Effect of Dowel Bar Embedment Length on Joint Load Transfer Efficiency of MnROAD Concrete Pavement Test Cells

Similar documents
Dowel Bar Alignment and Location for Placement by Mechanical Dowel Bar Insertion

The Need for Improved Specifications on Dowel Bar Placement Tolerance

Dowel Alignment: Measurement and Impacts on Pavement Performance

ABCDE. TechBrief. Best Practices for Dowel Placement Tolerances

R&T UPDATE. An Alternative to Traditional Round Dowel Bars Plate Dowel Innovations Driven by Industrial Concrete Paving

PERFORM WITH PRECISION WELDED DOWEL ASSEMBLY LOAD TRANSFER PRODUCTS CONCRETE CONSTRUCTION SOLUTIONS BROCHURE

Mark B. Snyder, Ph.D., P.E.

Dowel. Design. Performance-Based World of Concrete Official Show Issue. Lift-truck design changes require a new look at joint durability

Magnetic Imaging Technology

Research. Maria Masten, P.E and Gordy Bruhn MnDOT Concrete Engineering Unit CPAM Concrete Paving Workshop March 9, 2017

Design and Construction of Highway Pavement Joint Systems

4.1. Foremen 4.2. Concrete plant manager 4.3. Concrete plant operator 4.4. Personnel performing saw cutting and joint sealing

Research A PERFORMANCE TESTING OF EXPERIMENTAL DOWEL BAR RETROFIT DESIGNS PART 1 INITIAL TESTING. Final Report

Jointing Rural Intersections

Session 8: Load Transfer Restoration. (Dowel Bar Retrofit, Cross-Stitching, and Slot Stitching)

Table 5G-2.01: Transverse Joint Requirements. Transverse Joint Type 6 C 12 7 C 15 8 CD CD CD 1 20

TechBrief. Precast Concrete Panels for Repair and Rehabilitation of Jointed Concrete Pavements

Design and Construction of Highway Pavement Joint Systems

Temperature Correction of Falling-Weight-Deflectometer Measurements

MIT Product Demonstration

MnROAD Automated Laser Profile System ALPS

Retrofit Dowel Bars in Jointed Concrete Pavement Long-Term Performance and Best Practices

Project No.: VTRC 06-R22 March Period Covered: Contract No.

Evaluation of Dowel Bar Inserter Practices in PCC Pavements with Magnetic Tomography Technology

Plate Dowels. An Innovation Driven by Industrial Concrete Paving. Introduction

A New Load Transfer Assembly for the Jointed Concrete Pavements

prepared by Tom Burnham, Co-Chair Minnesota Department of Transportation Mark B. Snyder, Co-Chair Engineering Consultant for National Concrete

Dowel Load Transfer Systems Their Evolution and Current Innovations for Sustainable Pavements

DATE: April 22, 2016 (CPR Details Revised & Dated April 22, 2016)

Precast Concrete Panels for Rapid Pavement Repair

PCCP Preservation Steps to Take to Extend Pavement Life and Performance of Your Concrete Pavements

Glass Fiber Reinforced Polymer (GFRP) Dowel Bars - Aslan 600

Initiating Cracks in PCC Pavements. Malcolm K. Lim, PE

Dowel Alignment Considerations and Specification Update

Corrosion-Resistant Coated Dowel Bars

Design and Construction of Highway Pavement Joint Systems

ASLAN 600 GLASS FIBER REINFORCED POLYMER (GFRP) DOWEL BARS FOR LOAD TRANSFER IN CONCRETE SLABS

A Solution to Cracking and Stresses Caused by Dowels and Tie Bars

Edgerail Aluminum Bridge Railing System Specification & Installation Instructions

PERFORMANCE OF PRECAST CONCRETE PAVEMENTS

Section 914. JOINT AND WATERPROOFING MATERIALS

Double Bar Plate Dowels for Saw-Cut Contraction Joints

This brochure is provided by:

Responses to Concrete Specifications Survey with Summary (2011)

LABORATORY EVALUATION OF CONCRETE-FILLED GFRP DOWELS IN JOINTED CONCRETE PAVEMENTS

B. Installation Instructions. Provide installation instructions, including any special equipment, to address the following.

