Assembly instructions TerraWing Foundation System

Similar documents
INSTALLATION INSTRUCTIONS CONTOURED LIGHT BAR APPLICATION: CHEVY EQUINOX/ GMC TERRAIN PART NUMBERS: ,

LCD LIFT Flat Panel Display System Installation Manual. Table of Contents

Instruction Manual. Manual Furniture Mover. Note: Owner/Operator must read and understand this instruction manual before using the furniture mover.

Side Winder R o u t e r L i f t.

3.2.3 Rear Door Window and Quarter Window Carrier Assembly

Mounting Accessories. Installation Guide. VIVOTEK SD83XXE Speed Dome

Calf-Tel Pen System Assembly Instructions

1 of 2 3/3/2017 4:49 PM

Quick-Release Front Vise 05G34.01

INSTALLATION GUIDE. Version 2.0

LEG CURL IP-S1315 INSTALLATION INSTRUCTIONS

WSG 8-115; 8-125; P; WSG ; WSG P; WSG PS; WSG P; WSG 15-70Inox

DO35 MAINTENANCE INSTRUCTIONS

B-Too Drilling and Tapping Machine Instruction and Maintenance Manual

Installation Instructions for Vista Air Vertically Folding Walls

Powersafe Termination Guide

Formula Suspension Fork RCC INSTALLATION AND ASSEMBLY INSTRUCTIONS

M2 Antenna Systems, Inc. Model No: 20M6-125

Removing the Z-Axis lead screw

400A 40113V, 401A 40120V, & 401AL 40120VL ALUMINUM VERTICAL 4000 LB LIFT INCLUDES SCREW LEG ASSEMBLY INSTRUCTIONS

Preparatory work. Core activity

Klamp Trak. Instructions (39052)

ELECTRIC TOOL CORPORATION

MS25 OPERATION MANUAL

MODEL T " SPIRAL CUTTERHEAD INSTALLATION INSTRUCTIONS

7x --Tailstock Cam Lock

Mast and Antennas for Field Day & Emergencies

Door window. Front door window, assembly overview

Grand Slam 380 and Grand Slam 380XL Installation Instructions

Installation Manual for Gate Guard

Piazzola Pergola Awning Manufacturing and installation guide

Installation Instructions for FC2 & FC15 Forward Controls for the Super Magna

Install. Jeep JK Adventure Tire Carrier. Tools Needed. Hardware

Installation and Assembly - Universal Articulating Swivel Double-Arm for 42" - 60" Plasma Screens

18000 HDL FOUR POST LIFT LB CAPACITY INSTALLATION AND OWNER'S MANUAL

TABLE OF CONTENTS REQUIRED TOOLS

REPAIR INSTRUCTIONS. Cat. No Cat. No MILWAUKEE ELECTRIC TOOL CORPORATION. SDS Max Demolition Hammer. SDS Max Rotary Hammer

Model: SCD430 SCD640. Installation & Operation Guide P/N SCD640-95

Introduction. Rocky Mountain Westy Swing Away Carrier Kit Installation Instructions

INSTALLATION TORSION SPRING FRONT OR REAR MOUNT LOW HEADROOM. 1 Cutting Vertical Track. 2 Fully Adjustable Jamb Brackets

LORON SERVICE MANUAL / PARTS LIST SINGLE DOUBLE PALLET HANDLER CONTENTS: PAGE 1 Lift Truck Requirements General Installation Procedures

Installation Instructions

Assembly & Installation Instructions

MOUNTING INSTRUCTIONS CONCRETE PURLIN BRACKET

TELESCOPIC GATE MANUFACTURING AND INSTALLATION MANUAL.

M4 Foot Operated Underpinner Instruction Manual

Motorized M3 AX7200 Rotary-Style Gasket Cutter Operating Instructions

Preference Collection 5580 Treatment Console INSTALLATION GUIDE

INSTALLATION INSTRUCTIONS

Maintenance & Parts list for:

Installation and Assembly - Universal Articulating Swivel Double-Arm for 42" - 60" Plasma Screens

Model: SS660-OB Stainless Steel Floor Scale Series. Installation, Set-Up and Operation Manual

Bike Locker Model DBL1 & DBL2

RTI TECHNOLOGIES, INC.

