Reference Number PDS 04 (RIC Standard: EP SP)

Similar documents
Reference Number PDS 07 (RIC Standard: EP SP)

Status Date Prepared Reviewed Endorsed Approved

Title Operating Work - Low Voltage Distribution System. Reference Number POP 06 - (RIC Standard: EP SI)

Reference Number PCP 02 (RIC Standard: EP SP)

Title Substation Auxiliary Transformer from Rectifier Transformer Secondary. Reference Number PDS 01 (RIC Standard: EP SP)

Status Date Prepared Reviewed Endorsed Approved

Status Date Prepared Reviewed Endorsed Approved

Title Lightning/ Surge Protection - Power Inductors. Reference Number SPS 37 - (RIC Standard: SC SP)

Status Date Prepared Reviewed Endorsed Approved

Status Date Prepared Reviewed Endorsed Approved

Reference Number PPS 05 - (RIC Standard: EP SP)

Status Date Prepared Reviewed Endorsed Approved

Status Date Prepared Reviewed Endorsed Approved

SDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-I) UNDERGROUND NETWORK GROUNDING. Rev. 01

CSEE UM71 AF Jointless Track Circuits Set-up, Test and Certification

CONTINUING EDUC ATION

WB&S FS2500 AF Jointless Track Circuits Set-Up, Test and Certification

SDCS-03 DISTRIBUTION NETWORK GROUNDING CONSTRUCTION STANDARD (PART-II) OVERHEAD NETWORK GROUNDING. Rev. 01

ML TI21 AF Jointless Track Circuits Set Up, Test and Certification

HV Substation Earthing Design for Mines

Field Instruction. Induced voltages can occur in overhead lines, underground cables, or in switchyards.

Wisconsin Contractors Institute Continuing Education

SAFETY AND HEALTH STANDARD ELECTRICAL GROUNDING Effective Date: 07/17/10 Standard: Document Number: KUCSH0039 Rev: 4

American Electrical Institute

Collection of standards in electronic format (PDF) 1. Copyright

Australian Standard. Switchgear assemblies and ancillary equipment for alternating voltages above 1 kv AS

6B.6 Substation Grounding

Earthing Guidance Notes

Licensed Electricians Practical Assessment (LEP)

TS RES - OUTSTANDING ISSUES

FAQ ON EARTHING STANDARDS 16/08/2018

Options to Improve the MEN System into the 21 st Century

PRACTICAL PROBLEMS WITH SUBSTATION EARTHING

DMRC ELECTRICAL STANDARDS & DESIGN WING (DESDW)

6. Internal lightning protection

ER 87 Electrician Regulations Answer Schedule. Question 1 Marks Reference Marking notes. (1 mark) ESR 27(2) (2 marks) ESR 74A(1AA)

ECP HV INSULATION TESTING

NATIONAL RULES FOR ELECTRICAL INSTALLATIONS. Fourth Edition. Extracts from Amendment No.1: June 2011

Industrial and Commercial Power Systems Topic 7 EARTHING

Licensed Electricians Practical Assessment (LEP)

Company Directive STANDARD TECHNIQUE: TP21D/2. 11kV, 6.6kV and LV Earthing

IMP/007/011 - Code of Practice for the Application of Lightning Protection

kv AC substation

ECP HV INSULATION TESTING

2/15/2015. Current will always try to return to its source. In order for there to be current, there must be a complete circuit

ACCESS TO HIGH VOLTAGE APPARATUS

Article 250 Grounding & Bonding

Stake-less earth / ground testing

25kV A.C. Electrified Lines - Traction Bonding

2 Grounding of power supply system neutral

EI HIGH VOLTAGE INSULATION TESTING POLICY

Power Quality. Case Study. Conrad Bottu Laborelec January 2008

GROUNDED ELECTRICAL POWER DISTRIBUTION. Excerpt from Inverter Charger Series Manual BY: VIJAY SHARMA ENGINEER

