NVESTIGATIONS OF RECENT BLACK-

Similar documents
System Protection and Control Subcommittee

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

ECE 692 Advanced Topics on Power System Stability 5 - Voltage Stability

NERC Protection Coordination Webinar Series June 23, Phil Tatro

ESB National Grid Transmission Planning Criteria

Power Plant and Transmission System Protection Coordination

VOLTAGE STABILITY OF THE NORDIC TEST SYSTEM

Power Plant and Transmission System Protection Coordination Fundamentals

Power Plant and Transmission System Protection Coordination

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

EH2741 Communication and Control in Electric Power Systems Lecture 2

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

Generator Protection GENERATOR CONTROL AND PROTECTION

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

1

Power Plant and Transmission System Protection Coordination of-field (40) and Out-of. of-step Protection (78)

Transmission System Phase Backup Protection

System Protection and Control Subcommittee

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

Grid codes and wind farm interconnections CNY Engineering Expo. Syracuse, NY November 13, 2017

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Setting and Verification of Generation Protection to Meet NERC Reliability Standards

Reliability Guideline: Generating Unit Operations During Complete Loss of Communications

Wind Power Facility Technical Requirements CHANGE HISTORY

Considerations for Power Plant and Transmission System Protection Coordination

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell

Appendix C-1. Protection Requirements & Guidelines Non-Utility Generator Connection to Okanogan PUD

Keeping it up to Speed Off-Nominal Frequency Operations. CETAC 2018 San Ramon

Advanced Applications of Multifunction Digital Generator Protection

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

Unit Auxiliary Transformer (UAT) Relay Loadability Report

System Protection Schemes in Power Network based on New Principles

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

Generation and Load Interconnection Standard

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

Type KLF Generator Field Protection-Loss of Field Relay

System Operating Limit Definition and Exceedance Clarification

NERC Protection Coordination Webinar Series June 30, Dr. Murty V.V.S. Yalla

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

CHAPTER 4 POWER QUALITY AND VAR COMPENSATION IN DISTRIBUTION SYSTEMS

Combination of Adaptive and Intelligent Load Shedding Techniques for Distribution Network

Study on the Improvement of the Special Protection Scheme (SPS) in the Korean power system

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

Eliminating Power Transients When Switching Large Motors or Transformers during Power Outages or Engine Testing

TECHNICAL BULLETIN 004a Ferroresonance

Power Plant and Transmission System Protection Coordination

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction. See the Implementation Plan for PRC

A New Approach Applied to Adaptive Centralized Load Shedding Scheme

Although shunt capacitors

Determination of Practical Transmission Relaying Loadability Settings Implementation Guidance for PRC System Protection and Control Subcommittee

Standard PRC Generator Frequency and Voltage Protective Relay Settings. A. Introduction

Waterpower '97. Upgrading Hydroelectric Generator Protection Using Digital Technology

Generation and Load Interconnection Standard

Advantages and Disadvantages of EHV Automatic Reclosing

Relay Performance During Major System Disturbances

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network

NERC / TVA STABILITY WORKSHOP

Switch-on-to-Fault Schemes in the Context of Line Relay Loadability

Minnesota Power Systems Conference 2015 Improving System Protection Reliability and Security

PV CURVE APPROACH FOR VOLTAGE STABILITY ANALYSIS

Final ballot January BOT adoption February 2015

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

NERC Protection Coordination Webinar Series July 15, Jon Gardell

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

G. KOBET, I. GRANT, G. GOZA Tennessee Valley Authority USA. R. GIRGIS, M. ESPINDOLA ABB Corporation USA SUMMARY

Chapter 10: Compensation of Power Transmission Systems

Voltage Control with Distributed Generators to Enhance Voltage Stability

Table of Contents. Introduction... 1

ELEMENTS OF FACTS CONTROLLERS

Transmission Line Protection Objective. General knowledge and familiarity with transmission protection schemes

Chen-Ching Liu. Washington State University

ROSE - Real Time Analysis Tool for Enhanced Situational Awareness

Electrical Power Systems

REACTIVE POWER AND VOLTAGE CONTROL ISSUES IN ELECTRIC POWER SYSTEMS

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements

Hydro-Québec s Defense Plan: Present and Future

GridLiance Reliability Criteria

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies

EASING NERC TESTING WITH NEW DIGITAL EXCITATION SYSTEMS

Use of the Power System Outlook (PSO) and SMART 1 Programs to View PSLF Dynamic Simulation Data Files

Performance of Relaying During Wide-area Stressed Conditions

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Protective Relaying for DER

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

Sizing Generators for Leading Power Factor

COMPARATIVE PERFORMANCE OF SMART WIRES SMARTVALVE WITH EHV SERIES CAPACITOR: IMPLICATIONS FOR SUB-SYNCHRONOUS RESONANCE (SSR)

Acknowledgements Introduction p. 1 Electric Power Quality p. 3 Impacts of Power Quality Problems on End Users p. 4 Power Quality Standards p.

