Embedded Generation Connection Application Form

Similar documents
Embedded Generation Connection Application Form

Embedded Generation Connection Application Form

Impact Assessment Generator Form

Connection Impact Assessment Application Form

Connection Impact Assessment Application

Form B. Connection Impact Assessment Application Form Distribution System

Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

Owner/Customer Name: Mailing Address: City: County: State: Zip Code: Phone Number: Representative: Address: Fax Number:

APPLICATION FOR INTERCONNECTION & OPERATIONS OF MEMBER-OWNED GENERATION

GENERATOR INTERCONNECTION APPLICATION Category 3 For All Projects with Aggregate Generator Output of More Than 150 kw but Less Than or Equal to 550 kw

SOUTH CENTRAL INDIANA REMC Application for Operation of Member-Owned Small Power Generation Systems

Table of Contents. Introduction... 1

PART 1 OWNER/APPLICANT INFORMATION

EASTERN ILLINI ELECTRIC COOPERATIVE Application for Operation of Member-Owned Generation

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW

QUESTIONNAIRE for Wind Farm Power Stations only

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 150 KW BUT LESS THAN OR EQUAL TO 550 KW

Generation Interconnection Study Data Sheet Synchronous Machines

Distributed Generation Application Form (Generation of Greater than 20 kw to 15 MW)

Southern Company Interconnection Requirements for Inverter-Based Generation

ENGINEERING DATA SUBMITTAL For the Interconnection of Generation System

Initial Application Form for Connection of Distributed Generation (>10kW)

INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %

E N G I N E E R I N G M A N U A L

APPENDIX 1 to LGIP INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY

APPENDIX B: Generation Interconnection Application Form

State of North Dakota Engineering data submittal Page 1 For interconnection of distributed generation to Otter Tail Power Company

Transmission Interconnection Requirements for Inverter-Based Generation

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS

R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours

Target Mchunu and Themba Khoza Eskom Transmission Division, System Operator Grid Code Management

Settlements & Revenue Metering SLD Requirements INTERCONNECTIONS AT VOLTAGES 50KV

Capstone Turbine Corporation Nordhoff Street Chatsworth CA USA Phone: (818) Fax: (818) Web:

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

Effects of Harmonic Distortion I

Cork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours)

Level 6 Graduate Diploma in Engineering Electrical Energy Systems

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

Wind Power Facility Technical Requirements CHANGE HISTORY

CONTENTS. 1. Introduction Generating Stations 9 40

Revision Control. 0 18/07/2012 Initial Document Creation. STAKEHOLDERS The following positions shall be consulted if an update or review is required:

Generation and Load Interconnection Standard

TABLE OF CONTENT

Functional Specification Revision History

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

Phase-phase/phase-neutral: 24/13.8 kv star, 13.8 kv delta, 12/6.9 kv star.

Customer Standard. Standard for Embedded Generation (5MW and above)

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

Sizing Generators for Leading Power Factor

Generation Interconnection Requirements at Voltages 34.5 kv and Below

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

Shortcomings of the Low impedance Restricted Earth Fault function as applied to an Auto Transformer. Anura Perera, Paul Keller

Technical Requirements For Generation Connected to The ODEC System

POWER QUALITY IMPACTS AND MITIGATION OF DISTRIBUTED SOLAR POWER

Generation and Load Interconnection Standard

TECHNICAL GUIDELINE FOR THE INTERCONNECTION OF DISTRIBUTED ENERGY RESOURCES TO EPCOR DISTRIBUTION AND TRANSMISSION INC. S DISTRIBUTION SYSTEM

ATTACHMENT - AESO FUNCTIONAL SPECIFICATION

1

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

Problems connected with Commissioning of Power Transformers

MV ELECTRICAL TRANSMISSION DESIGN AND CONSTRUCTION STANDARD. PART 1: GENERAL 1.01 Transformer

Adaptive Relaying of Radial Distribution system with Distributed Generation

MV network design & devices selection EXERCISE BOOK

Section G2: PROTECTION AND CONTROL REQUIREMENTS FOR TRANSMISSION GENERATION ENTITIES

SYNCHRONOUS MACHINES

Facility Interconnection Requirements for Colorado Springs Utilities Version 03 TABLE OF CONTENTS

ESB National Grid Transmission Planning Criteria

BED INTERCONNECTION TECHNICAL REQUIREMENTS

GUIDE FOR GENERATOR INTERCONNECTION THE WIRES OWNER DISTRIBUTION SYSTEM

Electrical Description

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network

Version 2.6 October Comments to this document can be forwarded to:

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

ECET Modern Power

Connection of Embedded Generating Plant up to 5MW

ARC FLASH HAZARD ANALYSIS AND MITIGATION

Code No: R Set No. 1

Grid Code 2015 for Small Scale Distributed Generation (SSDG) Net Metering Scheme Version June 2017 Central Electricity Board

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF LARGE GENERATION FACILITIES. Document 9020

The Connecticut Light and Power Company

Simulations of open phase conditions on the high voltage side of YNd05-power plant transformers

ELECTRICAL POWER ENGINEERING

Conventional Paper-II-2011 Part-1A

IEEE sion/1547revision_index.html

Safety through proper system Grounding and Ground Fault Protection

Fault Ride Through Technical Assessment Report Template

DRAFT. City of Lethbridge Electric ENGINEERING STANDARDS GUIDELINE FOR GENERATOR INTERCONNECTION THE CITY OF LETHBRIDGE ELECTRIC DISTRIBUTION SYSTEM

Functional Specification Revision History

AGN 165 Parallel Operation with Mains Grid Systems

Grid Code. for Small Scale Distributed Generation (SSDG) Central Electricity Board. Wind turbine. PV module

Transcription:

Embedded Generation Connection Application Form This Application Form provides information required for an initial assessment of the Embedded Generation project. All applicable sections must be completed and all the required documents must be submitted with this form 1. Application Type: * For proper processing, please ensure application is typewritten. Program Feed-in- Tariff (FIT) Net Metering Other OPA FIT Reference Number: OPA FIT Project ID Number: OPA Contract Date: Specify: 2. Contact Information: Company/ Person Address Street City Postal Code Contact Name Telephone Cell E-mail Fax Toronto Hydro Service Location site of project Embedded Generation System Owner owner of project Engineering Consultant - (Electrical/Developer) 3. Billing Contact: Toronto Hydro Customer EG System Owner Engineering Consultant Other (please specify): Embedded Generation Connection Application Form - April 16, 2013 Page 1 of 10

4. Project Description: Dates: Account: Proposed Start of Construction: (dd/mm/yyyy) Proposed In-Service: (dd/mm/yyyy) GST/HST Number: Toronto Hydro Account Number: Type: Fuel Type: Synchronous Induction Inverter Other, please specify: Solar Photovoltaic Renewable Biomass Wind Bio-gas Co-generation/CHP Other, please specify: Manufacturer Model Number Generator: Power Factor (p.u) [A]: Number of Units: [B]: Rating of Each Unit: kw kva Proposed Total Capacity: = [A] [B] kw kva Proposed Total Capacity, Future: kw kva Number of Phases: one three Output voltage (V): Connection Configuration delta star Mode of Operation: Yes, existing load kw Load Displacement? new load kw No Power Export? Yes No kw Peak Period Only? Yes No kw Please be advised that the nameplate capacity for Solar PV systems is determined by taking the lesser of. i. The sum of the manufacturer's capacity ratings (in kw) for normal operation (e.g., continuous output ratings) of the installed solar modules (i.e. panels) of the Facility; or, ii. The sum of the manufacturer's capacity ratings (in kw) for normal operation (e.g., continuous output ratings) of the installed inverters of the Facility. Embedded Generation Connection Application Form - April 16, 2013 Page 2 of 10

5. Single Line Diagram (SLD) - stamped and signed by a Professional Engineer Provide an updated SLD of the Generating Facility, signed by a Professional Engineer, which includes the Interface Point/Point of Common Coupling ( PCC ) to Toronto Hydro s distribution system. The SLD shall contain details on the following: Electrical equipment at the embedded generation facility, principal ratings, impedances, winding configurations, neutral grounding methods, etc. Protective relaying, synchronizing and revenue metering arrangements. The device numbers should be in accordance with IEEE Standard Electrical Power System Device Function Numbers (ANSI/IEEE C37.2). Only dual winding transformers are acceptable for connection to the Toronto Hydro system. Provide the details at the connection point. Toronto Hydro Transformer Station, Toronto Hydro Feeder ID, Transformer Location number and ratings Note: If the project includes upgrades to existing Embedded Generation facilities, show the existing and new electrical equipment. SLD Drawing Number: Rev.: Single Line Diagram Checklist Item Description Toronto Hydro Transformer Station, Feeder ID, Transformer Location number and ratings (obtained from Pre-Assessment) Disconnecting device at the interface (PCC) point with Toronto Hydro system Check as applicable Load break switches Fuses / circuit Breakers Interface step-up transformer (intermediate transformer) Current Transformers and Voltage Transformers (quantity, location, connection, ratio) Power cables (length, type, impedance) Power factor correction capacitors and their switching arrangements (particularly for induction units) Generators (rotating / static) / Motors/ PV Inverter system Surge arresters Other Information Drawing attached/mailed separately Embedded Generation Connection Application Form - April 16, 2013 Page 3 of 10