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS

Status Date Prepared Reviewed Endorsed Approved

Protection of Electrical Networks. Christophe Prévé

Busbars and lines are important elements

Fatima Michael college of Engineering and Technology

Earthing Requirements for HV Transmission Structures

Title Common Requirements for Electric Power Equipment. Reference Number PDS 12 - (RIC Standard: EP SP)

CROSS-CONNECT CABINET

CHAPTER 15 GROUNDING REQUIREMENTS FOR ELECTRICAL EQUIPMENT

Education & Training

FINAL - ER 70 Electrician Regulations Answer Schedule. Question 1 Marks Reference Marking notes

Form-IV. Form of Inspection/Test Report. (Under Regulation 43)

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

IMP/010/011 Code of Practice for Earthing LV Networks and HV Distribution Substations

Grounding and Bonding of Service Equipment

Power Frequency Withstand Voltage On-site testing of 400 kv GIS

Agenda. Earthing of Telecom Installations using Single Point Earthing. Reference Documents. How many earths? Earthing Issue...

ET 40 - Electrician Theory Examination Marking Schedule

GROUP OF COMPANIES. MERLIN STEALTH Electric Fence Energizer INSTALLERS MANUAL

MESP TECHNICAL SPECIFICATION FOR AN AUXILIARY OR ESSENTIAL SERVICES AND AUXILIARY TRANSFORMER FOR USE IN A RAILWAY SUBSTATION

2394 EXAM PAPER. 1. State THREE circumstances that would require a periodic inspection and test to be carried out on an installation

ELECTRICAL NETWORKS SPECIFICATION TECHNICAL SPECIFICATION FOR A 230V/110V AND 400V/110V TRANSFORMER

Evaluating Step and Touch Potential Risks on Earthing Systems of High Voltage Cable Systems TP, THINUS DU PLESSIS ESKOM SOUTH AFRICA HJ, HARTMUT JAGAU

Grounding and Lightning arrestors

Chapter 1. Applied Grounding and Bonding. Applied Grounding and Bonding 9/18/2011. Introduction. Introduction. Paul Dobrowsky Member NEC Panel 5

SYNCHRONISING AND VOLTAGE SELECTION

Earthing of Electrical Devices and Safety

AC Voltage- Pipeline Safety and Corrosion MEA 2015

EMC Philosophy applied to Design the Grounding Systems for Gas Insulation Switchgear (GIS) Indoor Substation

, Power Industries and Communications Industry Training Board

National Marine Manufacturers Association Compliance Specialist Examination A.C. Electrical (2018 Model Year) ABYC E-11 Supplement 56

Substation HV Cables. Document Number: 1-11-FR-07

ELECTRICIAN S THEORY EXAMINATION 17 November 2012 QUESTION AND ANSWER BOOKLET

SAFETY ASPECTS AND NOVEL TECHNICAL SOLUTIONS FOR EARTH FAULT MANAGEMENT IN MV ELECTRICITY DISTRIBUTION NETWORKS

EPG. by Chris C. Kleronomos

60Hz Ratings. Typical Applications. Features & Characteristics. Ratings

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING DEPARTMENT OFFICE

SPTS 1 - Ratings and General Requirements for Plant, Equipment and Apparatus for The ScottishPower System and Connection Points to it.

TRANSMISSION ENGINEERING STANDARD TES-P , Rev. 0 TABLE OF CONTENTS 1.0 SCOPE 2.0 BONDING METHODS

Section 3. Test Procedures

EE 1402 HIGH VOLTAGE ENGINEERING

C&G Level 3 Award in the Periodic Inspection, Testing and Certification of Electrical Installations

Cable Protection against Earth Potential Rise due to Lightning on a Nearby Tall Object

Overview of Grounding for Industrial and Commercial Power Systems Presented By Robert Schuerger, P.E.

