TS-20KD-1010 LOW PROFILE CARGO SCALE INSTALLATION GUIDE

Similar documents
INSTALLATION GUIDE. Version 2.0

Pro-Weigh 84/SS/FLP Lo Pro 90 / SS Installation Guide. Version 1.0

Aegis Heavy Capacity 20K Floor Scale

Independent Containment System (ICS)

Equilibrium. Conference Table. Installation Instruction. Revision B 11/07/16

Installation Instructions

19 to 39 TV WALL MOUNT - FULL MOTION

DX-TVMLPTB03. Low-Profile TV Wall Mount ASSEMBLY GUIDE. For either wood-stud or concrete wall installations

Oceanside Outdoor Vinyl Shower Kit (3 x 3 Enclosure)

MPA-9000 Universal Ceiling Projector Mount Kit

DOCK WEDGE - STANDARD

Installation and Assembly - Universal Articulating Swivel Double-Arm for 42" - 60" Plasma Screens

Metro Series Sauna. installation instructions

Installation and Assembly - Universal Articulating Swivel Double-Arm for 42" - 60" Plasma Screens

Installation Instructions

PLAYLAND 72 SPIRAL SLIDE 3.5 Posts, 3.5 Posts / 48 Grid and 5 Posts

10x10 Trellis Pergola

Dura-Lock Roof System

10x10 Trellis Pergola

INSTALLATION INSTRUCTIONS

Mount to the Wall INSTALLATION MANUAL

Installation Instructions

ClearSpan PolyMax Windbreak Wall

MobileTrak5 Installation Instructions

Pergola PR100N1. Assembly Instructions. Systems Trading Corporation Customer service: (877)

MM340 Installation Instructions IMPORTANT SAFETY INSTRUCTIONS - SAVE THESE INSTRUCTIONS

INSTALLATION INSTRUCTIONS

VINYL CLASSIC FREESTANDING PERGOLA ASSEMBLY INSTRUCTIONS

11 6 Round Building Assembly Instructions

Deck Mount Installation with Bench

MantelMount. TM1A Installation Instructions IMPORTANT SAFETY INSTRUCTIONS - SAVE THESE INSTRUCTIONS

Installation Instructions for Vista Air Vertically Folding Walls

INSTALLATION INSTRUCTIONS

Assembly Instructions

Equilibrium Credenza

Installation Manual For ToddPod Outdoor Shower Enclosures

Track Rack. * Track Racks are not lockable

Original Gallery System

INSTALLATION INSTRUCTIONS, AND PARTS LIST

MM540 Installation Instructions IMPORTANT SAFETY INSTRUCTIONS - SAVE THESE INSTRUCTIONS

LEAVE THIS MANUAL WITH LIFT OWNER

Assembly Instructions

Model: SS660-PT-R Stainless Steel Poly-Top Floor Scale Series. Installation, Set-Up and Operation Manual

TV WALL MOUNT ASSEMBLY GUIDE RF-TVMLPT01V2

Leveling Foot RB210. Leg Extender RLT66

INSTALLATION INSTRUCTIONS FOR FRONT CASTING DECK RAIL Ranger

Installation and Assembly: In-wall Mount for 32" to 71" Flat Panel Screens

Medium Flat Panel Dual Swing Arm Wall Mount JWD-V

TURBOTWISTER TM ASSEMBLY AND INSTALLATION INSTRUCTIONS

CONTENTS TOOL LIST U P S I D E I N N O V A T I O N S, L L C RAMP AND STEP SYSTEM ASSEMBLY INSTRUCTIONS. Revised: June 2013

Fixed Wall Arm. Installation Guide. Part number Rev E 2012 PolyVision Corporation All rights reserved

TURBOTWISTER ASSEMBLY AND INSTALLATION INSTRUCTIONS

Spring Loaded All Season Roll-Up Doors

Kwik-Lock. Installation Instructions. Attention Dealers: Please give this owners manual to the customer when the product is delivered.

