set of protective elements to protect transformers from faults and abnormal operating conditions

An Example Distance Protection Application with Complicating Factors.

Standard PRC Coordination of Generating Unit or Plant Voltage Regulating Controls with Generating Unit or Plant Capabilities and Protection

PROTECTION of electricity distribution networks

Power Plant and Transmission System Protection Coordination of-field (40) and Out-of. of-step Protection (78)

This webinar brought to you by the Relion product family Advanced protection and control IEDs from ABB

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Communication Aided Tripping. Common Methods, Schemes and Considerations

Switch-on-to-Fault Schemes in the Context of Line Relay Loadability

CONTENTS. 1. Introduction Generating Stations 9 40

FACILITY RATINGS METHOD TABLE OF CONTENTS

System Protection and Control Seminar

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

Industry Webinar Draft Standard

System Protection and Control Subcommittee

NORMES DE FIABILITÉ DE LA NERC (VERSION ANGLAISE)

MODEL POWER SYSTEM TESTING GUIDE October 25, 2006

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

TABLE OF CONTENT

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies

VAR Voltage and Reactive Control

A. Introduction. VAR Voltage and Reactive Control

Power Plant and Transmission System Protection Coordination

Fixed Series Compensation

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

Power Plant and Transmission System Protection Coordination

Wind Power Facility Technical Requirements CHANGE HISTORY

Line Protection Roy Moxley Siemens USA

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition

Setting and Verification of Generation Protection to Meet NERC Reliability Standards

Power System Stability. Course Notes PART-1

VAR Voltage and Reactive Control. A. Introduction

OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS

Protection Challenges for Transmission Lines with Long Taps

RELAY LOADABILITY CHALLENGES EXPERIENCED IN LONG LINES. Authors: Seunghwa Lee P.E., SynchroGrid, College Station, Texas 77845

NERC Protection Coordination Webinar Series June 30, Dr. Murty V.V.S. Yalla

System Operating Limit Definition and Exceedance Clarification

Table of Contents. Introduction... 1

3Ø Short-Circuit Calculations

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network

Power System Protection Where Are We Today?

Power System Fundamentals

AUTOMATIC CALCULATION OF RELAY SETTINGS FOR A BLOCKING PILOT SCHEME

Overcurrent and Overload Protection of AC Machines and Power Transformers

(2) New Standard IEEE P (3) Core : (4) Windings :

Distance Element Performance Under Conditions of CT Saturation

MidAmerican Energy Company 69 kv Facility Ratings Methodology

May 30, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme Docket No. RM15-13-_

Table of Contents. 1 Introduction. 2 System-Level Electrostatic Discharge (ESD) and Electrical Fast Transient (EFT) 3 Electromagnetic Interference

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

COPYRIGHTED MATERIAL. Index

ENHANCING THE PERFORMANCE OF DISTANCE PROTECTION RELAYS UNDER PRACTICAL OPERATING CONDITIONS

System Protection and Control Subcommittee

EE402-Protection and Switchgear Dept. of EEE

Standard PRC Coordination of Generating Unit or Plant Capabilities, Voltage Regulating Controls, and Protection

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

Short Circuit Current Calculations

Alberta Interconnected Electric System Protection Standard

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

September 19, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme

Estimation of Fault Resistance from Fault Recording Data. Daniel Wong & Michael Tong 2014-November-5

ADDENDUM NO. 2 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030

each time the Frequency is above 51Hz. Continuous operation is required

USING SUPERIMPOSED PRINCIPLES (DELTA) IN PROTECTION TECHNIQUES IN AN INCREASINGLY CHALLENGING POWER NETWORK

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

Considerations for Power Plant and Transmission System Protection Coordination

NERC Protection Coordination Webinar Series July 15, Jon Gardell

August 25, Please contact the undersigned if you have any questions concerning this filing.

Standard MOD Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions

Standard VAR Voltage and Reactive Control

Transcription:

Agenda Notes for 4 th Meeting of Sub Group in respect of Preparation of Reliability Standards for Protection System and Communication System Meeting Date: 27.03.2017 Time: 1430 Hrs Venue: NRPC Conference Hall, 2 nd Floor, NRPC, Katwaria Sarai, New Delhi 1. Confirmation of MoM of 3 rd Meeting of Sub Group The Minutes of the 3 rd Meeting of Subgroup (Annexure-A) held on 20 th January 2017 was circulated vide letter No. 3/NRCE/NPC/CEA/2017/158-164 dated 14 th February 2017. No Comments were received form Members. 2. The draft material (Annexure-B) on the following items is put up for deliberation in 4 th Meeting of the Subgroup. Special Protection System Review Procedure Transmission Relay Loadability