SUBJECT HEADING: Switching Programmes ISSUE: 18

Grounding for Power Quality

FINAL - EST Electrical Service Technician Answer Schedule

Transcription:

Discipline Engineering Standard NSW Category Electrical Title Reference Number PDS 04 (RIC Standard: EP 12 10 00 10 SP) Document Control Status Date Prepared Reviewed Endorsed Approved Mar 05 Standards and Systems Refer to Reference Number Signalling Standards Engineer T Moore GM Infrastructure Strategy & Performance M Owens Safety Committee Refer to minutes of meeting 24/01/05

Disclaimer Australian Rail Track Corporation has used its best endeavors to ensure that the content, layout and text of this document is accurate, complete and suitable for its stated purpose. It makes no warranties, express or implied, that compliance with the contents of this document shall be sufficient to ensure safe systems of work or operation. Australian Rail Track Corporation will not be liable to pay compensation in respect of the content or subsequent use of this document for any other purpose than its stated purpose or for any purpose other than that for which it was prepared except where it can be shown to have acted in bad faith or there has been willful default. Document Approval The technical content of this document has been approved by the relevant ARTC engineering authority and has also been endorsed by the ARTC Safety Committee. Document Supply and Control The Primary Version of this document is the electronic version that is available and accessible on the Australian Rail Track Corporation Internet and Intranet website. It is the document user s sole responsibility to ensure that copies are checked for currency against the Primary Version prior to its use. Copyright The information in this document is Copyright protected. Apart from the reproduction without alteration of this document for personal use, non-profit purposes or for any fair dealing as permitted under the Copyright Act 1968, no part of this document may be reproduced, altered, stored or transmitted by any person without the prior written consent of ARTC. March 2005 Page 2 of 14

About This Standard The majority of System Substations in the ARTC network are traction locations with 1500 Vdc equipment and so require special precautions compared to standard transmission, subtransmission or zone substations owned by Transgrid and the local Electricity Distributors. Those System Substations that do not contain 1500 Vdc equipment are interconnected to the ARTC traction network and so must still follow these requirements. This document states the essential requirements for a safe earthing system at ARTC System Substations although the general methodology referred to in the document can also provide a general guidance to the design of earthing systems for System Substations. March 2005 Page 3 of 14

Document History Primary Source RIC Standard EP 12 10 00 10 SP Version 2.1 List of Amendments ISSUE DATE CLAUSE DESCRIPTION 1.1 05/01/2005 Reformatted to ARTC Standard 1.2 11/03/2005 Disclaimer Minor editorial change March 2005 Page 4 of 14

Contents 1. General...7 1.1. Earthing System Design...7 1.2. Equipment to be Earthed...7 2. Types of System Substations...8 2.1. Traction Substations...8 2.2. Sectioning Huts...8 2.3. AC Switching Stations...8 3. Earth grid...8 3.1. Electrodes...8 3.1.1. Standard Electrode...8 3.1.2. Electrode Spacing...9 3.1.3. Installation of Electrodes...9 3.1.4. Test Electrode...9 3.1.5. Earth Mesh...9 3.2. Earthing Connections...10 3.3. High Voltage Earth Conductor Sizing...10 4. Equipment Earthing...10 4.1. Auxiliary Supplies...10 4.2. Low Voltage Final Subcircuits...11 4.3. Surge Arresters...11 4.4. Batteries...11 4.5. Cable Sheath and Armour...11 4.6. Telecommunications Equipment...11 4.7. Metallic Pipes...11 4.8. Neutral Resistors...12 4.9. 1500 V Link Area (Voltmeter Rail)...12 4.10. Rail Earth Contactor...12 4.11. Frame Leakage Protection...12 March 2005 Page 5 of 14

5. Substation Metal Fences...12 5.1. Clearance to Other Earthed Equipment...12 5.2. Other Clearances...12 5.3. Bonding of Gates...13 5.4. Grading Ring...13 6. Supplies to Nearby Loads...13 7. Sectioning Hut Supplied from Distribution Substation...13 March 2005 Page 6 of 14

