Selective Coordination for Emergency and Legally-Required Standby Power Distribution Systems

Similar documents
SECTION OVERCURRENT PROTECTIVE DEVICE COORDINATION STUDY

This section applies to the requirements for the performance of power system studies by both the Design Engineer and the Contractor.

ARC FLASH PPE GUIDELINES FOR INDUSTRIAL POWER SYSTEMS

1960 Research Drive, Suite 100, Troy, Michigan with. REVISION: December 10, 2007 (Supersedes previous versions) Prepared by:

SECTION SHORT CIRCUIT, COMPONENT PROTECTION, FLASH HAZARD AND SELECTIVE COORDINATION STUDY

Design Approaches for Hospital Distribution Systems With Considerations for Future Expansion, Operator Safety, and Cost

2018 Consultant s Handbook Division 26 Electrical ARC Flash Hazard Analysis

ADDENDUM NO. 2 PROJECT: COURTLAND PUMP STATION CONTRACT: IFB NO COM.00030

Note: The let-through of the protective device must be equal to or less than the short-circuit current rating of the component being protected.

APPLYING LOW-VOLTAGE CIRCUIT BREAKERS TO LIMIT ARC FLASH ENERGY

Short Circuit Current Calculations

3Ø Short-Circuit Calculations

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

First Draft Language

PREFACE ********************************************************** IT IS NOT INTENDED THAT THESE STANDARDS BE COPIED AND USED AS A SPECIFICATION!

Power System Study for the Pebble #2 Lift Station Las Vegas, Nevada

Technical T TECHNICAL. C o n t e n t s SPEEDFAX TM 2017

Section 16621A - AUTOMATIC TRANSFER SWITCH. Part 1 General

Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc GE Consumer & Industrial Multilin

SECTION POWER SYSTEMS STUDIES

GE Multilin technical note

Arc Flash Analysis Training

Electrical Arc Hazards

Guide to Low Voltage System Design and Selectivity

Arc Flash Analysis and Documentation SOP

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

GUIDELINES FOR SELECTIVE OVERCURRENT PROTECTION FOR ELECTRICAL SYSTEMS OF SHIPS

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

{40C54206-A3BA D8-8D8CF }

POWER SYSTEM ANALYSIS TADP 641 SETTING OF OVERCURRENT RELAYS

Electrical Measurement Safety. Sponsored By:

How to maximize reliability using an alternative distribution system for critical loads

Paul Dobrowsky Innovative Technology Services

Protection of Electrical Networks. Christophe Prévé

TN, TT & IT Earthing Arrangements

1

Bus Protection Fundamentals

WAVEFORM CORRECTOR (WAVEFORM CORRECTORS) REPLACES SURGE PROTECTION DEVICES (SPD) PREVIOUSLY KNOWN AS (TVSS)

TABLE OF CONTENT

thepower to protect the power to protect i-gard LITERATURE Low and medium voltage

THREE PHASE PAD MOUNTED DISTRIBUTION TRANSFORMER ARC FLASH TESTING JUNE 23, 2009 FERRAZ SHAWMUT HIGH POWER LABORATORY NEWBURYPORT, MA

Michigan State University Construction Standards SWITCHBOARDS, PANELBOARDS, AND CONTROL CENTERS PAGE

Technical collection. Cahier technique. no Energy-based discrimination for low-voltage protective devices. M. Serpinet R.

Section 6: System Grounding Bill Brown, P.E., Square D Engineering Services

BED INTERCONNECTION TECHNICAL REQUIREMENTS

Busbars and lines are important elements

COMMON SOURCES OF ARC FLASH HAZARD IN INDUSTRIAL POWER SYSTEMS

Grounding for Power Quality

Webinar: An Effective Arc Flash Safety Program

Arc Flash Calculation Methods

AN EXAMPLE OF A STANDARD ARC FLASH PPE LABELING STRATEGY

NATIONAL ELECTRIC SAFETY CODE 2012 EDITION

2014 NEC Changes Part 1

Protective Relays Digitrip 3000

Unit Auxiliary Transformer Overcurrent Relay Loadability During a Transmission Depressed Voltage Condition

SUGGESTED SPECIFICATION for Series 300 Automatic Transfer Switches

Distribution/Substation Transformer

E S C R I P T I V E B U L L E T I N .,.,.,. Bulletin DB-106. October, Square D Company Power System Studies ---1 I SQU ARED COMPANY --

ET 51 - Electrician Theory Examination Marking Schedule

Description & Applications Questions & Answers Selection Charts Single Phase Selection Charts Three Phase...