To: New York State Department of Transportation ENGINEERING INSTRUCTION. Approved:

PAVEMENT SURFACE CHARACTERISTICS. Task 3 DEVELOPMENT OF A SOUND ABSORPTION PROTOCOL. Principal Investigator:

MODELLING OF CONCRETE PAVEMENT DOWEL-SLAB INTERACTION

Precast Concrete Pavement Background Concepts. Project 1517 FHWA, CTR & TxDOT Gary Graham November 15, 2001

POSTPRINT UNITED STATES AIR FORCE RESEARCH ON AIRFIELD PAVEMENT REPAIRS USING PRECAST PORTLAND CEMENT CONCRETE (PCC) SLABS (BRIEFING SLIDES)

TPF-5(188), Evaluation of Fiber Reinforced Composite Dowel Bars and Stainless Steel Dowel Bars

Dowel Bar Standardization. NC^2 Spring Meeting Savannah, GA

IGGA Guide Specification: Dowel Bar Retrofit (DBR) Introduction

Jointed Precast Concrete Pavement

Dowel Bar Alignment and Location for Placement by Mechanical Dowel Bar Insertion

Amplitudes Variation of GPR Rebar Reflection Due to the Influence of Concrete Aggregate Scattering

Ground Penetrating Radar (GPR) By Dr. Eng. Zubair Ahmed

COOLING TECHNOLOGY INSTITUTE AN INVESTIGATION OF PIN BEARING

Field Evaluation of Elliptical Fiber Reinforced Polymer Dowel Performance

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

Flanged Dowel Box. Load Transfer System INDUSTRIAL SLAB ON GROUND

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION

Dowels for the 21st Century

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

AMENDMENTS Manual of STANDARD SPECIFICATIONS. Adopted by Standard Specifications Committee. Amendment. No. 6. Published by

Non-Destructive Bridge Deck Assessment using Image Processing and Infrared Thermography. Masato Matsumoto 1

Dowel connections in laminated strand lumber

2008 MnROAD Unbound Quality Control Construction Report

Experimental and numerical study of nailed laminated timber elements for in plane and transverse loading

ABC and Innovative Bridge Construction for Minnesota Local Roads

JVI Vector Connector

USE OF TEAR-OFF RECYCLED SHINGLES IN ASPHALT PAVEMENTS

TxDOT Project : Evaluation of Pavement Rutting and Distress Measurements

Comparison of Four Different Methods for Measuring Deflections in Jointed Reinforced Concrete Pavements

Chapter 4 Results. 4.1 Pattern recognition algorithm performance

CITY OF BEVERLY HILLS Department of Public Works and Transportation Civil Engineering Division STREET/ALLEY IMPROVEMENT PLAN REVIEW CHECKLIST

CHAPTER 7: ALIGNMENT

Precast Concrete Pavement Panels on Minnesota Trunk Highway 62 - First Year Performance Report

Mobile Survey of Rail Track and Bed

PD 3 Dowel Cradle. Load Transfer System Industrial Slab on Ground

Dowel Placement Tolerances for Concrete Pavements

² TL Beton-StB 07 = German technical conditions for construction materials for concrete road pavements

CCFSS Technical Bulletin

Lawrence A. Soltis, M. and Robert J. Ross, M. 1

Diamond Dowel. Load Transfer System INDUSTRIAL SLAB ON GROUND

Fast Track Precast Concrete Pavement Rehabilitation Pilot Project

EVALUATION OF ALTERNATIVE DOWEL BAR MATERIALS

ASSESSMENT OF GROUTED GLASS FIBRE-REINFORCED POLYMER (GFRP) TUBES AS DOWEL BAR ALTERNATIVES

Chapter 8 PRE-INSTALLATION PROCEDURES COMMON TO ALL SYSTEMS

Joint Evaluation Report

Advanced Methods to Identify Asphalt Pavement Delamination (R06D) Minnesota DOT Evaluation: Calibration and Signal Analysis

