NEW equinox INSTALLATION GUIDE Issue

Similar documents
NEW equinox INSTALLATION GUIDE Issue

INSTALL IN 2 DAYS. *Assumes 3-man fitting team. equinox. Tiled roof system. Installation guide ISSUE 1

equinox INSTALLATION GUIDE Issue CONTENTS If in doubt at any stage BE SAFE WHEN WORKING AT HEIGHT

CONSERVATORY ROOF INSTALLATION GUIDE Issue

skypod INSTALLATION GUIDE Issue 2 CONTENTS 1. Preparing to install 3 2. Installation 4 3. Installing jack rafters Installation examples 11

Eurocell conservatory roof system. Installation manual Issue 3

Guardian warm roof conversion system. Installation Guide

INSTALLATION GUIDE SLIMLINE ROOF LANTERN 4 PANE CONFIGURATION

NEW skypod INSTALLATION GUIDE

skypod INSTALLATION GUIDE CONTENTS Issue 2 If in doubt at any stage NOW INCLUDES ACUTE BE SAFE WHEN WORKING AT HEIGHT

Installation guide. Step-by-step instructions

Installation guide for 20/20

Roll-Fix Kit The complete dry hip kit RFIG

Skypod. Pitched PVC-U skylights. Installation guide PITCHED PVC-U SKYLIGHTS ISSUE 1

The Leka System Installation Guide

Skypod. Pitched PVC-U skylights. Installation guide PITCHED PVC-U SKYLIGHTS ISSUE 1

Skypod. Pitched PVC-U skylights. Installation guide PITCHED PVC-U SKYLIGHTS ISSUE 1

This installation guide has been created to assist in constructing a Liniar conservatory roof from a kit format.

ENGINEERING STRENGTH INSTAL L AT I O N M A NUAL OUR STRENGTH IS OUR STRENGTH

VINYL CLASSIC FREESTANDING PERGOLA ASSEMBLY INSTRUCTIONS

Gardman Lean-to Greenhouse Assembly Instructions

TRADITIONAL GABLE ATTACHED PATIO AND CARPORT. Your complete guide to building an ATTACHED Outback TRADITIONAL GABLE PATIO or CARPORT

Installation. ng Kitt

Greenhouse Assembly Instructions

On-Roof Mounting Sets for Flat-Plate Collectors

This installation guide has been created to assist in constructing a Liniar conservatory roof from a kit format.

Recommended Slating Tools

CURVED ROOF ASSEMBLY INSTRUCTIONS ATTACHED VERANDAH. Your supplementary guide to building an ATTACHED CURVED ROOF VERANDAH or PATIO BEFORE YOU START

DUTCH GABLE FREESTANDING CARPORT

Shed Assembly Instructions

manthorpe Roll-Out Dry Fix Ridge System building products Fixing Instructions MBP 8265e

REGENCY TIMBER BUILDINGS

S H E D A S S E M B L Y I N S T R U C T I O N S

Cardo DOOR & RETURN SHOWER ENCLOSURE INSTALLATION PLEASE READ THESE INSTRUCTIONS CAREFULLY.

CountryAccents Pergola Assembly Instructions

ALL SEASON PATIO COVER

SuperFOIL Insulation. Solutions Guide. Pitched Roof - Under Rafter

Octagon Vinyl Gazebo Assembly Instructions

PINEHAVEN SHEDS Assembly Instructions FOR LEAN-TO SHEDS

How To Build Decorative. Timber Awnings

YWY M08 The new VELUX solution

Octagon Vinyl Gazebo Assembly Instructions For 10 & 12 Models

DUTCH GABLE CARPORT RECOMMENDED INSTRUCTION MANUAL

COMPONENTS OF THE CLICKFAST FASCIA AND GUTTER SYSTEM 5: INTERNAL MITRE

Installation Guide Simplicity Alfresco. V1.9 Lu070318

Gambrel Barn with Overhang Manual

MODEL No: GSS3030G. Model No:...GSS3030G Overall Size (W x D X H*) x 3000 x 2100mm Roof Type:...Gable *Minimum Wall Height

ROOF FRAMING INFORMATION BATTEN INSTALLATION CORONA SHAKE INSTALLATION ACCESSORY INSTALLATION ESTIMATING DATA GENERAL INFORMATION

ROOF KIT ASSEMBLY INSTRUCTIONS

Section 1 Specifications..

