Fast Track Precast Concrete Pavement Rehabilitation Pilot Project

Similar documents
Jointed Precast Concrete Pavement

Precast Concrete Pavement

To: New York State Department of Transportation ENGINEERING INSTRUCTION. Approved:

B. Installation Instructions. Provide installation instructions, including any special equipment, to address the following.

POSTPRINT UNITED STATES AIR FORCE RESEARCH ON AIRFIELD PAVEMENT REPAIRS USING PRECAST PORTLAND CEMENT CONCRETE (PCC) SLABS (BRIEFING SLIDES)

4.1. Foremen 4.2. Concrete plant manager 4.3. Concrete plant operator 4.4. Personnel performing saw cutting and joint sealing

PCCP Preservation Steps to Take to Extend Pavement Life and Performance of Your Concrete Pavements

Precast Concrete Panels for Rapid Pavement Repair

TechBrief. Precast Concrete Panels for Repair and Rehabilitation of Jointed Concrete Pavements

Precast Concrete Pavement Background Concepts. Project 1517 FHWA, CTR & TxDOT Gary Graham November 15, 2001

Design and Construction of Highway Pavement Joint Systems

PERFORMANCE OF PRECAST CONCRETE PAVEMENTS

PD 3 Dowel Cradle. Load Transfer System Industrial Slab on Ground

Project No.: VTRC 06-R22 March Period Covered: Contract No.

ABCDE. TechBrief. Best Practices for Dowel Placement Tolerances

IGGA Guide Specification: Dowel Bar Retrofit (DBR) Introduction

Section 914. JOINT AND WATERPROOFING MATERIALS

Session 8: Load Transfer Restoration. (Dowel Bar Retrofit, Cross-Stitching, and Slot Stitching)

Precast Bridge. in only Eight Days. profile. Minimizing construction-related traffic delays and improving workzone

Concrete Pavement Preservation

Plate 60 ArmourMate. Joint Edge Protection INDUSTRIAL SLAB ON GROUND. Plate 60 AmourMate. Joint Edge Protection

This brochure is provided by:

A. Extent of structural precast concrete work is shown on drawings and in schedules.

Precast Bendable Concrete Paving Slab for Speedy Road Construction

shawprecastsolutions.com BEBO Arch Systems PRODUCT GUIDE & TECHNICAL REFERENCE MANUAL Providing the right solutions.

AMENDMENTS Manual of STANDARD SPECIFICATIONS. Adopted by Standard Specifications Committee. Amendment. No. 6. Published by

Double Bar Plate Dowels for Saw-Cut Contraction Joints

Chapter 3: APPLICATIONS FOR JOINTED PRECAST PAVEMENT SYSTEMS

FOAMED BITUMEN STABILISATION PROJECT WARWICK, QLD

Flanged Dowel Box. Load Transfer System INDUSTRIAL SLAB ON GROUND

AFRL-RX-TY-TR

RAIL PANEL AT TRANSITION SECTION PLAN - POST DETAIL PLAN - TUBE SPLICE. Colorado Department of Transportation. Staff Bridge Branch

Table 5G-2.01: Transverse Joint Requirements. Transverse Joint Type 6 C 12 7 C 15 8 CD CD CD 1 20

SPECIFICATIONS FOR THE MANUFACTURE AND DESIGN OF PRECAST THREE SIDED ARCH STRUCTURES, WINGWALLS AND HEADWALLS

Research. Maria Masten, P.E and Gordy Bruhn MnDOT Concrete Engineering Unit CPAM Concrete Paving Workshop March 9, 2017

Chapter 8 PRE-INSTALLATION PROCEDURES COMMON TO ALL SYSTEMS

Deep Creek Canyon US Highway 12

Diamond Dowel. Load Transfer System INDUSTRIAL SLAB ON GROUND

Full-Depth Concrete Pavement Repairs on the Ohio Turnpike

Precast Concrete Pavement Panels on Minnesota Trunk Highway 62 - First Year Performance Report

