INTERNATIONAL. June 2017 Volume 13. A Buoyant Future. Reducing Cost and Risk in Floating Offshore Wind

Similar documents
Pelastar TLP Floating Wind Turbine Foundation

Jørn Scharling Holm DONG Energy

Design and validation challenges of floating foundations: Nautilus 5MW case. Iñigo Mendikoa Research Engineer

FOUNDATION INNOVATION

The offshore wind market deployment: forecasts for 2020, 2030 and impacts on the European supply chain development

UK offshore wind industry progress to cost reduction

The WindFloat Project. February 2010

Torgeir Ramstad Managing Director, Fred. Olsen United. European projects: Being part of the global supply chain

An insights report by the Energy Technologies Institute. Offshore Wind Floating Wind Technology

An insights report by the Energy Technologies Institute. Offshore Wind Floating Wind Technology

Offshore Renewable Energy Catapult

Wind Turbine Decommissioning in the UK Offshore Zone

Challenges in the Construction of Offshore Wind Structures. Dr Ned Minns IT Power UK

Offshore Wind Risks - Issues and Mitigations

Tidal Energy. Transmission & Distribution Network. Wind Energy. Offshore Substation. Onshore Substation. Tidal Stream Energy.

European Wind Energy Technology Roadmap

The WindFloat Project

Getting to Grips with Deepwater Handling Operations

5.1 Optimal integrated combination of foundation concept and installation method

TKI Wind op Zee. Program

NSRI/ORE Subsea Technological Challenges in Offshore Wind

Floating wind turbines: the future of wind energy? Axelle Viré Faculty of Aerospace Engineering

WAVE & TIDAL SERVICES WAVE & TIDAL

NURTURING OFFSHORE WIND MARKETS GOOD PRACTICES FOR INTERNATIONAL STANDARDISATION

Floating Systems. Capability & Experience

Next generation WTG foundation and WTG installation. WindDays Rotterdam, 14 June 2018 Arnoud Bosch Engineering Director

MACROECONOMIC BENEFITS OF FLOATING OFFSHORE WIND IN THE UK

Offshore Wind Floating Turbines

Founding Manifesto Friends of Floating Offshore Wind 18 May 2016

Windparks in tiefem Wasser: wie schwimmende Unterstrukturen das Potential von Offshore- Windenergieanlagen vervielfachen können

Cost of energy going below 100/MWh; the opportunities and barriers

Driving Cost Reductions in Offshore Wind THE LEANWIND PROJECT FINAL PUBLICATION

RENEWABLE ENERGY TECHNOLOGY ACCELERATOR (RETA) PROJECT

Offshore Drilling Rigs

Offshore Renewables Institute

SET-PLAN IMPLEMENTATION

FLOATING OFFSHORE WIND ENERGY

Offshore wind what s it all about? 01/11/2017 Owen Murphy & Andrew Tipping

Accelerating the Deployment of Offshore Renewable Energy Technologies. IEA Implementing Agreement on Renewable Energy Technology Deployment

Inter Array Cable Technology Development. Jeremy Featherstone Product Development Director JDR Cable Systems Ltd

EDP Innovation involvement in offshore energy

Subsea infrastructure in MRE ICOE November 6, By Don Bryan, BSc, MBA General Manager Pacific Northwest Operations

Wind Energy Technology Roadmap

RESEARCH, TESTING AND DEMONSTRATION

RENEWABLE ENERGY SOLUTIONS. oceaneering.com

Energy Transition Partner. Created and produced by

Lesson Learned from European development of offshore wind and ocean renewables. 5 th November 2015

James Fisher and Sons PLC. Marine Energy Supply Chain 14 th September 2017

Offshore Renewable. Energy Conversion platforms Coordination. Action

MOORING SOLUTIONS IN ASIA PACIFIC A SINGLE, LOCAL SOURCE OF MOORING, POSITIONING AND RIG MOVING SERVICES

Dagang Zhang China-America Frontiers of Engineering Symposium San Diego, USA

Marine Construction Support & Dimensional Control

Exploring the impact of innovative developments to the installation process for an