Maintenance Information

May 14, Installation Manual

Inventory (Figure 2)

F l a t S c r e e n A R M S I n s t a l l a t i o n

Referencing 0,0 position

MINI-LATHE QUICK CHANGE TOOL POST

Form No Assembly & Operating Instructions for: SAFETY PRECAUTIONS

STEP 1 : DESTROYER FRONT BUMPER INSTALL GATHER YOUR TOOLS AND LAY OUT YOUR PARTS... *shorty bumper to show hardware* Tools Required:

AFB (AIR FAN BEARING) INSTALLATION GUIDE

* * 98/9950WDC. Fire-Rated Devices include these. additional components. 1-Point Latch (LBL)

MUELLER. Improved, Centurion Series, Modern Improved, and 107. Fire Hydrants. Inserting Extention Sections. Reliable Connections

Flat Panel Stand FPZ-655. for 32" to 55" Flat Panel Screens FEATURES. Reinforced universal adapter plate for a strong hold

Shop Style Miter Saw Stand Kit

Tilting Flat Panel Wall Mount Installation Guide

Table of contents. 2 Safety E517EN_03.DOC. 1. Safety Description Correct use Technical data F Lock seams...

Quick-Release Sliding Tail Vise 05G30.01

RIVETING Rivet types Solid rivets Solid rivets are used less and less. They have been replaced in many cases by welding or bonding.

Fig Remove chain cover plate bolts. Fig Remove hammer member. Fig Loosen set screws at base of 12-tooth sprocket.

Inventory MODEL T10096 TAPER ATTACHMENT FOR G0509 & G0509G LATHE INSTRUCTIONS. Inventory (Figure 1) Needed Items

ROOFSAFE ANCHOR & CABLE

BABY WOLF LOOM. Assembly Instructions for Knocked-Down Looms

v1.0 ASSEMBLY GUIDE Mia Wide Bookcase

INSTALLATION INSTRUCTIONS FOR SL-LB MANUAL LIFT BARRIER GATE ARMS

Tools for Plumbing. Introduction

MAKO EC EXTENDED CABINET

MODEL D DIESEL PILE HAMMER

INSTALLATION INSTRUCTIONS GRILLE GUARD CHEVY TAHOE / AVALANCHE 1500/ SUBURBAN 1500 PART # /502795

Contractors Rack Assembly and Installation Instructions

1. TOOLS + MATERIALS REQUIRED

APS Small Seeds Box Assembly Instructions

Pontoon Installation Manual

Workbench Instructions for Assembly

STENCIL MACHINE OPERATION uline.com H-259, H-347 H-408 CUTTING THE OIL BOARD INSERTING THE OIL BOARD

MUELLER. Improved, Centurion Series, Modern Improved, and 107. Fire Hydrants. Inserting Extension Sections. Reliable Connections

Click Here to Go Back

INSTALLATION INSTRUCTIONS

EmagiKit. Privacy Pod Plus. Quiet. Easy. Affordable. INSTRUCTIONS ASSEMBLY

SINCE 1922 P UBLICATION N O

LOCKN LOAD FIRST TIME INSTALLATION

Rolling Curtain door Manual

DX-TVMLPTB03. Low-Profile TV Wall Mount ASSEMBLY GUIDE. For either wood-stud or concrete wall installations

It is highly recommended that you use a thread lock compound such as Loctite brand on all threads to keep them from vibrating loose.

HAND TOOL NOTES For each tool picture and name, please write what it s used for. You will have a quiz on this.

Gared Pro Portable Backstop

Elo Touch Solutions Wallmounting Kit for the 7001L IDS Touchmonitors

Model: SS660-PT-R Stainless Steel Poly-Top Floor Scale Series. Installation, Set-Up and Operation Manual

Transcription:

Industriell Effektivitet i Terrängen TM Rev: Date: Nyköping 2014-11-26 Assembly instructions TerraWing Foundation System Copyright 2014 TerraWing AB

Thank you for choosing the TerraWing Foundation System for your application! By the time you read this, you will probably soon be installing your foundation and will therefore need some information about the system, how it functions, what you can expect, and what it might be good to think about for the foundation. The TerraWing Foundation System has been available on the market since 2003. More than 25,000 foundations have been applied over the years. The benefits are: Project planning in accordance with Eurocode, complete documentation included in the delivery Fast and simple application in the terrain, normal capacity is 5-15 foundations/hour depending on geotechnics Overall cost-effectiveness, high quality in CE-marked production plants Take a few minutes to read through this pamphlet to ensure that the system is maximally utilised and that the application in the field is quick and easy. Don't hesitate to contact us if you have any queries. Good luck with your foundation!