Short-Circuit Current Calculations

SECTION LOW-VOLTAGE ELECT. DIST. DESIGN AND CONSTRUCTION STANDARDS _ February 2015 PART I: GENERAL

Table of Contents. Introduction... 1

Cutler-Hammer January 1999

ARC FLASH HAZARD ANALYSIS AND MITIGATION

S&C Vista Underground Distribution Switchgear Outdoor Distribution

BUCK-BOOST TRANSFORMERS

Effective System Grounding

NIPSCO Energy Symposium

Protection Introduction

Arrester Disconnector

B. Manufacturers: Square-D, G.E. or Westinghosue.

HPS Universal BUCK-BOOST TRANSFORMERS

UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS

Time-current Coordination

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

EPG. by Chris C. Kleronomos

(With the possibility of a tripping coil for remote control) (Generally optional with an electronic tripping device)

1. All electrical switches and outlets used shall be equal to Hubbell heavy duty, specification grade or equivalent quality.

Protection of a 138/34.5 kv transformer using SEL relay

2 Grounding of power supply system neutral

WHITE PAPER. Medium Voltage On-Site Generation Overview. BY MIKE KIRCHNER Technical Support Manager at Generac Power Systems

EPSITRON Electronic Circuit Breakers For Secondary Side DC Protection

SECTION AUTOMATIC TRANSFER SWITCH

The Importance of the Neutral-Grounding Resistor. Presented by: Jeff Glenney, P.Eng. and Don Selkirk, E.I.T.

E N G I N E E R I N G M A N U A L

Coordination of LV protection devices

SUBMITTAL TRANSMITTAL OCPS CLAY SPRINGS ES REVIEWED SUBMITTAL NUMBER: SUBMITTAL DETAILS: CONTRACTOR/CM:

SECTION DISTRIBUTION SWITCHBOARDS

Comparison of recloser and breaker standards

SECTION PANELBOARDS

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

Electricity Ten Year Statement November Electricity Ten Year Statement November Appendix D

CHANGEABILITY OF ARC FLASH PARAMETERS AND ITS IMPACT ON HAZARD MITIGATION IN LOW VOLTAGE POWER SYSTEMS

Bruce L. Graves /01/$ IEEE. IEEE Industry Applications Magazine PhotoDisc, Inc.

Healthcare Isolation Power Systems. Presented by: David Knecht

AN EXAMPLE OF A STANDARD ARC FLASH PPE LABELING STRATEGY

... avoid using constructionstyle generators that have master GFCIs.

Three-Phase VFI Padmount Transformers. Double Duty in a Single Package. www. ElectricalPartManuals. com

SECTION DISTRIBUTION SWITCHBOARDS

Transcription:

Selective Coordination for Emergency and Legally-Required Standby Power Distribution Systems Presented for the IEEE Central TN Section / Music City Power Quality Group August 1, 2006 By Ed Larsen and Bill Brown, P.E. Square D / Schneider Electric Codes and Standards / Power Systems Engineering

Presenters Ed Larsen Industry Standards Manager Square D / Schneider Electric Codes and Standards Group Bill Brown, P.E. Staff Engineer Square D / Schneider Electric Power Systems Engineering Group Codes and Standards / Power Systems Engineering

Topics 2005 NEC Requirements What is selective coordination? Issues with the 2005 NEC Requirements Overcurrent Protective Device Characteristics Specific Guidelines for Achieving Selectivity Slide 3

Topics 2005 NEC Requirements What is selective coordination? Issues with the 2005 NEC Requirements Overcurrent Protective Device Characteristics Specific Guidelines for Achieving Selectivity Slide 4

2005 NEC Requirements Definition of Emergency System per NEC 700.1: Emergency Systems are those systems legally required and classed as emergency by municipal, state, federal, or other codes, or by any governmental agency having jurisdiction. These systems are intended to automatically supply illumination, power, or both, to designated areas and equipment in the event of failure of the normal supply or in the event of accident to elements intended to supply, distribute, and control power and illumination essential to human life. Slide 5

2005 NEC Requirements Definition of Legally Required Standby System per NEC 701.2: Those systems required and so classified as legally required standby by municipal, state, federal, or other codes or by any governmental agency having jurisdiction. These systems are intended to automatically supply power to selected loads (other than those classed as emergency systems) in the event of failure of the normal source. Slide 6