The potential for windpower in the Baltic Sea

Oil and Gas Diversification: High Potential Areas, Key Challenges (Operations & Maintenance) BVG Associates ~ Alan Duncan

Mooring Capabilities. Angola Brazil Egypt Equatorial Guinea Malaysia Mexico Norway Singapore United Kingdom United States

Angola Brazil Mooring Egypt Equatorial Guinea Capabilities Malaysia Mexico Norway Singapore United Kingdom United States

Mooring Capabilities. Angola Brazil Egypt Equatorial Guinea Malaysia Mexico Norway Singapore United Kingdom United States

A Spatial-Economic Cost-Reduction Pathway Analysis for U.S. Offshore Wind Energy Development from

Founded in 1988, SAITEC is one of the most prestigious engineering firms in Spain at present. It carries out its activities from a professional and

-PILOT & Industry development -Decommissioning. Audrey Banner Head of Offshore Decommissioning Unit, DECC

Research, testing and demonstration.

NSRI Mastermining Wave & Tidal Workshop 16/05/18. Opening Address. David Rennie Head of Oil and Gas Scottish Enterprise.

Strategic performance in the toughest environments

Onshore & Offshore Engineering and Management of Subsea Cables and Pipelines

Summary of Changes and Current Document Status

Marine Risers. Capability & Experience

Taiwan Offshore Wind. Specialist technical issues affecting project development in Taiwan. 4 th Asia Offshore Wind Day.

Learn more at

Methodology to calculate mooring and anchoring costs of floating offshore wind devices

Morgan Stanley Houston Energy Summit

The offshore wind puzzle getting the pieces right

Simmons & Company International European Energy Conference 2013

OFFSHORE ENERGY DIVISION OFFSHORE WIND SOLUTIONS

Discipline. Technology TECHNOLOGY DEVELOPMENT. Technology WITHIN SBM OFFSHORE

Subsea Engineering: Our Action Plan

Development of a Semi-submersible Barge for the installation of a TLP floating substructure. TLPWIND case study

ORECCA European Offshore Renewable Energy Roadmap

An introduction to the Offshore Renewable Energy Catapult

Offshore Engineering. Design, Fabrication, Installation, Hook-up and Commissioning September 2017 Dubai, United Arab Emirates

Offshore Energy Solutions. Technologies and products

Kinsale Area Gas Fields Decommissioning Project Information Leaflet

The future of offshore wind in the US

Offshore Access to America s Oil and Natural Gas Resources

The European maritime industry & its role in the development of marine renewables

Adjusted revenues for the 3 rd quarter recorded a slight rise of 2.6% compared to the previous quarter (consolidated revenues up 4.

Optimizing wind farms

Oil and gas diversification Offshore wind NORWEP

Rampion Offshore Wind Farm Meet The Buyer Event

Umbilical Manufacturer s Perspective on the Challenges of Deep Water Operations. Presented by: James Young, JDR Engineering Director

Falmouth Bay Short Term Test Site for Marine Energy Converters

WEU Offshore Foundations Report 2013

Enabling Array Cable Cost Reduction

Strategic Innovation Acceleration - UK marine energy industry: pathway to commercialisation Simon Robertson

Deep offshore and new foundation concepts

Oil and gas diversification Offshore wind NORWEP

SIMON HINDLEY MENG, AMRINA MANAGING DIRECTOR, NAVAL ARCHITECT

Oil and Gas Seize the Opportunity Guides. Offshore Wind

Phil de Villiers 17 April Offshore Wind Accelerator (OWA)

Moorings & Foundations Richard Yemm

Transcription:

INTERNATIONAL June 2017 Volume 13 No. 4 A Buoyant Future Reducing Cost and Risk in Floating Offshore Wind

