BHARAT HEAVY ELECTRICALS LIMITED

Similar documents
INSPECTION AND TEST PLAN

Inspection and Test Plan for Water Tube Boiler


FORM A-1P MANUFACTURER'S DATA REPORT FOR PLATE HEAT EXCHANGERS As Required by the Provisions of the ASME Code Rules, Section VIII, Division 2

National Craft Assessment and Certification Program S P E C I F I C A T I O N S. INDUSTRIAL BOILERMAKER - MAINTENANCE V4 RBLMK34_04 October 2014

Heat Exchanger Construction Checklist

Specifications for EA31002 U Tube Bundle for CDU 3

National Craft Assessment and Certification Program S P E C I F I C A T I O N S

Essex County College - West Essex Campus Addition And Renovations dlb # / SECTION EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING

for industry.com

Select, wear adjust, use and maintain personal protective equipment

METAL FABRICATION SECTION 8: METAL FABRICATION SCOPE MATERIAL.

TCN 01. Page No. 1 of 2 Ref: PSER:SCT:ABJ:T1178:TCN-01 Date:

TENDER CHANGE NOTE 01 (TCN 01) DT:

Mechanical Design. Brian Brinson Mechanical Design Manager.

Note: Do not bury sulphur dioxide lines Use stainless steel pipe and fittings only where specified on project drawings.

NCCER Progress Blvd, Alachua, Florida Phone: (888)

National Craft Assessment and Certification Program S P E C I F I C A T I O N S

Assmann Corporation of America TANK INSTALLATION AND USE GUIDELINES FOR BULK STORAGE TANKS

A representative from Occupational Health is to be involved in the commissioning process to address any Respiratory Protection Program requirements.

FUEL GAS PIPING SECTION A. The provisions of SECTION 15010, MECHANICAL GENERAL REQUIREMENTS, apply to this section.

Reliance SG800 Series Steel Water Gage Valves

Tooling Approving Report

SERIES 4070-T GENERAL ASSEMBLY AND INSTALLATION INSTRUCTIONS

This specification describes the minimum requirements for piping systems for the following service:

Mould Precision Co., Ltd

18000 HDL FOUR POST LIFT LB CAPACITY INSTALLATION AND OWNER'S MANUAL

ISSUE MODIF. ORDER NO. WEEK ISSUE MODIF. ORDER NO. WEEK ISSUE MODIF. ORDER NO. WEEK 01 SME SME SME

Clopay Models 835/837 Sliding Door System Installation Guide

This specification describes the minimum requirements for service water piping systems (ie: cooling water, process water, etc.), located on surface.

WPS crew Doors Installation instructions

IOM 004 Effective 3/29/04 Rev A. MULTI-VENT Laminar Flow Panels Installation Operation and Maintenance

Lockformer / 16 Gauge Speednotch

University of Houston Master Construction Specifications Insert Project Name SECTION MECHANICAL SCOPE OF WORK PART 1 - GENERAL

Mould Precision Co., Ltd

SECTION EXPANSION FITTINGS AND LOOPS FOR HVAC PIPING

installation guide

KS SERIES - VERTICAL INSTALLATION

Chiltern Model Steam Engines

Series 1600 WeatherGuard Dock Enclosure

HD installation guide

Requirement for Holes - Holes for Hanging

Gared Pro-S Portable Backstop

This specification describes the minimum requirements for piping systems for the following service:

Inspection and Test Plan for Battery Charger

D300K 3+3 SE KUBOTA PARTS LIST FOR RETURN TO MAIN INDEX

Piping & Equipment Identification

Residential Construction Checklist Single and Two Family Construction

Sheet Metal Worker Level 2

SECTION STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS

JEFFERSON LAB TECHNICAL ENGINEERING & DEVELOPMENT FACILITY (TEDF ONE) Newport News, Virginia