2005 NEC Requirements NEC 700 Emergency Systems 700.27 Coordination. Emergency system(s) overcurrent devices shall be selectively coordinated with all supply side protective devices. NEC 701 Legally Required Standby Systems 701.18 Coordination. Legally required standby system(s) overcurrent devices shall be selectively coordinated with all supply side protective devices. Slide 7

2005 NEC Requirements Contrast these with the definition of selectivity per NEC 100: Coordination (Selective). Location of an overcurrent condition to restrict outages to the circuit or equipment affected, accomplished by the choice of overcurrent protective devices and their ratings or settings. The result: NEC 700.27 and 701.18 require device-todevice coordination, whereas NEC 100 implies system coordination. Slide 8

2005 NEC Requirements Also contrast NEC 700.27 and 701.18 with NFPA 110-6.5.1: 6.5.1* General The overcurrent protective devices in the EPSS shall be coordinated to optimize selective tripping of the circuit overcurrent protective devices when a short circuit occurs. * Explanation in NFPA 110 Annex A: A.6.5.1: It is important that the various overcurrent devices be coordinated, so far as practicable, to isolate faulted circuits and to protect against cascading operation on short circuit faults. In many systems, however, full coordination is not practicable without using equipment that could be prohibitively costly or undesirable for other reasons Slide 9

2005 NEC Requirements Article 517 Health Care Facilities now requires that the essential electrical system also meet the requirements of Article 700 517.26 Application of Other Articles. The essential electrical system shall meet the requirements of Article 700, except as amended by Article 517. Slide 10

Topics 2005 NEC Requirements What is selective coordination? Issues with the 2005 NEC Requirements Overcurrent Protective Device Characteristics Specific Guidelines for Achieving Selectivity Slide 11

What is Selective Coordination? Selective coordination exists when the smallest possible portion of the system experiences an outage due to an overcurrent condition. UTILITY SERVICE MAIN SWITCHBOARD A CB M1 CB F1 B FAULT LOCATION DEVICE THAT SHOULD OPERATE FOR SELECTIVE COORDINATION A UTILITY PROTECTIVE DEVICE B CB M1 LIGHTING PANEL "LP1" CB PM1 CB B1 C D C D CB F1 CB PM1 E E CB B1 Slide 12

What is Selective Coordination? The goal of selective coordination: Confine system outages due to overcurrents to the smallest possible number of loads The concept of protective zones is a useful tool to visualize this Slide 13

What is Selective Coordination? Primary protective zones for the previous example: UTILITY SERVICE Fault in this zone CB M1 Trips CB M1 CB F1 CB M1 PRIMARY PROTECTIVE ZONE Fault in this zone CB F1 Trips CB F1 PRIMARY PROTECTIVE ZONE Fault in this zone CB B1 Trips Fault in this zone CB PM1 Trips CB PM1 CB B1 CB B1 PRIMARY PROTECTIVE ZONE No overlapping of primary protective zones system is selectively coordinated CB PM1 PRIMARY PROTECTIVE ZONE Slide 14

How is selective coordination achieved? Selective coordination is achieved by coordinating the time-current characteristics of overcurrent protective devices Device closest to fault trips first because it is selected or set to respond faster than upstream devices If the device closest to the fault fails to trip, the next upstream device will trip Slide 15

Slide 16 Selective Coordination for Emergency/Legally-Required Standby Power Systems How is selective coordination achieved? CURRENT IN AM PERES 100 100 10 1000 1000 CB M1 1K 1K 100 100 CB F1 CB PM1 10 10 CB B1 1 1 0.10 0.10 0.01 0.01 10 CB PM1, CB B1 Coordinate Through 2kA 10K 10K 100K 100K TIM E IN SECONDS CB F1, CB PM1 Coordinate Through 21.6kA Time-Current Characteristic (TCC) plot of previous example No overlap for devices with time-current bandtype characteristics up to the available fault at the downstream device =>selectivity

How is selective coordination achieved? UTILITY SERVICE CB M1 Protective zone representation of previous TCC 30kA Avail. Fault CB F1 CB F1 PRIMARY PROTECTIVE ZONE CB M1 PRIMARY PROTECTIVE ZONE Overlapping protective zones => problem areas 21.6kA Avail. Fault 25kA Avail. Fault CB PM1 CB B1 CB B1 PRIMARY PROTECTIVE ZONE 2kA Avail. Fault CB PM1 PRIMARY PROTECTIVE ZONE Problem Area Slide 17

