.CCOM. Preliminary Hydrogeological Investigation. February 7, 2013

Similar documents
Dependence of Predicted Dewatering on Size of Hydraulic Stress Used for Groundwater Model Calibration

Appendix N. Preliminary Noise Assessment Technical Memorandum

GENERAL DEVELOPMENT APPLICATIONS. General Submission Requirements

Module 6 : Design of Retaining Structures. Lecture 30 : Dewatering [ Section 30.1 : Introduction ]

Diagnosis of Operating Mine Dewatering Wells Efficiency through Groundwater Modelling

Dewatering. Deep Wells Vacuum Wellpoints Eductor Wells Artesian Conditions System Design Water Treatment.

MATRIX SOLUTIONS INC. NOTICE OF ANNUAL MEETING OF THE SHAREHOLDERS AGENDA

Richard Martin Groundwater LLC

SECTION DEWATERING PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Dewatering observation wells are part of dewatering allowance.

Practices and Challenges. For Open Pit Geotechnical Characterization, Design and Execution

STANDARD OPERATING PROCEDURE FOR DEWATERING (Revision 3, Effective December 1, 2009)

GEOLOGICAL INVESTIGATIONS

INFORMATION SHEET. : Properties Subject to the Slope and Seismic Hazard Zone Protection Act (SSPA) Ordinance

In response to a request from Water Rights Branch, a short. In general, the sequence of post glacial events in the immediate. D. M.

SECTION DEWATERING TANKAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS

Notice of Advice. RevA: 18-September-2017 RevB: 26-September Engineering Assessment of Aurizon network's Capital Claim

Wellhead Protection Zone Delineation

STATEMENT OF QUALIFICATIONS for DECISION ANALYSIS & RISK ASSESSMENT (Multiple Accounts Analysis & Failure Modes and Effects Analysis)

Phase 2 Executive Summary: Pre-Project Review of AECL s Advanced CANDU Reactor ACR

STATEMENT OF WORK Environmental Assessment for the Red Cliffs/Long Valley Land Exchange in Washington County, Utah

B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422

Reference: Mt. Polley Mine Tailings Facility Optimization Potential Follow Up from Dam Safety Review

Draft Guidance Statement on Mine Dewatering

For personal use only

II. GENERAL GROUNDWATER DEWATERING REQUIREMENTS

City of Markham Bird Friendly Guidelines (October 2013 Draft)

CONVEYANCE PIPELINE AND PUMP STATION

GEO-SLOPE International Ltd, Calgary, Alberta, Canada Relief Well Spacing

9/17/90 (rev.) STATE OF MINNESOTA HINNESOTA DEPARTMENT OF HEALTH

Discussion Paper on the EBA s approach to financial technology (FinTech) Public hearing, 4 October 2017

DEPARTMENT OF THE AIR FORCE. SUBJECT: Excavation Dewatering at Eielson Air Force Base, Alaska

An alternative approach to managing dewatering in an open pit mine Keith Brown, Shane Trott and Aadil Nabi

Consolidation of Navigation Safety Regulations IMO - NCSR / MSC Updates

Thurston County Permitting System Policies &Procedures Page: 1 of 3

GCG ASSOCIATES, INC. February 8, Mr. Nathaniel Strosberg, Town Planner 101 Main Street Town of Ashland Ashland, MA 01721

Conceptual, Preliminary and Final Site Plan Review in Holladay City

FEE Comments on EFRAG Draft Comment Letter on ESMA Consultation Paper Considerations of materiality in financial reporting

MPD Application Process

Questions and Answers

Memorandum. Dear Ms. Allen,

Colossus Minerals Development Remains On Schedule for Initial Production In Second Half of 2013

DATE: May 16, C.agd

Tabriz Urban Railway Organization. An Introduction to Tabriz Metro Line 3 Project

SITE PLAN Application Packet (Required For All Non-Residential Development Projects)

Reservoir Management

Documents: Response letter and attachments, Prepared by: AMEC Massachusetts, Inc., Dated February 17, 2016.

September 2017 PGM:TSX-V

Section Meetings Section Material and Equipment. None Required

For personal use only

PREPARATION GUIDELINES FOR UDFCD MAINTENANCE SITE PLAN

Optimum Design of Nailed Soil Wall

Manually verifiable area calculations; and BC Land Surveyor certified area calculations (typically practical only for large development proposals).

