To: New York State Department of Transportation ENGINEERING INSTRUCTION. Approved:

Similar documents
B. Installation Instructions. Provide installation instructions, including any special equipment, to address the following.

IGGA Guide Specification: Dowel Bar Retrofit (DBR) Introduction

4.1. Foremen 4.2. Concrete plant manager 4.3. Concrete plant operator 4.4. Personnel performing saw cutting and joint sealing

Session 8: Load Transfer Restoration. (Dowel Bar Retrofit, Cross-Stitching, and Slot Stitching)

Jointed Precast Concrete Pavement

A. Extent of structural precast concrete work is shown on drawings and in schedules.

SPECIFICATIONS FOR THE MANUFACTURE AND DESIGN OF PRECAST THREE SIDED ARCH STRUCTURES, WINGWALLS AND HEADWALLS

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION

AMENDMENTS Manual of STANDARD SPECIFICATIONS. Adopted by Standard Specifications Committee. Amendment. No. 6. Published by

Design and Construction of Highway Pavement Joint Systems

POSTPRINT UNITED STATES AIR FORCE RESEARCH ON AIRFIELD PAVEMENT REPAIRS USING PRECAST PORTLAND CEMENT CONCRETE (PCC) SLABS (BRIEFING SLIDES)

CONSTRUCTION SPECIFICATION FOR MAINTENANCE HOLE, CATCH BASIN, DITCH INLET, AND VALVE CHAMBER INSTALLATION

Project No.: VTRC 06-R22 March Period Covered: Contract No.

3400 Tectura Designs Precast Concrete

14 March 2016 City Hall Station Renovations Bid Documents 15 th Street Station Phase Station Improvements SECTION PRECAST CONCRETE

Special Provision No. 904S14 October OPSS 904, January 1995, Construction Specification for Concrete Structures, is amended as follows:

SECTION MANHOLES

Section 914. JOINT AND WATERPROOFING MATERIALS

Precast Concrete Pavement Background Concepts. Project 1517 FHWA, CTR & TxDOT Gary Graham November 15, 2001

Fast Track Precast Concrete Pavement Rehabilitation Pilot Project

SECTION PRECAST CONCRETE SECTIONAL MANHOLES

Large Scale CalArc Pavers for Sand-Set Pedestrian Use Installations

Precast Concrete Pavement

Corrosion-Resistant Coated Dowel Bars

1. Architectural precast concrete cladding units.

SECTION COUNTERTOPS ecox PART 1 GENERAL

CONSTRUCTION SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS

BPDL Architectural precast concrete specifications USA TESTING AND INSPECTION A. Testing by Independent Agency : Materials and workmanship furn

Dowel Bar Alignment and Location for Placement by Mechanical Dowel Bar Insertion

SECTION 39 - MANHOLES TABLE OF CONTENTS

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 1990 EDITION

PCCP Preservation Steps to Take to Extend Pavement Life and Performance of Your Concrete Pavements

MANHOLES PART I: GENERAL. A. Precast Concrete Manholes

Standard Specifications

SECTION MANHOLES

SECTION 1085 PRECAST REINFORCED CONCRETE BOX CULVERT

Full-Depth Concrete Pavement Repairs on the Ohio Turnpike

2016 Specification Treads, Base, Stringers and other Amenities Wausau Tile Precast Epoxy Terrazzo

Chapter 6: SHOP DRAWINGS AND OTHER SUBMITTALS

CHAPTER 9: SYSTEM-SPECIFIC INSTALLATION PROCEDURES

Concrete Pavement Preservation

1. INTRODUCTION 2. REFERENCE SPECIFICATIONS. Page -1- Bonding and Grouting

CHAPTER 10 MICHIGAN DESIGN MANUAL BRIDGE DESIGN (SI) SHOP DRAWING REVIEW TYPES OF SHOP DRAWINGS Structural Steel

Glass Fiber Reinforced Polymer (GFRP) Dowel Bars - Aslan 600

NITTERHOUSE CONCRETE PRODUCTS, INC Molly Pitcher Highway South Chambersburg, PA

UNDERGROUND UTILITY TRENCHES AND VAULTS Page 1 of 6 ADDENDUM #1

SECTION 58 PRECAST CONCRETE BOX CULVERT. This work consists of furnishing and installing Pre-cast Concrete Box Culverts.