How is selective coordination achieved? But, be wary: Just because one overcurrent protective device is upstream from another does not mean they must selectively coordinate with each other in order for the system to be selectively coordinated This statement is true in several commonlyencountered scenarios Slide 18

What is Selective Coordination? One example of where selective coordination between two devices is not required for system selectivity to exist: Load PRIMARY CB PRIMARY CB PROTECTIVE ZONE TRANSFORMER SECONDARY CB Fault SECONDARY CB PROTECTIVE ZONE A fault in the location shown can cause either the Primary CB or Secondary CB, or both, to trip with no difference in the number of loads affected. In other words, for purposes of coordination, the Primary CB and Secondary CB can be considered as one device, which in this case serves to protect the transformer. Slide 19

What is Selective Coordination? Other examples of where device selectivity is not required for system selectivity: G ENGINE-GENERATOR SET CB 1 PANEL 1 CB 1 PANEL 2 CB 2 SWITCHBOARD CB 1 a.) b.) Slide 20

Topics 2005 NEC Requirements What is selective coordination? Issues with the 2005 NEC Requirements Overcurrent Protective Device Characteristics Specific Guidelines for Achieving Selectivity Slide 21

Issues with the 2005 NEC Requirements Clear conflict between the definition of selective coordination in NEC 100 vs. requirements of 700.27 and 701.18, as well as the requirements of 700.27 and 701.18 vs. NFPA 110-6.5.1! Wording of NEC 700.27 and 701.18 are in terms of device coordination, not system coordination So far, most reasonable Authorities Having Jurisdiction (AHJ s) have allowed interpretation of NEC 700.27 and 701.18 in terms of system coordination However, this is not guaranteed going forward With one exception, all proposals to date to change wording of, or remove, the selectivity requirements in the 2008 NEC have been rejected Slide 22

Issues with the 2005 NEC Requirements Another issue: Ground-Fault Protection Not addressed in NEC 700.27, 701.18 ~95% of all system faults are ground faults If ground-fault protection is not considered: Can cause practical lack of selectivity even though NEC 700.27 and 701.18 are complied with Slide 23

Issues with the 2005 NEC Requirements One scenario for a health-care facility: If utility service is 1000A and 150V < Service Voltage to Ground 600V, ground-fault protection, set to no more than 1200A pickup and no more than 1s time delay at 3000A, is required per NEC 230.95 NEC 517.17 (B) requires an additional level of ground-fault protection in healthcare facilities if service ground fault is provided per NEC 230.95 or NEC 215.10 For the service and additional level of ground-fault protection in this scenario to coordinate with the essential electrical system devices, additional levels of ground-fault protection would typically be required But NEC 517.17(B) prohibits additional levels of ground-fault protection on the load side of essential electrical system transfer switches All proposals to amend NEC 517.17(B) for the 2008 NEC have been rejected Slide 24

Issues with the 2005 NEC Requirements In other words, NEC 700.27 and 701.18 could be satisfied and the following scenario could still exist: With system supplied from normal source: A ground fault here Could force the normal source overcurrent protective device ground-fault protection to trip And force transfer to generators ATS will close into a ground fault! Slide 25

Issues with the 2005 NEC Requirements Why is selectivity in the NEC? NEC is a fire and electrical safety document, not a performance standard Why isn t this left to the discretion of the engineering community? NEC is not a design manual and following the requirements of the NEC, as they are currently written, will not, in and of itself, create a totally selectively-coordinated system. What about other systems that could take the normal source off-line, such as fire pumps in multi-building campus-style complexes? What about arc-flash hazards? Slide 26

Issues with the 2005 NEC Requirements What were they thinking? Requirements of 700.27 and 701.18 are generally well-intentioned intended to increase system reliability Unfortunately, they were written into the NEC in a way that was confusing. Only one manufacturer took a stand in the codemaking process against the impracticality of the requirements as written and received no backing Slide 27

Issues with the 2005 NEC Requirements What to do? Long-term actions: Submit proposals for change through the code-making process Short-term actions: Get with your local AHJ and be sure you understand his/her interpretation of NEC 700.27, 701.18 requirements Understand overcurrent protective device characteristics and how to best apply these devices to achieve selectivity Slide 28

Topics 2005 NEC Requirements What is selective coordination? Issues with the 2005 NEC Requirements Overcurrent Protective Device Characteristics Specific Guidelines for Achieving Selectivity Slide 29

Overcurrent Protective Device Characteristics Fuses Simplest overcurrent protective device Timing characteristics depend upon the design of the fuse Slide 30