6 1/2 x 6 1/2 Flat Top Pergola

3. Use base plate as template (see FIG. 4-1) to mark location for fasteners.

INSTALLATION INSTRUCTIONS

LEG CURL IP-S1315 INSTALLATION INSTRUCTIONS

Dodecagon Gazebo. Assembly Manual. If you are in the middle of your project and you need assistance Call (717)

TOOLS REQUIRED Metal Wood Wood and Metal Screws. #16 Drill #12-24 Tap. 1/8 Drill

Assembly Instructions

INSTALLATION INSTRUCTIONS

The Festival Assembly Instructions

Installing flat panels on the MPL15 wall mount

INS A KSCR INSTALLATION INSTRUCTIONS STANDARD PROCEDURE. 1. Unpacking the KSCR Splicing the KSCR (If Required)...

ULTRA SPACE SAVER SQUARED Installation Instructions

INSTALLATION MANUAL SFM3

Shetland Stalls Installation Instructions

WPS crew Doors Installation instructions

Model: SS660-OB Stainless Steel Floor Scale Series. Installation, Set-Up and Operation Manual

HOUSE PARTS PACKED IN HOUSE BOX PARTS IN PLASTIC BAG (HARDWARE) PARTS IN SMALL PLASTIC BAG (FLOOR CLIPS) PARTS PACKED IN BUNDLE

Installation Instructions

Gazebo GZ3584 Aluminum Composite Roof Panels

Sliding Door Kit

IMPORTANT: installation. FLOOR ANCHORED CEILING HUNG OVERHEAD BRACED FLOOR-TO- CEILING ANCHORED

- 2 JOINER ALIGNERS - 2 JOINING BRACKETS - 4 HEX BOLTS. Factory pre-installed mud flange TOOLS REQUIRED: Phillips screwdriver, 5/16 nut driver.

Melamine Plastic Laminate. Toilet Partition Installation Manual

END FRAMES. End frames built using pressure treated 2x4 (1 1/2" x 3 1/2") 36" 34" 7/16" pilot hole. 5 1/2" x 1/2" lag bolt 8" wheel 23"

INSTALLATION INSTRUCTIONS FOR PLASCORE NARROW STILE DOORS

Modular XP Ramp Assembly Manual

7141 & NATIONAL POLE VAULT STANDARDS SPECIFICATIONS

ED1300/1300F SERIES CONCEALED VERTICAL ROD DEVICE INSTALLATION INSTRUCTIONS

Bumper Sign INSTALLATION INSTRUCTIONS

Installation Manual Flat Track Series

Installation and Assembly: In-wall Mount for 32" to 71" Flat Panel Displays

6 1/2 x 6 1/2 Wood Grain Flat Top Pergola

ShorePort PWC Lift Instructions " x 138" Sandstone ShorePort " x 138" White ShorePort " x 138" Tan ShorePort

Model #SH & CH SH Pine CH Naturaline

Model MSPPWRTW Large Flat Panel Single Arm Wall Mount

INSTALLATION INSTRUCTIONS

ULTRA SPACE SAVER Installation Instructions

8x8 Spa Breeze Pergola Assembly Manual Outdoor Living Today

Installation Instructions Standalone or continuous run configurations - 2 JOINER ALIGNERS - 2 JOINING BRACKETS - 4 HEX BOLTS

INS A KSR INSTALLATION INSTRUCTIONS STANDARD PROCEDURE. 1. Verify Curb Installation Required Installation Tools...