To think about before you start the application in the field How is the TerraWing Foundation System structured? The TerraWing Foundation System consists in practice of a steel structure containing a pipe section with wings adapted to loads and geotechnical conditions. Above these is TerraWing s patented adjusting device consisting of a boom, and an adjusting plate with a centre bolt and corner bolts for connection to the post base. TerraWing can also supply posts for your object. If you procure poles from elsewhere, bear in mind that the pole's base plate must fit the foundation's adjusting plate with the right length, width and thickness dimensions, bolt pattern, and bolt size. Contact us for drawing of a suitable post base. Direction noise barrier Follow the assembly / foundation plan precisely. If incorrect accessories are installed the post will not fit. Holes and c/c (centerdistance)are different for different adjusting plates, be observant, check the marking Slots on adjusting plate perpendicular to barrier Secure tape measure in position 0 and measure 50 metres at a time, avoid compounding errors Trimming allowance in the foundation across the barrier +-30 mm Trimming allowance in post base across the barrier +-15 mm Trimming allowance in the foundation along the barrier +-45 mm Trimming allowance in post base along the barrier +-0 mm

Do I need a foundation plan? In its simplest and most functional form, a foundation plan is a calculation sheet in a program such as Excel. The information is presented in matrix form with each foundation position constituting a line with information such as screen height, c/c between posts, foundation type, adjusting plate, boom type, centre bolt, bolt set and post base. A foundation plan is a good way to: Plan which foundations should be where on the building site Simplify installation of the right accessories for the respective foundation type Document and quality assure what has been done A well thought-out foundation plan can deliver higher capacity when knocking posts down. TerraWing recommends that a foundation plan is always prepared

Delivery of foundations from the factory TerraWing notifies the delivery a few days before the delivery date. Delivery is normally with a carrier such as DHL, with which we have a freight contract, or direct delivery from our manufacturer in the Baltic States. Some of our drivers have limited language skills. In the event of any queries concerning your delivery please contact: TerraWing AB Gasverksvägen 15 611 35 Nyköping Tel: +46 (0)155-21 77 70 E-mail: info@terrawing.se

To achieve high capacity when knocking the foundations in, a foundation plan should have been prepared containing height of each individual foundation, type of foundation, as well as accessories for each position. The foundation should be located in the respective location where it is to be knocked in. The working party should ideally consist of a machine and driver, along with an additional person to assist with handling and direction of the foundation. Be careful to position the foundation correctly in height and level, for strength reasons the distance between adjusting plate and post base should be as small as possible after installation. Fine adjustment of c/c distance and lateral position is with our patented adjustment device.

Which equipment do I need alternatively used Tracked machine with hydralic hammer or alternative excavator with hydraulic hammer for knocking down Using the TerraWing Foundation System entails minimal handling of soil. The capacity for knocking down foundations is normally 5-15 foundations per hour depending on geotechnics, size and type of foundations and equipment.

TerraWing collaborates with Bopec Väst AB. Bopec has lorries equipped with hydraulic hammers which reach about 3m from the roadside. Bopec also has specialised tracked machines equipped with hydraulic hammers. To book Bopec for your project call +46 (0)304-45190

The pike and its parts The pike prepares the route for the foundation. The pike should be about 10 cm longer than the foundation With hard ground conditions such as boulder moraine/rocky banks, it is recommended that the pike is first driven in to its full length and the foundation subsequently mounted on the pike for insertion. It is important to lubricate the surface between the chisel and the pike with grease.