Overcurrent Protective Device Characteristics 100 100 1K 1K CURRENT IN AMPERES 1000 1000 100 100 10 10 1 1 0.10 0.10 0.01 0.01 10K 10K 100K 100K TIM E IN SECONDS Fuse displays an extremely inverse time current characteristic Below 0.01 second: currentlimiting fuses are operating in their current limiting region simple TCC comparisons are not enough determine coordination Coordination below 0.01s requires a comparison between the minimum melting energy of the upstream fuse and the total clearing energy of the downstream fuse. Slide 31

Slide 32 Selective Coordination for Emergency/Legally-Required Standby Power Systems Overcurrent Protective Device Characteristics 100 100 10 1000 1000 FU 1 1K 1K 100 100 FU 2 10 10 UTILITY BUS 1 1 FU 1 FU 2 CURRENT IN AMPERES 0.10 0.10 0.01 0.01 10 8200A 10K 10K 100K 100K TIM E IN SECONDS For selective coordination by TCC comparison, these two fuses will coordinate until both TCCs go below 0.01A In this case, the maximum fault current level for coordination is 8200A Above 8200A, coordination must be determined by energy comparison (minimum melting energy of upstream fuse vs. total clearing energy of downstream fuse) => fuse ratio tables

Overcurrent Protective Device Characteristics Circuit Breakers Available in thermal-magnetic and electronic tripping types Timing characteristics depend upon type of circuit breaker Circuit Breaker Type 1 Standard Tripping Type Molded-Case UL 489 Low-Voltage Power ANSI C37.13 UL 1066 Thermalmagnetic Electronic Electronic (insulated case) 3 Electronic Short-time Withstand Capability 2 Typically much lower than interrupting rating Typically lower than interrupting rating Often comparable to interrupting rating Typically comparable to interrupting rating 1. Other circuit breaker types, such as molded-case circuit breakers with instantaneous-only trip units, are available for specific applications, such as shortcircuit protection of motor circuits 2. Short-time current is defined by ANSI C37.13 as the designated limit of available (prospective) current at which the circuit breaker is required to perform a duty cycle consisting of two 0.5s periods of current flow separated by a 15s interval of zero current. For UL 489-rated circuit breakers short-time withstand is not defined and the duty cycle may vary. 3. Insulated-case circuit breakers exceed the UL 489 standard. The term insulated case is not a UL term. Slide 33

Overcurrent Protective Device Characteristics 100 100 CURRENT IN AMPERES 10 1000 1000 1K 1K 100 100 10 10 1 1 0.10 0.10 0.01 0.01 10 10K 10K 100K 100K TIM E IN SECONDS Thermal-magnetic circuit breaker TCC is similar to fuse TCC, except for instantaneous current levels This particular example is not a current-limiting circuit breaker Maximum Instantaneous clearing time Slide 34

Overcurrent Protective Device Characteristics Circuit Breakers The available range of instantaneous pickups on any circuit breaker is always a function of the short-time withstand capabilities of the circuit breaker A published short-time withstand capability is not required for molded-case circuit breakers per UL 489 (nor is the withstand time standardized), yet the capability still exists The withstand capability will manifest itself in the TCC for the circuit breaker, typically the allowable range of instantaneous pickup settings Slide 35

Overcurrent Protective Device Characteristics 100 100 CURRENT IN AMPERES 10 1000 1000 1K 1K 100 100 10 10 1 1 Short-Time Delay 0.10 0.10 Instantaneous Pickup 0.01 0.01 10 10K 10K Long-Time Pickup Selective Override = 21.6kA 100K 100K Long-Time Delay Short-Time Pickup TIME IN SECONDS 0.02s Some electronic-trip circuit breakers have a minimum tripping time above 0.01s associated with the instantaneous function This time delay helps to coordinate with downstream circuit breakers However, there is typically also a selective instantaneous override, above which the instantaneous characteristic is always enabled and has a faster operating time than the standard instantaneous characteristic Slide 36 Current Scale X 10^0 Reference Voltage: 480

Overcurrent Protective Device Characteristics 100 100 CURRENT IN AMPERES 10 1000 1000 1K 1K 100 100 10 10 1 1 Short-Time Delay 0.10 0.10 0.01 0.01 10 10K 10K Long-Time Pickup Selective Override = 21.6kA 100K 100K Long-Time Delay Short-Time Pickup TIME IN SECONDS If the instantaneous function is turned off, the instantaneous selective override remains Its purpose is to protect the circuit breaker when the instantaneous function is turned off The selective override level depends upon the circuit breaker design Slide 37 Current Scale X 10^0 Reference Voltage: 480