6. Location and Site Plan Provide a site plan outlining existing facilities and proposed embedded generator location. The site plan should include approximate line route for connection to Toronto Hydro, as well as roads, lot numbers, and nearby power lines. Provide meter room layout showing locations of all equipment and approximate clearances. Drawing Number: Rev. 7. Protection Philosophy Provide a document describing the protection philosophy for detecting and clearing: - Internal faults within the Embedded Generation facility; - External phase and ground faults (in Toronto Hydro s distribution system); - Certain abnormal system conditions such as over / under voltage, over / under frequency, open phase(s); - Islanding - Tripping matrix Drawing Number: Rev. 8. Monitoring and Control Monitoring and control readiness is required for the Embedded Generation facility. Real time monitoring is necessary for safety and control coordination with Toronto Hydro s control centre. Provisions for monitoring and control will include, but not be limited to: (a) The ability to obtain operational data (b) The ability to control the state (on/off) of the generator For further information about the monitoring and control requirements, refer to FIT Monitoring and Control Requirements, found on Toronto Hydro s FIT webpage. Please provide: 1. details/documentation on the communication protocol and equipment to be used; and 2. a Single Line Diagram, signed by a Professional Engineer, illustrating the monitoring and control configuration. 9. Is the Generation Facility financed by a lender? Yes No Customer Name (Print): Customer Signature: Date: Embedded Generation Connection Application Form - April 16, 2013 Page 4 of 10

Connection Impact Assessment (CIA) Generator Form For projects over 10kW, a Connection Impact Assessment (CIA) must be performed by Toronto Hydro. A CIA is a more detailed assessment of the proposed project s impact on the Toronto Hydro electricity grid. 1. to 9. Sections 1 through 9 of the Embedded Generation Connection Application Form are applicable to this CIA Generator Form. 10. Application Type: New CIA Application CIA Revision 11. Embedded Generator Fault Contributions at the Interface Point/PCC All values to be at the nominal connection voltage to Toronto Hydro s distribution system, i.e. the high voltage side of the Facility interface (step-up) transformer. Maximum Symmetrical (all generators online) Three phase fault (MVA) Phase-to-phase fault (MVA) Single Phase to ground fault (MVA) R 1 R 0 X 1 X 0 X 1 /R 1 X 0 /R 0 12. Generator Facility Characteristics: a. Rated Power: kw kva For SPC/Inverter type units b. Terminal voltage V c. Line - interactive type (i.e. intended for parallel operation with electric utility) Yes No d. Power factor e. Battery backup provided Yes No f. Maximum fault current for terminal faults A g. Standards according to which built h. Manufacturer i. Model Number j. Provide Manufacturer s technical brochure and specification sheet Doc. No ** Technical Information on inverter shall be provided with the connection application. Only Canadian Standards Association (CSA) approved inverters are acceptable. A single-phase inverter can ONLY connect on a single-phase system and a three-phase inverter MUST be used on a three-phase system. Single-phase inverters WILL NOT be allowed to connect on three-phase systems. Please contact Toronto Hydro for further information regarding the use of multiple inverters on a project site. Connection Impact Assessment Generator Form - April 16, 2013 Page 5 of 10

Nominal Rating a. Rated Power: kva b. Rated Voltage: kv LL c. Rated Current: A d. Active Generation: kw e. Power Factor: p.u f. Number of Poles: g. Starting inrush current (multiple of full load) p.u h. Minimum power limit for stable operation kw i. Max Reactive Power: j. Min Reactive Power: Impedances For Synchronous Units: k. Steady State, Z: p.u l. Transient, Z : p.u m. Subtransient, Z : p.u n. Zero Sequence, Z 0 : p.u o. Negative Sequence, Z 2 : p.u p. Grounding, Z g : ohms q. Unsaturated reactances on: Configuration r. Generator terminal connection delta star s. t. u. Grounding method of star connected generator Performance and Capability Limits of range of reactive power Lagging (over-excited) Limits of range of reactive power Leading (under-excited) R X Solid Impedance: kva base kv base Ungrounded R: Ohms X: Ohms Power factor Power factor v. Provide a plot of generator capability curve (MW output vs. MVAR) Dwg No w. Generator connecting on (phase): single three x. Type and characteristics of exciter: y. Document Number: Rev. Connection Impact Assessment Generator Form - April 16, 2013 Page 6 of 10

