Linfairn Wind Farm Addendum Chapter A13: Shadow Flicker

Similar documents
A10 Electronic Interference: Application 2 - LBHF

Appendix 8.2 Information to be Read in Conjunction with Visualisations

Non-Technical Summary of Environmental Statement

Control of noise from the operation of stationary systems

REVISED NOISE IMPACT STUDY

Control of Noise from the Operation of Stationary Systems

Noise Monitoring Program

Appendix 8.F Additional Great Crested Newt Survey 2009

NOISE IMPACT STUDY. Benton Boarding and Daycare 5673 Fourth Line Road Ottawa, Ontario City of Ottawa File No. D

CHAPTER ELECTRIC AND MAGNETIC FIELDS

Noise Mitigation Study Pilot Program Summary Report Contract No

NOISE IMPACT ASSESSMENT 2016

Antenna rotation variability and effects on antenna coupling for radar interference analysis

IEEE c-00/11. IEEE Broadband Wireless Access Working Group <

DEP 2008 ELECTRIC AND MAGNETIC FIELDS CHAPTER ELECTRIC AND MAGNETIC FIELDS

Energy Networks Association

Appendix 7-6 Collision Risk Assessment. Proposed Ardderroo Wind Farm, Co. Galway

Assured Monitoring Group

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS

RECOMMENDATION ITU-R M * Definition of availability for radiocommunication circuits in the mobile-satellite service

OWA Floating LiDAR Roadmap Supplementary Guidance Note

TPS 49 EDITION 2 JUNE 2009

DESIGN PRACTICE NOTE DESIGN/REVIEW REQUIREMENTS FOR TRACTION BONDING PLAN

Power Quality Requirements for Connection to the Transmission System

AC Voltage- Pipeline Safety and Corrosion MEA 2015

Wireless Facility Peer Engineering Review

MRO Delay Line. Performance of Beam Compressor for Agilent Laser Head INT-406-VEN The Cambridge Delay Line Team. rev 0.

Template Planning Condition on Amplitude Modulation Noise Guidance Notes

January 2012 Noise Impact Assessment Report for Proposed Cable Tow System For Wakeboarding & Water-skiing Grand Canal Dock, Dublin 4

Solar control devices; balance between thermal performance and daylight

DESIGN REVIEW PROCESS AND APPLICATION

Seagreen Wind Energy Limited C/o SSE Renewables 1 Waterloo Street Glasgow G2 6AY

Site Name. Bird Dimensions Species Hen harrier = data input required length (m) 0.55 = model calculates value wing span (m) 1.

City of Keizer Floodplain/Greenway Development Application

Galloper Wind Farm Limited. Galloper Wind Farm Project Environmental Statement Chapter 1 Introduction October 2011 Document Reference 5.2.

REPORT ITU-R M Impact of radar detection requirements of dynamic frequency selection on 5 GHz wireless access system receivers

APPENDIX M NOISE ANALYSIS

When surge arres t ers are installed close to a power transformer, overvoltage TRANSFORMER IN GRID ABSTRACT KEYWORDS

Recommended Changes to the Public Hearing Draft Zoning Ordinance

Transformer Thermal Impact Assessment White Paper TPL Transmission System Planned Performance for Geomagnetic Disturbance Events

Low Frequency Demand Disconnection Summary

Black. LWECS Site Permit. Stearns County. Permit Section:

2. As such, Proponents of Antenna Systems do not require permitting of any kind from the Town.

January 15, File: A. Urban Systems Ltd Homer Street Vancouver, BC V6B 2W9. Attention: Tim Stevens. Dear Tim:

Verizon Wireless Proposed Base Station (Site No Berkeley Bekins ) 2721 Shattuck Avenue Berkeley, California

Design guide to separating distances during construction

DESIGN OF A 45 CIRCUIT DUCT BANK

ISO INTERNATIONAL STANDARD. Petroleum and natural gas industries Offshore production installations Basic surface process safety systems

Modify Section , Major Impact Services and Utilities, of Chapter (Civic Use Types):

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition

Boa Vista Wind Farm Ponta do Sol

View flat at a comfortable arm s length Enoch Hill Wind Farm Environmental Statement