1 General This document is written on the premise that a System Substation will use a combined earthing system and will therefore have only one earth grid. There will be rare occurrences at nontraction locations where a separate earthing system may be a better option resulting in the use of two separate earth grids for the high and low voltage earths. This situation is most likely to arise at a small AC switching station with transmission line feeders where it is not economical to meet all the requirements of a combined earthing system. In this situation the earthing design principles of Specification PDS 05 - Distribution Substation Earthing should be followed. System substations in general tend to have: A high fault level A large earth grid that is walked over by substation staff A number of items of electrical equipment with electrical protection of various clearing times A number of aerial and/or cable feeders Fences with associated prospective touch voltages for people external to the substation Other services (eg water, communications) connected 1.1 Earthing System Design Due to all the variations and high fault levels a full detailed design must be carried out for the earthing system of each individual System Substation. The design methodology set out in figure 2.1 of the ESAA Substation Earthing Guide can be used as a guide for the calculations to ensure safe prospective touch and step voltages. Note: The fault duration time applicable for calculating acceptable touch and step potentials, is that for the primary protection to operate, it being recognised that the number of occasions when the stated time limit may be exceeded due to unavoidable malfunction or combination of unlikely circumstances is negligibly small. Refer to section 4.4.3 of the ESAA Substation Earthing Guide. 1.2 Equipment to be Earthed Equipment to be connected to the combined high and low voltage earthing system includes: Earth grid. All accessible exposed metal parts containing or supporting high voltage conductors, including metal parts mechanically connected to the exposed metal parts. Metallic substation enclosures of all high voltage and low voltage equipment. March 2005 Page 7 of 14

Surge protection devices. Cable sheaths/screens/armouring. Exposed metal of all floor and wall reinforcing. Metallic fences, both internal and boundary. Fixed metal items within the substation building, eg door frames, metal roofs and down pipes. Metal pipes, eg waterpipes, within the substation boundary. Transformer low voltage neutrals. The following equipment shall not to be connected to the combined high and low voltage earthing system: Any part of the 1500 V negative return path. Metal battery stands. Some existing 220 V auxiliary supplies (refer to section 4.1). Rectifier cubicles and dc circuit breaker frames. In most cases, and any future designs, this equipment shall be connected to earth through a frame leakage relay (refer to section 4.11). 2 Types of System Substations 2.1 Traction Substations These locations are the supply points for the overhead wiring. All the sections in this document may be relevant. 2.2 Sectioning Huts These locations are to sectionalise the overhead wiring for dc protection and voltage regulation. All the sections in this document may be relevant. Note, if the Sectioning Hut includes any high voltage ac switching equipment, then the design shall be the same as for a Traction Substation. 2.3 AC Switching Stations These locations are ac switching stations that have high voltage circuit breakers. There is no 1500 V equipment at these locations. 3 Earth grid 3.1 Electrodes 3.1.1 Standard Electrode The standard electrode is a 3.6 m length of copper tube (14.29 mm outside March 2005 Page 8 of 14

diameter, 11.03 mm inside diameter). Longer electrodes may be used if there is some difficulty obtaining the required resistance as the soil resistivity is usually found to be lower at a greater depth. The current rating of the earthing electrode is 5 ka for 1 second when tested in free air in an ambient of 15 C to 25 C without exceeding a temperature rise of 350 C. 3.1.2 Electrode Spacing The earthing system at a System Substation consists of a minimum of 4 earth electrodes installed around the inside perimeter of the substation and connected together with the earth mesh. The exact spacing of the electrodes will be determined by the final design, which will be based on local conditions, resistivity of the area and space available for electrodes. The spacing between electrodes should be greater than the electrodes length. Although the earth mesh will often result in a low enough resistance without the use of electrodes, a minimum of 4 electrodes are still necessary to ensure the fault level capability ie 4 x 5 ka. Electrodes are also required in case of the drying out of the soil at the depth of the earth mesh in long dry spells. It should also be noted that the electrodes should be placed around the perimeter as it has been shown that any centre electrodes will not reduce the resistance of the earth grid significantly. 3.1.3 Installation of Electrodes The electrodes shall not be driven. Use drilled holes (50 mm diameter) back filled with a conducting medium mixture, for example bentonite, gypsum and sodium sulphate (50%, 45% and 5% by weight respectively) mixed to AS 2239 - Cathodic Protection), or similar. The top of each electrode is to finish 200 mm below ground level. Each earth electrode is to have a collar and lid. 3.1.4 Test Electrode All new System Substations must have a test electrode installed. The test electrode is to be easily disconnected from the earth grid, without any effect on the grid, to allow resistance testing of the electrode and to check physical deterioration. The test electrode must be placed where it is easily accessible and can be withdrawn without the need to remove supply from any item of live equipment. The test electrode shal be identified by painting the word Test on the lid. 3.1.5 Earth Mesh Buried horizontal conductors are placed under the area of a substation to provide surface gradient control by reducing the values of prospective step voltages for persons working within the substation during a fault. The mesh configuration will also reduce the earth grid resistance. The size and spacing of conductors must be calculated as part of the design process. For further advice refer to the Electricity Supply Association of Australia guide EG1(95) - Substation Earthing Guide. March 2005 Page 9 of 14