Plan Preparation Checklist

SPECIFICATIONS FOR THE MANUFACTURE AND DESIGN OF PRECAST THREE SIDED ARCH STRUCTURES, WINGWALLS AND HEADWALLS

Cast-in Ferrule Connections Load/Displacement Characteristics in Shear

Standard Specifications

VILLAGE OF VILLA PARK CENTRAL BOULEVARD IMPROVEMENTS LOCATION MAP (NOT TO SCALE) CORTESI AVE. MYRTLE AVE. CENTRAL BLVD.

Sewer Line Extension Permit Design Checklist

RlGIDITY AND STRENGTH OF WALL FRAMES BRACED WlTH METAL STRAPPING

TOLERANCES AND CLEARANCES FOR COMMERCIAL HOLLOW METAL DOORS AND FRAMES

Transcription:

Effect of Dowel Bar Embedment Length on Joint Load Transfer Efficiency of MnROAD Concrete Pavement Test Cells Thomas R. Burnham, P.E. Abstract It is well understood that for heavily loaded concrete pavements, the use of dowel bars across transverse joints can significantly improve their performance. To function effectively, dowel bars must be properly aligned and have sufficient embedment length to transfer stresses to the surrounding concrete. The use of new high accuracy dowel bar location equipment has brought renewed interest to understanding reasonable construction tolerances for dowel bar alignment. The thirteen-year history of pavement performance data from the Minnesota Road Research (MnROAD) facility provides a unique opportunity to examine the effects of dowel bar alignment on joint performance. Specifically, this study investigated the effects of dowel bar embedment length on joint load transfer efficiency. Results of the analysis show that most test cells demonstrate little effect on the overall level and variability of LTE from dowel embedment lengths as low as cm (4 in). Findings of this study could lead to important changes in construction specifications for dowel bar embedment length. Introduction It is well understood that for heavily loaded concrete pavements, the use of dowel bars across transverse joints can significantly improve their performance. Proper positioning of the dowel bars in relation to the transverse joint is paramount to that performance. Only with correct alignment and sufficient embedment length can a dowel bar transfer its stress to the surrounding concrete without causing damage. The final positioning of the dowels bars is determined both by the placement of the dowels during construction, and the creation of the transverse joint. One method of measuring the performance of transverse joints in concrete pavements is by tracking the long term load transfer efficiency of the joints. Joint load transfer efficiency (LTE) is simply the measurement of how a tire load is transferred across a joint. Jointed concrete pavements typically begin life with very high load transfer efficiency values, and then as the pavement shrinks and experiences heavy vehicle loads, the load transfer efficiency gradually declines. Load transfer efficiency is affected by parameters such as slab shape and thickness, joint opening (available aggregate interlock), dowel bar size, and seasonal base layer support. The Minnesota Road Research (MnROAD) facility was constructed in the early 19 s to study concrete and asphalt pavement performance (Minnesota Department of Transportation 27). Long term monitoring and testing of the test sections at the Thomas R. Burnham, M.C.E., P.E., Member ISCP Senior Road Research Engineer, Minnesota Department of Transportation Office of Materials, 1 Gervais Avenue, Maplewood, MN 559 Phone: (651) 366-5452, Fax: (651) 366-5461, email: tom.burnham@dot.state.mn.us 1