Remedial Action Scheme Definition Development Background and Frequently Asked Questions

Considerations and Recommendations for the Harmonisation of Under Frequency Loadshedding Schemes in Multi Zone Meshed Grids

each time the Frequency is above 51Hz. Continuous operation is required

Reducing the Effects of Short Circuit Faults on Sensitive Loads in Distribution Systems

BED INTERCONNECTION TECHNICAL REQUIREMENTS

SYNCHROPHASOR TECHNOLOGY GLOSSARY Revision Date: April 24, 2011

E N G I N E E R I N G M A N U A L

RELIABILITY: Our Advantages, Challenges, and Opportunities

Application Example Document ID: SA Rev. - September 24, 2004

Transmission Protection Overview

Delayed Current Zero Crossing Phenomena during Switching of Shunt-Compensated Lines

September 19, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme

Transcription:

DIGITAL VISION outs indicate that the root cause of almost all major power system disturbances is voltage collapse rather than the underfrequency conditions prevalent in the blackouts of the 1960s and 1970s. Voltage relays have been used by industrial customers to determine whether the utility circuit that supplies them has tripped. However, voltage relays at industrial sites have Minimizing the impact of blackouts not been used to determine whether the utility system lacks security, leading voltage collapse. This article discusses the causes of voltage collapse as well as the design and security requirements for an undervoltage separation scheme. Nature of Power System Blackouts Power systems that supply power to industrial facilities BY CHARLES J. MOZINA today are much more susceptible to voltage collapses than they were 35 years ago because these systems increasingly depend on generation sources that are located remotely Digital Object Identifier 10.1109/MIAS.2008.927531 1077-2618/08/$25.00 2008 IEEE IEEE INDUSTRY APPLICATIONS MAGAZINE SEPT j OCT 2008 WWW.IEEE.ORG/IAS I NVESTIGATIONS OF RECENT BLACK- 45