Heavy and Medium Duty Fire Doors

INSTALLATION, OPERATION AND MAINTENANCE MANUAL

Gared Pro Portable Backstop

National Craft Assessment and Certification Program S P E C I F I C A T I O N S

BASE & WALL CABINET SETUP GUIDE BY SUNSTONE

Thank you for purchasing our product! *Please read these instructions and follow them step by step.*

A. Compatibility: Products shall be suitable for piping service fluids, materials, working pressures, and temperatures.

Bharat Heavy Electricals Limited (High Pressure Boiler Plant) Tiruchirappalli , TAMIL NADU, INDIA MATERIALS MANAGEMENT / CAPITAL EQUIPMENT

E-Z GROW HOBBY GREENHOUSE. I n s t r u c t i o n M a n u a l & D i s c l a i m e r s

LATTIMORE SHOWER SET INSTALLATION

CLASSIC 300D Kubota PARTS LIST FOR RETURN TO MAIN INDEX

STANDARD PHRASEOLOGY SECTION G. 1. This section of standard phraseology is for general use in piping disciplines.

INSTALLATION INSTRUCTIONS IMPERVIA (Vent and Fixed) AWNING, CASEMENT, and LARGE AWNING WINDOW WITH FINS

INS A KSCR INSTALLATION INSTRUCTIONS STANDARD PROCEDURE. 1. Unpacking the KSCR Splicing the KSCR (If Required)...

LOCOMOTIVE ENGINEERING DEPTT.

MUELLER GAS. DH-5 Drilling Machine. For use on 1 1 /2 & 2 Line Stopper Fittings. Reliable Connections. General Information 2

Requirements for manufacture of anchors

25 TONNE HYDRAULIC PRESS MODEL NO: AHP 26

RITE-HITE RAINGUARD TM

PRESTON HEALTH SERVICES ARCHITECT S NO. 2700

ONASSIS SHOWER SET INSTALLATION

MIL- B Rev NAVSEA 0900-LP

FIRE STATION NO TH STREET NORTH ST. PETERSBURG, FL M-1 SCOPE OF WORK SYMBOL DESCRIPTION SYMBOL DESCRIPTION HVAC SYMBOL LEGEND

DOLPHIN SHELL & TUBE MARINE CONDENSERS (DSTMC)

CALLAS THERMOSTATIC SHOWER SET

OWNER'S MANUAL TIE ROD, WALL & FLOOR MOUNTED JIBS. Model JIB-HC, JIB-LC, JIB-FM

SIG-032-B TRAFFIC SIGNAL MAST ARM POLE AND MAST ARM DETAILS - CATEGORY III LUMINAIRE ARM (SEE CONTRACT) 6'-0", 8'-0", 10'-0" NOMINAL SPREAD

NRS Installation Manual

TYPE OF PIPING PRESSURE TESTING. For large diameter piping hand wipe/ sweep should be applied as much as possible (inspection to be recorded).

A. Action Submittals: Written and graphic information that requires Engineer's responsive action.

This specification describes the minimum requirements for piping systems for the following service:

MPA-9000 Universal Ceiling Projector Mount Kit

CSP PSYCHIATRIC SERVICES UNIT SECTION IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

SERIES 360. Single Hung Windows. NOTE: Read instructions completely before attempting any installation.

STANDARD PHRASEOLOGY SECTION G. 1. This section of standard phraseology is for general use in piping disciplines.

PLAN CEILING FRAMING PLAN CEILING JOIST SCHEDULE. Tenant Improvements. UNLV Police Station Maryland Parkway.

Stepping ahead in technology & innovation PIPING INSTITUTE OF TECHNOLOGY & ANALYSIS SOLUTIONS

Reversing Gear. Shay Reversing Gear

SERVICE MANUAL. For the Vermont Castings. Please place picture here. MODELS: 2181 (Small) 2183 (Large) 2184 (Extra Large)

INSTALLATION INSTRUCTIONS for Wood/Clad Wood Windows without Exterior Trim or Nailing Fin (JII025) ImpOrTaNT INFOrmaTION & GlOssary.