Installation Guide. Guardian Slate Roof System. England, Scotland & Wales

Star Barn Manual. Tools Needed:

Sunhouse. Assembly Manual

Shingle Installation Guide

REDLAND DRY VALLEY. Installation Instructions for Redland Dry Valley. Version: 6. Date: May Redland Technical Solutions

Vinyl Gazebo Instructions

Pocket Door Kit PD1 / PD2 Installation Instructions. Kit Contents.

15 YEAR GUARANTEE. Tough and long lasting Guaranteed waterproof for 15 years Economical and easy to fix AVAILABLE IN A RANGE OF COLOURS

MONO PITCHED CHIMNEY FITTING INSTRUCTIONS STANDARD LITESTACK CHIMNEY FITTING INSTRUCTIONS HEALTH & SAFETY WARNING:

GV Standard PitchVent

Synseal assembly guide 2009:Synseal assembly guide /2/09 12:38 Page 1. Conservatory Roof Assembly Guide

8x4 SpaceSaver Garden Shed Assembly Manual

Pergola Installation Instructions

Installation Guide Contemporary Alfresco V1.3 LU

Assembly Instructions

GABLE END CHIMNEY FITTING INSTRUCTIONS STANDARD LITESTACK CHIMNEY FITTING INSTRUCTIONS. HEALTH & SAFETY WARNING:

SIMPLER BETTER FASTER

Installation Guidelines

ASSEMBLY GUIDE. Mia Narrow Bookcase

Safety Glasses Safety Gloves Ladders Measuring Tape Spirit Level String Line. Tin-Snips Rivet Gun Caulking Gun Silicone Socket Set

CHICKEN COOP & CHICKEN RUN. Tools required for assembly (not included)

Quick Hook SS & LS Standard and Low Height Hooks for Side Mount Rails

GROWING BETTER THROUGH DESIGN. 6ft Lean-To LEAN-TO. Assembly Instructions 04/02

S H E D A S S E M B L Y I N S T R U C T I O N S

STRATCO GABLE HOMESHED STRATCO GABLE HOMESHEDS STUBBIE INSTALLATION GUIDE

SteelChief Installation Instructions for pre-assembled panel form sheds GABLE ROOF

12x12 Pavilion. Assembly Manual

Corner Potting Store Assembly Instructions

INTRODUCTION. EqunioxRoof.com. Pro Tip

CLEARSPAN GABLE STRATCO OUTBACK ASSEMBLY INSTRUCTIONS. WITH GAZEBO END ATTACHED PATIO

INSTRUCTIONS FOR: GALVANIZED STEEL SHED 3 x 3 x 2.1mtr. MODEL No: GSS3030

Sandtoft installation guides

Contents. Stage 1. Preparation of the aperture 9. Interior finishing 25

Installation Instructions

Allora ALCOVE ENCLOSURE INSTALLATION BEFORE INSTALLATION CHECK THAT YOUR ALLORA SHOWER ENCLOSURE SYSTEM IS UNDAMAGED

Dura-Lock Roof System

Installation Guide. Please read before installing SIPs Kit. 1 Method Statement for the erection of a SIPS Industries Kit Materials...

Special Roofs and Vertical Slating

PV SLATE ROOF INSTALLATION GUIDE

Austin Standing Seam Awning Assembly and Installation Instructions. Assembly Instructions

Stratco Sanctuary INSTALLATION BEFORE YOU START TOOLS REQUIRED GUIDE

GLOSSARY OF TERMS SECTION 8

BEST PRACTICE GUIDE. Socket Bases. Working with Concrete Slabs

8x12 SpaceMaker Garden Shed Assembly Manual

Quick Hook SB & LB Standard and Low Height Hooks for Bottom Mount Rails

Assembly Instructions 10 X 10 Aluminum Roof Support

Assembly instructions for: HOT TUB ENCLOSURE KITS / HOT TUB PAVILION

v1.0 ASSEMBLY GUIDE Mia Wide Bookcase

9x9 Penthouse Garden Shed Assembly Manual

GIRTS ON BACK OF BUILDING

Transcription:

NEW equinox INSTALLATION GUIDE Issue 1 CONTENTS If in doubt at any stage 1. Preparing the ring beam 2 2. Installing the framework 3 3. Insulation and waterproofing 7 4. Tile application: Steel tiles 9 5. Non-standard roof crowns 11 6. Tile application: Composite slates 13 7. Roof windows 15 8. Finishing off 17 9. What next 19 Please contact our Equinox Technical Support for additional support or advice. 0333 777 3057 equinox@eurocell.co.uk