Slide 38 Selective Coordination for Emergency/Legally-Required Standby Power Systems Overcurrent Protective Device Characteristics 100 100 10 1000 1000 1K 1K 100 100 125A CURRENT IN AMPERES 10 10 1 1 0.10 0.10 0.01 0.01 10 2600A Current Scale X 10^0 Reference Voltage: 480 10K 10K 400A 100K 100K TIME IN SECONDS Two thermal-magnetic circuit breakers coordinate up to the instantaneous pickup level of the upstream circuit breaker In this case, that level is 2600A

Slide 39 Selective Coordination for Emergency/Legally-Required Standby Power Systems Overcurrent Protective Device Characteristics 100 100 10 1000 1000 1K 1K 100 100 125A CURRENT IN AMPERES 10 10 1 1 0.10 0.10 0.01 0.01 10 2600A Current Scale X 10^0 Reference Voltage: 480 10K 10K 400A 100K 100K TIME IN SECONDS Replace the 125A circuit breaker with fuses, and the coordination level is the same: 2600A

Slide 40 Selective Coordination for Emergency/Legally-Required Standby Power Systems Overcurrent Protective Device Characteristics 100 100 10 1000 1000 1K 1K 100 100 125A CURRENT IN AMPERES 10 10 1 1 0.10 0.10 0.01 0.01 10 5200A Current Scale X 10^0 Reference Voltage: 480 10K 10K 400A 100K 100K TIME IN SECONDS Replace the 125A circuit breaker with fuses, and the coordination level per the TCC is 5200A still a low level Selectivity ratio tables are required above 5200A

Slide 41 Selective Coordination for Emergency/Legally-Required Standby Power Systems Overcurrent Protective Device Characteristics 100 100 CURRENT IN AMPERES 10 1000 1000 1K 1K 100 100 10 10 1 1 0.10 0.10 0.01 0.01 10 Current Scale X 10^0 Reference Voltage: 480 10K 10K 21.6kA 100K 100K TIME IN SECONDS Coordination between an electronic-trip circuit breaker with.02s-delayed instantaneous characteristic is even better up to the selective override level of the circuit breaker In this case, that level is 21.6kA

Overcurrent Protective Device Characteristics In the past, the major differentiator between circuit breaker and fuse coordination was the existence of fuse ratio tables These allow comparison at fault currents that cannot be evaluated via TCC comparison If a given ratio is kept between two fuses of given types, they will always selectively coordinate This is based upon comparison between the minimum melting energy of the upstream fuses vs. the total clearing energy of the downstream fuses Slide 42

Overcurrent Protective Device Characteristics Circuit breakers also exhibit characteristics which cause the TCC results for coordination to be inaccurate Current-limiting effects: Even circuit breakers which are not UL listed as current-limiting can exhibit these effects for high fault currents Dynamic impedance effects: The downstream circuit breaker exhibits a dynamic impedance when it begins to interrupt, which effectively lowers the current seen by the upstream breaker These characteristics cause the TCC results to be overly conservative regarding selective coordination for higher fault currents Slide 43

Overcurrent Protective Device Characteristics One circuit breaker manufacturer has utilized these characteristics to produce short circuit selectivity tables for their circuit breakers These tables are based upon tested values and certified by the manufacturer These tables, in many cases, show coordination in the instantaneous region even where the CB TCCs overlap Slide 44

Overcurrent Protective Device Characteristics 100 100 10 1000 1000 CB M1 CURRENT IN AMPERES 1K 1K 100 100 CB F1 CB PM1 10 10 CB B1 1 1 0.10 0.10 0.01 0.01 10 10K 10K 21.6kA 100K 100K 25kA TIM E IN SECONDS In this example, CB F1 and CB PM1 coordinate up to 21.6kA per the TCC But, per the selectivity tables they coordinate up to the available fault current of 25kA at CB PM1 Slide 45

Overcurrent Protective Device Characteristics The existence of short-circuit selectivity tables makes the application of circuit breakers and fuses very similar In some cases, it actually gives an advantage to circuit breakers from a selectivity standpoint TCC comparisons are still required, however, to insure coordination down to 0.1s. However, TCC comparisons are required to insure adequate equipment protection in any case, with fuses or circuit breakers. Slide 46