IEEE INDUSTRY APPLICATIONS MAGAZINE SEPT j OCT 2008 WWW.IEEE.ORG/IAS 46 from load centers. Generators in eastern Canada and the midwestern United States provide large amounts of power to the east coast load centers such as New York City. Generators in Washington, Oregon, and western Canada provide substantial power to California. This contrasts with the operation of utilities 35 years ago, when each utility had in-house generation to supply its own load. Two factors promote generation that is remote from load centers: 1) the economics of purchasing power from lower-cost remote sources rather than more expensive local generation 2) the public s reluctance or refusal to permit new generating plants to be built in urban high-load areas, causing utilities/independent power producers (IPPs) to build these plants remote from these load centers. These two fundamental changes in the operation of the U.S. power grid result in the transmission of power over long distances. This makes the power grid dependent on the transmission system to deliver power to the load centers. It also results in increased reactive power losses because the impedance of transmission lines is primarily reactive. Thus, when transmission lines trip, the remaining lines must carry the load, which results in much higher reactive (vars) than resistive [megawatt (MW)] losses, and consequently, a voltage drop at the load center, whereas the frequency remains normal. Reactive power (vars) cannot be transmitted very far, especially under heavy load conditions and instead must be generated close to the point of consumption. This is because the difference in voltage causes vars to flow. Voltage on a power system can vary only by 5% of nominal. This small voltage change will not cause substantial var flow over long distances. Real power (MW) can be transmitted over long distances through the coordinated operation of the interconnected grid. Reactive power must be generated at, or near, the load center. Since vars cannot be transmitted over long distances, the sudden loss of transmission lines results in an instantaneous need for local reactive power to compensate for the increased losses of transporting the same power over fewer transmission lines. If that reactive support is not available at the load center, the voltage will decrease. System frequency, on the other hand, will remain stable because the real power from remote generators continues to flow over fewer transmission lines. For these reasons, voltage rather than frequency has become the key indicator that the power system is under stress. Utilities have begun to recognize this and are implementing undervoltage load shedding (UVLS) schemes to complement their existing underfrequency load shedding (UFLS). Industrial customers with in-house cogeneration have long used underfrequency as the principle means of deciding when to separate from the utility system and transfer their critical loads to their own generation. But frequency can remain normal, as voltage sags to a low level UNDERFREQUENCY AND UNDERVOLTAGE SCHEMES ON THE UTILITY SYSTEM ARE DESIGNED TO RESTORE THE BALANCE BY SHEDDING LOAD. prior to a complete system voltage collapse. Voltage separation, in addition to frequency, may be required to allow the industrial system to detect utility impeding system collapse. This article discusses the need for undervoltage as well as underfrequency separation and proposes secure undervoltage load separation schemes that avoid false operations for such events as slow-clearing system faults. Types of Power System Instabilities During System Blackouts Voltage Versus Frequency Stability In a power system, frequency is a measure of the balance of MW generation and MW load. When MW generation and MW load are exactly in balance, the frequency is at the normal level of 60 Hz. When the load exceeds generation, the frequency goes down. The rate of decline depends on the inertia of the generators within the system. Under normal conditions, there are slight changes of frequency when load suddenly increases or generation trips offline, which results in a slight (generally in hundreds of hertz) reduction in frequency until the aggregate generation in the system can be increased to meet the new load condition. If there is a large negative unbalance between MW load and MW generation, the frequency will go down. Underfrequency schemes on the utility system are designed to restore the balance by shedding load. Voltage in a power system is a measure of the balance of MVAr load and MVAr capability within the system. If that reactive support is not available, the voltage will drop. The impact of reduced voltage on load depends on the nature of the load. For resistive load, the load current will decrease and help limit the need for local reactive support. Motor loads are essentially constant kva devices. The lower the voltage, the more current they draw, increasing the need for local reactive support. Power system loads consist of both resistive loads as well as reactive motor loads. However, during hot weather, air conditioning motor loads make up a large portion of utility total load, thereby making the power system more susceptible to voltage collapse. Reactive power system support can only come from two sources: shunt capacitors and generators/synchronous condensers. Shunt capacitors are a double-edged sword. They do provide reactive support, but they also generate fewer vars as the voltage dips. The VAr output of a capacitor bank is reduced by the square of the voltage. Shunt capacitor banks cannot quickly adjust the level of reactive power. Generation at the load center can provide a dynamic source of reactive power. As the voltage goes down, the generator can quickly provide increased reactive support within its capability limits. Unlike shunt capacitors, the amount of reactive support does not drop as system voltage goes down. The amount of reactive power is controlled by the generator automatic voltage regulator (AVR). It is essential that the AVR control is properly set and the generator protection system allows the generator to contribute

the maximum reactive power to support the system without exceeding the generator s capability. Voltage Instability Figure 1 illustrates a simplified power system with a remote generator supplying a substantial portion of the load at the load center through six transmission lines. E s is the voltage at the remote generator buses, and E g is the voltage at the load center buses. Figure 2 illustrates how the voltage decays as real power transferred to the load center increases. This type of P-V analysis (real power relative to voltage) is an analysis tool used by utility system planners to determine the real power transfer capability across a transmission interface to supply local load. Starting from a base-case system (all lines in service), computer-generated load flow cases are run with increasing power transfers while monitoring voltages at critical buses. When power transfers reach a maximum level, a stable voltage cannot be sustained, and the system voltage collapses. On a P-V curve (Figure 2), this point is called the nose of the curve. The shape of the nose of the curve depends on the nature of the load at the load center. High levels of motor load combined with capacitor bank support of load center voltage tend to make the voltage drop very rapidly for a small increase of power at the nose of the curve. The set of P-V curves illustrates that for baseline conditions shown in Curve A, the voltage remains relatively steady (changing along the vertical axis) as local load increases. System conditions are secure and stable to the left of Point A1. After a contingency occurs, such as a transmission circuit tripping, the new condition is represented by Curve B, with lower voltages (relative to Curve A). This is because the power being transmitted from the remote generators is now flowing through five rather than six transmission lines. The system must be operated well inside the load level for the nose of Curve B. If the B contingency occurs, then the next worst contingency must be considered. The system operators must increase local generators to reduce the power being transmitted from the remote generators to reduce losses as well as increase voltage at the load center to within the safe zone to avoid going over the nose of Curve C. In the case of the 2003 East Coast blackout [1], three key transmission lines were lost in rapid succession because of tree contacts. The voltage at the load center was reduced before the system operators could take effective corrective action. Effective operator action was inhibited by the lack of data 100% Bus Voltage 0% A - No Circuits Out B - One Circuit Out C - Two Circuits Out Curve C Nose from key transmission system substations because of a computer problem at the system operating center. In the case described above, voltage decay was relatively slow and there was time for utility system operator intervention to address the voltage decay problem. There have been cases where the voltage decayed so rapidly that operator action was not possible. These cases involve slow-clearing multiphase transmission system faults that occur during heat storm conditions when the utility load is primarily made up of air conditioning motors. The extended length of the voltage dip causes motors in the area to stall and draw large amounts of reactive power after the fault is cleared. The rapid change in load power factor results in low system voltage. Since there is little reserve of reactive power during peak load periods, the area voltage collapses. Such an event occurred in western Tennessee and resulted in an outage to 1,100 MWof load. The entire event took less than 15 s [2]. Phase Angle Instability When the voltage phase angle between remote generators and local generators (h g h s in Figure 1) becomes too E g θ g A1 B1 Curve B Nose Remote Generation Power system example. B2 Stable Operating Space for N 1 A2 B2 Unstable N 1 Conditions Increasing Load (MW) A2 MW Power Flow A3 Line 1 Line 2 Line 3 Line 4 Line 5 Line 6 Local Load Center E s θ s Curve A Nose Real power (MW) versus voltage (P-V) curve. A2 is the highest load level where a transition to N--1 contingency (curve B) stable operating conditions may be possible. 1 2 IEEE INDUSTRY APPLICATIONS MAGAZINE SEPT j OCT 2008 WWW.IEEE.ORG/IAS 47

