Posi-Joist Installation Guide. A guide for storage, handling and installation of the MiTek Posi-Joist floor system

Similar documents
UPPER FLOORS TIMBER AND CONCRETE

Cl/SfB (23.9) VALUE OPEN WEB FLOOR SOLUTION. ALPINE. Advancing timber fabrications through design : components : manufacture

Site Installation Guide


BRACING BRACING SECTION 7 SECTION 7

Installation Guide: Timber stairs. A Guide to safe stair installation from the BWF Stair Scheme

hyjoist Options Range Installation Guide

INSTALLATION INSTRUCTIONS for TB6.2,TB7.0, TB7.8 & TB8.4

Strong, lightweight composite structural I -Beam.

INSTALLATION GUIDE Timber Stairs

Installation Guide: Timber stairs. A Guide to safe stair installation from the BWF Stair Scheme

Installation Guide. Please read before installing SIPs Kit. 1 Method Statement for the erection of a SIPS Industries Kit Materials...

How-To-build guide Garden shed

Sections & Details VOCABULARY

ISSUE Erection Manual

Horizontal Shaft Wall

VERSA-LAM. An Introduction to VERSA-LAM Products

LVL8 H1.2 GENERAL FRAMING. Eco Friendly Revolutionary H1.2 Treatment Azotek by Zelam

SECTION R507 DECKS DECKING LEDGER BOARD BEAM. FOOTING BEAM SPAN CANTILEVER For SI: 1 inch = 25.4 mm FIGURE R507.2 DECK CONSTRUCTION

Method of Build 1. Fire. Sound

F I X I N G B R O C H U R E

Standard Details. Glosford Timber Solutions Ltd. Homer Road Hereford HR4 9BP

Chapter 7 - Porch Framing

T-BRACE / I-BRACE DETAIL WITH 2X BRACE ONLY

RAPID RIVER RUSTIC, INC.

Table of Contents. e-joist Design Information Page 2. Floor Joists Supporting Floor and Ceiling Loads Only 3. e-joist Construction Information 4

Installation Instructions for. Before You Begin TOOLS REQUIRED

The Influence of Nails and Plasterboard on the Racking Resistance of Stud Walls

SECTION: 15 ZONING RULE LOT AREA 6134 S.F S.F. BUILDING AREA (FOOTPRINT) LOT COVERAGE 20.2% 24.86' FRONT YARD SIDE YARD 8.

method of build Komfire-75 partitioning system 75mm Steel Stud & Plasterboard Partitioning System with Square Aluminium Cover Trims KOMFORT

Clopay Models 835/837 Sliding Door System Installation Guide

Method of Build 1. General

Glulam Connection Details

Wood structures Copyright G G Schierle, press Esc to end, for next, for previous slide 1

3.1 General Provisions

VERSA-LAM BCI INSTALLATION GUIDE LIMIT STATES DESIGN CANADA

4.0 GENERAL WALL AND CEILING INSTALLATION

Introducing AJSTM INSTALLATION GUIDE USA. 8 th Edition USA

Timber to Timber - Timber to Concrete - Timber to Steel

Plasterboard Ceiling Systems

NewTech - CleverDeck Composite Decking Installation Guidelines

C.00. Ullrich Aluminium Co. Ltd. Ulltraclad Aluminium Cladding September Wall Batten Elevation. Horizontal battens between verticals at soffit

Shaft Wall SYSTEMS 210 INSTALLATION 211. Shaft Wall systems are fire rated non-load bearing walls used for shafts and service ducts.

Roofs SECTION. Contents for this section: Components and Elements of Roofs

NORMAL WEIGHT CONCRETE TOTAL-LEWIS-DECK GYPSUM BOARD 2 OR 3-PLY COMPOSITE TOTALJOIST TOP CHORD CONNECTION

SINGLE PIECE MASONRY HANGERS

hy JOIST futurebuild structural lvl design & Installation Guide: 2.1 december 2013

INSTALLATION GUIDE. Outback. Flat Attached BEFORE YOU START ADDITIONAL MATERIALS TOOLS REQUIRED. VERAnDAHS PATIOS CARPORTS

E-Z BUILD SHED GUIDE 12' 12' 12' 16' 12' 20'

Acceptable Standards of Domestic Construction

LP SolidStart LSL. LP SolidStart LSL Prescriptive Roof Framing Technical Guide 2500F b-1.75e, 2360F b -1.55E and 1730F b -1.

OUTBACK FLAT ATTACHED VERANDAH PATIO CARPORT - INSTALLATION GUIDE BEFORE YOU START TOOLS REQUIRED ADDITIONAL MATERIALS

Unit 9. Wall and Ceiling Framing

Timber joist. Timber joist ceilings and separating / compartment floors. Timber joist.