facility has provided a useful database of information about modern pavement performance, including load transfer efficiency trends for jointed concrete pavements. Readily available access to the test sections at the MnROAD facility also provides the opportunity to determine the physical aspects of each test section in detail. In terms of load transfer efficiency, this means determining the position of individual dowel bars within a transverse joint. Many studies have examined the effects of the misalignment of dowel bars on concrete pavement performance (Burnham 1999, FHWA 27, Lechner 25, Teller and Cashell 1958, Weaver and Clark 19). Most of the studies focused on the effects caused by vertical translation or rotational misalignment of the dowel bars. Much less emphasis has been placed on understanding the effects of dowel bar embedment lengths. Transverse joint performance may be reduced as a result of low dowel bar embedment length, which can be a result of dowel bar movement during paving, or by misalignment of the joint formation (sawing) in relation to the dowel bars. An earlier study (Burnham 1999) on a pavement in Fergus Falls, Minnesota, revealed that dowel embedment lengths could be as low as 6.3 cm (2.5 in) and still maintain reasonable load transfer efficiency across a transverse joint. Similar results from laboratory testing of specimens with a 6.8 cm (2.6 in) dowel embedment length have been reported (Freudenstein 21). Most transportation organizations, however, specify a minimum dowel embedment length of 7 inches for an 18 inch long dowel bar (Lane and Kazmierowski 26). The Minnesota Department of Transportation has no specified criteria for minimum dowel embedment length, but has an available dowel bar embedment length of 1 mm (7.5 inches) for the standard 3 mm (15 inch) long dowel bars. There can be many causes for low dowel embedment length in the field. Sawing of the transverse joints is often done at night, where it can be difficult to see the alignment marks painted on the grade adjacent to the new slabs. The baskets that the dowel bars are installed on are also prone to shifting during the paving process. While the current standard for Minnesota concrete pavement is the use of perpendicular (to traffic flow) transverse joints, the old standard (used at MnROAD) was skewed transverse joints. Informal investigations of other Minnesota concrete pavements with skewed transverse joints demonstrated that it was easy to find at least a few transverse joints on each project where the dowel embedment length ranged from low to nonexistent. Current standards of sawing perpendicular transverse joints should inherently decrease the frequency of lower dowel bar embedment lengths. The thirteen-year history of pavement performance data from the MnROAD facility provides a unique opportunity to examine the effect of dowel bar embedment length on joint load transfer efficiency. This study focuses on six of the MnROAD interstate design concrete pavement test sections. Research Significance The recent availability and increasing use of new high accuracy dowel bar location equipment is bringing renewed interest to understanding reasonable construction tolerances for dowel bar alignment. This study focuses on one aspect dowel bar alignment, namely the minimum required embedment length for satisfactory long term joint performance. Findings of this study could lead to important changes in construction specifications for dowel bar embedment length. 2

Data Acquisition MnROAD Test Sections The data used in this study came from six of the jointed concrete pavement test sections at the MnROAD facility. The test sections are designated as Cells 6, 7, 9,, 12, and 13, and have been loaded by interstate traffic since August 1994. Design details for the selected test sections are shown in FIGURE 1. Note that dowel bar diameters in the test sections vary range from 25 mm (1 in) to 38 mm (1.5 in), panel lengths range from 4.6 m (15 ft) to 6.1 m (2 ft), and driving lane widths vary from 3.6 m (12 ft) to 4.3 m (14 ft). The transverse joints in each test cell are skewed.6 meters (2 ft) forward (near the shoulder, in the direction of traffic) for each 3.6 m (12 ft) of lane width. As previously described, the test sections in this study have been open to traffic and Minnesota s extreme climate since August 1994. They have been loaded by over 11 million concrete pavement equivalent single axle loads (ESALs). 6 7 9 12 13 19 cm PCC, 4.6 m L x 4.3 m W, 25 mm dowel 15 mm CL 4 Silty/Clay Subgrade 19 mm PCC, 6.1 m L x 4.3 m W, 25 mm dowel mm PASB 75 mm CL 4 Silty/Clay Subgrade 19 cm PCC, 4.6 m L x 4.3 m W, 25 mm dowel mm PASB 75 mm CL 4 Silty/Clay Subgrade 2 mm PCC, 6.1 m L x 3.6 m W, 32 mm dowels mm PASB 75 mm CL 4 Silty/Clay Subgrade 2 mm PCC, 4.6 m L x 3.6 m W, 32 mm dowels 125 mm CL 5 Silty/Clay Subgrade 2 mm PCC, 6.1 m L x 3.6 m W, 38 mm dowels 125 mm CL 5 Silty/Clay Subgrade FIGURE 1 MnROAD concrete pavement test cell design details. Dowel Bar Location Measurements Measurement of the location of dowel bars in MnROAD concrete test cells took place in 1998. A pulse induction metal location device was used to closely estimate the lateral and longitudinal locations of at least 4 dowels (per lane) within each transverse joint. Longitudinal dowel bar embedment length measurements were referenced to the approach slab side of the joint. All dowel bars are epoxy-coated steel, 3 mm (15 in) in length. See FIGURE 2 for information showing dowel bar details and slab identification. Load Transfer Efficiency Testing Since 1994, all MnROAD concrete pavement test cells have been periodically tested for transverse joint load transfer efficiency using a Falling Weight Deflectometer (FWD) device. Within each test cell, five transverse joints in each lane were selected as routine 3

