Apache Subsea Projects NORTH SEA REGION Richard Stark Paul Williams
INTRODUCTION TO APACHE Presenters Richard Stark, Project Services Manager, Apache North Sea Paul Williams, Subsea Projects Manager, Apache North Sea Itinerary Apache and Apache North Sea 2011 Subsea Campaigns 20 mins Lunch 2 In progress projects Upcoming projects Apache North Sea The Future Procurement Questions 20 mins
APACHE A GLOBAL COMPANY Canada Kittimat pipeline Central Gulf of Mexico Shelf Deepwater North Sea FASP Egypt Argentina Australia Julimar tie back to platform Wheatstone - LNG plant Balnaves FPSO Conniston Tie back to FPSO Macedon - Onshore 3
APACHE A GROWTH COMPANY 2011 Financial Results 748 MBOE/D net +14 % YOY (50% liquids) $10.2 BN* cash flow +39 % YOY $4.5 BN earnings +50 % YOY 1Q 2012 Results 769 MBOE/D net Up 7% YOY (50% liquids) $1.2 BN adjusted earnings up 4% YOY $2.6 BN cash flow up 18% YOY 3 BN boe in 2011 YE reserves at all time high (46% liquids)
APACHE GROWTH THROUGH EXPLORATION
APACHE LARGEST INDEPENDENT 1,000 900 2011 PPRODUCTION (Mboe/d) 800 700 600 500 400 300 200 100 0 6 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% % OF PRODUCTION OUTSIDE NORTH AMERICA
APACHE IN THE NORTH SEA Richard Stark 7
APACHE LOCAL GROWTH AND ASSETS Acquired Mobil North Sea Limited (Beryl) and a non operated interest in the Nelson field Q1 2012 production up 67% YoY, 41% sequentially with plans for continued ramp up Bacchus well 1 online April 2012 @ ~6,000 Bbls/d gross Zero to 40 subsea wells 15 to 80+ pipelines 0% to 20% production from subsea 110,000 100,000 Net Rate (boe/d) 90,000 80,000 70,000 60,000 50,000 40,000 30,000 20,000 Oct-11 Dec-11 Feb-12 Apr-12 Jun-12 Aug-12 Oct-12 Dec-12 Nelson IMS Bacchus IMS Beryl IMS Forties + Maule IMS Telford BPF Scott BPF Nelson BPF Beryl BPF Forties + Maule BPF
NNS BERYL PLATFORMS Beryl Bravo Steel jacket Oil and gas export to Beryl Alpha 1 x drilling rig Nevis / Ness / Linnhe 9 Beryl Alpha Condeep structure RAT and flare tower 2 x drilling rigs Tanker export (oil) SAGE export pipeline (gas) Buckland / Skene / Nevis / Ness / Lewis Gryphon
NNS SUBSEA BERYL AREA
SAGE GAS PLANT
CNS FORTIES PLATFORMS 5 x platforms + FASP Oil export through Forties Charlie via FPS Limited gas (power)
CNS SUBSEA FORTIES AREA 14 x infield pipelines 1 (+) x subsea well (Bacchus) Impressed Current Cathodic Protection (ICCP)
APACHE NORTH SEA NEW LOCATION
IN PROGRESS PROJECTS Paul Williams 15
16 2011 CAMPAIGNS
2011 VESSEL CAMPAIGNS - FORTIES Survey and ROV Inspection 21 Days Subsea Construction (Non Diving) 22 Days Diving Support Vessel Works (DSV) 110 Days Pipelay & Trenching 30 Days 17
2011 VESSEL CAMPAIGNS - BERYLS Seven Atlantic Hydrotest of Riser D1. Switch Skene Power B to C. Riser base spool UT 12th Feb to 22nd Feb 10 Ernest Shackleton Beryl Survey (UK portion) 1st July to 14th Aug 20 Bibby Topaz N11 riser re-route and leaking N12 grease nipple repair. N12 AMV visual inspection 8th Aug to 20th Aug 12 Bibby Topaz Skene IR investigation and S48 greasing 27th Sept to 1st Oct 4 Bibby Topaz N13 (N1y) SCM changeout. Nevis IR investigation and repairs. Attempt at skene caisson 15th Oct to 23rd Oct 8 Survey and ROV Inspection 20 Days Subsea Construction (Non Diving) 0 Days Diving Support Vessel Works (DSV) 34 Days Pipelay & Trenching 0 Days 18
This image cannot currently be displayed. FORTIES ALPHA SATELITTE MANHOURS ENGINEERING 331,532hrs CONSTRUCTION 1,453,303hrs WEIGHT STRUCTURAL WEIGHT (tons) 16,647 EQUIPMENT WEIGHT 1,550 PIPING LENGTH (Miles) 10.5 No. OF VALVES 2107 ELECTRICAL, INSTRUMENT & TELECOMMS ELEC. CABLE (Miles) 31.9 ELEC. BULKS (Lights etc.) No. 18435 INST. CABLE (Miles) 86.9 INST. BULKS (Gland/Term etc.) No. 21388 19 19
BACCHUS SUBSEA TIE-BACK
FORTIES CHARLIE SSIV