Main Floor Revisions: 38' 0" Rm1 H3 50' 0" Bk1 B1 Rm2 B5 (26)-2 H2 B2 H3 (3)-3 B3 (11)-4 Bk1 B1 (5)-5 Rm4 Bk1 Rm3 Bk1 24' 0" 6' 0" 20' 0" START FRAMIN

RIDGE-JOIST CONNECTION 12/12 maximum slope

Evorail Guardrail has Evolved

Ijoist floor framing book. Ijoist floor framing book.zip

GlasRoc Sheathing Type X

How to Build Good Decks..

METHOD STATEMENT FOR THE CONSTRUCTION OF LIGHTWEIGHT HALLS

Call (770) STEP 6: Caulk bolt hole within the bracket for protection from the elements.

The WANZ Guide to Window Installation

Dura-Lock Roof System

SunTrackerTwo Preparation

ROOF TRUSS Installation INSTRUCTIONS

With Illustrations, Drawings & Step By Step Details. Click Here To Download 12,000 Shed Plans. 1 P a g e Download 12,000 More Shed Plans

FASTENERS BUILDING DEPARTMENT

Stratco Sanctuary INSTALLATION BEFORE YOU START TOOLS REQUIRED GUIDE

Sound insulating floor system

Featuring TJ Rim Board and TimberStrand LSL

10. Vents, Baffle Guard and Blocking

8 x 10 Timber-frame Garden Shed

Sections & Details. WOOD SILL and FLOOR CONSTRUCTION NOTES

rondo exangle drywall finishing sections

WHY YOU SHOULD USE TUFFLOOR. components

Fibre Cement G C. Batten Fixing Setout ST-01. Jan 2014 A4 PROFILE DATE SCALE DETAIL DETAIL NO. Plank joint. 600mm stud crs.

Installation Instructions

Chapter 33: Lofts (Or Second Floors)

A. Rough carpentry includes but is not limited to the following:

Dave's Glossary of Construction Terms. by Dave Osborne (

Chapter 6 - Walls & Stairs

ENGINEERED BUILDING PRODUCTS. I-Beam HANGERS. NEW Enhanced Capacity with YELLOW MiTek 40 x 3.75mm nails

TOLL FREE:(888) FAX:(941) ASSEMBLY of ProTEC CONCRETE STRUCTURAL INSULATED PANEL

Description. Lesson Outcomes. Assumptions. Build a Floor. Carpenter

SECTION ROUGH CARPENTRY

4. Components and Stairs

Linear Open Style Suspended Ceiling Installation Guide

Installation Instructions for. Handrail Component System

Catnic Pontypandy Industrial Estate Caerphilly CF83 3GL T: F: English version

Sound insulating floor system

Beam & Header Technical Guide. LP SolidStart LVL. 2900F b -2.0E. U.S. Technical Guide U.S. TECHNICAL GUIDE

How to make a Wendy house Part One: The Floor and the Frame

nam4t/m6 ubracreboaardl

PANEL CRIB PIERS AND TOWERS

ROOF TRUSS Installation

Builders Metalwork Product Selector

CELLBOARD DECK CLIP FIXING INSTALLATION MANUAL CBWD14525

Use the Design Properties (100% Load Duration) Table from Page 3 for questions 1-7

METALWORKS Concealed. Installation Instructions

Transcription:

Posi-Joist Installation Guide A guide for storage, handling and installation of the MiTek Posi-Joist floor system

Posi-Joist Installation Details A B C D F E A Masonry Wall Connection Details Blockwork to continue between joists to provide restraint. Note: This is not allowed on solid external walls. Top Chord restraint fixed between joists. Minimum bearing determined by design. (Choose correct full depth hanger relative to coursework, load, bearing width and level).

Temporary Bracing B Soil Pipe Corner Details Full depth masonry hanger Bearers fixed directly to the wall to pick up both floor and ceiling Full depth masonry hanger Full depth masonry hanger Solid timber or LVL trimmer (depth to suit) Proprietary hangers Top chord restraint omitted for clarity. This may not perform well acoustically as sound will be transmitted directly from the floor to the bearer through the inner leaf of the wall. C Internal Bearing Details Full blockfill only required when there is a load bearing wall above the floor level Solid timber block (grain parallel to span) Masonry built up to under side of floor to provide restraint Note: This is not allowed on external walls or fire walls. D Strongback Bracing Details WEB SIZE PS8,PS9 & PS10 PS12,PS14 & PS16 Min. STRONGBACK SECTION 47 x 97 TR26 36 x 145 TR26 Strongback(See table for minimum sizes) Position strongback tight to the underside of top chord 38x75mm (min) blocks twice nailed to top and bottom members and twice nailed to brace using 3.1x75mm long galvanised wire nails. Insert strongback through joists before fixing joists, it may not be possible after joists have been fixed. Strongback twice nailed to brace using 3.1x75mm long galvanised wire nails Note: Minimum recommended strongback sizes are given above which may be different when floor is designed to EC5 vibration check, see Posi-Joist calculations. Strap fixed along top edge of strongback with a minimum of four fixings of which at least one is to be over the third joist