SIG-030-B TRAFFIC SIGNAL MAST ARM POLE AND MAST ARM DETAILS - CATEGORY I LUMINAIRE ARM 6'-0", 8'-0", 10'-0" NOMINAL SPREAD (SEE CONTRACT) POLE CAP

MIL- B B. MIL- B Rev NAVSEA 0900-LP II: ATTRIBUTES: YES NO N/A

My Career in Welding Engineering

INSTALLATION MANUAL Sluice Gates, Stop-logs & Screens

Freight Door Installation Instructions - HG Series OPENING QUALITY DOORS AROUND THE WORLD. JOB NAME: JOB LOCATION: COURION JOB #:

SUMMARY SHEETS OF BAR COUPLER CONNECTIONS

EXIRA SHOWER SET INSTALLATION

INS A KSR INSTALLATION INSTRUCTIONS STANDARD PROCEDURE. 1. Verify Curb Installation Required Installation Tools...

MODEL 1500, 2500 & 2700 MANUAL CONTROLS. Service Manual

Transcription:

FIELD QUALITY PLAN OF BOILER PRESSURE PARTS (Erection & Commissioning) FOR BHEL-JHANSI BHARAT HEAVY ELECTRICALS LIMITED BHEL-JHANSI DOC. NO.: REV. NO. : R00

FIELD QUALITY PLAN OF BOILER PRESSURE PARTS (Erection & Commissioning) FOR BHEL-JHANSI APPROVED BY DOCUMENT NO. ORIGINAL DATE OF ISSUE --/--/---- REVISION NO. & DATE R00 Dt. --/--/----- COPY NO. ISSUED TO DATE OF ISSUE CONTROLLED / INION COPY ISSUED BY (SIGNATURE & DESIGNATION) BHARAT HEAVY ELECTRICALS LIMITED BHEL JHANSI

CONTENTS FQP No. : REV. No.: 00 JHANSI SHEET 1 / 1 SHEET Sl.No. Description No. of Sheets 1.0 Status of Amendments 01 2.0 Authorization for different categories of checks 01 3.0 Quality Plan for Installation of BOILER PRESSURE PARTS (Erection & Commissioning) For BHEL JHANSI 3.1 Statement of checks 12 3.2 Documents referred in Quality Plan 01 3.3 Record of Quality checks 01

Doc. No. : JHANSI STATUS OF AMEDMENTS REV. No.: 00 SHEET 1 / 1 SHEET S l. Reference of Sheet(s) Revision No. Remarks No. Revised & Date NIL

JHANSI AUTHORISATION FOR DIFFERENT REV. NO. : 00 CATEGORIES OF CHECKS SHEET 1 / 1 SHEETS Classification of Check Checking Authority Accepting Authority -------------------------------- Symbol Description A Critical BHEL HOS & Task Performer B Major BHEL & Task Performer HOS C Minor Task Performer Task Performer Legend: NOTE: HOS: Head of section 1. Quantum of check shall be 100% for all characteristics unless otherwise mentioned in reference documents. 2. QAE is also authorized to carry out Surveillance in any of the B & C category of checks at his discretion. 3. In case of non-conformity, accepting authority shall ensure dispositioning before accepting and the dispositioning shall be reflected in log sheets / Protocols.

STATEMENT OF CHECKS REV. No.: 00 JHANSI SHEET 1 / 12 SHEETS Capacity System Sub System Area : 12MTPH : BOILER : PRESSURE PARTS : ERECTION & COMMISSIONING For checks where log sheets are not called for, suitable records should be maintained in the form of log book / protocols. As an evidence of having carried out the work satisfactorily, a general-purpose log sheet L-00 shall be maintained for all the checks. Abbreviations used in the column Type of check are : R : Record Verification M : Measurement V : Visual