1 MUNICIPAL INFRASTRUCTURE

QUALITY: BRACKETING AND MATRIXING DESIGNS FOR STABILITY TESTING OF NEW VETERINARY DRUG SUBSTANCES AND MEDICINAL PRODUCTS

HIGH GRADE INTERCEPTS FROM LISEIWI PROSPECT, BLOCK 14

RESOLUTION MEPC.290(71) (adopted on 7 July 2017) THE EXPERIENCE-BUILDING PHASE ASSOCIATED WITH THE BWM CONVENTION

August 25, 2017 VIA ELECTRONIC FILING

ASX s replacement of CHESS for equity post-trade services: Business Requirements September 2016

clarify the roles of the Department and minerals industry in consultation; and

TO Derek Holmes BURNCO Rock Products Ltd CC FROM Zhaohui Yu, Virgini Senden

April Developing Zinc, Gold & Silver Projects in Nevada and Ontario

ENVIRONMENTAL IMPACT ASSESSMENT

August 25, Please contact the undersigned if you have any questions concerning this filing.

COUNCIL OF EUROPE COMMITTEE OF MINISTERS. RECOMMENDATION No. R (89) 5 OF THE COMMITTEE OF MINISTERS TO MEMBER STATES

South West Public Engagement Protocol for Wind Energy

GEOTECHNICAL SERVICES

Subdivision Application Checklist

CITY OF BAYTOWN CENTRAL DISTRICT WASTEWATER TREATMENT PLANT GRIT, SECURITY, AND SCADA IMPROVEMENTS SCOPE OF SERVICES

January 8, Licensing Requirements for Implantable Medical Devices Manufactured by 3D Printing; Draft Guidance. Dear Sir or Madame:

Proposed International Standard on Auditing 315 (Revised) Identifying and Assessing the Risks of Material Misstatement

Page 1 of 5 Revision 1.0

2. As such, Proponents of Antenna Systems do not require permitting of any kind from the Town.

Introduction to the Revised Environmental Review Primer for Connecticut s Historic Properties

PROGRAMMING SCHEMATIC DESIGN DESIGN DEVELOPMENT CONSTRUCTION DOCUMENTS. room) Scalable bubble diagrams schedules describing programmatic

APPENDIX D: DRAWING SUBMISSION STANDARDS

APPLICATION FOR SITE PREPARATION PERMIT

RE: 13UN034 City of Iqaluit New Landfill and Waste Transfer Station NIRB Screening

Building Standards Department. Markham eplan Submission Standards For Building Permits, Sign Permits and Zoning Preliminary Review

July Developing Zinc, Gold & Silver Projects in Nevada and Ontario

Design guide to separating distances during construction

CRIRSCO and evolving international accounting standards: IFRSs

EXCALIBUR GROUP, LLC

Pasinex Announces Maiden High-Grade Zinc Resource in Turkey

RESIDENTIAL DEMOLITION PERMIT APPLICANT CHECKLIST

REP N Bank St. Rooftop Patio Noise Study. N45 Architecture Inc. 852 Bank Street Project Rooftop Patio Environmental Noise Study

Office for Nuclear Regulation

System Operating Limit Definition and Exceedance Clarification

Design Deliverables. Summary. A. Expectations for Design Deliverables:

Proposed Changes to the ASX Listing Rules How the Changes Will Affect New Listings and Disclosure for Mining and Oil & Gas Companies

(1) A computer program is not an invention and not a manner of manufacture for the purposes of this Act.

February 23, Re: EO & Well Control and Blowout Preventer Rule. Via Electronic Transmittal. Dear Mr. Whiteman:

ORCA GOLD S ROBUST INITIAL RESOURCE AND SUCCESSFUL EXPLORATION SUPPORT PRELIMINARY ECONOMIC ASSESSMENT AT BLOCK 14 NEW CFO APPOINTMENT

SITE STATISTICS SQ.FT [ SQ.M.]

June Phase 3 Executive Summary Pre-Project Design Review of Candu Energy Inc. Enhanced CANDU 6 Design

Abstract #1693. English. French. Author(s) and Co Author(s) Mining the Moon: A Step wise Approach. Details to follow. No abstract title in French

Clair Creek Meadows 30T Blocks 47, 48 & 49 Zone Change Functional Servicing and Stormwater Management Brief

Underground Storage Operation & Maintenance Services

Woodside Community Meeting Bird in Hand Project. 15 November 2006

EXPERT OPINION EVIDENCE IN CONSTRUCTION CASES. Andrew J. Heal, B.A. (Hons.), J.D., LL.M.* Blaney McMurtry LLP

Transcription:

.CCOM AECOM 300-300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax www.aecom.com February 7, 2013 Ms. lsa James Planner Town of W hitchurch-stouffville 111 Sandiford Drive Stouffville, ON L4A OZ8 Dear Ms. James: Project No: 60272713 Regarding: Peer Review Preliminary Hydrogeological Investigation, Regulatory Requests, Site Plan Approval Comment Responses, and Response to Preliminary Geotechnical Investigation, 6233, 6441 & 6245 Main Street, Stouffville, Ontario, SPA 12.004 We are pleased to provide our peer review of the following reports: Technical Memorandum Preliminary Hydrogeological Investigation, Proposed Pace Redevelopment- Lloyd Street and Main Street, Stouffville, Ontario, prepared by Golder Associates Ltd., January 17, 2013; Response to comments on Lloyd Street- Pace Savings and Credit Union Limited, Site Plan Approval- 2nd Submission, 181 Project No. W06028.01 00 F2182, prepared by SCS Consulting Group Ltd., January 17, 2013; Response to Peer Review Comments of Preliminary Geotechnical Investigation Site Plan Application Pace Redevelopment, Stouffville, Ontario, prepared by Golder Associates Ltd., August 24, 2012; and Regulatory Requests for 6233, 6441 & 6245 Main Street, Stouffville, Ontario, prepared by Golder Associates Ltd., January 18, 2013. The means and methods of the site investigation and the corresponding data reduction were not reviewed. AECOM did not perform independent site investigations or testing. Preliminary Hydrogeological Investigation AECOM provides the following peer review of the Golder Associates Ltd. (Golder) Preliminary Hydrogeological Investigation Proposed Pace Redevelopment- Lloyd Street and Main Street, Stouffville, Ontario, prepared for Geranium Corporation, dated January 17, 2013. L_2013-02-07_Peer Review_60272713_T3. 0oc

Page 2 A.:COM February 7, 2013 It is understood that the proposed development will consist of a six storey building with two levels of underground parking for mixed commercial/residential use. The site is located at the southeast corner of Main Street and Lloyd Street in the Town of Stouffville. The objective of this exercise is to review the hydrogeological investigation prepared by Golder to verify the methods/calculations/recommendations adopted are in conformance with generally accepted hydrogeological standards and practice. It is our overall assessment that the report has adopted hydrogeological methodologies and approaches that follow the principles of generally accepted practice. Notwithstanding this, we have a few comments for your consideration as outlined below: 1. The number of groundwater monitoring wells (6), standpipe piezometers (2), and monitoring well nest (1 shallow well and 1 deep well) are considered to be sufficient to provide reasonable characterization of the hydrogeological conditions at the site. 2. The type of hydraulic testing conducted (i.e., single well response tests and a short term pumping test), as well as the duration of these tests (i.e., 4-hour pumping test) are considered to be sufficient to provide reasonable estimates of the hydraulic properties of the soils for the purposes of providing preliminary dewatering rate estimates. 3. The report would greatly benefit from the addition of a hydrostratigraphic crosssection, as well, but to a lesser extent, a potentiometric surface map showing groundwater flow direction and a figure showing the radius of water level drawdown related to the pumping test. 4. Inconsistencies in rounding or not rounding of calculated results were identified throughout the memorandum, but they do not affect the overall interpretation, results or conclusions presented. 5. Section 1.2 - Scope of Work a) We support the installation of three additional groundwater monitoring wells outside of the initial geotechnical drilling program for the specific purpose of hydraulic testing. 6. Section 2.1 - Estimates of Hydraulic Conductivity b) Measured and calculated hydraulic conductivity values seem reasonable for the soils present at the site. c) In our opinion, the Aquifer Anisotropy Ratio (Kz/Kr) used for single well response test analysis (Attachment B) should be 0.5 or less for the glacially deposited (glaciofluvial and/ or glaciolacustrine) fine and coarse-grained soils. However, this difference does not affect the overall interpretation, results or conclusions presented. 7. Section 2.2- Estimate of Transmissivity d) The transmissivity and corresponding hydraulic conductivity value presented for the coarse-grained soils seem reasonable for soils present at the site. The approach to calculate these values is consistent with standard hydrogeological practices. L_20 13 02~ 07_Peer Revlew_60272713_ T3.Coc