3.2 Earthing Connections All underground connections shall use an exothermic welding process such as a cad weld. This includes connections to electrodes. The exothermic weld is preferable to a clamp because of the high fault levels of System Substations and the electrolysis problems associated with Traction locations. C clamp connections may be used on above ground joints that are visible for inspection. Typical connection diagrams are currently shown in drawing C/79930 which will be replaced by A3/90093 sheet 6. 3.3 High Voltage Earth Conductor Sizing The size of the high voltage earthing conductors is determined by the earth fault level and shall be in accordance with AS 3000, clause 7.8.10.7.2, but in any case shall be not smaller than 70 mm 2 copper. This value is larger than the 35 mm 2 copper conductor specified in the standard, but is required due to the proximity of the traction system. Note 1: The fault duration time applicable for calculating the size of conductors (including cable screens), is the duration of the back-up clearance time, that is, assumes that one primary protection system fails to operate. The temperature rise will not exceed the maximum temperature for the selected conductor size when carrying the maximum earth-fault current for this fault duration time. Note 2: The recommended inputs to the K factor referenced from AS 3008 are an initial temperature of 40 C and a final temperature of 160 C for PVC insulated conductors, or 250 C for bare or XLPE insulated conductors. 4 Equipment Earthing 4.1 Auxiliary Supplies The auxiliary services in a System Substation can include lighting, low voltage power, dc power supplies (not dc traction loads), ventilation and compressed air. The auxiliary services may be three phase 415 V or single phase 240 V, although a three phase 220 V system has been used in the past which is described at the end of this section. There is always a back-up auxiliary supply from a second source. It is usual practice to supply the auxiliary services in a ARTC System Substation from a transformer (designated auxiliary transformer) whose primary winding is supplied from one of the secondary windings of the rectifier transformer. The case of the Auxiliary transformer shall be connected directly to the earth grid with a 70 mm 2 copper conductor. In some situations the Auxiliary supply originates from a supply external to the substation, for example, a back-up emergency supply in a single rectifier substation. In these circumstances if the external supply is from the local distributor then the external supply must be connected via an isolating transformer. Refer to PDS 07 - Low Voltage Distribution Earthing fo relevant guidelines. Irrespective of the supply source, the neutral bar and the earth bar shall be connected together in the Auxiliary panel switchboard. This shall be the only neutral March 2005 Page 10 of 14