INDEX TO CLAUSES PART 1 - GENERAL

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

PERFORM WITH PRECISION WELDED DOWEL ASSEMBLY LOAD TRANSFER PRODUCTS CONCRETE CONSTRUCTION SOLUTIONS BROCHURE

TxDOT Project : Evaluation of Pavement Rutting and Distress Measurements

Dowel Bar Alignment and Location for Placement by Mechanical Dowel Bar Insertion

Jointing Rural Intersections

Plate Dowels. An Innovation Driven by Industrial Concrete Paving. Introduction

Hyper ArmourMate. Joint Edge Protection INDUSTRIAL SLAB ON GROUND

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS

Application Guidelines for Pavement Markings in Grooved Pavement Surfaces

Designer s NOTEBOOK CORNERS AND RETURNS

Construction Tolerances - The following tolerances apply to cast-in-place structures:

Texas Transportation Institute The Texas A&M University System College Station, Texas

CHAPTER 9: SYSTEM-SPECIFIC INSTALLATION PROCEDURES

² TL Beton-StB 07 = German technical conditions for construction materials for concrete road pavements

ABC and Innovative Bridge Construction for Minnesota Local Roads

Job Report Cold Milling. Wirtgen FCS Light: Increased flexibility and utilization of cold milling machines

AFRL-RX-TY-TR

1.1 RELATED DOCUMENTS

DATE: April 22, 2016 (CPR Details Revised & Dated April 22, 2016)

FRAMELESS GLASS FENCING DIY GUIDE

580 - NOISE BARRIERS OPSS 580 INDEX

Responses to Concrete Specifications Survey with Summary (2011)

CONSTRUCTION SPECIFICATION FOR MAINTENANCE HOLE, CATCH BASIN, DITCH INLET, AND VALVE CHAMBER INSTALLATION

R&T UPDATE. An Alternative to Traditional Round Dowel Bars Plate Dowel Innovations Driven by Industrial Concrete Paving

State-of-the-art Report On FULL-DEPTH PRECAST CONCRETE BRIDGE DECK PANELS (SOA )

Glass Fiber Reinforced Polymer (GFRP) Dowel Bars - Aslan 600

Large Scale CalArc Pavers for Sand-Set Pedestrian Use Installations

USE OF TEAR-OFF RECYCLED SHINGLES IN ASPHALT PAVEMENTS

PRECAST CONCRETE BRIDGE SUBSTRUCTURE COMPONENTS. Presented by: Matthew Youngblood, PE, SE Scott Noyer, PE Janssen & Spaans Engineering

Chapter 6: SHOP DRAWINGS AND OTHER SUBMITTALS

Design of structural connections for precast concrete buildings

SECTION MANHOLES

EKSPAN. Standard F Series Bearings. Description. Bearing types F series bearings are available in three forms - Typical 21F details.

B422 - PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS - OPSS 422

SECTION MANHOLES

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION

Economical paving of 4.0-m to 12.0-m wide concrete slabs. Slipform Paver SP 1200

Rodney Hunt. A GA Industries Company Glydaseal Gates

Section 7 Specification 7.2 Painted Roadway Lines TABLE OF CONTENTS

TECHNICAL MANUAL. OPTIMAJOINT Free Movement Joint. Free Movement Joint System for Heavy Traffic

TECHNICAL CORRECTION October Process Industry Practices Structural. PIP STF05121 Fabrication and Installation of Anchor Bolts

Practical Bolting and Gasketing for the Non Standard-Flanged Joint

Pioneers in Gate Design

1. CONNOLLY KEYJOINT 1. PRODUCT NAME 2. SUPPLIER 3. PRODUCT DESCRIPTION 4. KEY FEATURES 5. FIXING INSTRUCTIONS 6. SPECIFICATIONS 7.