TechBrief. Precast Concrete Panels for Repair and Rehabilitation of Jointed Concrete Pavements

TABLE OF CONTENTS. 1.0 Scope. 2.0 References. 3.0 Definitions. 4.0 Submission and Design Requirements. 5.0 Materials 5.1 General 5.

CVO/169897A OCTOBER 29, GROUT

Australian Standard. Precast reinforced concrete box culverts. Part 1: Small culverts (not exceeding 1200 mm width and 900 mm depth) AS 1597.

Special Provision No. 999F29 March 2018 REQUIREMENTS FOR INSTALLATION OF METALLIC DOWELS INTO CONCRETE

SECTION SAND CUSHION TERRAZZO FLOORING

WAL-MART SUPERCENTER # ; Milwaukie, OR: SPECIFICATIONS. Revisions to Specification Fence

Table 5G-2.01: Transverse Joint Requirements. Transverse Joint Type 6 C 12 7 C 15 8 CD CD CD 1 20

² TL Beton-StB 07 = German technical conditions for construction materials for concrete road pavements

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1073 PRECAST CONCRETE CERTIFICATION PROGRAM JULY 20, 2018

SECTION STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 RELATED DOCUMENTS

MATERIALS DIVISION MEMORANDUM

SECTION ARCHITECTURAL PRECAST CONCRETE

Research A PERFORMANCE TESTING OF EXPERIMENTAL DOWEL BAR RETROFIT DESIGNS PART 1 INITIAL TESTING. Final Report

Chapter 8 PRE-INSTALLATION PROCEDURES COMMON TO ALL SYSTEMS

Proposal PROJECT MANUAL P R O P E R T Y M A N A G E M E N T F A L L O N C O U N T Y. Baker, MT P.O. Box 846

STRUCTURES FOR SANITARY AND STORM SEWERS

This brochure is provided by:

Precast Concrete Panels for Rapid Pavement Repair

Retrofit Dowel Bars in Jointed Concrete Pavement Long-Term Performance and Best Practices

AFRL-RX-TY-TR

A Solution to Cracking and Stresses Caused by Dowels and Tie Bars

ASLAN 600 GLASS FIBER REINFORCED POLYMER (GFRP) DOWEL BARS FOR LOAD TRANSFER IN CONCRETE SLABS

PERFORMANCE OF PRECAST CONCRETE PAVEMENTS

FASTENERS C O M P AT I B L E W I T H F E R O T I E S Y S T E M S. Which FERO Tie Systems Require Fasteners?

PART MATERIALS. Section Fencing Materials. Description

MH Table of Contents Standard Title/Scope Page Table of Contents SCE Public

Manholes Table of Contents

Edgerail Aluminum Bridge Railing System Specification & Installation Instructions

November 16, 2017 BOARD OF COUNTY COMMISSIONERS ORANGE COUNTY, FLORIDA. Y CH / Addendum #6 SHERRY DRIVE BRIDGE REPLACEMENT

EKSPAN. Standard F Series Bearings. Description. Bearing types F series bearings are available in three forms - Typical 21F details.

Scheduling, dimensioning, bending and cutting of steel reinforcement for concrete Specification

CITY OF LA MARQUE CHAPTER GRAPHIC REQUIREMENTS CONSTRUCTION PLAN AND MISCELLANEOUS REQUIREMENTS

SECTION ARCHITECTURAL PRECAST CONCRETE PART 1 - GENERAL

Diamond Dowel. Load Transfer System INDUSTRIAL SLAB ON GROUND

METRIC TT-B-1325C June 1, 1993 SUPERSEDING TT-B-1325B April 25, 1978 FEDERAL SPECIFICATION BEADS (GLASS SPHERES) RETRO-REFLECTIVE

Precast Concrete Pavement Panels on Minnesota Trunk Highway 62 - First Year Performance Report