SYNCHRONISING AND VOLTAGE SELECTION

VISUALISATION STANDARDS

1. Terrestrial propagation

THE GRID CODE OC7.5 INTEGRAL EQUIPMENT TESTS GUIDANCE NOTES

David J. Gellner, AICP, Principal Planner

Radar Signatures and Relations to Radar Cross Section. Mr P E R Galloway. Roke Manor Research Ltd, Romsey, Hampshire, United Kingdom

LIMITS FOR TEMPORARY OVERVOLTAGES IN ENGLAND AND WALES NETWORK

REPORT ITU-R M

Transformer Thermal Impact Assessment White Paper TPL Transmission System Planned Performance for Geomagnetic Disturbance Events

Higher National Unit specification. General information for centres. Photography: Darkroom Techniques. Unit code: DW81 34

POWER TRANSFORMER. Failure Analysis & Troubleshooting. H.H. Sheik Sultan Tower (0) Floor Corniche Street Abu Dhabi U.A.E

System Operating Limit Definition and Exceedance Clarification

NATS Swanwick. Interface Agreement. Owners: General Manager Swanwick. General Manager XXX

1 Guidance to protect MoD systems using the 2.3 GHz band

Environmental Noise Assessment Cambourne to Cambridge options

TECHNICAL REPORT 2016 IEL ENVIRONMENTAL NOISE SURVEY OF THE DAIRYGOLD CASTLEFARM FACILITY, MITCHELSTOWN, CO. CORK.

WIRELESS TELECOMMUNICATION FACILITIES. Chapter 15

APPENDIX K.1 TELECOMMUNICATIONS AND AVIATION IMPACT STUDY

Home CSP Inc. Trackers and electronics for home solar energy

MidAmerican Energy Company 69 kv Facility Ratings Methodology

Conceptual, Preliminary and Final Site Plan Review in Holladay City

INFCIRC/57. 72/Rev.6. under. Safetyy. read in. Convention. involve. National Reports. on Nuclear 2015.

17 Telecommunication Interference

Graphic Communication Assignment General assessment information

Transformer Thermal Impact Assessment White Paper Project (Geomagnetic Disturbance Mitigation)

Government of Karnataka Department of Technical Education Board of Technical Examinations, Bengaluru

ADDAM (Atmospheric Dispersion and Dose Analysis Method)

Application for Site Plan Review

Liddell Coal Operations

ENGINEERING REPORT CONCERNING THE EFFECTS UPON FCC LICENSED RF FACILITIES DUE TO CONSTRUCTION OF THE (Name of Project) WIND PROJECT Near (City, State)

ABERDEEN HARBOUR EXPANSION PROJECT November Volume 2: Environmental Statement

Petroleum Safety Levy Methodology. Decision Paper

Clair Creek Meadows 30T Blocks 47, 48 & 49 Zone Change Functional Servicing and Stormwater Management Brief

Herts Valleys Clinical Commissioning Group. Review of NHS Herts Valleys CCG Constitution

Radiowave Propagation Prediction in a Wind Farm Environment and Wind Turbine Scattering Model

Transformer Thermal Impact Assessment White Paper (Draft) Project (Geomagnetic Disturbance Mitigation)

Verizon Wireless Proposed Base Station (Site No South Goleta ) 4500 Hollister Avenue Santa Barbara, California

Pfizer Ireland Pharmaceuticals

Re. Invitation to Comment on a Proposed Small Cell Telecommunications Installation Near (Road reserve) Coogee Bay Road COOGEE NSW 2034

CHAPTER 26 SITE PLAN REVIEW

Innogy Renewables UK Ltd i Harryburn Wind Farm: ES Technical Appendix 8.6: Bird Collision Modelling April 2017

AGN 022 Conditions for Parallel Operation

Migration of Birds MARC

AT&T Mobility Proposed Base Station (Site No. CN4779A) 1101 Keaveny Court Walnut Creek, California

See Benchmark Geomagnetic Disturbance Event Description white paper, May 12, Filed by NERC in Docket No. RM15 11 on June 28, 2016.

The following is the summary of Keane Acoustics community mechanical noise study for the City of St. Petersburg.