JHANSI SHEET 2 / 12 SHEETS SYSTEM : BOILER SUB-SYSTEM : PRESSURE PARTS AREA : ERECTION 1.0 DRUM : 1.1 Check for inspecting authority s stamp on drum and certificate. V/R A 100% Drawing / IBR Certificate 1.2 Readiness of structure for boiler drums erection. V/R B 100% Drawing / Structures log Sheet 1.3 Verification of capacity of drum lifting equipment/arrangements. V B 100% 1.4 Ground inspection of drum, its orientation. V B 100% Drawing 1.5 Ensure clearance between drum and structural members during V B 100% hoisting. 1.6 Drum suspension U rod dimensions and freeness of nuts. M Tape B 100% Drawing L-01 1.7 Drum suspension supports alignment. M Water level / B 100% - do - L-02 Tape 1.8 Alignment of drum. M -do- A 100% -do- L-02 1.9 Minimum projection of threads above the nuts in the drum M Tape B 100% - do - suspension rods. 1.10 Verify verticality of column after Drum Erection. V/R Theodolite A 100% Drawing / Structure log sheet 1.11 Assembly of drum internal. V/R B 100% Drawing

JHANSI SHEET 3 / 12 SHEETS SYSTEM : BOILER SUB-SYSTEM : PRESSURE PARTS AREA : ERECTION 2.0 HEADERS : 2.1 Check for Inspecting Authority s stamp on headers and certificate. V/R A 100% Drawing / IBR certificate 2.2 Identification of the headers. V/R C 100% Shipping List / Drawing 2.3 Clearance during lifting of Headers. V B 100% Drawing 2.4. Cleanliness of headers. V/R C 100% 2.5 Bow in headers (Tolerance : 1 mm / M, Max. 8mm for membrane M/R Water level / B 100% Drawing panel headers and Max. 10mm for other headers). Tape 2.6 Header scarffing line (Tolerance : 2 mm Max. for membrane M/R -do- B 100% -dopanels and 4mm Max. for others). 2.7. Completion of supports. V C 100% -do- 2.8 Alignment of headers and elevation, horizontally and distance from M/R Water level / A 100% - do - L-03 reference axes. Tape 3.0 WELDING : 3.1 Qualification of welders. V / R A 100% IBR Welders Certificate / Welding Manual / WPS / PQR / WPR 3.2 Adoption of correct procedure, method and approved consumables. V/R B 100% EWS / Welding Manual

JHANSI SHEET 4 / 12 SHEETS SYSTEM : BOILER SUB-SYSTEM : PRESSURE PARTS AREA : ERECTION 3.3 Completion of pre-heating, welding and post heating of weld joints. V B 100% Drawing / EWS / Welding Manual / Heat Treatment Manual 3.4 NDE of welds. V/R A As per EWS / Ref. Doc. NDE Manual 3.5 Post Weld Heat Treatment (PWHT) of welds. M/R Time-Temp. A - do - EWS / Heat Treatment Recorder Manual 3.6 Identification of weld joints and maintenance of records indicating V / R A 100% Drawing / EWS / number of weld joint, heat treatment carried out, NDE results, Welding Manual / acceptance and rejection / repair details. Heat Treatment Manual / NDE Manual 4.0 PANELS : 4.1 Identification of panels. V C 100% Shipping List / Drawing 4.2. Width, diagonals & location of openings of the panels (Tolerance : M Tape C 100% Drawing Panel width : + 2mm or 5mm. Diagonal difference (D1 ~ D2) : 10mm Max.). 4.3 Cleanliness of the panels (sponge test with compressed air). V C 100% Cleaning Procedure 4.4 Completion of supports. V C 100% Drawing 4.5 Completion of panel to panel joints V B 100% -do-

