WHITE ROSE DEVELOPMENT PROJECT. Canada-Newfoundland and Labrador Benefits Report. For the Period April 1 June 30, 2004

Similar documents
WHITE ROSE OILFIELD DEVELOPMENT APPLICATION

Commercial. Committee. Technical Planning. Committee. Development and Construction. Operations

6.1 Management, Engineering, Procurement and Administrative Support

Husky Energy East Coast Update

2 THE PROPOSED WHITE ROSE OILFIELD DEVELOPMENT 2.1 PROJECT DESCRIPTION

Overview. One of Canada s largest integrated energy companies. Headquarters in Calgary, Alberta. Permanent Employees: ~5,000

WHITE ROSE OILFIELD COMPREHENSIVE STUDY REPORT SUBMITTED BY:

Husky White Rose Development Project. New Drill Centre Construction & Operations Program. Project Description

4 DEVELOPMENT AND PRODUCTION SCENARIOS

Technological and Logistical Challenges during Construction & Installation of Deepwater Mega Subsea Development in West Africa

Husky Energy - Development Plan Amendment Application. White Rose Extension Project. Public Review. Noia s Submission

Rig worker (CBC Newfoundland and Labrador) Oil and Gas

3 ASSESSMENT METHODOLOGY

Overview of the C-NLOPB and the Can-NL Offshore Oil and Gas Industry. Sean Kelly MA, APR, FCPRS May 15, 2017

Offshore Construction Management Services. Capability & Experience

OFFSHORE PETROLEUM: NEWFOUNDLAND CASE STUDY. Mark Shrimpton Jacques Whitford

REPLACING FULL MOORING SYSTEM FOR COOEC IN THE SOUTH CHINA SEA

Global Energy Group s multi-client contract showcases UK-based engineering talent to achieve first oil for Catcher

The Regulator s Perspective on the Canada-Newfoundland and Labrador Offshore Oil and Gas Industry

VIRTUS CONNECTION SYSTEMS Advanced Diverless Connection Solutions for any Subsea Field Application

Local Contribution to the Aasta Hansteen development

Bay du Nord Framework Agreement

Offshore Drilling Rigs

Gulfstar One FPS. Nathan Davidson. February 26, 2015

Statement of Qualifications

Husky s Focus on East Coast Exploration and Production

Next Generation FPSO: The Engineering & Construction Contractor Solution

SOCIO-ECONOMIC BENEFITS FROM PETROLEUM INDUSTRY ACTIVITY IN NEWFOUNDLAND AND LABRADOR

Department of Natural Resources Petroleum Development Activity Report

InterMoor Innovation in Action. InterMoor: USA Mexico Brazil Norway Singapore & Malaysia UK West Africa

Local Content Development in Newfoundland and Labrador

Implementing FPSO Digital Twins in the Field. David Hartell Premier Oil

Oceans of Information

Opportunities and Challenges in Deepwater West Africa Projects

Marginal Field Development Concept

Prelude FLNG Project. DOT conference presentation. November Jaap de Vries, Prelude FLNG Project Director FINAL

FLNG Opportunities for WA A Contractor s Perspective. Sam ALLEN Managing Director, Technip in Australia Perth, 12 March 2015

Managing Offshore Field Development & Marine Asset October 2017 Dubai, United Arab Emirates

Offshore Development Concepts: Capabilities and Limitations. Kenneth E. (Ken) Arnold Sigma Explorations Holdings LTD April, 2013

Offshore Engineering. Design, Fabrication, Installation, Hook-up and Commissioning September 2017 Dubai, United Arab Emirates

Marine Well Containment Company Outer Continental Shelf Summer Seminar

Subsea Positioning In deep water

Swiber Holdings Limited 1Q FY08 Results Briefing

FPSO Engineering. From Concept to Commissioning. Iv-Oil & Gas

Canada-Newfoundland and Labrador Benefits Annual Report 2013

FSRU READY FOR THE FUTURE?

The use of an integrated contract model (iepci) for Subsea developments

Dagang Zhang China-America Frontiers of Engineering Symposium San Diego, USA

Floating Systems. Capability & Experience

Engineering. Drafting & Design. Regulatory Interface. Project & Construction Management. Marine Operations Services

Statoil Canada Ltd Exploration Drilling Program MOU West Aquarius

Enabling Local Innovation. Scott Tessier, Chair and Chief Executive Officer NewLeef, October 2016

Investor Update. April 14, 2015

Engineering Procurement Construction Installation. Company Profile.