Page 3 A:'COM February 7, 2013 8. Section 3.0- Summary of Hydrogeological Conditions e) It is agreed that the interpreted vertical hydraulic gradient at the site is downwards, however it is important to note that a small upwards hydraulic gradient was observed between the shallow and deep wells at BH12-2 during the September 12, 2012 monitoring event. 9. Section 4.1 -Assumed Construction Dewatering Program f) The assumptions made regarding the potential method, depth and extent of dewatering are reasonable given the anticipated groundwater conditions and construction design. g) Based on the table in Section 4.1 it is unclear how the till soils above the silty sand to sand unit will be dewatered or if Golder simply considers the contribution from these soils to be negligible to the overall dewatering rate estimate due to their low hydraulic conductivity. 10. Section 4.2- Dewatering Zone of Influence h) The dewatering zone of influence presented for the silty sand to sand unit and the shallow zone, mainly fine-grained soils seem reasonable for type of soils present at the site. The approaches to calculate these values are consistent with standard hydrogeological practices and approximately match the pumping test results. 11. Section 4.3- Dewatering Rate Estimates i) The steady state groundwater flow rate estimates presented for depressurization of the confined silty sand to sand aquifer unit and the shallow fine grained soils seem reasonable given the hydrogeological conditions and proposed construction at the site. The approach to calculate these values is consistent with standard hydrogeological practices. j) The volume of overburden storage seems underestimated; particularly if the volume of water stored in the dewatering zone of influence is also taken into account (this condition seems likely given the assumption of non-watertight vertical soil support for the excavation -Section 4.1 ). k) We assume the total requested construction dewatering rate of 200m 3 /day is based on experience given the estimated rates for steady-stage flow, direct rainfall inputs and removal of overburden storage. I) It is agreed that a Category 3 PTTW submission is appropriate given the expected rate and duration of construction dewatering. A factor of safety or contingency dewatering rate higher than that predicted may be useful during formal PTTW submission to provide flexibility during construction. m) In our experience, the MOE generally does not issue PTTWs for passive water takings such as a sub-slab drainage system. However, this is considered on a case-by-case basis and should form part of the consultation with the MOE prior to PTTW submittal. 12. No guidance related to groundwater monitoring, mitigation, dewatering discharge, or contingency actions were provided in the Report. L_2013 02-07 _Peer Review_60272713_T3.0oc

Page 4.CCOM February 7, 2013 Response to Comments on Site Plan Approval AECOM has reviewed comment/response number P1.16 of the Response to comments on Lloyd Street- Pace Savings and Credit Union Limited, Site Plan Approval- 2"d Submission, 181 Project No. W06028.0100 F2182, prepared by SCS Consulting Group Ltd. (SCS), January 17,2013, and have the following comments: Construction dewatering will require a Category 3 PTTW, not a Category 1 PTTW as indicated in the response by SCS; The recommended construction dewatering flow rate was estimated by Golder to be 2.3 Lis or 200m 3 /day. The 1.7 Lis or about 150 m 3 /day, as indicated by SCS, refers to the volume of dewatering required to remove water from overburden storage; and The long term dewatering flow rate of 0.7 5 Lis or 65m 3 /day, is consistent with the steady-state dewatering flow rate estimated by Golder. No other comment/responses in the letter provided by SCS were reviewed by AECOM. Golder Peer Review Responses AECOM previously provided peer review comments on the Phase I Environmental Site Assessment 1 (AECOM letter dated July 16, 2012) and the Preliminary Geotechnicallnvestigation 2 (AECOM letter dated July 26, 2012). We reviewed our July 2012 comments with respect to the responses provided by Golders and have presented our responses below. Regulatory Requests -Phase I ESA Our July 2012 peer review of the Phase I ESA presented the following: Golders concluded that no issues of environmental concern were identified in association with the site. AECOM generally agrees though we recommend the following: follow-up should be conducted with the MOE, the Region and the Town to ensure that no potential environmental concerns were identified; and Any deleterious debris found on the site during demolition must be removed and disposed of properly. The January 18, 2013 Regulatory Request letter states that as of January 18, 2013, no response has been received from the MOE, the Town or the Region. When a response is received, Golder will forward them to the proponent with comments if the results alter the findings of the June 2012 Phase I ESA. AECOM is satisfied with this response. 1. Phase I Environmental Site Assessment, 6233, 6237, 6241 and 6245 Main Street, Stouffville, Ontario, dated June 2012 2. Preliminary Geotechnical Investigation, Site Plan Application Redevelopment Stouffville, Ontario, dated June 7, 2012 1.._2013 02-07 _Peer Revlew_60272713_T3.Doc

Page 5 A:'COM February 7, 2013 Preliminary Geotechnical Investigation Our July 2012 peer review of the Preliminary Geotechnical Investigation presented several items for clarification/additional comment. The responses provided by Golder in their August 24, 2012 letter have addressed these items to AECOM's satisfaction. Should you have any questions, please do not hesitate to contact the undersigned. Sincerely, AECOM Canada Ltd. Jason Cole, M.Sc., P.Geo. Hydrogeologist Jason. Cole@aecom. com Rob Frizzell, M.Sc., P.Geo. Senior Hydrogeologist Rob.Frizze/l@aecom. com Patty Wong, B.Sc., P.Geo Senior Geologist Patty. Wong@aecom.com L_2013 02 07_Peer Review_6027271 3_TJ_Ooc