E Timber Frame Details 38x89 C16 (min) noggings at max 600mm centres Z clips 47x89mm continous pack Posi-Joists bearing on wall Ringbeams in solid timber or LVL Non-load bearing partitions parallel to Posi-Joist First Posi-beam set back approx 200mm from wall 47x89mm packs between joists 47x89mm packing piece Posi-web over bearing by min 15mm Timber frame separating floor E-FT-3 (Refer to robust detail) Floor comprising: A minimum 253mm deep Posi-Joist with 18mm T&G flooring on 19mm gypsum based board (nom 13.5Kg/m2) onto FFT1Resilient composite batten system minimum 70mm deep with 25mm insulation (10-36Kg/m3) laid between and all on a 18mm T&G sub-deck. 100mm insulation quilt (10-36Kg/m3) is laid between the joists. Ceiling treatment CT2 (not shown) comprising: 2 Layers of 15mm gypsum based board (nom 11.7Kg/m2) onto resilient bars at 400mm centres. The first layer of board is fixed with 25mm screws and the second layer of board is fixed with 42mm screws staggered with the first board. The second layer is laid in echelon pattern with staggered joints. Max 6mm gap 40x47mm continuous plasterboard noggin Note: Ceiling board fixings must not penetrate or touch joists. F Stairwell Details Proprietary screw connectors. See suppliers approved list Proprietary hangers Proprietary hanger Proprietary hangers Proprietary screw connectors. See suppliers approved list Floor packers added to suit trimmer size Solid timber or LVL trimmer (depth to suit) Trimmer to be notched over the bottom flange of hanger Reinforcement may be to stairwell side or both sides, determined by design. Do not notch bottom member of Posi-Joist over bottom flange of hanger.

Posi-Joist Site Handling and Storage Storage on site should be for a limited period of time prior to erection of the Posi-Joists. Posi-Joists should either be stored vertically or on the flat. If stored vertically there should be intermediate bearers at node points not within the bay of a joist, as shown below. If stored in a flat position, sufficient bearings should be provided to prevent excessive lateral bending. Bearers as close as possible to web points It is recommended that completed Posi-Joists be strapped together and wrapped in a waterproof protective covering to protect them from short term exposure to inclement weather. Special precautions should be taken when stacking top chord supported floor cassettes to prevent the stack lozenging in storage. Additional bracing to the ends of the stack should be fixed to stop lateral movement. Care should be taken when handling the Posi-Joists to avoid bending, twisting or dropping. When loading/offloading with a crane, slings should always be attached to the timber chords or the cassette lifting points, and not to the metal webs to avoid buckling. Slings should be attached at panel points closest to the quarter points of the Posi-Joists as shown below. Use fabric sling. Do not use chains or wire rope which may damage webs Bearers directly under web points 60 or less 6 The Posi-Joists are positioned to coincide with the deck joints, the first of which is normally 1210mm away from the wall face in masonry construction or 1200mm from the cavity face in Timber Frame construction when the deck extends to the cavity face; when the joists are spaced at 400 or 600mm centres. There is normally a 10mm perimeter gap between the face of the deck and the face of the wall in masonry construction to allow for potential expansion of the deck. The board material is normally 1200 x 2400mm, the long dimension spanning at 90 to the joist span. The remaining joists are normally spaced on a grid of 400, or 600mm centres, on occasion at 480mm centres. 7 When the deck is set out from the face of the wall it is normal to have the first joist edge 50mm from the face of the wall where in Timber Frame construction with the deck set out from the cavity face it is normal to not have a joist close to the wall, the deck and plasterboard being supported on a timber ledger nailed to the frame. Carefully follow the layout drawing and the wall/joist interface details provided by the Building Designer, in particular in Timber Frame where the joist centres and the stud centres may have to line through. 8 The penultimate Posi-Joist in the run is set out on the standard module and the last joist is positioned similar to the first in the run. 9 Posi-Joist stair trimmer joists and trimmers will be required around stair openings which may be on the main joist grid or usually off the grid. Set these joists out strictly in accordance with the architectural and Posi- Joist layout drawing and fix the trimmer joist to the stair trimmer and the trimmed joists to the trimmer joist with the metal hangers specified making sure that any 2 ply joists are adequately connected together as detailed. 10 To temporary brace and space the Posi-Joists which have been laid in position fix a piece of 22 x 97 bracing to the top of the joists at their ends and mid span or around 2.4m centres on spans longer than 4.8m. 11 Install the strongback bracing as detailed, the strongback is always installed on edge not on flat and must be fixed to the integral strongback blocks or nogging pieces nailed to the face of the joist. Due to the width of the Posi-Joist chords and the additional stiffness installed in the floor due to the strongback bracing, it will not normally be necessary to employ any temporary diagonal bracing. 12 When all the Posi-Joists have been positioned and fixed in place, the partition noggings, perimeter noggings, rim boards, when required can be installed, and in the case of masonry construction the steel lateral restraint straps should be fixed in place at no greater than 2m centres and should extend over 3 joists. 13 The floor carcass is now ready now to receive the decking material and acoustic material where required. Set Out & Placement Posi-Joists are generally placed perpendicular to the load bearing supporting walls and should be located so that the distance between them does not exceed the design spacing always consult the Posi-Joist layout drawing and proceed with erection of the floors as follows:- 1 Plan the erection sequence and place the Posi-Joists close to where they are required, only distribute a sufficient number of joists around the building which an be erected in a reasonable period of time. Posi-Joists should be protected from inclement weather and stored as noted above. 2 Before lifting the Posi-Joists to scaffold level do make sure the correct end of the joist is at the appropriate support as the end details may be different. Also be aware of any internal supports which are being used and that the special internal bearing detail for the joist is in the correct position. 3 If the Posi-Joists are supported over more than 2 supports make sure all the supports are the same level and when the joists are lifted into place they rest on all of the supports. 4 If the Posi-Joists are supported on masonry hangers, make sure they are the ones specified and are firmly anchored in place. Joists should have a full bearing with no more than a 5mm gap between the end of the joist and the face of the hanger. Masonry hangers with a cavity return and integral strap provide lateral restraint to wall heads. 5 Make sure the Posi-Joists are erected the correct way around, the joists will normally be marked TOP and the first metal web will normally start at the top of the Posi-Joists. 14 The maximum load of sheet materials temporary stored on the Posi-Joists is 250kg/m 2 and should not be greater than mm deep. This equates to 16 sheets of 18mm chipboard, 13 sheets of 22mm chipboard or 20 sheets of15mm plasterboard. Where the sheets are stacked by hand they should span lengthways across the joists, (Fig 1), when lifted mechanically they should be seated on 5 bearers the width of which are 600mm longer than the width of the board. (Figs 2 & 3). 600 2400 FIG 1 FIG 3 600 FIG 2 1200