1. Architectural precast concrete cladding units.

A. Rough carpentry includes but is not limited to the following:

6X3 Patio Garden Shed Assembly Manual

3400 Tectura Designs Precast Concrete

MANHOLES PART I: GENERAL. A. Precast Concrete Manholes

ALUMINUM PIPE GUIDERAIL 01/01/

Falling Weight Deflectometer

Dowel. Design. Performance-Based World of Concrete Official Show Issue. Lift-truck design changes require a new look at joint durability

SECTION SAND CUSHION TERRAZZO FLOORING

SECTION PRECAST CONCRETE SECTIONAL MANHOLES

SCI-FAB Product Specifications. Casework Section 1. Part 1 General

ARMTEC.COM. Built to last. Custom Precast Solutions For Your Home. Custom Steps Custom Decks Standard Steps Window Wells Brackets Stairwells

AASHTO TIG Promoting the use of Precast Concrete Pavement Systems. Highways for Life PCPS Showcase NJDOT, Mt. Arlington NJ Timothy J.

SECTION 39 - MANHOLES TABLE OF CONTENTS

6/19/2014. Milton Madison Bridge Slide. Project Partners. The Challenge. Aaron L. Stover, PE, SE Michael Baker Jr., Inc.

Transcription:

Fast Track Precast Concrete Pavement Rehabilitation Pilot Project Susanne Chan, M.A.Sc, P.Eng. Pavement Design Engineer, Ministry of Transportation Ontario Warren Lee, M.A.Sc, P.Eng. Pavement Design Engineer, Ministry of Transportation Ontario Becca Lane, P.Eng. Manager, Materials Engineering Research office, Ministry of Transportation Tom Kazmierowski, P.Eng Senior Consultant, Pavement and Materials Engineering, Golder Associates Ltd. Paper prepared for presentation at SES - Innovations in Pavement Management, Engineering and Technologies Session of the 2017 Conference of the Transportation Association of Canada St. John s, NL

ABSTRACT As Ontario s highway network expands and is subjected to increasing traffic volumes, the Ministry of Transportation Ontario (MTO) is challenged to look for new and innovative solutions to preserve and maintain the highway system. The ministry has identified a few high truck traffic sections having Average Annual Daily Truck Traffic (AADTT) greater than 25,000 that are experiencing progressively early rutting failure, and a few thick asphalt pavements experiencing full depth cracking. To reduce impacts to the travelling public, these high volume highways require all major maintenance and rehabilitation works to be performed under tight nightly construction closures. The typical rehabilitation holding treatment of mill and overlay at these locations may last only 3 to 5 years, rather than the expected 8 to 12 years, before the rutting and cracking return. Based on the progressively shorter lifecycles of this holding strategy, the ministry is investigating a potentially more life cycle friendly option of using overnight precast concrete mill and inlay techniques to mitigate this progressive rutting and cracking challenge. This paper describes an MTO pilot project using precast concrete slabs to rehabilitate a deep strength flexible pavement. The paper discusses how three different slab support systems were evaluated based on factors such as load transfer and ease of construction; the challenges of construction staging based on an 8 hours work window, with adaptations of horizontal and longitudinal joint details for the anticipated temporary and permanent works; lessons learned and next steps. Furthermore, the paper presents post construction roughness, load transfer efficiency and friction results of the tined longitudinal texture on the precast slabs. 1

1. INTRODUCTION The Ministry of Transportation Ontario (MTO) is challenged to look at innovations to preserve and maintain the highway system. Several high volume flexible highways are experiencing progressive early rutting failure with full depth cracking issues. The typical holding strategy used is mill and overlay with HMA, which lasts only 3 to 5 years, rather than the expected 8 to 12 years, before the rutting and cracking issues return. To reduce the construction impact to the travelling public, these locations require all maintenance and rehabilitation work be performed under tight nightly closures. With this operational constraint, MTO is interested in studying a new method for rehabilitation that has a longer service life but can still be installed during overnight construction windows. 2. BACKGROUND The ministry investigated a potentially more life cycle friendly use of precast concrete inlay on deep strength flexible pavement to mitigate the progressive rutting and cracking performance. The idea was inspired by the use of precast concrete slabs to repair existing concrete on some high volume composite pavements in the Toronto area. In 2004, MTO carried out its first trial project to evaluate construction techniques for precast concrete slab repairs on concrete/composite pavements. The initial trial was carried out on Highway 427, in Toronto (1). Based on MTO experience with this trial contract, a specification was developed and additional precast repair work carried out through the years. MTO has successful experience on the use of precast concrete repairs on concrete pavement, and this experience inspired the use of precast concrete slab to repair flexible pavement. 3. PROJECT LOCATION The pilot project is located on the northbound section of Highway 400 between the intersections of Highways 88 (to the south) and 89 (to the north). The 2013 average annual daily traffic (AADT) in both directions was estimated to be 87,300. Figure 1 below shows the approximate location of the pilot project. 2