TYPE 4-C TYPE 6 TYPE 7 TYPE 8

AFRL-RX-TY-TR

StormTrap Guide Specification. StormTrap SingleTrap on Pad Foundation Groundwater BELOW Invert Revised 11/21/18

Flanged Dowel Box. Load Transfer System INDUSTRIAL SLAB ON GROUND

City of Regina Standard Construction Specification SECTION 2999 LISTING OF ROADWAY STANDARD DRAWINGS

STANDARD SPECIFICATIONS SECTION PRECAST CONCRETE 1.2 REQUIREMENTS FOR MANUFACTURERS AND SUPPLIERS BEFORE DELIVERY

Precast Bridge. in only Eight Days. profile. Minimizing construction-related traffic delays and improving workzone

1.1 RELATED DOCUMENTS

JVI Vector Connector

Item 550 Chain Link Fence

SPECIFICATIONS FOR THE INSTALLATION OF CONDUIT SYSTEMS IN RESIDENTIAL SUBDIVISIONS. Notification of Completed Conduit Sections

SECTION G ESTIMATE OF QUANTITIES

PERFORM WITH PRECISION WELDED DOWEL ASSEMBLY LOAD TRANSFER PRODUCTS CONCRETE CONSTRUCTION SOLUTIONS BROCHURE

W DESIGN ASSOCIATES. Consulting Engineers & Architects McCook, Nebraska Hastings, Nebraska 68901

2' x 3' Polymer Pull Box Cover 4'-0" 7'-0" 24" x 76" Access Opening 3'-6"

Joint with Bent Dowels. David Cronin, P.E. City Engineer. Jason Hoskinson, P.E., PTOE BG Consultants, Inc. DATE: January 23, 2014

Transcription:

To: New York State Department of Transportation ENGINEERING INSTRUCTION Title: PRECAST CONCRETE PAVEMENT SLAB SYSTEMS STANDARD SPECIFICATION Distribution: Manufacturers (18) Local Govt. (31) Agencies (32) Surveyors (33) Consultants (34) Contractors (39) ( ) Approved: /s/ Robert L. Sack Robert L. Sack, Deputy Chief Engineer, Technical Services EI 05-041 21DEC05 Date ADMINISTRATIVE INFORMATION: This Engineering Instruction (EI) is effective beginning with projects submitted for the letting of 09/07/2006. No EIs or Engineering Bulletins are hereby superseded. The shelf note transmitted by this EI, 704-15 Precast Concrete Pavement Slab Systems, will be incorporated into a future revision of the Standard Specifications. PURPOSE: To issue a new specification for precast concrete pavement slab production. TECHNICAL INFORMATION: The following are issued concurrently: EI 05-043, Precast Concrete Pavement Slab Systems - Design Guidance. EI 05-042, Precast Concrete Pavement Slab Systems Special Specification. The Materials Bureau will generate an approved list of precast concrete pavement slab systems and their designers. IMPLEMENTATION: The Design Quality Assurance Bureau will insert the transmitted shelf note into contract proposals beginning with projects submitted for the letting of 09/07/2006. Standard Specification 704-15 Precast Concrete Pavement Slab Systems, is approved by this EI. TRANSMITTED MATERIALS: A shelf note, 704-15 Precast Concrete Pavement Slab Systems, is attached to this EI. BACKGROUND: Precast concrete slabs have been used in New York since 2000 without any governing specifications. The transmitted shelf note details production requirements. CONTACT: Address questions concerning this issuance to the Materials Bureau. Current contacts are James Reidy (jreidy@dot.state.ny.us) at (518) 457-4591, Michael Brinkman (mbrinkman@dot.state.ny.us) at (518) 457-4584, or William Cuerdon (wcuerdon@dot.state.ny.us) at (518) 485-5278.