TRAFFIC Test Point 6 inches Test Point 1 (15 mm) Approach Panel d/2 Leave Panel Measured dowel bar embedment length Cells 5-9 = 25 mm diameter by 3 mm long Cells - 12 = 32 mm diameter by 3 mm long Cell 13 = 38 mm diameter by 3 mm long FIGURE 2 Dowel bar and slab testing details for study. test locations. Additional test points identified as having lower dowel embedment lengths were also tested several times in 1998-2, and again in 27. To determine joint load transfer efficiency, FWD testing was conducted at test points located 15 mm (6 in) on either side of the joint in the outside w heelpath of each lane. See FIGURE 2 for identification and location of the LTE test points. The FWD loading pattern consisted of three drops at each load level load of 26.6 kn, kn, and 66.7 kn (,, 15 lbs). A 12-inch diameter FWD load plate was used. During the testing, air and pavement surface temperatures were captured by infrared sensors on the FWD device. Internal slab temperature data from embedded thermocouple sensors was also collected for each test cell, and were used to verify and supplement the FWD readings. Testing was typically done at temperatures conducive to load transfer efficiency testing (recommended by AASHTO to be less than 26 C ( F)(AASHTO 1993), however LTE testing also occurred at higher slab temperature conditions, which often resulted in artificially elevated LTE values. Data Analysis E mbedment Length As previously mentioned, an individual dowel bar embedment length depends on a number of factors, m ostly determined during the construction process. Dowel bars can shift within a support basket, a support basket can move due to poor anchorage, or the joint sawing operation can cause longitudinal misalignment. Before the effect of dowel bar embedment length on LTE is examined, it is useful to understand the typical variation in embedment length. FI GURE 3 shows a histogram of dow el bar embedment lengths for transverse joints in the MnROAD test cells considered in this study. With a Mn/DOT design embedment length of 19.1 cm (7.5 in), the distribution appears approximately normal. For this study, embedment lengths less than 16.5 cm (6.5 in) were categorized as low embedment. The minimum embedment length measured in the test cells for this study was 11 cm (4.3 in). 4