earth connection in the System Substation auxiliary supply. The size of the connecting conductor shall be based on the size of the active conductors from the auxiliary transformer. The earth bar shall be connected directly to the Substation earth grid with 70 mm 2 copper conductor. In the past, several variations of the auxiliary supply design have been used. Some of these variations are still in existence, but they should not be used in any new designs. In one variant used in Traction Substations the earth-neutral connection is made at the auxiliary transformer. This is undesirable as it can result in circulating currents at two rectifier locations where there are two earth-neutral connections, one at each transformer. An older method used in Traction Substations and Sectioning Huts used a floating three phase 220 V system with C phase connected to earth via a spark gap and an earthed screen in the auxiliary transformers. 4.2 Low Voltage Final Subcircuits Each low voltage final sub-circuit shall contain an earthing conductor in accordance with AS 3000. 4.3 Surge Arresters The connection between the earth side of the high voltage arrester and the earth side of the equipment being protected must be as short as possible (the same applies to the live side of the surge arrester). The resistance connection to remote earth is not critical to the surge arrester operation but it is important to consider the touch potentials during the surge arrester operation. 4.4 Batteries All System Substations require a set of batteries, and battery charger, to supply power for the control circuits of circuit breakers and SCADA equipment. The dc battery system shall not be earthed. 4.5 Cable Sheath and Armour All high voltage and 1500 V positive screened cable sheaths and armouring must be connected directly to the earth grid. 4.6 Telecommunications Equipment Refer to RailCorp publication EP90100003SP - Co-ordination of Communication and Power Systems - Earth Potential Rise. 4.7 Metallic Pipes All underground metallic pipes (eg water or air) entering a System Substation shall be electrically isolated by the permanent installation of an approved isolating joint one metre outside the substation boundary, as shown on drawing D/89147. Isolation is to provide protection against electrolysis corrosion. An approved sign, as also shown on drawing D/89147, is to be secured to the fence directly above the pipe. Any metallic pipes within the substation boundary must be bonded to the substation earth grid by a 70 mm 2 copper conductor. March 2005 Page 11 of 14

4.8 Neutral Resistors Neutral resistors are employed at some System Substations to reduce the earth potential rise under fault conditions. The neutral resistor shall be connected to the System Substation earth through a neutral leakage relay. 4.9 1500 V Link Area (Voltmeter Rail) A short length of rail shall be installed in the 1500 V link area to facilitate the connection of a voltmeter to test dead the feeders. The rail is to be connected to the track side of the negative reactor in a Traction Substation and to the negative of the REC in a Sectioning Hut. The rail should be placed 1 m clear of any other metalwork, if this is not possible a warning sign is to be erected on the fence of the link area opposite the voltmeter rail stating: WARNING VOLTMETER RAIL IS CONNECTED TO TRACTION NEGATIVE DO NOT BRIDGE TO EARTH. 4.10 Rail Earth Contactor A rail earth contactor is to be installed at all Traction Substations and Sectioning Huts. This is a normally open latched contactor connected between rail and earth that is designed to close when its voltage sensing circuit detects a dangerous potential difference between rail and earth. It will remain closed until manually reset on-site. Refer to drawing D/82590 for Schematic Diagram, D/78180 for Connection Diagram and B/82194 for Panel Arrangement. 4.11 Frame Leakage Protection The rectifier cubicles and dc circuit breaker frames in Traction Substations and the dc circuit breaker frames in Sectioning Huts shall be connected to earth through a frame leakage relay. An earth conductor is connected from the DCCB frame leakage bar to each DCCB frame in turn. If a breakdown occurs between frame and earth on any one DCCB causing a current to flow, the frame leakage relay will open a set of contacts disconnecting supply for the 120 V controls to al DCCB s, as shown on drawing D/86513 sheet 1. In addition at a Traction Substation the rectifier, whose frame is sitting on a sheet of 3 mm Cadco (insulating material), has an auxiliary relay connected into the circuit as shown on drawing D/86513 sheet 2. This locks out the rectifier to prevent it feeding into the busbar and frame to earth. The rail earth contactor will also operate, refer to section 4.10. 5. Substation Metal Fences 5.1 Clearance to Other Earthed Equipment A 2 m clearance shall be maintained between the substation boundary fence and any equipment connected to an external earthing system, such as an ARTC Distribution Substation or other local Electricity Distributor Substation. A clearance is required to reduce the risk of a prospective touch voltage. The distance of 2 m has been selected to ensure that a person cannot contact the substation fence, substation earth, and the other earthing system at the same time. 5.2 Other Clearances A 2 m clearance shall be maintained between the substation boundary fence and March 2005 Page 12 of 14