Verizon Wireless Proposed Base Station (Site No Lake Cachuma ) 2680 Highway 154 Santa Barbara County, California

Memorandum 1.0 Highway Traffic Noise

Transcription:

A13. SHADOW FLICKER 13.1 Introduction The purpose of this chapter is to review amendments to the Project design and to advise of any consequent alterations to potential shadow flicker impacts as previously reported in ES Chapter 13. The assessment has been carried out by SgurrEnergy Ltd. 13.2 Scope of the Assessment 13.2.1 Study Area and Assessment Criteria There have been no updates to guidance, of relevance to the shadow flicker assessment, since the ES was submitted. Therefore the assessment criteria remain as detailed in Section 13.2.1 of ES Chapter 13. Using the ReSoft WindFarm software, a potential shadow flicker impact map was produced for the revised layout of 17 WTGs (see Figure A13.1) which highlights proties potentially affected by the Project. 13.2.2 Consultation Responses The Section 36 application was submitted to the Scottish Government ECDU on 27 September 2013 with responses received in November and December 2013. No consultation responses were received in relation to shadow flicker. 13.3 Assessment Methodology 13.3.1 Analysis 13.3.1.1 Software Parameters The shadow flicker analysis was conducted using the Shadow Flicker module of the ReSoft WindFarm software. Please refer to Section 13.3.1.1 of ES Chapter 13 which provides further detail. 13.3.1.2 Parameters used in the Analysis WTG dimensions and layout The modelling was undertaken based on the proposed 17 WTG layout and a WTG with a 101m rotor diameter and 76m hub height, which is a larger rotor diameter and lower hub height than originally modelled. 14/7048/001/GLA/O/R/001 Revision B1 Page 1 of 7

Shadow flicker potential impact area and receptor locations As identified in section 13.2.1 of the ES, the shadow flicker impact is likely to be negligible beyond a distance of 10 rotor diameters. This is equal to 1,010m for a WTG with a 101m rotor diameter. Using the WindFarm software, a potential shadow flicker impact area map has been produced (Figure A13.1). As shown on the figure, only certain houses are predicted to be within this potential impact area. Consequently, only these proties would be expected to exience shadow flicker effects and therefore have been included in the modelling analysis. It should be noted that the amended Project design, with 17 WTGs, has a reduced impact area compared with the layout in the ES. Consequently, proty numbers 1, 2 and 3 which were considered in the ES Chapter 13, are no longer relevant to the shadow flicker assessment. Proty number 5 consists of non-residential outbuildings and has therefore been removed from the assessment. The numbering of proties remains consistent with the original ES. Window distribution, orientation and size The same approach was adopted as described in section 13.3.1.2 of the ES. 13.3.2 Assessment Results 13.3.3 WindFarm Shadow Flicker Analysis Results For each of the potential shadow flicker receptors, a total number of shadow flicker hours in a year was modelled. The results of this modelling are shown in Table A13-1. It should be noted that these results represent theoretical hours for which the individual receptor could potentially be affected by shadow flicker based on worse case scenario modelling. Again it should be noted that the results do not take into account factors that would reduce shadow flicker such as iods when there is insufficient sunshine due to cloud-cover, iods when the WTG is not rotating or screening from any existing vegetation and buildings. The sensitivity is considered to be High at the proties which are residential receptors. The results have been provided and then examined in relation to the guidance limits, as section 13.2.1 of the ES, of 30 hours year or 30 minutes day on the worst affected day, based on an astronomical worst case scenario. 14/7048/001/GLA/O/R/001 Revision B1 Page 2 of 7