Frequency 5 3 2.1 11.1 12.1 13.1 14.1 15.1 16.1 17.1 18.1 19.1 2.1 21.1 22.1 23.1 24.1 25.1 26.1 27.1 28.1 29.1 3.1 31.1 FIGURE 3 Distribution of dowel bar embedment lengths (into approach panel) for MnROAD test cells 6, 7, 9,, 12 and 13. Mn/DOT design embedment length is 19.1 cm (7.5 in). (1 inch = 2.54 cm) LTE Calculations Joint load transfer efficiency (LTE) values in this study were determined using the method outlined in Section 3.5.4 of the 1993 AASHTO Guide for Design of Pavement Structures (AASHTO 1993). Equation 1 was used for the analysis, du d je = x (1) dl where d je is the load transfer efficiency in percent, d u is the deflection near the joint of the unloaded slab, and d l is the deflection near the joint of the loaded slab. Slab bending and panel warp and curl correction factors were neglected during the analysis. Only the right (or driving) lane LTE trends were examined in this study. Data for this study came from 2 sources. The first source was five routine testing locations (2 test points at each joint) within each test cell, with a LTE history going back to 1994. The second source was additional joints tested periodically since 1999. The additional test points included joints with dowel bars embedded to the design specified length, as well as joints with lower dowel bar embedment lengths. During the analysis, LTE data was first determined for individual test locations and test points. For each test point and 1 near each joint tested, EQUATION 1 was then used to calculate the LTE using the average of three measured FWD deflection basins for a kn ( lb) load sequence. Once the LTE calculations were complete, the data were plotted to observe overall trends. FIGURES 4 and 5 demonstrate the 5

5 3 2 1994 1996 1998 2 22 24 26 28 Time Cell 6 Cell 7 Cell 9 FIGURE 4 History of LTE for MnROAD test cells 6, 7, 9. Data for test point, FWD load= kn ( lbs), design (19 cm) dowel embedment. 5 3 2 1994 1996 1998 2 22 24 26 28 Time Cell Cell 12 Cell 13 FIGURE 5 History of LTE for MnROAD test cells, 12, 13. Data for test point, FWD load= kn ( lbs), design (19 cm) dowel embedment. 6

change in LTE with time for test cells 6, 7, 9 and test cells, 12, 13, respectively. The data shown in the figures is for kn ( lbs) loading on the approach panel side of joints and dowel bar embedment lengths near the specified design length of 19 cm (7.5 in). Expecting a decline of LTE with time, it is readily apparent from FIGURES 4 and 5 that many LTE tests were conducted when slabs were experiencing expansion due to high internal temperatures and/or moisture, therefore leading to artificially elevated LTE values. This led to the decision to more closely examine the LTE trends and behavior during fall time periods, when temperatures and moisture in the slabs are lower and more consistent from year to year. In fact, supplemental testing was carried out in the fall of 27 to gather additional data that would best represent the current level of LTE within the joints. LTE data from fall testing periods was extracted from the overall data and plotted in FIGURES 6 and 7. 5 3 2 1994 1996 1998 2 22 24 26 28 Time Cell 6 Cell 7 Cell 9 FIGURE 6 LTE data during fall time periods for test cells 6, 7, 9. One interesting trend in LTE was demonstrated by test Cell 7. While other test cells exhibited higher LTE values early in life, followed by a decline in LTE with time, test cell 7 began with fairly low LTE values. Test cell 7 then exhibited a more constant, if not cyclic, behavior in LTE with what appears to be an increase in LTE with time. Initial thoughts are that the behavior may be influenced by panel length or base type, although test cell 9 has the same base type (but a different panel length). Future forensic investigations of test cell 7 may reveal some answers on whether the condition of the PASB (permable asphalt stabilized base) has changed with time and is influencing transverse joint LTE behavior. Despite the lower levels of LTE exhibited in test cell 7, joint faulting still remains at very low levels, as with all other MnROAD interstate traffic loaded test cells. 7