Reducing Cost and Risk in Floating Offshore Wind By Robert Proskovics and Gavin Smart, A Buoyant Future ORE Catapult, Glasgow, UK In recent years, floating wind has gradually matured as a technology, progressing from being the subject of academic research to a handful of full-scale, stand-alone prototype projects (Hywind in Scotland, Principle Power in Portugal and the FORWARD project in Japan), to the development of multiple pre-commercial arrays. Technological advances in floating wind will open up opportunities to exploit the abundant wind resource in deeper water sites where it is currently not possible to deploy fixed-bottom foundations, making this an important area of research for the offshore wind industry. This article analyses the costs and risks of the three most common types of floating wind structure and compares them to those of a fixed-bottom monopile wind farm. It also provides an outlook on the technology s future and notes areas where further research is needed. Floating wind still lags far behind fixed-bottom wind in terms of commercial readiness and will rely on governmental support in the medium term if it is to achieve or even outstrip costs associated with conventional fixed foundations in the long term. However, as floating wind moves closer to full commercialisation, new supply chain opportunities are emerging. The natural synergies with the oil and gas sector mean this technology offers potential for those affected by the recent downturn in the oil and gas industry. The three most common types of floating wind substructure are spar, tension leg platform (TLP) and semi-submersible (see Figure 1). In this article we have analysed the costs and risks of these typologies and compared them to those of a fixed-bottom monopile wind farm. To reflect on the recent increase in designs that use concrete as the primary material, both a steel and a concrete semi-submersible are included in the analysis. The four substructures analysed are generic floating wind substructures and do not represent specific concepts. The following assumptions are used: The monopile has a grouted transition piece and is installed in water 40 metres deep. The monopile benchmark is part of a 500MW wind farm with 8MW turbines. The steel TLP has no selfstability in tow. Steel and concrete semisubmersibles do not use active ballasting. The steel spar employs a slurry ballast. Analysis We have considered the costs and risks associated with all three technologies against a fixed turbine reference for the key stages of an offshore wind project. Development and Consent Cost: Slightly less expensive (than fixed-bottom monopile wind farm) Risk: Slightly more risky The cost of developing and consenting a floating wind farm is expected to be slightly more favourable than a fixed-bottom, with a possible exception in the case of TLPs. Shallower bore samples for geotechnical surveys could potentially contribute to these savings; however, more samples would be required to account for multiple anchors. The risk profile for floating wind may be perceived to be higher than for monopiles, due to the emerging nature of environmental monitoring and consenting. The front-end engineering is also less developed for floating wind, and lacks bespoke standards, including for each typology. Visual impact could be reduced by installing turbines further offshore in deeper waters. However, this advantage could be cancelled out if assembly and major repairs were to be performed near densely populated areas. Some opposition might also be voiced from the fishing community (particularly for catenary mooring designs), airspace users (MoD, airports and air traffic control) and other stakeholders, such as the shipping industry. Wind Turbines The wind turbines used in fixedbottom and floating situations are nearly identical. Both use adapted onshore turbines, and modifications are made to the blade pitch control algorithms for floating turbines. In some cases this can lead to hardware implications, such as the necessity for new blade pitch actuators. Substructure and Mooring System Cost: More expensive Risk: Less risky Compared to monopiles, substructures for floating wind turbines are, for now, considerably more expensive to manufacture and assemble. Steel substructures are many times heavier and more labourintensive to assemble, whereas concrete substructures are cheaper per tonne of material but an order