IEEE INDUSTRY APPLICATIONS MAGAZINE SEPT j OCT 2008 WWW.IEEE.ORG/IAS 48 large, phase angle instability can occur. In many cases, this event happens in conjunction with the voltage collapse scenario described earlier. There are two types of phase angle instability. Steady-State Instability Steady-state instability occurs when there are too few transmission lines to transport power from the generating source to the local load center. Loss of transmission lines into the load center can result in voltage collapse as described earlier, but it can also result in steady-state phase angle instability. The ability to transfer real (MW) power is described by the power transfer equation and is plotted graphically (Figure 3). From the power transfer equation in Figure 3, it can be seen that the maximum power (P max ) that can be transmitted is when h g h s ¼ 90, i.e., sin 90 ¼ 1. When the voltage phase angle between local and remote generation increases beyond 90, the power that can be transmitted is reduced and the system becomes unstable and usually splits apart into islands. If enough lines are tripped between the load center and the remote generation supplying the load center, the reactance (X) between these two sources increases, thereby reducing the maximum power (P max ), which can be transferred. The power angle curve in Figure 3 illustrates this reduction as Line 1 trips the height of the power angle curve and maximum power transfer is reduced because the reactance (X) between the two systems has increased. When Line 2 trips, the height of the power angle curve is reduced further to where the power being transferred cannot be maintained and the system goes unstable. At this point, the power system is in deep trouble. During unstable conditions, the power system breaks up into islands. If there is more load than generation within the island, frequency and voltage go down. If there is an excess of generation in an island, frequency and voltage generally go up. Voltage collapse and steady-state instability occur together as transmission line tripping increases the reactance Maximum Power Transfer P e P max = E g E s X 0 90 180 θ g θ s Power angle analysis: steady-state instability. VOLTAGE RATHER THAN FREQUENCY HAS BECOME THE KEY INDICATOR THAT THE POWER SYSTEM IS UNDER STRESS. between the load center and remote generation. Generally, the voltage drop at the load center is the leading indicator that the system is in trouble with low frequency occurring only after the system breaks up into islands. Analysis of major blackouts confirms that voltage is the leading edge indicator of power system impending collapse. Waiting for the frequency reduction may be waiting too long to separate from the utility power system. Transient Instability Voltage phase angle instability can also occur because of slow-clearing transmission system faults. This type of instability is called transient instability. Transient instability occurs when a fault on the transmission system near the generating plant is not cleared rapidly enough to avoid a prolonged unbalance between mechanical and electrical output of the generator. A faultinduced transient instability has not been the cause of any major system blackout in recent years. However, generators need to be protected from damage that can result when transmission system protection is slow to operate. Relay engineers design transmission system protection to operate faster than a generator can be driven out of synchronism, but failures of protection systems that resulted in slowclearing transmission system faults have occurred. It is generally accepted [2] that loss-of-synchronism protection at the generator is necessary to avoid machine damage. The larger the generator, the shorter is the time to drive the machine unstable for a system fault. Figure 4 illustrates a typical breaker-and-a-half power plant substation with a generator and a short circuit on a transmission line near the substation. If the short circuit is three phase, very little real power (MW) will flow from the generator to the power system until the fault is cleared. The high fault current experienced during the short circuit is primarily reactive or VAr current. From the power transfer equation (Figure 3), it can be seen that All Lines in Service Line 1 Tripped Line 2 Tripped Power Transfer Equation P e = E g E s sin (θ g θ s) X E s = Voltage at the Load Center Generation E g = Voltage at the Remote Generation P e = Electrical Real Power Transfer X = Reactance Between Local and Remote Generation θ s = Voltage Angle at Local Generation θ g = Voltage Angle at Remote Generation 3

