Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS

Similar documents
PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

GridLiance Reliability Criteria

Single Line Diagram of Substations

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

Unit 2. Single Line Diagram of Substations

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

Southern Company Interconnection Requirements for Inverter-Based Generation

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Protective Relaying Philosophy and Design Guidelines. PJM Relay Subcommittee

BUS2000 Busbar Differential Protection System

Arizona Public Service Company and the Transmission Partnership for National Electric Power Company of Jordan

Table of Contents. Introduction... 1

Relay Communication Misoperations. Southwest Power Pool System Protection and Control Working Group

Transmission Line Protection Objective. General knowledge and familiarity with transmission protection schemes

Utility Interconnection and System Protection

Switch-on-to-Fault Schemes in the Context of Line Relay Loadability

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell

Transmission Protection Overview

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

This webinar brought to you by The Relion Product Family Next Generation Protection and Control IEDs from ABB

Module 10. Initiation Code RELIABILITY ACCOUNTABILITY

INTERIM ARRANGEMENTS FOR GRID TIED DISTRIBUTED ENERGY RESOURCES. Technical Requirements for Grid-Tied DERs

Wind Power Facility Technical Requirements CHANGE HISTORY

Transmission Interconnection Requirements for Inverter-Based Generation

Power System Fundamentals

Module 9. Fault Type Form 4.X RELIABILITY ACCOUNTABILITY

ReliabilityFirst Regional Criteria 1. Disturbance Monitoring and Reporting Criteria

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

BED INTERCONNECTION TECHNICAL REQUIREMENTS

ESB National Grid Transmission Planning Criteria

Transmission System Phase Backup Protection

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

Busbars and lines are important elements

What s New in C TM -2015, IEEE Guide for Protective Relay Applications to Transmission Lines

This document covers common questions concerning the design of an effectively grounded system.

Notes 1: Introduction to Distribution Systems

ELECTRIC TRANSMISSION (ET) Guideline G0104

NERC Protection Coordination Webinar Series July 15, Jon Gardell

Power System Protection Where Are We Today?

Babak Enayati National Grid Thursday, April 17

1

Alberta Interconnected Electric System Protection Standard

Fixed Series Compensation

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies

Phase-phase/phase-neutral: 24/13.8 kv star, 13.8 kv delta, 12/6.9 kv star.

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS

A short introduction to Protection and Automation Philosophy

COPYRIGHTED MATERIAL. Index

Appendix C-1. Protection Requirements & Guidelines Non-Utility Generator Connection to Okanogan PUD

The Connecticut Light and Power Company

Power System Protection. Dr. Lionel R. Orama Exclusa, PE Week 9

Oklahoma Gas and Electric Co. Facility Connection Requirements MAINTAINED BY. Transmission Planning Engineering Department

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES. Document 9020

Imperfections in Coordinating Facility Ratings between Operations, Planning and Maintenance

System Protection and Control Subcommittee

ENOSERV 2014 Relay & Protection Training Conference Course Descriptions

TECHNICAL GUIDELINE FOR THE INTERCONNECTION OF DISTRIBUTED ENERGY RESOURCES TO EPCOR DISTRIBUTION AND TRANSMISSION INC. S DISTRIBUTION SYSTEM

SYNCHRONISING AND VOLTAGE SELECTION

6CARRIER-CURRENT-PILOT AND MICROWAVE-PILOT RELAYS

Bus Protection Fundamentals

Summary Paper for C IEEE Guide for Application of Digital Line Current Differential Relays Using Digital Communication

FACILITY RATINGS METHOD TABLE OF CONTENTS

OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

PROTECTION SIGNALLING

Using a Multiple Analog Input Distance Relay as a DFR

Transmission Interconnection Handbooks For NERC Reliability Compliance Program. Pacific Gas and Electric Company. Combined Version

MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology

N. TEST TEST DESCRIPTION

Transmission Lines and Feeders Protection Pilot wire differential relays (Device 87L) Distance protection

Capstone Turbine Corporation Nordhoff Street Chatsworth CA USA Phone: (818) Fax: (818) Web:

FACILITY CONNECTION REQUIREMENTS

UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS

HUTCHINSON UTILITIES COMMISSION TRANSMISSION INTERCONNECTION GUIDELINES

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Company Replaces previous document Document ID Issue E.ON Elnät Sverige AB Ny engelsk utgåva D

Transmission Availability Data System Definitions

Power systems Protection course

CARRIER-AIDED PROTECTION OF TRANSMISSION LINES

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

SHUNT CAPACITOR BANK DESIGN AND PROTECTION BASICS

EH2741 Communication and Control in Electric Power Systems Lecture 2

Power Plant and Transmission System Protection Coordination

Facility Interconnection Requirements for Colorado Springs Utilities Version 03 TABLE OF CONTENTS

I WP Asset # I ~:2 3. I Review Annual. ~c~~ Date: 'l/j(j/! ZL>IJ,...