Feature Figure 1. Floating wind typologies (left to right: spar, tension leg platform (TLP), semi-submersible) of magnitude heavier. In addition to this, all floating wind turbines require mooring lines and anchors. In terms of risk, this is of a comparable scale between monopiles and steel substructures. The latter can make use of the existing supply chain for fixedbottom wind, and are exposed to the volatility of steel prices. Floating substructures consist of more parts, and as a result are more complex to assemble. However, they benefit from much higher standardisation as they are not directly coupled to the seabed. Concrete substructures are an exception, in terms of risk profile. These are manufactured and assembled in one process that can be performed in a port, cutting out the need for transporting the large, heavy substructure sections from their manufacturing facility to the assembly site. They are also much less exposed to the high volatility of steel prices, although some steel is still required for concrete reinforcement. The main risks for concrete substructures lie in the concrete curing process, which requires long periods in a controlled environment, and soil-bearing capacity at ports, which need to bear the weight of the heavy structures. Mating Cost: Less expensive Risk: Mixed/varies by typology Mating is one of the areas where floating wind has a clear advantage over fixed-bottom: turbines can be installed on their substructures in a much more controlled environment, and without the use of expensive jack-up vessels. While semi-submersibles (steel and concrete) and TLPs can perform turbine and substructure mating at port, this is not the case for spars. These require deep, sheltered waters for the spars to be up-righted by means of installing the ballast, followed by mating using expensive offshore cranes. Currently, this process is highly costly and brings additional risks compared to other floating wind typologies (e.g. the mating being performed in a floating floating arrangement and a lack of deep, sheltered waters). Array Cables Cost: Slightly more expensive Risk: More risky Floating wind array cables can be installed before turbine installation, allowing multiple processes to be performed in parallel. This gives floating wind an advantage over fixed-bottom, in which array cables are installed only once foundations are in place. Array cables for floating wind are currently more expensive, as they require dynamic cables (umbilicals) and bespoke electrical connectors, of which there is a limited availability. Installation (TLPs: More expensive) (TLPs: More risky) Installation of floating wind turbines and connecting all the dynamic cables and mooring lines requires deploying multiple vessels for an extended period of time specifically tug boats for towing the foundations and anchor handling vessels (AHVs) for electrical and mechanical coupling. While more vessels are required for floating wind installation compared to monopiles, these are considerably cheaper to charter than a jack-up vessel. An exception would be in the case of TLPs that, if not selfstable in towing, require bespoke installation barges, which would incur a significant expenditure. Installation of TLPs would also have to be performed in a highly

Feature floating turbine and a CTV must be accounted for. Major Repairs Cost: Varies by typology Risk: Varies by typology The cost of performing major repairs is highly dependent on the typology, and the process is, in essence, a reversal of the installation procedure. Semi-submersible structures can be decoupled from the mooring and electrical systems, and towed back to port for repairs. This makes them cheaper than monopiles, as expensive jack-up vessels are not required. Bespoke equipment is required for TLPs and spars in the case of TLPs this means transportation barges and for spars a heavy lift vessel (HLV) or crane barge in deep, sheltered water. These would all simultaneously incur costs and increase risks. Additionally, spar repairs would have to be performed in a floating-to-floating configuration, increasing risk. Table 1. Summary of current costs and risks for floating wind compared to monopiles controlled environment to guarantee tendon and substructure integrity. Project Management, Contingency and Other Costs The costs around project management, contingency and insurance are expected to be broadly similar for monopiles and floating wind. While there are more operations to undertake offshore for floating wind, these include fewer offshore heavy lifts, balancing the cost and risk profile of both technologies. Transmission Cost: More expensive Risk: More risky The higher costs and risks for floating wind transmission come from the necessity of putting an electrical substation in deep waters. While this could take the form of a fixed or floating platform, a floating solution would require the development and qualification of very high-power dynamic cables, which are currently not available on the market. Scheduled O&M and Minor Repairs The costs and risks for scheduled O&M and minor repairs are expected to be very similar for monopiles and floating wind. Tests have demonstrated the applicability of crew transfer vessels (CTVs) used in fixed-bottom offshore wind to floating turbines. In the case of concrete substructures, inspection frequency could be further reduced. While the majority of risks are very similar in fixed and floating wind, the floating-to-floating configuration of technician transfer between a Decommissioning Cost: Less expensive Risk: Varies by typology Decommissioning costs for floating wind turbines are expected to be lower than for fixed-bottom. This is particularly true for semisubmersibles that do not require bespoke equipment or heavy lift operations offshore. While the cost is lower for all typologies compared to a monopile, the risk profile is only favourable for semisubmersibles. TLPs require bespoke vessels, while spars require HLVs for turbine decommissioning in deep, sheltered waters, and removal of hard ballast before substructures can be decommissioned in port. Despite all this, steel substructures benefit from greater recyclability and resale value. Summary Table 1 summarises the findings of our analysis, with cost and risk placed alongside each factor for easier comparison. In general, cost and risk are both reduced compared to fixed-bottom where operations can be performed onshore rather than offshore, or are still performed offshore but with less complex,