1 Lugs For suspension of pike 2 Drag chain Provided by operator 3 4 2 1 3 Chisel Diameter 100-115 mm 5 4 Draw ring Included in rental of pike The hammer energy When knocking down noise barrier foundations should be 2300 Joules(CIMA method 1500 J) and for road sign foundations about 3200 Joules(CIMA method 2900 J) 5 Pike Available for rent Pikes are available to rent from TerraWing in the lengths 1600 mm and 2100 mm. The following rules apply for TerraWing's rental pikes: Diameter chisel 100-115 mm (chisel dimension over 115mm results in chisel and pike merging) Chisel length minimum 255 mm (is needed for clearance against pike edge) The chisel must have a flat end (risk of cantilevering and merging)

Knocking down foundations to achieve Industrial efficiency in the terrain When knocking in light foundations that can be raised by hand, the foundation is raised and the pike is inserted down in the foundation. The lifting hooks are then secured in the holes in the wings and the foundation is lifted into place. For heavier foundations, the pike is secured in the foundation when the foundation is lying on the ground. The plate lock is then secured in a wing and the foundation is lifted into place. The capacity can normally increase to 5-15 foundations/hour depending on size of the foundation and prevailing geotechnics. With rocky banks and boulder moraine, the pike should first be knocked down to the right depth on its own, after which the foundation is threaded on and driven down.

It is important that the noisereducing screen is tight against the ground. It has major importance for the screen's noisesuppressing capacity. You can choose to add soil to seal below the noise-reducing screen after it is mounted. You can also choose to make an approximately 40 cm wide and 30 cm depth gulley using a cable bucket. The soil is placed at the edge of the gulley and used to backfill around the screen.

Secure a tape measure with, for example, a screw clamp in the first foundation inserted and carefully measure the c/c distance to subsequent foundations. Use GPS, pipe laser or a line to set out direction of the foundation. It is a good idea to install the pin bolts in the mounting plate in a workshop where you have access to an impact wrench. Adjust the adjusting plates and then loosely tighten the centre bolts. When you are satisfied with the position, tighten the centre bolts according to the following pages in the assembly instructions.

Third nut Adjustment of the correct height before mounting the post. Start by adjusting an optional pin bolt per foundation. Calibrate the third nut on the pin bolt using a calibrator. Then lock the nut with LOCTITE 243 and for safety's sake, make a mark with a felt tip pen. Now continue to adjust the third nut on the other pin bolts with the starting point from the first pin bolt. Use a small spirit level for this. Remember to put a washer above the nut before you put the post on. When the post is in place, tighten the nuts to the required torque and lock with LOCTITE 243 or alternatively a centre punch mark of the thread as thread lock. Installation of the screen can now commence.

Tightening of pin bolts to posts In connection with installing the posts, the pin bolts should be tightened using torquing. The torque specified in the table below can be achieved through use of a sleeve with the lever specified. Tightening should be with the strength of a man. According to the table below this is about 600 Nm with a 1 metre lever. In other words, this is equivalent to about 60 kg tightening with the lever. Bolt - dimension (mm) Lever s length with manual tightening Bolt in delivery condition Waxed bolt Torque when tightening (Nm) Bolt in delivery condition Waxed bolt 20 500mm 300mm 350Nm 210Nm 24 1000mm 600mm 600Nm 350Nm 27 1500mm 900mm 900Nm 550Nm 30 2000mm 1300mm 1250Nm 750Nm 36 2400mm 2350Nm 1400Nm

Mounting of accessories Angular tightening of the centrum bolt After adjustment the centrum bolt is pulled fully for contact between the parts. Thereafter the bolt angle specified in the documentation that arrives togheter with the delivery of the foundations. The angle is different for various foundations, plate thicknesses, boltdimensions and bolt lengths. A B A XXX Angle routing can be done by hand or machine, the main thing is that the correct angle is achived: 1. Make a pencil mark on the plate and on the bolt as positioning mark before tightening 2. Then measure specified angle and make the new mark with the pen Tighten the bolt from mark 1 to 2 above Angle routing provides a bias that is necessary for a full function of the foundation

TerraWing Foundation System TerraWing Foundation system has been on the market since 2003. More then 43,000 foundations has been applied during these years. The benefits are: Projecting according to Eurocode, complete documentation is included in the delivery Fast and simple application in the terrain, normal capacity is 5-15 foundations/hour depending on geotechnics Total cost efficiency, high quality in CE-marked fabrics Dimensions and constructions of the foundations is calculated with TerraWing s calculation program adapted to Eurocode. Togheter with the delivery of the foundation following a extensive calculation document. Keep in mind that we have your tender documentation as the basis for all the calculations of the foundations! TerraWing AB Gasverksvägen 15 611 35 Nyköping 0155-21 77 70