Figure 1: Pilot Project Location on Highway 400 and between Highway 88 and 89 (Source: Google Map) 4. METHODOLOGY The pilot project used precast concrete slabs based on the Fort Miller Super-Slab Method. The hot mix asphalt (HMA) in lane 3 (outside lane) was milled partial depth and the precast slabs were placed within the milled-out recess. Three slab support methods or systems were employed for this pilot study: 1) Asphalt Supported Slab; 2) Graded Supported Slab; and 3) Grout Supported Slab. Also, long term monitoring instrumentation was installed as part of the work in partnership with University of Waterloo, Center for Pavement and Transportation Technology (CPATT). 4.1 Precast Concrete Slab Fabrication There were a total of 22 reinforced precast slabs required for this contract and they were fabricated in late August to early September 2016 at the Armtec production facility located in Mitchell, Ontario. To ensure good friction, sufficient micro and macro texture on the precast surface was mandatory. Several trials were performed on the precast concrete surface to produce an acceptable surface texture. The final surface texture was a broom finish, followed by longitudinal tining. Care was exercised to ensure a constant pressure was applied during the brooming and longitudinal tining processes to provide the required texture. Figure 2 below shows the precast concrete slab production. 3

Figure 2: Precast Slab Production 4.2 Design Considerations Cores of the site location were taken to ensure sufficient asphalt depth was available to provide uniform support of the precast slabs. Three cores indicated the northbound lane 3 asphalt thicknesses were 355, 375 and 375 mm. With a precast concrete slab of 205 mm, there was sufficient asphalt thickness to mill down and place the precast concrete inlay slab, with about 150 mm asphalt remaining as the base support. Figure 3 is the schematic of the precast concrete slab inlay repair of the flexible pavement. Figure 3: Precast Concrete Slab Repair Rehabilitation on Asphalt Pavement 4

The precast concrete slabs were 205 mm thick, 3.7 m wide (lane width) and 4.6 m long. Epoxycoated dowels at 300 mm centers were embedded at the transverse joints. The precast concrete was designed for 30 MPa at 28 days with 3% air void. The precast slab was reinforced by 2 mats of 15M bars at 300 mm spacing. Due to limited lane closure constraints, all the trial slabs needed to be installed over a few nights. To facilitate a better transition for the next night s operation, a temporary 1.0 meter longitudinal slab (sleeper slab) was employed. The temporary slab was placed over the exposed dowels to support traffic during the un-grouted condition. The temporary slab was removed prior to the next night s slab placement. Figure 4 below shows the schematic of the precast slab and temporary end slab details. Figure 5 below shows the temporary and permanent longitudinal joint details. The temporary HSS tube had been installed at the casting plant, but was removed after placing the slabs to facilitate the edge grouting. Figure 4: Precast Concrete Slab and Temporary End Slab Details 5

Figure 5: Temporary and Permanent Longitudinal Joint Details 5. CONSTRUCTION There were a total of 22 precast concrete slabs with three support methods used in this pilot study. The contractor planned to install 7 to 8 slabs for each of the three methods in three consecutive nights. Due to the tight timeline, the nightly activity needed to be well planned in advance to avoid any possible construction delay. Figure 6 below is the nightly construction activity schedule. Figure 6: Precast Concrete Trial Activity Schedule 6