more readily available vessels. This is seen predominantly in turbine and substructure mating, O&M and decommissioning. Areas where we see cost and risk downsides in the near term are those requiring further technology development, such as dynamic export and array cables. Outlook For floating wind to continue reducing costs and risks, the key areas of focus should be in the following: Decreasing substructure manufacturing costs through floating wind-specific fabrication, assembly, load-out and staging facilities, as well as learning. Reducing installation time through experience and optimisation of designs for at-sea operations. De-risking of bespoke barges for TLPs for installation, major repairs and decommissioning. Proving of TLP designs that are self-stable in tow. The potential development of techniques and/or technology to reduce costs and eventually reduce risks for mating procedures for spars (also applicable to major repairs and decommissioning). An example of this can be seen in Statoil s Hywind floating wind installation innovation challenge. Developing and verifying dynamic cables and connectors. Developing substations for deep water, including offshore transmission modules (OTMs). Better understanding of meantime-to-failure of components due to motions and accelerations associated with floating wind turbines. Developing techniques for hard ballast recovery in spars. Table 2 illustrates the potential for cost and risk for floating wind compared to monopiles, this time assuming that the suggested learning and innovation in floating wind is developed and implemented, and no significant developments occur to reduce the costs and risks around monopiles. Table 2. Summary of costs and risks for floating wind compared to monopiles if suggested innovations are implemented It should be noted that monopiles have been, and will continue to be, put through continuous and rigorous cost-cutting exercises. Some of the innovations that could reduce the costs and risks of monopiles include the development of integrated monopile and transition piece designs, which would result in fewer lifting operations offshore, fewer parts and a reduction in weight. Robert Proskovics is an engineer at ORE Catapult, and is responsible for ORE Catapult s floating wind project portfolio. His primary work includes risk assessment of floating wind turbines. Prior to working at ORE Catapult, he was involved in dynamic simulations and aerodynamics of spar-type floating wind turbine investigations as part of his PhD. Gavin Smart is the Investment & Financial Analyst at ORE Catapult, and is responsible for financial and economic modelling. He has played a leading role Once floating wind technology matures, there are no areas (apart from the cost of substructures) where cost or risk will lag materially behind monopiles. Reductions in the cost and risk of floating wind will be driven by the development of specific components and enabling systems, techniques and infrastructure, such as electrical connections, and bespoke vessels and port facilities. in a number of floating wind-related projects and studies. Gavin spent three years as Senior Investment Analyst for a major European utility; prior to this, he worked as a Valuation & Business Modelling consultant for one of the big four accounting and consultancy firms. Affiliation Offshore Renewable Energy Catapult Inovo 121 George Street Glasgow G1 1RD, UK info@ore.catapult.org.uk http://ore.catapult.org.uk (Disclaimer: The results presented in Tables 1 and 2 are an amalgam of outputs from a number of different ORE Catapult projects, and are not representative of any one particular project or specific concept.) Copyright Windtech International Dr C Hofstede de Grootkade 28, 9718KB, Groningen, The Netherlands www.windtech-international.com