8.0 Special Protection System Review Procedure (1). Definition: A documented SPS review procedure to ensure that SPSs comply with Regional criteria and various Standards and Regulations. (2). Objective: 1. To ensure that all Special Protection Systems (SPS) are properly designed, meet performance requirements, and are coordinated with other protection systems. 2. To ensure that maintenance and testing programs are developed and misoperations are analyzed and corrected. (3). Requirements: 1. Each RPC that uses or is planning to use an SPS shall have a documented SPS review procedure to ensure that SPSs comply with Regional criteria and various Standards and Regulations. The Regional SPS review procedure shall include: 1.1. Description of the process for submitting a proposed SPS for RPC review. 1.2. Requirements to provide data that describes design, operation, and modeling of an SPS. 1.3. Requirements to demonstrate that the SPS shall be designed so that a single SPS component failure, when the SPS was intended to operate, does not prevent the interconnected transmission system from meeting the requirements Central Electricity Authority (Grid Standards) Regulations. 1.4. Requirements to demonstrate that the inadvertent operation of an SPS shall meet the requirement of CEA s Transmission Planning Criterion as that required of the contingency for which it was designed. 1.5. Requirements to demonstrate the proposed SPS will coordinate with other protection and control systems and applicable emergency procedures. 1.6. Definition of misoperation (In consistent with the definition mentioned in the item of these standards Monitoring of Special Protection System (SPS) Misoperation ). 1.7. Requirements for analysis and documentation of corrective action plans for all SPS misoperations. 1.8. Identification of the Subgroup at the regional level responsible for the SPS review procedure and the process for approval of the procedure. 1.9. Determination, as appropriate, of maintenance and testing requirements. 2. The RPC shall provide other RPCs and CEA/NLDC with documentation of its SPS review procedure on request (within 30 calendar days). (4). Measures 1. The RPC using or planning to use an SPS shall have a documented review procedure as defined in Requirement 1. 2. The RPC shall have evidence it provided other RPCs and CEA/NLDC with documentation of its SPS review procedure on request (within 30 calendar days).

9.0 Transmission Relay Loadability (1). Definition: Transmission Relay Loadability means the loading permitted in the transmission line by the relay including a security margin. The relay Loadability is to be arrived in such a way not interfere with system operator actions, while allowing for short-term overloads, with sufficient margin to allow for inaccuracies in the relays and instrument transformers. Transmission relay do not prematurely trip the transmission elements out-of-service and allow the system operators from taking controlled actions consciously to alleviate the overload. (2). Objective: Protective relay settings shall 1. Not limit transmission loadability; 2. Not interfere with system operators ability to take remedial action to protect system reliability and; 3. Be set to reliably detect all fault conditions and protect the electrical network from these faults. 4. This standard includes any protective functions which could trip with or without time delay, on load current i.e. load responsive phase protection systems including but not limited to: i. Phase distance. ii. Out-of-step tripping. iii. Switch-on-to-fault. iv. Overcurrent relays. v. Communications aided protection schemes including but not limited to: Permissive overreach transfer trip (POTT). Permissive under-reach transfer trip (PUTT). Directional comparison blocking (DCB). Directional comparison unblocking (DCUB). vi. Phase overcurrent supervisory elements (i.e., phase fault detectors) associated with current based, communication-assisted schemes (i.e., pilot wire, phase comparison, and line current differential) where the scheme is capable of tripping for loss of communications. 5. The following protection systems are excluded from requirements of this standard: i. Relay elements that are only enabled when other relays or associated systems fail. For example: Overcurrent elements that are only enabled during loss of potential conditions. Elements that are only enabled during a loss of communications except as noted in section 4 (vi) ii. Protection systems intended for the detection of ground fault conditions. iii. Protection systems intended for protection during stable power swings. iv. Relay elements used only for Special Protection Systems. v. Protection systems that are designed only to respond in time periods which allow 15 minutes or greater to respond to overload conditions.

vi. vii. viii. Thermal emulation relays which are used in conjunction with dynamic Facility Ratings. Relay elements associated with dc lines. Relay elements associated with dc converter transformers. (3). Requirements: 1. Each Transmission Licensee, Generator Company, or Distribution Licensee shall use any one of the following criteria for any specific circuit terminal to prevent its phase protective relay settings from limiting transmission system loadability while maintaining reliable protection of the Grid for all fault conditions. Each Transmission Licensee, Generator Company, or Distribution Licensee shall evaluate relay loadability at 0.85 per unit voltage and a power factor angle of 30 degrees. Criteria: i.set transmission line relays so they do not operate at or below 150% of the highest seasonal rating of a circuit, for the available defined loading duration nearest 4 hours (expressed in amperes). ii.set transmission line relays so they do not operate at or below 115% of the maximum theoretical power transfer capability (using a 90-degree angle between the sending-end and receiving-end voltages and either reactance or complex impedance) of the circuit (expressed in amperes) using one of the following to perform the power transfer calculation: An infinite source (zero source impedance) with a 1.00 per unit bus voltage at each end of the line. An impedance at each end of the line, which reflects the actual system source impedance with a 1.05 per unit voltage behind each source impedance. iii.set transmission line relays on series compensated transmission lines so they do not operate at or below the maximum power transfer capability of the line, determined as the greater of: 115% of the highest emergency rating of the series capacitor. 115% of the maximum power transfer capability of the circuit (expressed in amperes), calculated in accordance with Requirement 1, criterion (ii), using the full line inductive reactance. iv.set transmission line relays on weak source systems so they do not operate at or below 170% of the maximum end-of-line three-phase fault magnitude (expressed in amperes). v.set transmission line relays applied at the load center terminal, remote from generation stations, so they do not operate at or below 115% of the maximum current flow from the load to the generation source under any system configuration. vi.set transmission line relays applied on the bulk system-end of transmission lines that serve load remote to the system so they do not operate at or below 115% of the maximum current flow from the system to the load under any system configuration. vii.set transmission line relays applied on the load-end of transmission lines that serve load remote to the bulk system so they do not operate at or below 115% of the maximum current flow from the load to the system under any system configuration.