The World Floating Production Report

Dry trees for cost effective solution with the Wellhead Barge: WHB

Subsea Structural Engineering Services. Capability & Experience

Workshop: Examining the Science & Technology Enterprise in Naval Engineering

FPSO Update for NOIA 2012 Fall Meeting

Deep Panuke Project Update CORE 2009 Dave Kopperson, Vice President, Atlantic Canada

FPSO Design and Technology

Orbost Gas Plant Upgrade Project Community Information Sessions. 18 & 19 September 2018

Oil&Gas Subsea Production

A marginal field (re-)development using several alternative methodologies 1

MOORING SOLUTIONS IN ASIA PACIFIC A SINGLE, LOCAL SOURCE OF MOORING, POSITIONING AND RIG MOVING SERVICES

Goliat FPSO Marine Installation Execution Highlights and Learnings

Offshore. Christian Tribout Senior Vice President, Offshore. Investor Presentation Paris, October 17, New York, October 19, 2007

Mooring Capabilities. Angola Brazil Egypt Equatorial Guinea Malaysia Mexico Norway Singapore United Kingdom United States

Angola Brazil Mooring Egypt Equatorial Guinea Capabilities Malaysia Mexico Norway Singapore United Kingdom United States

Mooring Capabilities. Angola Brazil Egypt Equatorial Guinea Malaysia Mexico Norway Singapore United Kingdom United States

3D OFFSHORE PROJECT SIMULATION. Singapore Shipyard. Replace all chain. Adding a riser

Floating LNG facilities

Oil & Gas Activity in the Canadian Arctic and Eastern Canada Activity

2016 Employee Product Education Courses

PRESS KIT IVAR AASEN DET NORSKE OLJESELSKAP ASA

Offshore Engineering. Design, Fabrication, Installation, Hook-up and Commissioning Sep 2017, Dubai

BENEFITS TO THE WEST COAST FROM OFFSHORE INDUSTRY

Subsea UK Neil Gordon Chief Executive Officer Championing the UK Subsea Sector Across the World

Marine Risers. Capability & Experience

Subsea 7 Norway. Monica Th. Bjørkmann Sales and Marketing Director

Learn more at

Offshore Decommissioning Conference Fairmont Hotel, St Andrews 8 th October 2014

Discipline. Technology TECHNOLOGY DEVELOPMENT. Technology WITHIN SBM OFFSHORE

QUARTERLY UPDATE. Summary

NO. ONGC/EOA/KG-DWN-98/2 Cluster 2/ONSHORE/EOI/2016/ Date: EXPRESSION OF INTEREST (EOI)

Catcher field partners. Contents. 50% (operator)

Capital Marked Presentation. Dof Subsea Atlantic Region

Technip Floating Production: A Comprehensive Portfolio

Project Management Leads to Zero NPT: How Total E&P Angola and Halliburton Successfully Managed the CLOV Lower Completion Campaign

Deepwater Mooring Deeper and Leaner

Click to edit Master title style APPEA AWIC UPDATE. Self Audit Checklist Source Control First Response

Development of Floating Exploration & Production Solutions for Remote and Arctic Environments

MPF1000 Multi Purpose Floater. 24 April 2007

ACTEON FLS - DECOMMISSIONING

0 Minister of Public Works and Government Services Canada 1997 ISBN : o Cat. No.: En /l 997E

MAERSK SUPPLY SERVICE. Actively taking part in solving the energy challenges of tomorrow

One Ocean Oil Spill Prevention and Response Initiative: Application of Gulf of Mexico Key Findings to the Newfoundland and Labrador Region

ENVIRONMENTAL ASSESSMENT (EA) PROCESS

Experienced project management Total flexibility of the workforce Modern drydocking facilities

Well Integrity Life Cycle Management for Subsea Field Development A Regulator s Perspective

Transcription:

WHITE ROSE DEVELOPMENT PROJECT Canada-Newfoundland and Labrador Benefits Report For the Period April 1 June 30, 2004 HDMS ID: 003839954

TABLE OF CONTENTS 1.0 INTRODUCTION... 1 2.0 SUMMARY OF PROJECT ACTIVITIES... 2 2.1 Husky Project Management... 2 2.2 FPSO Project Management & Operations... 2 2.3 Hull... 2 2.4 Topsides... 2 2.5 Offshore Installation... 3 2.6 Subsea... 3 2.7 Drilling and Completions... 3 2.8 Transportation... 3 2.9 Logistics... 4 3.0 EMPLOYMENT SUMMARY... 5 3.1 Employment by Residence Status... 5 3.2 Employment by Location (Person Hours)... 5 4.0 PROJECT EXPENDITURE... 6 August 2004 Page i HDMS ID: 003839954

1.0 INTRODUCTION The following represents Husky Energy s (Husky s) Canada-Newfoundland and Labrador Benefits Report for the quarter ending June 30, 2004, as required under the Conditions set out in Decision 2001.01 for the White Rose Development Project. This report provides a summary of progress/activities related to the Project for the period with the exception of Project expenditures, which are captured for the period February 1, 2002 to June 30, 2004. August 2004 Page 1 HDMS ID: 003839954