when E g drops to almost zero, almost no real power can be transferred to the system. The generator AVR senses the reduced generator terminal voltage and increases the field current to attempt to increase the generator voltage during the fault. The AVR control goes into field-forcing mode, where field current is briefly increased beyond steady-state field circuit thermal limits. During the short circuit, the mechanical turbine power (P M ) of the generator remains unchanged. The resulting unbalance between mechanical (P M ) and electrical power (P e ) manifests itself with the generator accelerating, increasing its voltage phase angle with respect to the system phase angle as illustrated in the power angle plot in Figure 5. The speed with which the generator accelerates depends on its inertia. If the transmission system fault is not cleared quickly enough, the generator phase angle will advance so that it will be driven out of synchronism with the power system. Computer transient stability studies can be used to establish this critical switching angle and time. The equal area criteria can also be applied to estimate the critical switching angle (h c ). When area A 1 ¼ A 2 in Figure 5, the generator is just at the point of losing synchronism with the power system. Note that after opening Breakers 1 and 2 to clear the fault, the resulting power transfer is reduced because of the increase in reactance (X) between the generator and the power system. This is due to the loss of the faulted transmission line. In the absence of detailed studies, many users establish the maximum instability angle at 120. Because of the dynamic nature of the generator to recover during fault conditions, the 120 angle is larger than the 90 instability point for steady-state instability conditions. The time that the fault can be left on the system that corresponds to the critical switching angle is called the critical switching time. If the fault is left on longer than that time, the generator will lose synchronism by slipping a pole. For this condition, the generator must be tripped to avoid shaft torque damage. Out-of-step protection, which is also called loss-of-synchronism protection (Relay Function 78), is typically applied on large generators to trip the machine, thereby protecting it from shaft torque damage and avoiding a system cascading event [3]. Mitigating Blackouts at Utilities and Industrial Facilities When we analyze the causes of power system instability that result in major system blackouts, the following questions arise: What can the utilities and industrial customers with in-house cogeneration do to protect them from being dragged into the blackout? Is the common practice of separating from the utility using frequency as a measure of utility system security adequate for the type of blackouts that are occurring on today s power systems? Utilities themselves are beginning to recognize that frequency alone is not a good measure of system security. A number of utilities have put into service UVLS schemes to complement their existing underfrequency shedding schemes. To date, North Electric Reliability Council (NERC) has not mandated such schemes. However, a number of major utilities have installed them on their own, while many other utilities are considering adding such schemes. Regional reliability groups such as the Western Electricity Coordinating Council (WECC) have developed UVLS guidelines for their members [4]. Utility Load-Shedding Programs Automatic load-shedding programs are designed into utility electrical systems to operate as a last resort, under the theory that it is wise to shed some load in a controlled fashion if it can forestall the loss of a great deal of load to an uncontrolled cascading event. There are two kinds of automatic loadshedding installed in North America UVLS, which sheds load to prevent local area voltage collapse, and UFLS, designed to rebalance load and generation within an electrical island once it has been created by a system disturbance. Automatic UVLS responds directly to voltage conditions in a local area. UVLS drops several hundred megawatts of load in preselected blocks within load centers, Substation Power System 1 2 GSU E s θ s Three-Phase Short Circuit E s = System Voltage E g = Generator Voltage θ s = System Voltage Phase Angle θ g = Generator Voltage Phase Angle G T E g θ g 4 Typical breaker-and-a-half power plant substation with a generator and a short circuit on a transmission line near the substation. Maximum Power Transfer P M = P e P max = E g E s X A 1 A 2 All Lines in Service Breakers 1 and 2 Tripped θ c 0 90 180 θ g θ s Power angle analysis: transient instability. 5 IEEE INDUSTRY APPLICATIONS MAGAZINE SEPT j OCT 2008 WWW.IEEE.ORG/IAS 49