Topics 2005 NEC Requirements What is selective coordination? Issues with the 2005 NEC Requirements Overcurrent Protective Device Characteristics Specific Guidelines for Achieving Selectivity Slide 47

Specific Techniques for Achieving Selectivity Recognize that fuses and circuit breakers can both be used to achieve total selective coordination CBs give performance advantages over fuses in other areas beyond selective coordination these will not be elaborated upon here, but be aware that the advantages do exist Slide 48

Specific Techniques for Achieving Selectivity Recognize that ~ 95% of system faults are ground-faults Defeats the purpose of the NEC 700.27 and 701.18 requirements in health-care facilities in light of NEC 517.17(B) unless a specific waiver for 517.17(B) from the AHJ can be obtained For other types of facilities: Give due consideration to ground-fault protection Slide 49

Specific Techniques for Achieving Selectivity Recognize that true short-circuit conditions are most likely to occur during commissioning of a new system, rather than during normal operation Due to nicks in cable insulation during cable pulling and errors in equipment installation Makes an argument against the requirement for total selective coordination if the AHJ is receptive Can certainly be the subject of proposals to change future editions of the NEC to modify selectivity requirements Slide 50

Specific Techniques for Achieving Selectivity Recognize that a time-current coordination study is required for successful system protection and coordination Claims to the contrary, regardless of the source simply not true! Implementation is very similar for both fuses and circuit breakers Consider selective coordination early in the design process Slide 51

Specific Techniques for Achieving Selectivity Understand the difference between system selectivity and device-to-device selectivity NEC requirements for selectivity are in conflict in this matter, and with the requirements of NFPA 110 Only system selectivity makes a practical difference in system reliability Where AHJ will accept system selectivity, so much the better Slide 52

Specific Techniques for Achieving Selectivity Typical examples G ENGINE-GENERATOR SET CB 1 PANEL 1 PRIMARY CB CB 1 PANEL 2 CB 2 TRANSFORMER SWITCHBOARD SECONDARY CB CB 1 a.) b.) Slide 53

Specific Techniques for Achieving Selectivity Examples re-designed to eliminate series devices, if necessary: ENGINE-GENERATOR SET PANEL 1 Be careful in this situation: Some AHJ s may not allow due to interpretation of NEC 445.18 G CB 1 SWITCHBOARD CB 1 PANEL 2 a.) b.) Slide 54

Specific Techniques for Achieving Selectivity Recognize the pitfalls of generator protection Selective coordination often is difficult or impossible while maintaining adequate generator protection Trade-offs often must be made Be wary of circuit breakers supplied with engine-generator sets these may need to be LS w/electronic trip and high withstand (possibly ANSI LV power circuit breakers) Care must be taken with protective functions built into generator controllers as well Slide 55

Specific Techniques for Achieving Selectivity Typical application with paralleled generators: G G TO NORMAL SOURCE CB 1 CB 2 CB 3 CB 4 CB 5 AUTOXFER SW E N E N AUTOXFER E N AUTOXFER SW SW Slide 56

Specific Techniques for Achieving Selectivity Typical primary protective zones if CB1 and CB2 provide both generator overload and short-circuit protection: G G TO NORMAL SOURCE CB 1 PROTECTIVE ZONE CB 1 CB 2 CB 2 PROTECTIVE ZONE Zones overlap Selectivity issues CB 3 PROTECTIVE ZONE AUTOXFER SW CB 3 CB 4 CB 5 E N E N AUTOXFER E N AUTOXFER SW SW CB 6 CB 6 PROTECTIVE ZONE Slide 57

Specific Techniques for Achieving Selectivity One solution: More, smaller generators w/o paralleling CB 1 PROTECTIVE ZONE G CB 1 G G TO NORMAL SOURCE Expensive! AUTOXFER SW E N E N AUTOXFER E N AUTOXFER SW SW Reliability issues CB 6 CB 6 PROTECTIVE ZONE Not always practical Slide 58

Specific Techniques for Achieving Selectivity Better solution: Allow paralleling swgr feeders to provide short-circuit protection, supplemented by bus-differential protection for the generator paralleling bus Not a cure-all but does often help Slide 59