Make the following changes to the Standard Specifications of January 2, 2002. Page 7-45, line 41, insert the following: 704-15 PRECAST CONCRETE PAVEMENT SLAB SYSTEMS SCOPE. This specification covers material and fabrication requirements for precast concrete pavement slab systems. Approved systems can be supplied by any manufacturer appearing on the Department s Approved List entitled Precast Concrete Manufacturers Approved for QC/QA Production Groups 1 & 6, provided they obtain approval from the system designer. SYSTEM APPROVAL. For Approved List consideration, the system designer must submit the following information to the Materials Bureau. After the Materials Bureau reviews the submitted information, the system designer will be required to perform a trial installation as detailed herein. A. Fabricator Standard Drawings. Apply 704-03, Precast Concrete General. Include the following details: Transverse joint support type, locations, spacing, and the mechanism used to transfer loads across transverse joints after slabs are placed. Longitudinal joint tie type, locations, spacing and the mechanism used to tie adjacent slabs together. Lifting insert type, location, positioning, and capping or backfill method. Grout port type, location, positioning, and capping or backfill method. B. Installation Instructions. Provide installation instructions, including any special equipment, to address the following. 1. Subbase Preparation. Instructions for any recommended subbase preparation. 2. Slab Installation. Instructions for lifting, moving, protecting, lowering, and adjusting the slabs into position. 3. Bed and Level Slabs. Instructions to ensure slabs are fully supported by underlying layers at the correct line, grade, and cross slope while meeting contract smoothness requirements. Slabs may be either: Placed on a precisely graded bedding layer and grouted in-place to fill any small, isolated voids between the slabs and bedding layer (grade-supported). Placed or held near final position and jacked into place (grout-supported). Placed by other methods approved by the Director, Materials Bureau. For grade-supported slabs, include all pertinent bedding and leveling instructions, including: Bedding material composition and gradation. Bedding grout mix design and anticipated strength gain. Bedding grouts must develop a minimum compressive strength of 4 MPa in 12 hours. Method used to place the bedding material and grout beneath the slab. Method used to ensure complete bedding when placed. EI 05-041 Page 1 of 4 L 09/07/2006

For grout-supported slabs, include all pertinent bedding and leveling instructions, including: Material properties, composition, mix design, and anticipated strength gain of any slabjacking material. Method used to place the slab-jacking material beneath the slab. Method used to ensure complete slab contact with jacking material when placed. 4. Backfilling Pavement Hardware. Instructions to completely encase load transfer devices, longitudinal joint ties, lifting inserts, and grout ports. Include all pertinent information, including: Material properties, composition, mix design, and anticipated strength gain of any backfill material that is not named in Backfill Material for Pavement Hardware, or, revised instructions for those materials if the manufacturer s instructions are not followed. Method used to place backfill material. Method used to ensure complete hardware encasement. Subsequent to system approval, any change to approved installation instructions must be submitted to, and approved by, the Director, Materials Bureau, to maintain Approved List status. The Department reserves the right to require additional trial installations if the changes are deemed significant. C. Trial Installation. Perform a trial installation at a facility agreeable to the Regional Materials Engineer that is within a 1-hour drive of a Regional Materials Laboratory. Ensure Materials Bureau and Regional Materials personnel are present. Place 4 (minimum) 3.67 m x 3.67 m slabs simulating 2 lanes of traffic. Provide a drill rig, with operator, capable of retrieving 100 mm diameter cores through any portion of the slab, and a technician capable of fabricating test specimens in accordance with Test Method NY 701-13P, C, Concrete Repair Material. As a minimum, the following will be evaluated: 1. Bedding Grout Properties and Completeness of Placement. Fabricate 24 cubes meeting Test Method NY 701-13P, C, Concrete Repair Material. 2. Leveling Material Properties and Completeness of Placement. Fabricate 24 cubes meeting Test Method NY 701-13P, C, Concrete Repair Material. 3. Backfill Material Properties and Completeness of Placement. If a material identified in this specification as Backfill Material for Pavement Hardware (under Material Requirements) is used in accordance with the manufacturer s written instructions, no further material testing is required. If a different material is used (or if a material is not used in accordance with the manufacturer s instructions), fabricate a sufficient amount of test specimens to determine the properties identified in Table 704-15-1, Backfill Material Requirements, when tested in accordance with Test Method NY 701-13P, C, Concrete Repair Material. 4. Dimensions and Tolerances. Slabs must conform to the Fabricator Standard Drawings and be capable of being placed in an essentially true plane. 5. Instruction Completeness. Manufacturer s instructions must accurately reflect the processes used in the trial installation. 6. Load Transfer Efficiency (LTE). The Department reserves the right to conduct falling weight deflectometer testing to determine LTE at the joints. Poor LTE ( 70 %) is cause for rejection. EI 05-041 Page 2 of 4 L 09/07/2006

