WishTown, Noida PLANNED COMPLETION SCHEDULE [Residential s] [PHASE III (95 s) having 8,953 Units]
Total of s at WishTown, Noida are 291 out of which 59 s (5,283 Units) have been Handed Over in Phase I. Planned Completion Schedule for Phase II (70 s) having 6,572 Units was released on 29 th -April-2017. This Planned Completion Schedule is for Phase-III (95 s) having 8,953 Units. Name and ID s of along with respective s have been mentioned against each. Planned Completion Schedule for balance 67 s will be released by 1 st June 2017. Monthly Progress Update for s will be available on the website from July 2017 onwards.
Project wise breakup of 95 s of Phase III Project of s Planned to be Completed during Phase - III 1 Kasa Isles (KSI) 15 2 Kensington Boulevard (KBA) 21 3 Kensington Park & Heights (KPA) 14 4 Klassic (KLC) 3 5 Kosmos (KM) 23 6 Krescent Homes (KRH) 6 7 Pebble Court (PB) 4 8 Knight Court (KGT) 8 9 Pavilion Court (PVC) 1 Total 95 s
Project: Kasa Isles (KSI) wise Planned Completion Schedule 1 KSI1 OCT - DEC 2018 A. P. Singh 2 KSI2 OCT - DEC 2018 - do - 3 KSI4 OCT - DEC 2018 - do - 4 KSI14 OCT - DEC 2018 - do - 5 KSI3 OCT - DEC 2019 - do - Anshul Grover & kasaisles@jalindia.co.in 6 KSI5 OCT - DEC 2019 - do - 7 KSI6 OCT - DEC 2019 - do - Chandan Ghosh 8 KSI7 OCT - DEC 2019 - do - 9 KSI8 OCT - DEC 2019 - do - 10 KSI9 OCT - DEC 2019 - do - 11 KSI10 OCT - DEC 2019 - do - 12 KSI11 OCT - DEC 2019 - do - 1. The Planned Completion Schedule represents the time by which the will be ready for applying
Project: Kasa Isles (KSI) (contd.) wise Planned Completion Schedule 13 KSI12 OCT - DEC 2019 A. P. Singh Anshul Grover & 14 KSI15 OCT - DEC 2019 - do - Chandan Ghosh kasaisles@jalindia.co.in 15 KSI16 OCT - DEC 2019 - do - 1. The Planned Completion Schedule represents the time by which the will be ready for applying
Project: Kensington Boulevard (KBA) wise Planned Completion Schedule 1 KBA 2 JUL - SEP 2018 Vikas Kumar 2 KBA 3 JUL - SEP 2018 - do - 3 KBA 5 OCT - DEC 2018 - do - 4 KBA 9 OCT - DEC 2018 - do - 5 KBA 10 OCT - DEC 2018 - do - Aparna Bajpai & 6 KBA 1 JAN - MAR 2019 - do - Bhoopesh Sharma kensingtonboulevard@jalindia.co.in 7 KBA 8 JAN - MAR 2019 - do - 8 KBA 6 APR - JUN 2019 A. K. Rana 9 KBA 11 APR - JUN 2019 - do - 10 KBA 12 APR - JUN 2019 - do - 11 KBA 14 APR - JUN 2019 - do - 1. The Planned Completion Schedule represents the time by which the will be ready for applying
Project: Kensington Boulevard (KBA) (contd.) wise Planned Completion Schedule 12 KBA 15 APR - JUN 2019 A. K. Rana 13 KBA 16 APR - JUN 2019 - do - 14 KBA 17 APR - JUN 2019 - do - 15 KBA 18 APR - JUN 2019 - do - 16 KBA 20 JUL - SEP 2019 - do - Aparna Bajpai & 17 KBA 4 OCT - DEC 2019 - do - Bhoopesh Sharma kensingtonboulevard@jalindia.co.in 18 KBA 7 OCT - DEC 2019 - do - 19 KBA 19 OCT - DEC 2019 - do - 20 KBA 21 OCT - DEC 2019 - do - 21 KBA 22 OCT - DEC 2019 - do - 1. The Planned Completion Schedule represents the time by which the will be ready for applying
Project: Kensington Park & Heights (KPA) wise Planned Completion Schedule 1 KPA 11 JUL - SEP 2018 Sandeep Agarwal 2 KPA 12 JUL - SEP 2018 - do - 3 KPA 14 JUL - SEP 2018 - do - 4 KPA 15 JUL - SEP 2018 - do - 5 KPH 1 OCT - DEC 2018 - do - Bhoopesh Sharma & kensingtonapartments@jalindia.co.in 6 KPH 2 OCT - DEC 2018 - do - Sapna Singh 7 KPH 3 OCT - DEC 2018 - do - 8 KPA 7 OCT - DEC 2018 - do - 9 KPA 5 JAN - MAR 2019 - do - 10 KPA 6 JAN - MAR 2019 - do - 11 KPA 10 APR - JUN 2019 - do - 1. The Planned Completion Schedule represents the time by which the will be ready for applying