a. Rated Power: kva For Induction Units b. Rated Voltage: kv LL c. Rated Current: A d. Active Generation: kw e. Efficiency % f. Power Factor p.u g. Rated speed RPM h. Slip regulation interval % i. Rated slip j. Subtransient Impedance, Z : k. Actual power factor at delivery point (after power factor correction): l. Generator reactive power requirements: Total power factor correction installed Number of regulating steps R: p.u X: p.u Full output: No output: Full output: No output: p.u p.u m. Power factor correction switched per step Power factor correction capacitors are Yes automatically switched off when generator breaker opens No n. Starting inrush current limited to (multiple of full load current) p.u o. Locked rotor current (at rated voltage) p.u p. Fault current vs. time curves (for various types of faults near the generator) Dwg No q. Document Number: Rev. Connection Impact Assessment Generator Form - April 16, 2013 Page 7 of 10

Interface Step- Up Transformer: (dual winding only) i) Transformer rating kva ii) Manufacturer iii) Nominal voltage of high voltage winding kv iv) Lightning impulse level of high voltage winding, full wave kv v) Nominal voltage of low voltage winding kv vi) vii) viii) ix) x) xi) xii) xiii) Number of phases Construction (core or shell) Number of legs kva base Impedances on: kv base R: p.u X: p.u High voltage winding connection delta star Solid Ungrounded Grounding method of star connected high voltage winding neutral Impedance: R: Ohms X: Ohms Low voltage winding connection delta star Grounding method of star connected high voltage winding neutral Tapping range, location and type of tap changer Expected tap settings Solid Impedance: Ungrounded R: Ohms X : Ohms HV LV kv kv Note: The term High Voltage, used above, refers to the connection voltage to Toronto Hydro s distribution system, and Low Voltage, used above, refers to the generation or any other intermediate voltage Connection Impact Assessment Generator Form - April 16, 2013 Page 8 of 10

Intermediate Transformer: (dual winding only) i) Transformer rating kva ii) Manufacturer iii) Nominal voltage of high voltage winding kv v) Nominal voltage of low voltage winding kv v) vi) vii) viii) ix) kva base Impedances on: kv base R: p.u X: p.u High voltage winding connection delta star Solid Ungrounded Grounding method of star connected high voltage winding neutral Impedance: R: Ohms X: Ohms Low voltage winding connection delta star Solid Ungrounded Grounding method of star connected high voltage winding neutral Tapping range, location & type of tap changer Expected tap settings Impedance: R: Ohms X: Ohms HV LV kv kv Note: The term High Voltage, used above, refers to the intermediate voltage that is input to the interface step-up transformer, and Low Voltage, used above, refers to the generation voltage 13. Load Information: Maximum continuous load: i) Total kva kw Generator Auxiliary Load Only kva kw ii) Maximum start up load kva kw iii) Largest motor size that would be started hp kw iv) Maximum inrush current of the motor (multiple of full-load current) For load displacement generators: p.u v) Max. present load at Generator's facility kva kw Max. future load at Generator's facility (excluding Auxiliary Loads) Indicate the means by which injection of power into Toronto Hydro's system will be prevented kva kw Connection Impact Assessment Generator Form - April 16, 2013 Page 9 of 10

14. Operation Information: i. Mode of Operation: ii. Annual Capacity Factor: % iii. Prospective number of annual scheduled starts / stops, and timing thereof : 15. Expected Monthly Generation, Consumption and Output From the Facility: January February March April May June July August September October November December Total Generation (a) Total Internal Consumption (b) Total Output (To Toronto Hydro Distribution System) (a b)* kwh Peak kw kwh Peak kw kwh Peak kw * This value would be negative when the generators are not in operation or when the internal consumption exceeds generation. 16. Other Relevant Information: Any material revisions to the design, planned equipment or plans for the embedded generation facility shall be filed with Toronto Hydro and a new CIA will be prepared as per Distribution System Code (DSC) section 6.2.15. The new CIA will be performed at the Generator s expense. Customer Name (Print): Customer Signature: Date: Connection Impact Assessment Generator Form - April 16, 2013 Page 10 of 10