MSP-DCCLFSD LCD Flat Screen Swing-Down Mount

6 1/2 x 6 1/2 Wood Grain Flat Top Pergola

INSTALL INSTRUCTIONS WELCOME TO THE NEWAGE PERFORMANCE CABINETRY SERIES NEWAGE STEEL WELDED CABINETRY

ASSEMBLY GUIDE. Barcelona Pergola. 12 X16 (365CMx487CM) VER /01/19

Desk/Wall-Mount Rack

10 x 10 Flat Top Two Tone Pergola

Transcription:

TS-20KD-1010 LOW PROFILE CARGO SCALE INSTALLATION GUIDE Triner Scale & Mfg. Co., Inc. 8411 Hacks Cross Rd. Olive Branch, MS 38654 Phone: 800-238-0152 Fax: 662-809-2386

Description The Triner Scale Model TS-20KD-1010 Low Profile Cargo Scale with wrap around ramps is designed for dependable daily use and precision built for year after year accuracy. Only three inches high, it is designed to accommodate tugs, aircraft carts, dollies, and pallet jacks. Technical Specifications Capacity: 20,000 lb x 10 lb Platform Size: 10 x 10 (2 section) Overall Height: 3 Corner Capacity: 50 % of total capacity Summing Junction: Signal trim summing card in NEMA 4x stainless steel enclosure Load Cells: Six 10,000 lb sheer beam type, 350 ohm, 3 mv/v Required Installation Equipment Tape measure Heavy Hammer Large pry bar Hammer Drill 1/2" Concrete Hammer Drill Bit 1/4" Concrete Hammer Drill Bit 3/4" Deep well Socket with extension 1 1/8 Socket with Extension Level Cable tie wraps Roll of tape Calibration weights Installation Procedure Outline If there are any questions about the use or installation of the scale system, please call 800-238-0152. 1. Unpack and lay out all parts. Use the packing list included in this manual to verify that all parts are accounted for. If any parts are damaged or missing please call 800-238-0152. 2. Refer to Figures 1, 2, and 3. Review the drawings carefully as they will help the installation procedure go smoothly without unexpected problems. 3. Orient and install Platform Weldments #1 and #2. 4. Route load cell cables around the scale to a common exit point. 5. Orient and install the approach and side ramps.

6. Connect six (6) load cells to summing junction box. 7. Connect home run cable from the junction box to the digital indicator. 8. Perform corner test with 2,000 lbs of test weight. 9. Calibrate the scale per digital indicator manual. Weldment #1 Installation 1. Choose an area of concrete where the scale is to be installed. The area should be level and free of debris. Be sure to install the scale so the traffic runs parallel to the center seam (see Figure 1). Never install the scale platform on asphalt or blacktop. It will sink in warm weather and cause errors in the weight reading. 2. Be sure to install Platform Weldment #1 first (See Fig. 1). With a forklift, raise Platform Weldment #1 to a comfortable working height. 3. Using load cells marked 1-4, match the load cells to their respective corners. The corner numbers are stamped into the deck plate between the bolting holes. Bolt each load cell into place making sure that the arrow on the load cell is pointing up (see Fig 2.). Securely tighten all bolts. 4. Using load cell stands and spherical washers provided, slide the spherical washers over the 5/8 diameter rod on the load cell stand (see Fig 2.). Make sure to put the concave washer on the bottom and the convex washer on the top. 5. Take one load cell stand (with spherical washers) and slide the 5/8 rod through the hole in the #1 load cell. Make sure the holes in the load cell stand are toward the outside to allow for the installation of the lag bolts. The load cell stand should run diagonally across each corner. Use some tape to temporarily hold the stand in place. Repeat for the remaining three (3) corners. 6. Now that all four load cells stands are properly aligned and secured in place, take the excess bundles of load cell cable and put them on top of the platform to avoid damage. 7. Lower Platform Weldment #1 into the desired position. Once the platform is in position, the tape securing the load cell stands can be removed. 8. Shim the corners with the flat washers provided to level the platform. During shimming, make sure to put the shim washers under the spherical washers. After shimming is complete, make sure each of the four load cell stands have equal pressure against the ground.