viii.set transformer fault protection relays and transmission line relays on transmission lines terminated only with a transformer so that the relays do not operate at or below the greater of: 150% of the applicable maximum transformer nameplate rating (expressed in amperes), including the forced cooled ratings corresponding to all installed supplemental cooling equipment. 115% of the highest operator established emergency transformer rating. Set load-responsive transformer fault protection relays, if used, such that the protection settings do not expose the transformer to a fault level and duration that exceeds the transformer s mechanical withstand capability. ix. For transformer overload protection relays that do not comply with the loadability component of Requirement 1, criterion (viii) set the relays according to one of the following: Set the relays to allow the transformer to be operated at an overload level of at least 150% of the maximum applicable nameplate rating, or 115% of the highest operator established emergency transformer rating, whichever is greater, for at least 15 minutes to provide time for the operator to take controlled action to relieve the overload. Install supervision for the relays using either a top oil or simulated winding hot spot temperature element set no less than 100 C for the top oil temperature or no less than 140 C for the winding hot spot temperature. x. When the desired transmission line capability is limited by the requirement to adequately protect the transmission line, set the transmission line distance relays to a maximum of 125% of the apparent impedance (at the impedance angle of the transmission line) subject to the following constraints: a. Set the maximum torque angle (MTA) to 90 degrees or the highest supported by the manufacturer. b. Evaluate the relay loadability in amperes at the relay trip point at 0.85 per unit voltage and a power factor angle of 30 degrees. c. Include a relay setting component of 87% of the current calculated in Requirement 1, criterion (x) in the rating determination for the circuit. xi. Where other situations present practical limitations on circuit capability, set the phase protection relays so they do not operate at or below 115% of such limitations. 2. Each Transmission Licensee, Generator Company, or Distribution Licensee shall set its out-of step blocking elements to allow tripping of phase protective relays for faults that occur during the loading conditions used to verify transmission line relay loadability per Requirement 1. 3. Each Transmission Licensee, Generator Company, or Distribution Licensee that uses a circuit capability with the practical limitations described in Requirement 1, criterion (v), (vi), (vii), (x), or (xi) shall use the calculated circuit capability as the rating of the circuit and shall obtain the agreement of the CTU/CEA, Transmission Licensee, and RPC with the calculated circuit capability. 4. Each Transmission Licensee, Generator Company, or Distribution Licensee that sets transmission line relays according to Requirement 1 criterion (x) shall provide an updated list of the circuits associated with those relays to its RPC at least once each calendar year, with no

more than 15 months between reports, to allow the RPC to compile a list of all circuits that have protective relay settings that limit circuit capability. (4). Measures 1. Each Transmission Licensee, Generator Company, or Distribution Licensee shall have evidence such as spreadsheets or summaries of calculations to show that each of its transmission relays is set according to one of the criteria in Requirement 1, criterion (i) through (xi) and shall have evidence such as coordination curves or summaries of calculations that show that relays set per criterion (viii) do not expose the transformer to fault levels and durations beyond those indicated in the standard. 2. Each Transmission Licensee, Generator Company, or Distribution Licensee shall have evidence such as spreadsheets or summaries of calculations to show that each of its out-ofstep blocking elements is set to allow tripping of phase protective relays for faults that occur during the loading conditions used to verify transmission line relay loadability per Requirement 1. 3. Each Transmission Licensee, Generator Company, or Distribution Licensee with transmission relays set according to Requirement 1, criterion (v), (vi), (vii), (x), or (xi) shall have evidence such as rating spreadsheets or rating database to show that it used the calculated circuit capability as the rating of the circuit and evidence such as dated correspondence that the resulting rating was agreed to by its associated CTU/CEA, Transmission Licensee, and RPC. 4. Each Transmission Licensee, Generator Company, or Distribution Licensee that sets transmission line relays according to Requirement 1, criterion (x) shall have evidence such as dated correspondence that it provided an updated list of the circuits associated with those relays to its RPC within the required timeframe. The updated list may either be a full list, a list of incremental changes to the previous list, or a statement that there are no changes to the previous list.