The final site location and layout of the three installation methods was decided upon discussion with MTO, CPATT, the Consultant and the Contractor. Figure 7 below shows the planned layout of the installation method. Figure 7: Site Layout of the Three Support Methods The Contractor began the site layout on September 15 th, 2016, followed by saw-cutting of the perimeter of the asphalt area to be milled on September 19 th, 2016. 5.1 Option 1: Asphalt Supported Slab Method The first night of slab installation commenced on Sept 20 th, 2016 with the Asphalt Supported Slab method. This method requires the precast concrete slabs to be supported directly onto a precisely milled asphalt base and then grouted in place the following night. The milling machine was a Wirtgen Model W120 CFI, with a 1.2 m-wide milling head. Three passes of the milling unit were carried out to mill to the required width. (Figure 8) Figure 8: Wirtgen Milling Machine 7

Since the Asphalt Supported Slab method requires a precise milling depth of the asphalt (tolerance of ± 3 mm), the Fort Miller grade check apparatus was adopted to ensure milled surface tolerances were achieved prior to placing the slab (Figure 9). (2) Figure 9: Fort Miller Grade Checker Apparatus After first slab placement, the surface deferential between the adjacent lane surface and the precast slab surface was found to be approximately 9 mm. This was corrected by slab removal and additional milling of 12 mm based on the readings from Fort Miller s grade checker. The surface differential between adjacent slabs was found to be small (within ± 3 mm tolerance as required in the specification) for the remainder of the slabs. The CPATT instrumentation was installed beneath the fourth and eighth Asphalt Supported Slab. Figure 10 shows the installation of the precast concrete slab. 8

Figure 10: Precast Concrete Slab Installation (Asphalt Supported Slab) A total of 8 asphalt supported slabs were placed in approximately 1 hour 10 minutes, for an average placement time of approximately 9 minutes/slab. Following placement of the 8 slabs, the temporary end slab was then installed (Figure 11). The fast-setting bedding grouting, dowel grout and edge grout for longitudinal joints were applied the next night (Figure 12). Figure 11: Asphalt Supported Slab and Temporary End Slab 9

5.2 Option 2: Grade Supported Slab Method Figure 12: Pumping the Dowel Grout The Grade Supported Slabs were placed on September 21 st, 2016. This method involved milling of the asphalt, followed by placement, grading, and wetting of the cement-treated bedding material (CTBM) prior to placing the precast concrete slab on top. The same milling machine (Figure 8) and Fort Miller Grade Checker (Figure 9) were used as in the Asphalt Supported Slab method. The CPATT instrumentation was installed underneath the second and fourth slabs prior to placement of the CTBM. The CTBM was graded using a manual leveling screed and compacted using the plate tamper to the correct elevation. The material was wetted to begin hydration and the slabs were placed directly on this bedding layer (Figure 13). Figure 13: Compaction of the CTBM Grade Supported Slab Method A total of 7 grade supported slabs were placed in approximately 90 minutes, for an average of approximately 13 minutes/slab. Following placement of the 7 slabs, the temporary end slab was then installed. The edge grout for longitudinal joints was applied the next night. 10

5.3 Option 3: Grout Supported Slab Method The Grout Supported Slabs were placed on September 22 nd, 2016. This method used built-in leveling screws (or jacking bolts) which rested on the milled asphalt surface. These leveling screws have the capability of adjusting the level of the concrete slab to the required elevation, Quick setting bedding grout was then injected to support the slab. The same milling machine (Figure 8) used for the Asphalt Supported Slab method was used to remove the asphalt for this support method, and the CPATT instrumentation was installed prior to slab placement. Three grout mixers were used to produce the increased amount of bedding grout required to fill the void beneath the Grout Supported Slab. Figure 14 below shows the adjustment of the levelling screw for this method. Figure 14: Grout Supported Slab Levelling Screw and Adjustment A total of 7 grout supported slabs were placed in approximately 85 minutes, for an average placement time of approximately 12 minutes/slab. 5.4 Summary of Construction Table 1 below shows the summary of the construction timing and usage of bedding grout for each installation method. Table 1: Summary of Construction Activity Asphalt Supported Grade Supported Grout Supported Date Installed Sept 20, 2016 Sept 21, 2016 Sept 22, 2016 Milling time (min) 215 120 75 Slab Placement Time (min) 70 90 85 Time per Slab (min/slab) 9 13 12 Bedding Grout per slab (bags) 12 4 14 11