Table A13-1: Potential Shadow Flicker Occurrence at Identified Proties (WTG with 76 m Hub Height and 101 m Rotor Diameter) No. Name Co-ordinates Window Orientation (degrees from north) Days year* Max hrs day* Mean hrs day* Total hrs year* 4 Knockskae 237292 601404 163 53 0.6 0.5 25 6 Linfairn 238178 601217 210 131 0.9 0.6 72 7 Genoch Cottage 239025 600811 200 39 0.4 0.3 12.7 *Theoretical modelled values As can be seen in Table A13-1, only one proty (proty number 6: Linfairn) is predicted to exience more than 30 hours of shadow flicker year, using worst case modelling. It is understood that the owner and occupier of proty 6 (Linfairn) has a financial interest in the project. Proties 4 (Knockskae) and 7 (Genoch Cottage) do not exceed 30 hours year. Proty 4 (Knockskae) is predicted to exience slightly over 30 minutes in the maximum hours day assessment. A summary of when shadow flicker is expected to occur at Proties 4, 6 and 7 is given in Table A13-2 below. Table A13-2: Timing of Shadow Flicker Occurrence at Key Proties (WTG with 76 m Hub Height and 101 m Rotor Diameter) Proty Distance to WTG (m) Potential Shadow Flicker Occurrence Time of the Year Time of the Day 4: Knockskae 695 Winter Late morning 6: Linfairn 837 Autumn, Winter Afternoon 7: Genoch Cottage 992 Autumn, Winter Afternoon Based on this worst case modelling exercise, proties 4 (Knockskae) and 6 (Linfairn) are both predicted to exience a maximum daily duration above 30 minutes day, specifically 0.6 hours (36 minutes) and 0.9 hours (54 minutes) respectively. 13.3.4 Potential Factors Reducing Shadow Flicker Impact There are a number of factors that are likely to reduce the incidence of shadow flicker. Details of these and annual average sunshine for the study area can be found in Section 13.4.2 of the ES. The annual average sunshine, as the ES, was 25.1%. This was applied to the annual shadow flicker results for proties 4, 6 and 7. 14/7048/001/GLA/O/R/001 Revision B1 Page 3 of 7

The adjusted shadow flicker hours for individual proties are given in Table A13-3. Table A13-3: Adjusted Shadow Flicker Results based on Sunshine Hours (WTG with 76m Hub Height and 101m Rotor Diameter) Proty Total Shadow Flicker Hours Year (as modelled) Adjusted Shadow Flicker Hours 4: Knockskae 25 6.3 6: Linfairn 72 18.1 7: Genoch Cottage 12.7 3.2 As can be seen, proty 6: Linfairn is predicted to exience 18.1 hours of shadow flicker year following the adjustment to account for sunshine hours. This equates to approximately 0.4% of the available daylight hours year, which is not considered to represent a significant impact. The adjusted shadow flicker hours for proties 4 and 7 are lower still and are likewise deemed insignificant impacts. This adjustment for sunshine hours results in a more realistic prediction of shadow flicker effect and duration. However, the adjusted results are still considered to be conservative because the modelling assumes a worst case scenario with regard to wind direction / WTG alignments and screening effects. In addition, the results are still based on a conservative window size, window orientation and minimum sun height. Accounting for sunshine hours and the other considerations discussed in the ES would also be expected to reduce the maximum daily duration of shadow flicker exienced at nearby proties 4 (Knockskae), 6 (Linfairn) and 7 (Genoch Cottage). 13.4 Assessment of Effects Following assessment of the revised Project layout design and WTG dimensions, the potential magnitude of change in relation to shadow flicker is considered to be Negligible at the oational phase. Mitigation has however been provided to address the potential shadow flicker effects on the three proties identified above. 13.5 Mitigation Measures Mitigation includes software control on relevant WTGs during iods when conditions exist that could result in shadow flicker effects. The potential impact from shadow flicker will be monitored for 12 months after commissioning has been completed and a shadow flicker mitigation scheme will be submitted and approved as part of a suitable condition. This will address any potential significant effects on affected proties. 14/7048/001/GLA/O/R/001 Revision B1 Page 4 of 7

13.6 Summary of Effects Table A13-4 provides a summary of the potential effects associated with the revised Project. 14/7048/001/GLA/O/R/001 Revision B1 Page 5 of 7

Table A13-4: Summary of Effects Receptor Development Stage Sensitivity Magnitude of Change Predicted Effect Prior to Mitigation Mitigation Residual Effect Proty No. 4: Knockskae Proty No. 6: Linfairn. Proty No. 7: Genoch Cottage Oational Oational High High Software control on relevant WTGs during iods when conditions exist which could result in shadow flicker effects. Oational High 12 month monitoring scheme following commissioning of the Project. Shadow flicker mitigation scheme produced as part of any relevant condition. 14/7048/001/GLA/O/R/001 Revision B1 Page 6 of 7

13.7 Statement of Significance The assessment has concluded that there will be no significant impacts on proties in the vicinity of the Project as a result of shadow flicker. 14/7048/001/GLA/O/R/001 Revision B1 Page 7 of 7