IEEE INDUSTRY APPLICATIONS MAGAZINE SEPT j OCT 2008 WWW.IEEE.ORG/IAS 50 triggered in stages when local voltage drops to a designated level (likely 89 94%) with a several second delay. The goal of a UVLS scheme is to shed load to restore reactive power relative to demand, to prevent voltage collapse, and to contain a voltage problem within a local area rather than allowing it to spread in geography and magnitude. If the first load-shed step does not allow the system to rebalance and voltage continues to deteriorate, then the next block of UVLS is dropped. Use of UVLS is not mandatory but is done at the option of NERC regional area reliability councils (WECC and others) as well as individual utilities. UVLS schemes and trigger points should be designed to respect the local area s system vulnerabilities on the basis of voltage collapse studies. In contrast to UVLS, automatic UFLS is designed for use in extreme conditions to stabilize the balance between generation and load after an electrical island has been formed, dropping enough load to allow frequency to stabilize within the island. By dropping load to match available generation within the island, UFLS is a safety net that helps to prevent the complete blackout of the island and allows faster system restoration afterward. UFLS is not effective if there is a voltage collapse within the island. Today, UFLS installation is a NERC requirement, designed to shed at least 25 30% of the load in steps within each reliability coordinator region. These systems are designed to drop predesignated customer loads automatically if frequency gets too low (since low frequency indicates too little generation relative to load), starting generally when frequency drops to 59.3 Hz. More load is progressively dropped as frequency levels fall farther. The last step of load shedding is set at the frequency level just above the setpoint for generation underfrequency protection relays (around 57.5 Hz) to prevent frequency from falling so low that generators could be damaged. There are two basic types of UVLS schemes that utilities have installed. Both types involve the installation of undervoltage relays at key utility substations. These relays must measure the transmission system voltage and are typically Utility Transmission System 27 Trip Selected Circuits (A-D) 81 A Typical utility substation load shedding. B C Typical Distribution Substation Transformer with LTC 27 = Relay 81 = Underfrequency Relay D THE ROOT CAUSE OF MOST MAJOR POWER SYSTEM DISTURBANCES IS VOLTAGE COLLAPSE RATHER THAN THE UNDERFREQUENCY CONDITIONS. 6 installed at the primary of distribution substations located close to key transmission substations. Figure 6 shows a typical utility installation of both undervoltage (27) and underfrequency (81) relays. Because of voltage transformer (VT) availability, underfrequency relays are usually connected on the secondary of the distribution station because frequency is the same on both the high and low side of the transformer. The voltage measurement for UVLS must be on the transformer primary because transformer losses and load tap changing (LTC) controls will distort the true transmission system voltage level. Figure 6 illustrates a direct tripping type of UVLS. To add security, some UVLS schemes are only enabled if system conditions have occurred that indicate that the power system is in a stress condition. Conditions such as net power import versus local generation or undervoltage measurements at key transmission substation buses are used to arm these UVLS schemes. Some utilities call such schemes special protection schemes. These schemes add an additional level of complexity and generally rely on communications to arm the scheme. Also, they may not be armed quickly enough to be activated for undervoltage events caused by slow-clearing, multiphase transmission system faults that occur during heat storm conditions. Industrial System Separation Schemes Today, most industrial facilities use frequency as a measure of utility power system security and initiate separation when the frequency drops to a specific level for a short time (typically 8 12 cycles). Some industrial facilities use rate of change of frequency to separate from the utility. The use of frequency alone will not separate the industrial facility for cases where the voltage is collapsing. Since voltage is the leading edge indicator of recent utility power system collapse, voltage as well as frequency needs to be used to initiate separation from the utility system. Figure 7 shows a typical industrial installation with both undervoltage (27) and underfrequency (81) relays. Because of VT availability, underfrequency relays are typically connected on the secondary at the industrial facility because frequency is the same on both the high and low side of the transformer. In new installations, both voltage and frequency could be measured for the VTs on the primary of the utility supply transformer. As in the case of utility UVLS, voltage measurement for undervoltage separation must be on the transformer primary because transformer losses and LTC controls will distort the true transmission system voltage level. Once the signal to separate from the utility is generated, the main incoming breakers (A and/or B) are tripped and the facility load is isolated on to in-house cogeneration. This may result in a momentary overload on the in-house generation. Traditionally, after separation, some industrial facilities have used in-house UFLS schemes to match load to cogeneration. In recent years, load-monitoring systems that monitor in-house generation and facility loads in real