6. POST-CONSTRUCTION DATA ANALYSIS The post construction data collected right after construction included Falling Weight Deflectometer (FWD), friction and roughness testing. Out of the 22 slabs placed, only one slab did not meet the 3 mm tolerance and needed to be diamond ground as per the specification. 6.1 Falling Weight Deflectometer MTO retained a consultant to carry out the load transfer testing using the FWD at the transverse joints of the precast slabs. The testing was completed on October 6 and 7, 2016 according to ministry s requirement. (3) A total of 23 joints were tested for load transfer efficiency (LTE %) and void detection. Below is the summary table showing the FWD testing results. Table 2: FWD Testing Results Summary Outer Wheelpath (OWP) Inner Wheelpath (IWP) Joint Station Approach (LTE %) Leave (LTE %) Void Approach (LTE %) Leave (LTE %) Void 1 17+550 67.8 66.7 No 66.6 87.8 No 2 17+555 73.3 84.4 No 81 74.3 No 3 17+560 84.3 81.7 No 81.3 81.4 No 4 17+565 85.3 83.4 No 79.5 75.7 No 5 17+570 81.5 81.6 No 83.6 85.1 No 6 17+575 78.1 79.3 No 79.1 77.6 No 7 17+580 86 82.2 No 80.2 78 No 8 17+585 77.7 79.9 No 78 80.3 No 9 17+590 78.8 85.4 No 75.7 77.7 No 10 17+595 76.7 79.8 No 80.2 83.1 No 11 17+600 77.1 77.5 No 83.8 76.3 No 12 17+605 77.5 81 No 82.3 79.3 No 13 17+610 80.8 79.2 No 84.8 82.9 No 14 17+615 80 82.8 No 81.9 82.2 No 15 17+620 78.8 83.5 No 83.6 78.4 No 16 17+625 83.3 82.3 No 82.6 76.3 No 17 17+630 80.4 79.5 No 79.9 77.7 No 18 17+635 86.8 84 No 84 83.4 No 19 17+640 87.2 83.3 No 79.8 77.5 No 20 17+645 89.3 87.2 No 83.7 80.9 No 21 17+650 88 82.6 No 83.4 77.9 No 22 17+655 89 81.4 No 82.5 82 No 23 17+660 90 78.2 No 54.5 50.9 No 12

As a general practice, the load transfer is considered to be acceptable when LTE is greater than 70%. The average LTE for all 23 joints was 80.3%, which indicates a relatively good load transfer for this precast concrete slab placement. Breaking it down to the different installation methods, joint 2 to 9 for asphalt supported method achieved an average 80.4% LTE; joint 10 to 16 for grade supported method averaged 80.6% LTE; and joint 17 to 22 for grout supported method averaged 83% LTE. The first and last joints were not counted in the breakdown because those joints were adjacent to the asphalt with no load transfer device installed. Overall, all three methods of support provided good load transfer efficiency and no voids were encountered, with the grout supported method providing slightly better LTE when compared to the 2 other support methods. 6.2 Roughness Roughness was assessed by measuring the International Roughness Index (IRI) using the Automated Road Analyzer (ARAN). IRI is a roughness index with 0 mm/m representing a perfectly smooth pavement, and as the IRI increases, the measure represents a less smooth/rougher pavement. Typical IRI values for a concrete surface are higher than a HMA surface because the longitudinal profile measurement will capture the tining of the concrete surface resulting in a higher reading. The average IRI summarized in 10 m intervals for all the precast concrete inlay slabs was 2.14 mm/m and for the adjacent asphalt pavement was 0.76 mm/m. Table 3 below is the breakdown of the IRI result for each installation method, and it appears Grout Supported Slab method was smoother when compared to the other 2 methods. Table 3: Summary of IRI Result Asphalt Supported Grade Supported Grout Supported IRI (mm/m) 2.39 2.57 1.81 6.3 Friction Frictional resistance testing was performed using a locked wheel Friction Tester unit per ASTM E-274 with ASTM E 501 standard ribbed tire. The tined longitudinal texture provided friction numbers in excess of FN30. 7. LESSONS LEARNED Precast concrete slabs require a uniform base for support. The challenge of this pilot project was to precisely mill the asphalt to a specific depth and provide a uniform surface for the precast slab to sit on. Thus, precise surface measurement and milling head control is critical for the success of this process. Base on this pilot experience, it was found that milling slightly deeper is better than under milling. The specialized milling machine was able to meet the specified grade requirement of ± 3 mm and provide a uniform milled surface texture. 13