5 3 2 1994 1996 1998 2 22 24 26 28 Time Cell Cell 12 Cell 13 FIGURE 7 LTE data during fall time periods for test cells, 12, 13. As shown in FIGURE 7, the LTE trends for test cell also stand out from similar thickness test cells 12 and 13. Similar to test cell 7, test cell exhibited slightly lower LTE throughout its life (compared to cells 12 and 13). More recently however, the trend in test cell shows signs of a more rapid decline in LTE with time. Both test cells 7 and have a PASB base layer and 2 foot panel lengths. More evidence will be gathered in the future to determine if these physical parameters are affecting LTE behavior, or whether it is coincidental. Embedment Length vs. LTE Utilizing joint load transfer efficiency values from LTE testing performed in September, October and November 27, the effect of dowel bar embedment length on LTE was examined. FIGURES 8-13 show the results from LTE testing with a kn ( lbs) FWD load. In each figure, the solid vertical line indicates the design specified embedment length of 19.1 cm (7.5 in). The dashed lines indicate the ±25 mm (±1 in) longitudinal misalignment tolerances, below (and above, depending on which side of the joint is loaded) which this study defines as low embedment. Before the trends shown in the figures are discussed, it must be noted that the observations stated are strictly empirical, as it was determined there was insufficient data to perform statistical analyses, and the scope of this study did not include the development of a LTE versus dowel bar embedment length model. The results of the analysis show that for test cells 6, 9,, and 13, there is little effect on the overall level and variability of LTE from lower dowel embedment lengths (for the range of embedment lengths available at MnROAD). This observation is regardless of whether the load is applied on the approach or leave side of a joint. 8

5 Approach Panel Leave Panel Point Point 1 3 2 12. 13. 14. 15. 16. 17. 18. 19. 2. 21. 22. 23. 24. 25. 26. FIGURE 8 LTE for various dowel bar embedment lengths (into approach panel) as measured on MnROAD test cell 6 during the fall of 27. Specified design embedment length is 19.1 cm. 5 Approach Panel Leave Panel Point Point 1 3 2 11. 12. 13. 14. 15. 16. 17. 18. 19. 2. 21. 22. 23. 24. 25. 26. 27. FIGURE 9 LTE for various dowel bar embedment lengths (into approach panel) as measured on MnROAD test cell 7 during the fall of 27. 9

5 Approach Panel Leave Panel Point Point 1 3 2 12. 13. 14. 15. 16. 17. 18. 19. 2. 21. 22. 23. 24. 25. 26. 27. 28. FIGURE LTE for various dowel bar embedment lengths (into approach panel) as measured on MnROAD test cell 9 during the fall of 27. 5 Approach Panel Leave Panel Point Point 1 3 2 12. 13. 14. 15. 16. 17. 18. 19. 2. 21. 22. 23. 24. 25. 26. FIGURE 11 LTE for various dowel bar embedment lengths (into approach panel) as measured on MnROAD test cell during the fall of 27.

5 Approach Panel Leave Panel Point Point 1 3 2 11. 12. 13. 14. 15. 16. 17. 18. 19. 2. 21. 22. 23. 24. 25. FIGURE 12 LTE for various dowel bar embedment lengths (into approach panel) as measured on MnROAD test cell 12 during the fall of 27. 5 Approach Panel Leave Panel Point Point 1 3 2 11. 12. 13. 14. 15. 16. 17. 18. 19. 2. 21. 22. 23. 24. 25. 26. 27. FIGURE 13 LTE for various dowel bar embedment lengths (into approach panel) as measured on MnROAD test cell 13 during the fall of 27. 11