time have been used to match load to generation after utility separation [5]. Without the use of voltage to augment frequency to decide when to separate from the utility, the industrial facility risks being dragged down for a voltage collapse. If utilities are starting to implement UVLS, it makes sense for industrials to consider installing undervoltage separation schemes. Designing a Secure Separation Scheme The design of a secure undervoltage separation scheme that avoids false operations for such events as slow clearing system faults requires some logic as well as a relay that can accurately measure voltage within acceptable limits. The undervoltage relay needs to be highly accurate. A measurement accuracy of 0.5 V on a 120 V basis is required. Also, the undervoltage relay that is used needs to have a high pickup-dropout ratio. This ratio needs to be near 100% so that when voltage recovers after a system fault, the relay will quickly reset to the non-trip condition. To meet these requirements, as well as the logic described in the following section, digital relays are almost exclusively being used for UVLS. Industrial facilities can benefit from the logic schemes employed by utilities that have implemented UVLS. Single-Phase Separation Logic Logic can be used to enhance the security of an undervoltage separation scheme to prevent false operation due to slow-clearing system faults. Figure 8 illustrates a scheme using single-phase voltage measurements. The voltage collapse is generally a balanced voltage event with voltage on all three phases being approximately equal. Fault conditions (with the exception of three-phase faults) result in unbalanced phase voltages. This fundamental difference between low voltages caused by faults versus voltage collapse can be used to add security to a separation scheme. Figure 8 logic requires that all three line-to-neutral voltages must drop below Setpoint 1. Additional security can be added using undervoltage (27B) blocking. Since the magnitude of undervoltage due to impending voltage collapse is 89 94%, blocking operation for low voltages that are fault induced adds more security. Figure 8 indicates that any line-to-neutral phase voltage that drops below Setpoint 2 will block the operation of the scheme. The last security measure in Figure 8 logic is the use of negative sequence voltage (47B) to block operation of the separation scheme. During unbalanced fault conditions (all faults except three-phase faults), negative sequence voltage will be present. Since voltage collapse events are balanced voltage conditions, only a very small level of negative sequence voltage is present. The equation that defines negative sequence voltage is shown below [6]: V 2 ¼ 1=3(V a þ a 2 V b þ av c ), where V a, V b, and V c are line-to-neutral voltages, a ¼ 1=120, a 2 ¼ 1=240 : To account for the 120 phase angle displacement between phases, unit phasors (a and a 2 ) are used in symmetrical component terminology. For completely balanced threephase voltages, the negative sequence voltage is zero. Negative sequence voltage blocking is used to detect unbalanced fault conditions and block the separation scheme from improper operation. Positive Sequence Separation Logic Another logic scheme to enhance security for voltage separation is shown in Figure 9. The scheme is similar to that shown in Figure 8. The blocking elements are the same. But, this logic scheme uses positive sequence rather than individual phase-to-neutral voltages to detect an undervoltage condition. Positive sequence voltage is a symmetrical component term and is defined by the following equation: V 1 ¼ 1=3 (V a þ av b þ a 2 V c ), where V a, V b, and V c are line-to-neutral voltages, Transformer 1 27 Single-Phase 27B Block 47B Negative Sequence Overvoltage Block a ¼ 1=120, a 2 ¼ 1=240 : Utility Transmission System 27 81 81 N.O. = Normally Open A 27 = Relay B 81 = Underfrequency Relay N.O. G G 7 Typical industrial installation with both underfrequency and undervoltage separation. V a < Setpoint 1 V b < Setpoint 1 V c < Setpoint 1 V a < Setpoint 2 V b < Setpoint 2 V c < Setpoint 2 V 2 > Setpoint 3 AND OR Single-phase undervoltage separation logic. x 27 Separate to In-House Generation x AND Transformer 2 Adjustable Timer Trip 8 IEEE INDUSTRY APPLICATIONS MAGAZINE SEPT j OCT 2008 WWW.IEEE.ORG/IAS 51