Specific Techniques for Achieving Selectivity Bus differential protection provides short-circuit protection for generators for faults on generator paralleling bus 87B PROTECTIVE ZONE CB 1 PROTECTIVE ZONE CB 3 G CB 1 CB 4 G CB 2 CB 2 PROTECTIVE ZONE CB 5 TO NORMAL SOURCE CB1 and CB2 set to provide overload, but not short-circuit, protection for generators. These settings allow coordination with CBs on the level of CB3. CB 3 PROTECTIVE ZONE AUTOXFER SW E N E N AUTOXFER E N AUTOXFER SW SW CB s on CB3 level provide short-circuit protection for generators CB 6 CB 6 PROTECTIVE ZONE Slide 60

Specific Techniques for Achieving Selectivity When using circuit breakers: Specify circuit breakers with high withstand capabilities Not always published for UL 489 molded-case circuit breakers but will be borne out in TCCs Consider ANSI power circuit breakers at higher levels in the system, such as the service and generator paralleling switchgear Slide 61

Specific Techniques for Achieving Selectivity Utilize step-down transformers to lower fault current If loads can be converted from 480Y/277V to 208Y/120V Method of last resort in some cases Slide 62

Specific Techniques for Achieving Selectivity Increase circuit breaker frame size May require larger feeder size but larger frame sizes are more likely to be able to coordinate Slide 63

Specific Techniques for Achieving Selectivity Utilize the tools at your disposal Circuit breaker short-circuit selectivity tables Local mfr. technical support they can work with you to achieve selectivity for a given system design Slide 64

Specific Techniques for Achieving Selectivity For particularly difficult low-voltage transformer protection/selectivity problems, increase transformer size 30kVA to 45kVA, 45kVA to 75kVA, etc. Allows larger size overcurrent protective devices, which are more likely to coordinate Slide 65

Specific Techniques for Achieving Selectivity Zone-Selective Interlocking (ZSI) know the facts vs. the myths Available only between electronic-trip circuit breakers Used to decrease fault energy (and arc flash hazard) by allowing faults between two circuit breakers to be cleared in the minimum time But, ZSI cannot be used to force selectivity: In fact, selectivity must exist before ZSI can be implemented Slide 66

Specific Techniques for Achieving Selectivity Don t forget on-site adjustment requirements when circuit breakers are used Most manufacturers set circuit breakers at minimum settings except for long-time trip adjustments, if applicable Must be based upon time-current coordination study Slide 67

Summary 2005 NEC Selectivity Requirements 700.27 requires emergency systems to be selectively coordinated 701.18 requires legally required standby systems to be selectively coordinated 700.27 and 701.18 imply "device-to-device" coordination, whereas the definition in Article 100 implies system coordination Slide 68

Summary Issues With 2005 NEC Selectivity Requirements Don't always make sense Don't necessarily belong in the NEC Conflicts are present Requirements in conflict with NFPA 110 Slide 69

Summary Overcurrent Protective Device Characteristics Simple TCC comparisons are not always enough to judge selectivity Fuses ratio tables are required to judge selectivity between two fuses operating in current-limiting range Circuit breakers short-circuit selectivity tables may be used to judge selectivity between circuit breakers in instantaneous region may be better than shown on TCC Slide 70

Summary Specific Guidelines for Achieving Selectivity A coordination study is always required, regardless of the protective device type used True short-circuits are rare, ground-faults are common Best approach is system rather than device-to-device selectivity Slide 71

Summary Specific Guidelines for Achieving Selectivity (cont d) Recognize the pitfalls of generator protection Specify circuit breakers with high withstand capabilities Use step-down transformers to lower fault current Use larger circuit breaker frame sizes Increase transformer sizes Slide 72

Summary Specific Guidelines for Achieving Selectivity (cont d) Know the realities vs. the myths regarding ZSI Don t forget on-site adjustment requirements Long-Term Change the NEC to put this issue back into the hands of the engineering community Both fuses and circuit breakers may be used to achieve selective coordination! Slide 73

Contact Information Ed Larsen Square D Codes and Standards Group 3700 Sixth Street, Southwest Cedar Rapids, Iowa Phone 319-369-6422 Fax 319-369-6600 E-mail: ed.larsen@us.schneider-electric.com Slide 74

Contact Information Bill Brown, P.E. Square D Power Systems Engineering 1010 Airpark Center Drive Nashville, TN 37217 Phone 615-844-8767 Fax 859-817-4965 E-mail: bill.brown@us.schneider-electric.com Slide 75

Selective Coordination for Emergency and Legally-Required Standby Power Distribution Systems Presented for the IEEE Central TN Section / Music City Power Quality Group August 1, 2006 By Ed Larsen and Bill Brown, P.E. Square D / Schneider Electric Codes and Standards / Power Systems Engineering