JHANSI SHEET 5 / 12 SHEETS SYSTEM : BOILER SUB-SYSTEM : PRESSURE PARTS AREA : ERECTION 4.6. Verticality of panels. M Plumb / Tape B 100% Drawing L-04 /Piano wire 4.7 Alignment of Combustor. M Tape / Scale A 100% - do - L-05 4.8 Welding of refractory anchor pin. M C 100% -do- 5.0 GRATE PANELS: 5.1 Alignment of panel with header. M Tape B 100% Drg//EWS 5.2 Height of Expansion sleeves from pin. M/R Tape C 100% Drawing 5.3 Expansion sleeves welding ( NDT check as per EWS). V/R C 100% EWS /Welding manual 5.4 Identification of Nozzles. V B 100% Drawing 5.5 Height of Nozzles. M/R Tape B 100% -do- 5.6 Nozzle welding. V C 100% EWS /Welding manual 6.0 COILS AND TUBES : 6.1 Identification of the coils. V C 100% Shipping list / Drawing 6.2 Cleanliness of the coils (sponge test with compressed air). V C 100% Cleaning Procedure 6.3 Alignment of coils w.r.t. inlet and outlet headers. M/R Tape / B 100% Drawing Water level

JHANSI SHEET 6 / 12 SHEETS SYSTEM : BOILER SUB-SYSTEM : PRESSURE PARTS AREA : ERECTION 7.0 PLATEN SUPER HEATERS: 7.1 a) Identification of SH Coils. V C 100% Drawing /Shipping List b) Clearance between end coil assembly and steam M/R Tape B 100% Drawing L-06 cooled wall (Front & rear). c) Individual pitches between coils. M Tape B 100% -do- L-06 d) Clearances between coil ends and steam cooled front M Tape A 100% -do- L-07 rear wall). 8.0 ECONOMISER : a) Identification of economiser coils. V C 100% Drawing / Shipping list b) Clearance between coil end and duct front/ rear wall. M Tape B 100% -do- L-07 c) Individual pitches between coils. M Tape B 100% -do- L-07 d) Pitch between end coil assembly and duct side walls. M Tape A 100% -do- L-07 e) Alignment and locking of cassette baffles. M/R Tape B 100% -do-

JHANSI SHEET 7 / 12 SHEETS SYSTEM : BOILER SUB-SYSTEM : PRESSURE PARTS AREA : ERECTION 9.0 REHEATER : a) Identification of reheater coils. V C 100% Drawing / Shipping list b) Clearance between end coil assembly and steam cooled M Tape B 100% Drawing L-08 side walls. c) Individual pitches between coils. M Tape B 100% -do- L-08 d) Clearance between coil ends and steam cooled front/rear M Tape A 100% -do- L-08 wall.

JHANSI SHEET 8 / 12 SHEETS SYSTEM : BOILER SUB-SYSTEM : PRESSURE PARTS AREA : ERECTION 10.0 DOWNCOMER PIPES (DC PIPES) : 10.1 Identification of the DC pipes. V C 100% Shipping list / Drawing 10.2 Cleanliness of the pipes. V/R C 100% Cleaning Procedure 10.3 Orientation of DC pipes. V B 100% Drawing 10.4 Alignment of DC pipes (Verticality of DC pipes : M Tape / B 100% - do - 1mm / M, 5mm Max.). Plumb bob 10.5 Alignment of supports. V C 100% -do- 10.6 Completion of seismic guides. V C 100% - do - 11.0 RISER TUBES / CORNER TRANSITION TUBES : 11.1 Identification of the tubes. V C 100% Shipping list / Drawing 11.2. Cleanliness of the tubes (sponge test with compressed air.) V C 100% 11.3 Alignment of tubes. M Tape B 100% Drawing 11.4 Completion of supports and seismic guides. V C 100% - do -

JHANSI SHEET 9 / 12 SHEETS SYSTEM : BOILER SUB-SYSTEM : PRESSURE PARTS AREA : ERECTION 12.0 BUCKSTAYS : 12.1. Identification of the components. V C 100% Shipping list / Drawing 12.2 Completion of buck stay channel, stirrup angle with beams. V B 100% Drawing 12.3. Completion of attachment welds such as scalloped plates and V B 100% -dolugs. 12.4 Alignment of buck stay beams. M Tape B 100% - do - 12.5 Completion of corner joints. V B 100% -do- 12.6 Completion of guides. V B 100% - do - 13.0 GENERAL : 13.1. Verticality and loading of suspensions. V B 100% - do - 13.2 Cold compression of all springs and locking of the V B 100% -do- Spring assembly. 13.3 Completion of pressure parts attachment welds. V B 100% -do- 13.4. Closing of voids and cut-outs made during erection. V B 100% -do- 13.5 Locking of supports for hydraulic test. V B 100% -do- 13.6 Servicing of valves. V B 100% -do-