Just as the overall trend of LTE with time for test cell 7 exhibited a different trend than other test cells (see FIGURE 6), cell 7 also showed a unique trend in LTE versus dowel bar embedment. FIGURE 9 shows that in test cell 7, LTE values actually trend higher with decreasing dowel bar embedment lengths, although there appears to be much higher variability in the LTE values than other test cells. Whether the behavior is a perhaps a function of panel size, or even built-in slab warp and curl, future research will be required to ascertain the more complex characterization that is needed to identify the causes. Test cell 12 exhibits an opposite trend to test cell 7. As shown in FIGURE 12, the LTE in test cell 12 is noticeably lower for the approach panel embedment length of 12 cm (4.75 in). Given the variability of the LTE at other embedment lengths, particularly at 16 cm (6.25 in), it was unclear however, whether the LTE trend was consistent. The LTE values on the right side of FIGURE 12 indicate that lower dowel bar embedment lengths into the leave panel behave similarly to test cells and 13. As a side observation, for most of the test cells in this study, FWD loads applied to the leave panel (test point 1) yielded slightly lower load transfer efficiency values than for approach panel (test point ) loading. Conclusions and Recommendations Data from six interstate traffic loaded MnROAD concrete pavement test cells was used to determine the effects of dowel bar embedment length on joint load transfer efficiency. Plots of LTE testing results over 13 years revealed that more consistent trends in LTE could be observed if results from fall testing periods were examined. Utilizing joint load transfer efficiency values from LTE testing performed in September, October and November 27, the effect of dowel bar embedment length on LTE was observed. Results of the analysis show that for the range of embedment lengths available at MnROAD, most test cells demonstrate little effect on the overall level and variability of LTE from lower dowel embedment lengths. Exceptions to the observed trends will need to be addressed in future related research, however may be attributed to the highly variable nature of the vertical and horizontal profile of transverse joints and slabs. Given the moderate range of available low dowel bar embedment lengths at MnROAD, there is a need for more focused field research studies examining a range of dowel bar embedment lengths, especially down to the critical lengths as determined in previous studies (6 cm [2 in]). Additional LTE testing, especially during fall time periods will continue to be performed on MnROAD test cells to support such future studies. The recent availability and increasing use of new high accuracy dowel bar location equipment is bringing renewed interest to understanding reasonable construction tolerances for dowel bar alignment. This study has shown that dowel embedment length specifications need to acknowledge the insensitivity of dowel embedment length on LTE performance, at least with embedment lengths as low as cm (4 in). Of course every measure needs to be taken to construct the joints over the mid-point of the dowel bars to ensure optimal long term performance. Acknowledgements The author would like to acknowledge the following individuals for their contribution to this study. Erland Lukanen, Mn/DOT, who provided the author with an invaluable 12

spreadsheet tool for visualizing joint load transfer efficiency behavior. David Morrow, Dynatest Corporation, who provided a conversion program for binary FWD time history files. Finally, the various FWD operators at the MnROAD facility, for their consistent testing over the last 13 years. Disclaimer The contents and opinions presented in this paper are those of the author, who is responsible for the facts and accuracy of the data. The contents do not necessarily reflect the views or opinions of the Minnesota Department of Transportation. References AA SHTO Guide for Design of Pavement Structures 1993 (1993). American Association of State Highway and Transportation Officials, Washington, D.C. Burnham, T.R. (1999). A Field Study of PCC Joint Misalignment Near Fergus Falls, Minnesota. Report 1999-29. Minnesota Department of Transportation, St. Paul, MN. FHWA TechBrief (27). Best Practices for Dowel Placement Tolerances. Publication FHWA-HIF-7-21, FHWA, U.S. Department of Transportation. Freudenstein, S. (21). Untersuchungen über den Einfluss reduzierter Dübeleinbindelängen auf die Wirksamkeit der Fugenkonstruktion bei Betonstraßen, Mitteilungen des Prüfamtes für Bau von Landverkehrswegen der Technischen Universität München. Lane,B. and T. Kazmierowski (26). Use of MIT Scan Data for Improved Dowel Bar Tolerances. Proceedings of International Conference on Long-Life Concrete Pavements. Chicago, IL, October 25-27. Lechner, B. (25). Joint Design and Joint Performance of Plain Concrete Pavements (JPCP) Investigations and Experiences in Germany. CD-ROM. Proceedings of 8 th International Conference on Concrete Pavements. Colorado Springs, CO, August 14-18. The Minnesota Road Research Project (27). Minnesota Department of Transportation. http://www.mnroad.dot.state.mn.us/research/mnresearch.asp. Accessed July 19, 27. Teller, L.W., and H.D. Cashell (1958). Performance of Doweled Joints Under Repetitive Loading. Public Roads, Vol. 3, No. 1. Weaver, J and A.J. Clark A.J. (19). The Effect of Dowel-Bar Misalinement in the Joints of Concrete Roads, Cement and Concrete Association, SBN 72 437 7, London. 13