MATERIAL REQUIREMENTS. Apply 704-03, Precast Concrete General, except as noted herein. A. Concrete. Use concrete having a minimum 28-day compressive strength of 30 MPa unless noted otherwise in the contract documents or approved fabrication drawings. Use aggregate meeting the friction requirements of Sections 501, Portland Cement Concrete General, and 502, Portland Cement Concrete Pavement, for precast slabs that will remain concrete surfaced. Friction aggregate type is identified in the contract documents by pay item. B. Reinforcement. Use bars meeting 709-04, Epoxy-Coated Bar Reinforcement, Grade 420. As a minimum, fabricate slabs with single-mat reinforcement located in the bottom third of the slab. Provide 50 mm (minimum) concrete cover between the mat and the slab bottom. Fabricate mats using a size and spacing of steel (in both directions) that results in a steel area to cross-sectional area ratio of 0.0018 (minimum). Maximum bar spacing is 450 mm. The manufacturer may provide additional reinforcement based on jobsite loading conditions. (A typical example is when slabs must be loaded before a bedding grout is placed.) C. Backfill Material for Pavement Hardware. If the precast slab system requires a backfill material around pavement hardware, use DBR Retrofit Mortar, HD-50, Five Star Highway Patch, or an alternate prepackaged material submitted as an approved equal. If the brands named above are mixed in accordance with their manufacturer s written instruction, no further testing is required. If the manufacturer s written instructions are not followed, or if an alternate material is proposed for use, the material must meet Table 704-15-1, Backfill Material Requirements, when tested in accordance with Test Method NY 701-13P,C, Concrete Repair Material. Material submission instructions can be found at the Department s web site, www.dot.state.ny.us, under Approved List of Materials and Equipment Submission Instructions. TABLE 704-15-1 BACKFILL MATERIAL REQUIREMENTS Property Minimum Maximum Compressive Strength, Opening to Traffic 17 MPa - Compressive Strength, 28 Day 28 MPa - Expansion - 0.40 % Contraction - 0.05 % Freeze - Thaw Loss (25 cycles at 10% NaCl) - 1.0 % Bond Strength (to dry PCC) 2.1 MPa - Initial Set Time 15 minutes - Chloride Content - 0.05 % Sulfate Content - 5.0 % DRAWINGS. Apply 704-03 Precast Concrete General, except as noted herein. Provide job-specific Fabricator Working Drawings, from the system designer, for each contract. Use these drawings, in conjunction with approved Fabricator Standard Drawings, to manufacture the pavement slabs. Copies of approved working drawings will be returned to the system designer. If the manufacturer is not the system designer, include the manufacturer s name, address, and telephone number on the drawings. FABRICATION. Apply 704-03, Precast Concrete General, except as noted herein. EI 05-041 Page 3 of 4 L 09/07/2006

Texture. Apply 502-3.10, Texturing, to the top surface of the slab. Curing. When membrane curing compound is the selected curing method and the slabs are exposed to sunlight while curing, use a white pigmented membrane curing compound from the Department s Approved List instead of a clear compound with fugitive dye. SAMPLING AND TESTING. Apply 704-03, Precast Concrete - General. MARKING. Apply 704-03, Precast Concrete - General. FINAL PRODUCTION INSPECTION. Apply 704-03, Precast Concrete - General. SHIPPING. Apply 704-03, Precast Concrete - General. BASIS OF ACCEPTANCE. Apply 704-03, Precast Concrete General, and the following: The system must appear on the Department s Approved List entitled Precast Concrete Pavement Slabs Systems ( 704-15). Written approval from the system designer to use the approved system if the manufacturer is not the system designer. EI 05-041 Page 4 of 4 L 09/07/2006