INSTALLATION GUIDE 2. INSTALLING THE FRAMEWORK PRE-INSTALLATION CHECKS 2.1 2.2 Equinox roof kits should be checked against the order acknowledgement provided by Eurocell. Before discarding any packaging, check all components are accounted for. Prior to commencing any installation work, the size, type, and condition of all Equinox roof kits should be checked against the survey sizes. When retro-fitting the Equinox tiled roof system, ensure the existing conservatory is structurally sound before conducting any installation work. Align the locating nib with the front edge of the frame. Clamp to frame to hold in position. Continue locating the ring beam using the internal and external brackets and 40mm self-drill screws (supplied). 1. PREPARING THE RING BEAM 1.1 1.2 2.3 2.4 All the M6 x 30mm flat plate studs should already be set Where a box gutter is required Ensure the window frames are correctly aligned. Once the ring beam is in place, screw up from the frame in position on the ring beam. Check the position of the Fix the pre-cut box gutter to the property wall with 7.5mm using self-drill baypole screws (not supplied) to secure. studs and that they are all there. Slide in additional studs x 100mm Concrete Screws (not supplied) at 400mm if required. centres before installing the ring beam. 2 EQUINOX INSTALLATION GUIDE 3

2.5 2.6 2.9 2.10 Position the first two Boundary Members (BM) against the wall to check position against previous conservatory. Mark these positions. Attach nuts, but do not fully tighten. If necessary, tidy up any plaster above the marked lines. The hips are a two-part component and locate into the ring beam and rest on the top plate. Position all hips and locate on to bottom studs. Do not fully tighten the nuts. 2.7 2.8 2.11 2.12 Using the pre-positioned bolts, locate the rafter in the ring beam and ridge. Do not fully tighten the nuts. Again, check alignment of frames. Once the ridge is in place, locate the hips. Aligning the centre of the hip with the corner of the frames. Locate any jack rafters on the ring beam and studs. Use studs supplied to fix top of the jack rafter to the hip. Do not fully tighten the nuts. Check the location and level of the ridge. Ensure all rafters are aligned. Tighten all nuts in the ridge and ring beam. Do not tighten jack rafters and hips at this point. 4 EQUINOX INSTALLATION GUIDE 5

3. INSULATING & WATERPROOFING 2.13 2.14 3.1 3.2 Clamp the wok to the hip. Insert the stud into the pre-drilled hole and bolt together. Do not fully tighten. Ensure jack rafters and hips are correctly aligned. Set hips in position using 40mm self-tapping screws, then tighten all remaining nuts in the hips, jack rafters and ridges. Once all of the framework for the roof is assembled, start fitting the pre-cut 100mm insulation. Additional insulation. At the crown and ridge of the roof, insert cavity insulation (supplied) between aluminium. 2.15 3.3 3.4 Fix gable rafters (at 400mm centres) to the back wall using suitable 7.5mm x 100mm concrete screws (not supplied). Once insulation is fully fitted, cover the entire roof with the pre-cut 12mm plywood. To fix on to bottom of ring beam, use 20mm self-drilling screws (supplied). Fix these 55mm from the front edge, every 300mm. Then, fasten up the hips and rafters every 300mm, using 40mm self-drilling screws (supplied). Once the plywood is fitted and secure, fit the drip tray around the edge of the roof. 6 EQUINOX INSTALLATION GUIDE 7

3.5 4. TILE APPLICATION: STEEL TILES 4.1 LOOKING FOR COMPOSITE ROOF SLATE INSTRUCTIONS? GO TO PAGE 13 Cover the roof with a breathable membrane. Ensure at least 50mm of membrane runs over the edge of the roof (this can be trimmed back later). When the roof is felted, tile application can commence. Position the tile cleat to overhang the roof by approximately 50mm and attach to roof using a batten (running vertically up the roof). Attach tile cleat at either end of the facet, then install battens across the whole facet at 300mm centres. 4.2 4.3 Once the cleat is in place, hook the first tile over the cleat to locate. Continue to install the tiles by fixing to the battens along the top edge of the tile. 8 EQUINOX INSTALLATION GUIDE 9