Posi-Joist Temporary Bracing Temporary Bracing This does not apply to top hung Posi-Joists in timber frame construction which do not require temporary bracing (See Section E). Temporary Erection Bracing Notes 1 Un-braced Posi-Joists may be unstable. The builder is responsible for identifying and minimising the risks involved in erecting Posi-Joists to ensure that the health and safety of all workers is maintained. Builders should be aware of the health and safety responsibilities imposed on them by the Construction (Design and Management) Regulations 1994. Proper erection procedures and bracing are vital to the safe construction of Posi-Joist floors. The following notes may assist builders in preparing a safety assessment. Construction materials should only be stored in the 1.5m edge zone at one end of the joist only. Min 675mm cured masonry above hanger level or as advised by hanger manufacturer. 2 M.4m AX. 2 Do not allow anyone to walk on un-braced Posi-Joists. 3 Do not store building materials on un-braced Posi-Joists. 22x97mm diagonal braces. Decking can be laid in lieu of diagonal bracing. Nail all binders and braces to each joist with 2-3.35 x 65mm nails. Do s and Don ts Drill holes in the timber chords Cut or remove the metal webs Cut through the timber chords 5 Temporary bracing comprises diagonal bracing, longitudinal binders and permanent strong-backs. 6 All longitudinal binders, diagonal braces, strong-backs and hangers should be completely installed and fully nailed as detailed. 2 M.4m AX. 22x97mm longitudinal binders connected to diagonal bracing at one end of joist run. 4 Posi-Joists should be erected straight and vertical. The maximum deviation from horizontal should not exceed 10mm and the maximum deviation from vertical should not exceed 2mm. Cut notches in the timber 7 Lateral strength should be provided by a diagonally braced system across at least 3 Posi-Joists as shown in the Erection Bracing diagram. Additional braced and blocked systems should be added at 12m spacing in long joist runs. 8 Temporary bracing may be progressively removed as decking is fixed. Store as shown in handling & storage section Lift the joists in a vertical position Protect joists from inclement weather Use the open web feature for services Authorised Posi-Joist Manufacturer Shaping the Future of Timber Engineering MiTek Industries Ltd MiTek House, Grazebrook Industrial Park, Peartree Lane, Dudley, DY2 0XW, UK. Telephone: 01384 451400 www.mitek.co.uk