EE Lecture 14 Wed Feb 8, 2017

How to maximize reliability using an alternative distribution system for critical loads

Dairyland Power Cooperative June Transmission to Transmission (T-T) Interconnection Guidelines

Power Plant and Transmission System Protection Coordination Fundamentals

TRAINING Learning and Training application on site. QUALIFYING Evaluation of quiz Knowledge Validation To learn required skills

Switch-on-to-Fault Schemes in the Context of Line Relay Loadability

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

KENYA ELECTRICITY GENERATING COMPANY LTD

ENGINEERING STANDARD FOR INSTRUMENTS ELECTRICAL POWER SUPPLY AND DISTRIBUTION SYSTEMS FIRST EDITION MAY 2013

System Protection and Control Seminar

PC IEEE Guide for Grounding of Instrument Transformer Secondary Circuits and Cases

Power System Stability. Course Notes PART-1

Transcription:

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS S1. Standard Interconnection Methods with Typical Circuit Configuration for Single or Multiple Units Note: The protection requirements and station configurations will depend on the voltage class and the size and number of generation units. All new busses must be BAAH however building in a BAAH configuration and operating as a ring is acceptable. S1.1. Generator Connected Into a Breaker-and A-Half (BAAH) Bus PG&E Owned Customer Owned To Generation Facilities AS-1

S1.3. Bus Fault Clearing (Optical Fiber or Microwave) 1. Can clear bus faults--sta A and the NEW generator can be protected by two differentially connected relays for pilot protection, using digital communication equipment and medium1. 2. Cannot clear for bus faults--when the NEW generator cannot clear BUS Faults substation Sta A a DTT signal must be sent to clear the faults at the NEW generator site. The DTT feature may be incorporated as a function within the respective current differential relaying schemes, provided the relay and medium selected support DTT. S2. Interconnection Methods with Special Circuit Configurations for Single Unit S2.1. Alternative--Generator Tapping To Existing between Two Terminals, considered only at voltages below 100kV 1. Can clear faults--if the NEW generator can clear faults on its interconnecting transmission line, additional communications-based protection to trip the NEW generator may not need to install at Sta A or Sta B. 2. Cannot clear faults--if the NEW generator cannot clear faults on its interconnecting transmission line, Sta A, Sta B, or both Sta A and Sta B will be required to be equipped with Transfer Trip (TT) equipment to send Direct Transfer Trip (DTT) signal(s) to clear for faults on the interconnecting transmission line. AS-2

Notes: a. Application of DTT is independent of line protection 1. b. The DTT transfer trip receiver signal must be wired to trip the generator breaker. 3. When the line is protected by current differential relays or phase comparison type relay systems, the DTT may be incorporated as part of the line protection. (see S2.6) S2.3. Generator Tapping closely outside the Substation Between Two Existing Terminals for below 100 kv only and by approved exception. Line Relays Sta A Ground Grid The following applies: Connect ground grids between Sta A and NEW generator together. Combine Current Transformer (CT) inputs from Sta A breaker and the NEW generator breaker to line relays at Sta A. Line relays trip both Sta A breaker and either the NEW generator line breaker terminal, or in the absence of the line breaker, will be wired to trip the generator breaker via a auxiliary relays. The auxiliary relays must be suitable for tripping and lockout applications. PG&E reclose block is supervised by line voltage or generator s breaker status. PG&E breaker failure relay trips the generator breaker directly via an auxiliary relay. This configuration may require DTT from Sta B. See S2.5 and S2.6 1 Refer to Appendix F for communication-assisted protection and associated requirements. AS-3

S2.4. Generator Connected Close Outside the Substation with a Dedicated Line Differential Ground Grid The following applies: Connect ground grids together between Sta A and the NEW generator station (not required if fiber optic network is used) Install new line differential relays at Sta A. Connect CT inputs from Sta A breaker and NEW generator s breaker to line differential relay. Line differential relay trip Sta A breaker and the NEW generator breaker via auxiliary relays. Direct trip NEW generator breaker via an auxiliary relay for Sta A breaker failure. See S2.5 and S2.6 S2.5. Requirements for S2.3 and S2.4 Alternatives A Ground Grid study 2 is required for both Stations A and B and the NEW generator to determine conductor size and routing. Each generating site needs to conform to the IEEE Std 80-2000 for grounding requirements. Transient Studies are required to determine the amount of exposure to PG&E and the respective NEW generating facility equipment prior to PG&E performing a detailed feasibility evaluation and specifying the equipment specification. Exposure in this instance refers to the susceptibility of PG&E s system to excessive transient voltage dip, frequency deviation, or voltage deviation. Interposing relays are required for tripping and status circuits between Sta A and the NEW generating facility and to isolate the DC control batteries. 2 PG&E may be contacted for a list of consultants who can provide this type of service. AS-4

The Generation Entity must be aware that common ground grid could result in additional exposure to transients caused by switching and faults at Sta A. Operating procedures and protection needs to be in place to address bypassing of breaker at Sta A for maintenance or other clearances. Otherwise the NEW generating facility will need to be cleared. S2.6. Additional Items for Consideration Design and operating standards are not available for alternatives S2.3 and S2.4. For alternatives S2.2 and S2.3, NERC redundancy requirements should be followed as appropriate for the voltage level. Alternatives S2.1 and S2.3 are not recommended if existing line protection uses a power line carrier. Two concerns are: o Signal will be degraded unless wave trap is installed at the new generation facility. o Risk of over-tripping for faults in NEW generator facility Economic analysis is recommended to compare alternatives S2.1 and S2.3, or S2.2 and S2.4. When simulating End-of-Line faults, generator unit steady state synchronous impedance shall be considered. AS-5