Project: Kensington Park & Heights (KPA) (contd.) wise Planned Completion Schedule 12 KPA 16 APR - JUN 2019 Sandeep Agarwal Bhoopesh Sharma & kensingtonapartments@jalindia.co.in 13 KPA 8 JUL - SEP 2019 - do - Sapna Singh 14 KPA 9 JUL - SEP 2019 - do - 1. The Planned Completion Schedule represents the time by which the will be ready for applying
Project: Klassic (KLC) wise Planned Completion Schedule 1 KLCD04 APR - JUN 2019 K. P. Singh 2 KLCD05 APR - JUN 2019 - do - Meenakshi Verma & 3 KLCD06 APR - JUN 2019 - do - Ranjit Kumar klassic@jalindia.co.in 1. The Planned Completion Schedule represents the time by which the will be ready for applying
Project: Kosmos (KM) wise Planned Completion Schedule 1 KM44 JUL - SEP 2018 Shahid Ali 2 KM45 JUL - SEP 2018 - do - 3 KM47 JUL - SEP 2018 - do - 4 KM60 JUL - SEP 2018 K. P. Singh 5 KM70 JUL - SEP 2018 - do - Varun Talreja & kosmos@jalindia.co.in 6 KM71 OCT - DEC 2018 - do - Nivedita 7 KM23 OCT - DEC 2018 Shahid Ali 8 KM24 OCT - DEC 2018 - do - 9 KM25 OCT - DEC 2018 - do - 10 KM26 OCT - DEC 2018 - do - 11 KM46 OCT - DEC 2018 - do - 1. The Planned Completion Schedule represents the time by which the will be ready for applying
Project: Kosmos (KM) (contd.) wise Planned Completion Schedule 12 KM67 OCT - DEC 2018 K. P. Singh 13 KM68 OCT - DEC 2018 - do - 14 KM69 OCT - DEC 2018 - do - 15 KM72 OCT - DEC 2018 - do - 16 KM72A OCT - DEC 2018 Mukesh Gupta 17 KM72B OCT - DEC 2018 - do - Varun Talreja & kosmos@jalindia.co.in 18 KM66 JAN - MAR 2019 K. P. Singh Nivedita 19 KM72C JAN - MAR 2019 Mukesh Gupta 20 KM79 JAN - MAR 2019 - do - 21 KM79A JAN - MAR 2019 - do - 22 KM79B JAN - MAR 2019 - do - 23 KM80 JAN - MAR 2019 - do - 1. The Planned Completion Schedule represents the time by which the will be ready for applying
Project: Krescent Homes (KRH) wise Planned Completion Schedule 1 KRH 16 JUL - SEP 2019 Akhilesh Kr. Singh 2 KRH 14 JUL - SEP 2019 - do - 3 KRH 15 JUL - SEP 2019 - do - 4 KRH 10 JUL - SEP 2019 Salimuddin Khan 5 KRH 11 JUL - SEP 2019 - do - 6 KRH 12 JUL - SEP 2019 - do - Anand Kumar Dubey & Amrita Singh krescenthomes@jalindia.co.in 1. The Planned Completion Schedule represents the time by which the will be ready for applying
Project: Pebble Court (PB) wise Planned Completion Schedule 1 PB 1 JUL - SEP 2018 Ashok Sharma 2 PB 2 OCT - DEC 2018 - do - Sunil Singh & kasablanca@jalindia.co.in 3 PB 3 OCT - DEC 2018 - do - Achila Bhatt 4 PB 4 OCT - DEC 2018 - do - 1. The Planned Completion Schedule represents the time by which the will be ready for applying
Project: Knight Court (KGT) wise Planned Completion Schedule 1 KGT1 OCT - DEC 2018 Vikas Kumar 2 KGT2 OCT - DEC 2018 - do - 3 KGT3 OCT - DEC 2018 - do - 4 KGT4 JAN - MAR 2019 - do - Amit Sharma & knightscourt@jalindia.co.in 5 KGT5 JAN - MAR 2019 - do - Sunil Singh 6 KGT6 JAN - MAR 2019 - do - 7 KGT7 JAN - MAR 2019 - do - 8 KGT8 JAN - MAR 2019 - do - 1. The Planned Completion Schedule represents the time by which the will be ready for applying
Project: Pavilion Court (PVC) wise Planned Completion Schedule Project Manager 1 PVC005B OCT - DEC 2018 Arvind Kumar Chandan Ghosh pavilion@jalindia.co.in 1. The Planned Completion Schedule represents the time by which the will be ready for applying