Manual chipping of localized high spots and chipping of the asphalt rounding from the milling head delayed installation by about 1 hour. Therefore, it is recommended that Bobcat mounted chipping equipment be used to significantly reduce the chipping time. The slabs should be broom finished and longitudinally grooved at the plant and then diamond ground or grooved on site as a post installation process. Saw cutting of longitudinal joints prior to milling is not needed; however, transverse end joints should be sawcut. The milling width dimension required over-milling by 75 mm to freely accommodate the precast slab. However, the installation process shows a need for only 25 mm of over-milling. With the narrower gap, the temporary longitudinal steel channel is not required. In addition, the use of the temporary 1 meter long end slab was a success to facilitate the next day s start up. In order to achieve full production speed, two crews with separate grout mixing equipment are required for the production of dowel grout and bedding grout as the two grouts haves different mixing consistency. It was found that grouting slabs in the same night before opening to traffic provided sufficient set time to achieve the required grout strength. 8. CONCLUSIONS AND RECOMMENDATIONS This pilot project of installing precast concrete inlay slabs on a milled flexible pavement structure was a success. A total of 22 precast concrete slabs using three different slab support systems were successfully placed on three consecutive nights as per schedule. When the base support was prepared, each slab placement took about 10 minutes. At full production speed, 30 to 40 slabs could be placed in an 8 hour construction window. Based on the post construction data collected to date, the Grout Supported Slab method is slightly superior in terms of load transfer and roughness. However, based on a constructability/cost perspective, the ministry prefers the Asphalt Supported Slab method as the final grading is achievable by the precision milling, and it does not require additional bedding grout. It is recommended that for future projects, the Asphalt Supported method be used incorporating embedded leveling screws in the precast slab as a contingency to correct any grade issues. Ongoing performance monitoring will be carried out by MTO. Instrumentation installed beneath all trial inlay slabs will be monitored by CPATT in partnership with MTO. Revisions to the specification based on the lessons learned, and standardizing the method of installation is required prior to full implementation.. 14

9. REFERENCES 1. Short Term Performance of Innovative Precast Concrete Slab Repairs on Highway 427, Toronto. Becca Lane and Tom Kazmierowski. Saskatoon, Saskatchewan : Transportation Association of Canada, 2007. 2. Tighe, Dan Pickel and Susanne. Precast Concrete Inlay Panel Installation on Highway 400: Construction Report. Waterloo, Ontario : CPATT, 2017. 3. Warren Lee, Fiona Leung, Susanne Chan and Becca Lane. Falling Weight Deflectometer (FWD) Testing Manual 2016 Edition. Toronto, ON : MTO, MERO, 2016. 10. ACKNOWLEDGEMENTS This trial project would not have been completed without the technical input and leadership of Stephen Lee, Head, Pavements and Foundations Section and the support of MTO Central Region Operations and Geotechnical Section, Bill Cung, Head of Geotechnical Section and Fouad Tannous, Geotechnical Engineer. 15