5. NON-STANDARD ROOF CROWNS (STEEL TILE ONLY) 4.4 4.5 5.1 5.2 Once the roof is fully tiled, lay the framework to tile the ridges. Using a ridge tile to set the width, fix timber battens over ridge and hip ready for the ridge tiles application. Using high-quality flash band (supplied), seal the ridge joints with a heat gun. Once the ridge tile position has been established, mark the flash band with the central location of each hip. This will identitfy the capping point of the roof. Using a ridge tile position, fix the battens for the ridge and hips to create a framework for the cap. The ridge tiles running up the hips should be spread to reduce their height. This way they can fit under the ridge tile. 4.6 4.7 5.3 5.4 Affix ridge tiles to timber battens and finish with end caps. Complete the tiling by fitting the ridge moulding. Once the cap is created, use the centre line drawn in step 5.1 to line up and mark the tiles that cover each of the hips. Once you are happy with the position of the tiles, you can cut them to sit in position. 10 EQUINOX INSTALLATION GUIDE 11

6. TILE APPLICATION: COMPOSITE SLATE TILES 5.5 5.6 6.1 Continue working your way around the cap, cutting each ridge tile into the previous one. Once all the hip tiles are in place, position the ridge tile. Mark carefully so the ridge tile sits at the cap of the roof. Begin tiling along the roof edge, starting from the centre and work your way out, allowing for a 50mm overhang over the ring beam. Tiles should be screwed onto the plywood directly using 2 x 35mm steel screws or clout nails. Tiles should be aligned using the centre markers and gauge pre-marked on the tiles. Gauge Roof pitch 6 14-25 6.5 25-27.5 7 27.5-30 7.5 30 + 5.7 5.8 6.2 6.3 Cut the tile to size and fit into position. Use the glue and dust kits (supplied) if additional cover of the joins is required When you reach the ridge edges, you need to cut the tiles to shape and size to fit the ridges of the roof. Using a high quality flash band, seal the ridge joints with a heat gun and install the ridge tiles. 12 EQUINOX INSTALLATION GUIDE 13

7. ROOF WINDOWS OPTIONAL 6.4 6.5 7.1 7.2 Affix ridge tiles using 2 x 30mm stainless steel screws. Complete the tiling using ridge tiles. Before installing the roof window, install the first course of tiles. Place the roof window in position and mark the position of the roof. Cut the breathable membrane using a Stanley knife leaving at least 75mm on each side to overlap the outside of the frame (see inset). 7.3 7.4 Reposition the frame and mark the position of the roof window on the plyboard. Cut the hole to size using a jigsaw. 14 EQUINOX INSTALLATION GUIDE 15

8. FINISHING OFF 7.5 7.6 8.1 8.2 Drop the roof window into place. Ensuring the breathable membrane covers the outside of the frame. Install the roof window following the manufacturer s instructions. Install capping board by positioning the first gutter bracket and marking its location. Screw will then be covered by the gutter bracket. These steps can be done before or after the drip tray and membrane are installed. Fix the gutter brackets into the ring beam using 40mm self-tapping screws at maximum 450mm centres. 8.3 Fix the guttering into position on the gutter brackets, taking care to seal the external angles. Affix corner trims onto fascia boards. 16 EQUINOX INSTALLATION GUIDE 17

9. WHAT NEXT? To complete your Equinox installation, you will need to 8.4 8.5 finish the roof off internally. Please note: the materials to complete this part of the job are not supplied. 9 FOR A PLASTERED FINISH To achieve 0.15 U-value To meet Building Regulations in Scotland Use a 65mm PIR insulation and plaster board To achieve 0.18 U-value To meet Building Regulations in England and Wales Use a 50mm PIR insulation and plaster board Optional downlights (not supplied) can be installed before decorating is undertaken. Reposition the exisiting lead to complete the external installation We advise carrying out a water test for both steel and composite slate tile installations. This should be done before internal work commences. Alternatively, tongue and groove effect is popular among customers. YOUR FINISHED ROOF 18 EQUINOX INSTALLATION GUIDE 19

ALSO AVAILABLE Visit eurocell.co.uk to find more installation guides and installation videos for Eurocell products. Product specification is subject to change without notification. Please also note that colours shown are illustrative only, as the printing process does not allow 100% accurate colours to be reproduced. EQUINOXINSTALL/APR15/H&S