IEEE INDUSTRY APPLICATIONS MAGAZINE SEPT j OCT 2008 WWW.IEEE.ORG/IAS 52 For completely balanced three-phase voltages, the positive sequence voltage is equal to the value of the normal phase-to-neutral voltages, i.e., V 1 ¼ V a ¼ V b ¼ V c. Positive sequence voltage provides a single quantity as the actuating voltage for undervoltage separation and does not require that all three voltages be below a given setpoint as required in the logic scheme shown in Figure 8. Both schemes shown in Figures 8 and 9 are easily programmed into modern digital relays. One of the benefits of digital relay logic is that the blocking logic can be modified to suit the user. If undervoltage and/or negative sequence blocking is not desired by the user, it can be easily eliminated in the logic. Additional security can be provided at critical facilities using a voting logic scheme. The voting logic means that multiple protective relays are applied with identical settings and logic at the same measuring point on the system. A majority of the devices must agree before action is taken. The purpose of voting logic is to get confirmation of the system conditions from more than one protective relay, thus avoiding potential false separation based upon a malfunctioning protective relay. If two relays are installed at each location, two-out-of-two logic is used. This logic requires both relays to operate before separation is initiated. If three relays are used, two-out-of-three logic is used, which requires any two relays to confirm the trip condition. Two-out-of-three logic is common in nuclear plant voltage separation schemes. Setting Considerations Prior to embarking on the design of an undervoltage separation scheme, it is prudent to contact the utility to which the industrial customer is connected and also the local area NERC regional reliability council. Councils such as the WECC have developed UVLS guidelines for their members [4]. It is also difficult for the industrial customer to 27 Positive Sequence 27B Block 47B Negative Sequence Overvoltage Block V 1 < Setpoint 1 V a < Setpoint 2 V b < Setpoint 2 V c < Setpoint 2 V 2 > Setpoint 3 OR AND Positive sequence undervoltage separation logic. x x VOLTAGE RELAYS HAVE BEEN USED BY INDUSTRIAL CUSTOMERS TO DETERMINE THAT THE UTILITY CIRCUIT THAT SUPPLIES THEM HAS TRIPPED. Adjustable Timer Trip 9 develop specific settings because the voltage level for separation is based on the area power system to which the industrial customer is connected. This is similar to the requirements for underfrequency separation where utilities have provided guidance for industrial customers. separation at the industrial customer must be coordinated with utility UVLS. The typical voltage range for UVLS is between 89 94% of normal voltage with a time delay of 1 3 s. Conclusions Investigations of recent blackouts indicate that the root cause of almost all of these major power system disturbances is voltage collapse rather than the underfrequency conditions prevalent in the blackouts of the 1960s and 1970s. The operation of today s power system with generation frequently being remote from the load centers has made the power system very dependent on the utility transmission system. When transmission lines trip, voltage drops at the load center, whereas frequency may remain normal until a complete system collapse occurs. Utilities have begun to recognize this problem and are installing UVLS programs. Also the industrial customers that have in-house generation that operates in parallel with the utility need to recognize the problem. These industrial cogeneration customers should consider the use of undervoltage separation schemes in addition to their existing underfrequency schemes to address the voltage collapse scenario. This article proposes undervoltage separation logic schemes that can be easily installed within digital relays to enhance the security of an undervoltage separation to prevent false operation due to slow-clearing system faults. The article also indicates the required point of installation of these relays so that they properly measure system voltage. References [1] U.S.-Canada Power System Outage Task Force. (2004, Apr. 5). Final report on the August 14, 2003 blackout in the United States and Canada: Causes and recommendations [Online]. Available: http://www.nerc.com [2] G. C. Bullock, Cascading voltage collapse in West Tennessee, presented at Georgia Tech Protective Relaying Conf., Atlanta, GA, May 1990. [3] IEEE Guide for AC Generator Protection, ANSI/IEEE C37.102-1992. [4] UVLS Task Force, WECC. (1999). Load Shedding Guidelines [Online]. Available: http://www.wecc.biz [5] K. Shah, R. Hofstetter, M. S. Miguel, and M. Tiffany, Load preservation systems at facilities utilizing co-generation for real time protection of critical loads during utility outages, in Proc. IEEE Industry Applications Society 52nd Annu. Petroleum and Chemical Industry Conf., 2005, pp. 85 93. [6] J. L. Blackburn, Symmetrical Components for Power System Engineers. New York: Marcel Dekker, 1993. Charles J. Mozina (cmozina@aol.com) is with Beckwith Electric Co. Inc., Largo, Florida. He is a Member of the IEEE. This article first appeared as Power System Blackouts Minimizing Their Impact at Industrial Cogeneration Facilities at the 2006 Petroleum and Chemical Industry Conference.