FORTIES CHARLIE SSIV 22 3D Visualisation of SSIV Layout (Brae Import) Completion Status Design 100% complete Valves 100% complete Structures 50% complete Umbilical 100% complete Flange manufacture 80% complete Pipe manufacture 80% complete Conduit 40% complete Valve and Actuator Post Testing Man
FORTIES CHARLIE SSIV 36 Pipe Weld Qualification Tests 3D Model of SSIV & Structure 23 Base Frame (shows scale) 36 Concrete Coated Pipes Schedule to Completion All manufacturing complete, Sept 2012 Final items into storage, Oct 2012 Site integration tests, Feb 2013 Phase 1 installation, June 2013 Phase 2 installation, Aug 2013
FORTIES D TO C PIPELINE REPLACEMENT Completion Status Design 100% complete Pipelay 100% complete Trenching 100% complete Riser manufacture 90% complete Clamp manufacture 90% complete 24
GAS RINGMAIN REPAIR
1 ST BERYL CAMPAIGN NEVIS SOUTH REPAIR Leak at N13 (greenish fluid) 26 Well N13 leaking hydraulic fluid 165 Litres per day being discharged Decision taken to mobilise DSV Original schedule was 3 days for Nevis works SCM changed out in 10 hours All Nevis works completed in 1.5 days Well now back online, no leaks reported Airbag change out of SCM
1 ST BERYL CAMPAIGN SAGE FREESPAN Around 500 unsupported pipeline lengths, freespans, have been identified on the SAGE pipeline (lengths 10m-57m/ gaps 0.1-2.0m) 5 of these were addressed in detail as the spans fail the pre-determined criteria 1 freespan was rectified in March 2012 at the Beryl Alpha SSIV (44m) to prevent any potential for further growth and requirement for annual monitoring 4 remaining critical spans will be re-inspected in 2012 Freespan Prior to Repair 2012 Freespan Repair 27
28 UPCOMING PROJECTS
NNS SUBSEA BERYL AREA
30 LORISTON SOUTH WEST
LORISTON SOUTH WEST Currently based on using an existing and available tree Use of PL893 2.5km flexible flowline extension required Flexible flowline is available and under Apache control Controls & chemicals, new umbilical required Umbilical chemical hoses to directly tie into the new tree FEED engineering starting 31
32 NESS SOUTH
NESS SOUTH Currently based on using an existing and available tree Flexible jumper from N7 flowbase to tree Injection gas also from N7 or other local flowbase Controls & chemicals, new umbilical required Jumpers (6 and 8 ) are available in the market New umbilical required Umbilical chemical hoses to directly tie into the new tree FEED engineering starting 33
34 NEVIS CENTRAL LEWIS 4
NEVIS CENTRAL LEWIS 4 Currently based on using an existing and available tree New flowline required, longest lead item currently 12 months Controls & chemicals, new umbilical required, or alternately put enough cores in Loriston South umbilical Umbilical chemical hoses to directly tie into the new tree FEED engineering will start in the next quarter 35
AVIAT FORTIES Aviat (WI 100%) Aviat-1 was drilled in 3Q 2010 and successfully tested A fuel gas resource for Forties Field 26kM from Forties Alpha Two well tie back A final appraisal well currently being planned Project delivery planned for 2014 Engineering works will commence Q3 2012 NELSON power demand diesel Forties gas 2006 2020
APACHE NORTH SEA THE FUTURE Richard Stark 37
NORTH SEA REGION EXPLORATION, DRILLING AND APPRAISAL UK Norway FASP Forties Echo Isabella 3D Wide Azimuth Seismic Tryfan well Seagull North Well Seagull Well 27th License Round Tryfan Beryl Forties & Nelson Seagull & Seagull North Isabella 38
PROCUREMENT Richard Stark 39
PROCUREMENT Qualification for work FPAL Offshore Construction - Currently Petrofac Onshore Engineering / Offshore Construction Award Pending Subsea Project Management Flexlife Subsea Engineering Detailed Design Award Pending Subsea Construction ITT being prepared 40
SUMMARY Apache have been in the North Sea for almost a decade Forties has been a great success for Apache The plan is that the Beryls will be too Questions 41