JHANSI SHEET 10 / 12 SHEETS SYSTEM : BOILER SUB-SYSTEM : PRESSURE PARTS AREA : ERECTION 13.7 Completion of drain / vent valves. V B 100% Drawing 13.8 Ensure welding of metal temperature pads on super- heater V B 100% - do - and reheater coils. 14.0 HYDRAULIC TEST : 14.1 Welding of insulation hooks / studs and attachments to V C 100% Drawing pressure parts completion before hydraulic test. 14.2 Seal welding of all site RT plugs. V L P I kit B 100% Drawing / NDE Manual 14.3 Readiness of total system for hydraulic test. V A 100% Drawing L-09 14.4 Completion of air test of the system. V/M Pressure gauge A 100% Hydrostatic Test L-10 Procedure 14.5 Rectification of leak joints and details. V/R A 100% L-10 14.6 Clearance of milestone activity. V A 100% 14.7 Completion of hydraulic test. V/M Pressure gauge A 100% Hydrostatic Test L-11 Procedure

FQP No. JHANSI SHEET 11 / 12 SHEETS SYSTEM : BOILER SUB-SYSTEM : PRESSURE PARTS AREA : COMMISSIONING 1. Completion of hydraulic test. V/M Pressure gauge A 100% 2. Completion of gas tightness test of furnace and connected V A 100% Commissioning ducts. Procedure 3. Availability of interlocks and protection to the equipments V B 100% Drawing / O & M Manual 4. Completion of trial operation of individual equipments. V A 100% Commissioning Procedure / O & M Manual 5. Clearance of milestone activity for light up. V A 100% -do- 6. Completion and readiness of systems for initial light up. V A 100% Drawing / Commissioning Procedure 7. Completions of alkali boil out of the system. V A 100% -do- L-12 8. Completion of chemical cleaning of the system. V A 100% Commissioning L-13 Procedure / O & M Manual 9. Completion of passivation activity of the system. V A 100% Commissioning Procedure

JHANSI SHEET 12 / 12 SHEETS SYSTEM : BOILER SUB-SYSTEM : PRESSURE PARTS AREA : COMMISSIONING 10. Clearance of milestone activity for steam blowing. V A 100% Commissioning Procedure 11. Completion of steam blowing operation of the system. V A 100% -do- L-14 12. Clearance of milestone activity for safety valve floating. V A 100% -do- 13. Completion of safety valve floating. M Pressure A 100% Commissioning L-15 gauge Procedure / O & M Manual 14. Free expansion of the system at various elevations and at M Tape B 100% Drawing L-16 different pressures.

JHANSI DOCUMENTS REFERRED IN FIELD QUALITY PLAN FQP No. : REV. NO.: R00 Sheet: 1 / 1 Sheet SL.NO. Reference Document Issuing Authority 1. Erection Welding Schedule (Erection drawing) BHEL, Trichy 2. Recommended Hydrostatic Test Procedure BHEL, Trichy 3. Welding Manual BHEL, PSNR, NOIDA 4. NDE Manual BHEL, PSNR, NOIDA 5. Heat Treatment Manual BHEL, PSNR, NOIDA

JHANSI OF QUALITY CHECKS DRAWING / RESULTS SHEET CHECK DOCUMENT OF INSPECTED BY CLEARED BY ACHIEVED NO. OF FQP NO. REFERENCE SIGN. & DATE SIGN. & DATE OK / NOT OK REMARKS Note : Any protocol made is to be numbered & mentioned in Format of Record column. FQP No. : SYSTEM SUB-SYSTEM AREA PROJECT REV. NO. : R00 UNIT NO. LOG SHEET NO. : L-00 RATING SHEET 1 / 1 SHEET