9. Drill holes into the concrete with ½ concrete bit to anchor the load cell stands. Install and tighten all anchor bolts, except the two near the center seam of the scale (see Fig 1). In the two holes near the center seam (see Fig 1), DO NOT use the nuts or washers. Simply hammer the anchor bolt flush with the top of the load cell stand. This will ensure that the anchor bolt will not touch the bottom of Platform Weldment #2 when it is put in place. See the Caution statement above! Weldment #2 Installation 1. Follow the same basic procedure as previously with Platform Weldment #1. 2. Make sure load cells 5 and 6 are securely fastened to Weldment #2, the load cell stands are properly aligned, and secured with tape. Place the bundles of wire on top of the platform 3. Carefully place platform Weldment #2 into position. The platforms interlock with each other (see Fig 3) with the load arm witting inside the load receiving pocket. Once platform Weldment #2 is in place and properly aligned, shim each corner as needed to achieve level. Make sure each load cell stand has equal pressure against the ground. 4. Drill the remaining holes, with ½ concrete bit, in the load cell stands. Anchor and secure with the ½ anchor bolts. Run Load Cell Cables 1. One of the side ramps has two notches for the cables to exit (see Fig 1) allowing the cables to exit in the middle of the scale or at one of the corners. 2. Route all load cell cables around the perimeter of the platforms to a common exit point. Use the clips welded to the edge of the platforms to hold the wires off the ground. Use cable ties to secure the wires to the clips. Any excess cable can be stored under the triangular corner attachment of the ramps (see Fig 1). Ramp Installation 1. Layout all eight ramps around the scale as shown in Figure 1. 2. Make sure there is approximately ½ gap all the way around the scale. Note: If a ramp touches the scale platforms there will be errors in the weight reading.

3. Make sure to place the side ramp with cable exit notches where the load cell cables exit. 4. When all ramps are properly aligned, use ½ concrete bit to drill the holes. Install all anchor bolts and tighten them securely. Platform to Junction Box Connection 1. Locate an area, approximately 5 feet away from the scale, in which to mount the indicator/summing junction stand. Secure the stand to the ground with four ½ anchor bolts. 2. Mount the junction box to the stand with the hardware provided. 3. Feed the six (6) load cell cables through the ribbon conduit provided. Be sure all six (6) load cell cables are numbered with wire tags. 4. Secure the ribbon conduit to the floor with the ¼ anchors provided. 5. Connect all six load cell cables to their respective terminals on the summing card. Use the color code chart below for reference. Load Cell Color Code +E Red -E Black +S Green -S White SH Bare Junction Box to Indicator Connection 1. Mount the digital indicator to the indicator stand with the hardware provided. 2. Connect the home run cable to the junction box using the same color codes as above. 3. Make sure to tighten all liquid tight fittings to prevent moisture from entering the junction box. Corner Adjustment The scale ships from the factory with pre-adjusted corners. However, if adjustments are needed use the potentiometers to adjust each corner as necessary. It is recommended to use 2,000 lbs of test weight to adjust the corners.

Final Calibration Calibrate the scale system with a minimum of 5,000 lbs of test weight per the digital indicator manual. Packing List Item Description Qty Check Platform Weldment #1 (Female) 1 Platform Weldment #2 (Male) 1 15 Side Ramps 3 15 Side Ramp with Cable Exit Notches 1 15 or 30 Approach / Exit Ramps (Left) 2 15 or 30 Approach / Exit Ramps (Right) 2 Load Cell Stands 6 Indicator / Junction Box Stand 1 Digital Indicator with 6 Home Run Cable 1 SBS-10K Sheer Beam Load Cells (Numbered 1-6) 6 6 Load Cell Stainless Steel Junction Box 1 5 Ribbon Conduit 1 ¾ - 10 x 2 ¼ Hex Cap Screw 12 5/8 Spherical Washer Sets 6 5/8 Flat Shim Washers 12 ¼-20 x 1 Hex Cap Screw 8 ¼ Flat Washer 8 ¼ Lock Washer 8 ¼-20 Hex Nut 8 ½ x 4 ¼ Concrete Anchor Bolts with Washers and Nuts 40 ¼ x 3 ¼ Concrete Anchor Bolts with Washers and Nuts 8