any continuous metal structure, such as a fence, pipe or signal troughing, that can be connected to a remote earth. Where the 2 m clearance cannot be obtained, a suitable approved method such as installing two isolating breaks 2 m apart in the continuous metal structure shall used. Alternatively the situation can be proved safe by calculation and testing for dangerous touch voltages in accordance with the ESAA Substation Earthing Guide. 5.3 Bonding of Gates Bonding conductors must be used where there are any breaks in continuity in the fence, such as for gates. The size of this conductor is dependent on the fault level at the substation, but in any case shall be a minimum of 70 mm 2 copper. 5.4 Grading Ring Grading conductors, where required, are to be placed around the fence to reduce prospective touch potentials, usually one bare 70 mm 2 copper conductor is installed 1 m outside the fence and at a depth of not more than 0.5 m. The grading conductor is to be regularly bonded to the fence at intervals not greater than calculated in Appendix C3 of AS 2067. This grading ring is included as part of the overall earth grid design and included in the resistance calculations. 6. Supplies to Nearby Loads Low voltage supplies are not to be provided to nearby loads, such as depots, camps or private consumers, external to the System Substation unless a detailed design is carried out. The connection of a load external to the substation will transfer the substation earth potential which, under a high voltage fault, will result in high prospective touch voltages at the remote site. Note, a 33 kv fault can result in voltages over 10 kv but a standard 240/240 V isolating transformer has a design withstand voltage of only 5 kv. Where an isolating transformer is used in a System Substation the case of the transformer must be connected to the Substation earth. This requirement is based on the necessity to earth all metalwork in a substation. (refer to section 1). It is not an electrical requirement with regard to isolation. The screen of the isolating transformer must also be connected to the Substation earth grid. The connection is to be sized to carry the maximum fault currents that may flow for the time required for the back-up protective device to operate. Refer to section 3.3, except that the minimum size shall be 16 mm 2 copper. 7. Sectioning Hut Supplied from Distribution Substation A Sectioning Hut is usually supplied from a dedicated ARTC Distribution Substation located outside of the Sectioning Hut boundary. In this situation the relevant section of the Specification PDS 05 - Distribution Substation Earthing in Volume 2 shal be used for the high voltage earthing only. The secondary of the transformer shall not be earthed at the Distribution Substation, the only low voltage earth system will be the Sectioning Hut earth grid. The transformer mains active and neutral conductors must be double insulated all the way into the supply main switchboard of the Sectioning Hut. The Sectioning Hut supply main switchboard shall have the neutral bar and the earth bar connected together; this shall be the only earth-neutral connection for the Sectioning Hut supply. The earth bar of the switchboard shall be directly connected to the Sectioning Hut s earth grid. March 2005 Page 13 of 14

In the situation where a Sectioning Hut is not supplied from a dedicated Distribution Substation, that is, other loads are connected to the same Distribution Substation as the Sectioning Hut then the Sectioning Hut must be supplied through an isolating transformer located within the boundary of the Sectioning Hut. If the high voltage supply to the Distribution Substation is greater than 11 kv then a detailed design shall be carried out to ensure the withstand voltage of the isolating transformer is rated for all possible fault conditions. The screen of the isolating transformer must also be connected to the Sectioning Hut earth grid. The connection is to be sized to carry the maximum fault currents that may flow for the time required for the back-up protective device to operate. Refer to section 3.3, except that the minimum size shall be 16 mm 2 copper. If the supplying Distribution Substation is owned by a Local Distributor, refer to Specification PDS 07 - Low Voltage Distribution Earthing for additional guidelines. Due to the relatively low ac fault levels at Sectioning Huts and the fact that the 1500 Vdc system is unearthed, the earth grid resistance can be based on the size of the transformer of the Distribution Substation supplying the Sectioning Hut. Refer to Specification PDS 05 - Distribution Substation Earthing. This policy is based on EC 5 - Guide to Protective Earthing - Electricity Council of N.S.W. - 1992 which recommends a maximum touch voltage of 4000 V when a fault duration of 0.2 seconds can be achieved at frequented locations with an operating voltage less than or equal to 66 kv. The dc circuit breakers and rail-earth contactor operate well under this time, therefore, a 1500 V fault will not cause any dangerous touch and step voltages The Sectioning Hut can then be treated as a Distribution Substation for calculation of earth grid resistance, although all other aspects should be based on this document, including minimum numbers of electrodes. March 2005 Page 14 of 14