2.0 SUMMARY OF PROJECT ACTIVITIES Canada-Newfoundland and Labrador Benefits Report This section provides progress information for major Project components during the period April 1 to June 30, 2004. 2.1 Husky Project Management Since arriving in Marystown, Newfoundland and Labrador, the SeaRose FPSO has undergone preparatory work in anticipation of the installation of the topside facilities onto the vessel, which commenced mid-june 2004. The Lampson 2600 Trans-lift crane, located at the Cow Head Fabrication Facility in Marystown, will carry out a total of 17 lifts. Components of the vessel mooring system have been installed at the White Rose field, including anchor piles, anchor and riser base pile frames and anchor chain, which has been laid out on the seafloor bed. The subsea production system installation will commence July 2004 and continue over the following three to four months and then resume in 2005. The first of the four White Rose development wells drilled to total depth, a water injector, was successfully completed. A second water injector is currently undergoing completions operations. First oil remains on target for late 2005 or early 2006. 2.2 FPSO Project Management & Operations The document management and development contract is progressing with ongoing development of HSE and standard operating procedures manuals. The training contract with the Marine Institute is progressing. The dynamic simulator and test bed have been received in St. John s. Risk Management Risk Institute Company (RMRI) issued the Safety Plan for review. The integrity management bids, for the development of the structural, subsea and process piping integrity manuals, are under review. 2.3 Hull The SeaRose FPSO arrived on schedule at the pilot boarding station in Placentia Bay on April 5, 2004 and subsequently berthed at the Cow Head facility on April 6, 2004. 2.4 Topsides M12 (MER, HVAC, Workshop and Lab) arrived in Marystown from its Bull Arm fabrication site on May 16, 2004. M01 (Manifolds and Flare KO) departed St. Catherines, Ontario on June 25, 2004. August 2004 Page 2 HDMS ID: 003839954

Four of the 16 topside pre-assembled modules have been lifted onto the vessel M02 (HP/MP Separation), M03 (LP/Test Separation), M45 (Chemical Injection/Utilities) and M08 (Forward Laydown). Installation and commissioning of the topside facilities will continue to be the focus at Marystown for the next several months. 2.5 Offshore Installation The riser buoy, anchor piles and mooring wires arrived in Bay Bulls. The Atlantic Hawk completed the wet stowage of anchor chain and installed the long baseline survey array to facilitate subsea and mooring system positioning for the installation program. The CSO Constructor completed the pile driving program and the mooring wire deployment in early July 2004. The Dove finished connecting the chain clump weight section and will commence the buoy hook-up program. 2.6 Subsea 2.6.1 Glory Hole Excavation Glory hole excavation is complete. 2.6.2 Subsea Production System (SPS) Trees 9 and 10 were shipped from Leeds to Newfoundland. The GSF Grand Banks completed installation of the first x-mas tree. System integration testing (SIT) was completed on the northern gas injection manifold, while final preparations and testing are ongoing for the subsea manifolds. 2.7 Drilling and Completions The completions program began during May 2004, with the batch x-mas tree program. The first three deviated water injectors were drilled, cased and suspended. The first horizontal producer was drilled, cased and suspended. The conductor and surface casing was set in two gas injectors in the northern glory hole. The first water injector was completed (B-07 1). 2.8 Transportation As of the end of June 2004, approximately 80% of the first Knutsen shuttle tanker blocks and approximately 40% of the second hull blocks have been fabricated. Keel laying for the first shuttle tanker is scheduled to commence early July 2004. August 2004 Page 3 HDMS ID: 003839954

Knutsen finalized the terms of an arrangement with Canship Ugland for ship management of the White Rose shuttle tankers. Canship also manages the three shuttle tankers that service the Terra Nova and Hibernia developments. 2.9 Logistics Husky issued invitations to bid for Infrastructure, Facilities and Services; contract award is anticipated during Q3 2004. August 2004 Page 4 HDMS ID: 003839954

3.0 EMPLOYMENT SUMMARY 3.1 Employment by Residence Status As at June 30, 2004, a total of 2,880 management, engineering, technical, skilled trades, support and consultant employees of Husky and its contractors were employed directly on the White Rose Development Project. Of this total, 1,827 or 63.4% were residents of Newfoundland and Labrador when hired, while another 718 or 25.0% were residents of other regions of Canada at the time of hire. Table 3.1: Participation of Newfoundland and Labrador, Canadian and Non- Canadian Residents in White Rose Activity by Location of Work as of June 30, 2004 Newfoundland & Labrador Other Canadian Non-Canadian Male Female Sub-Total Male Female Sub-Total Male Female Sub-Total Total Employment Total 1639 188 1827 692 26 718 321 14 335 2880 3.2 Employment by Location (Person Hours) From April 1 to June 30, 2004, Husky project management, major contractors and subcontractors carried out a total of 1,493,853 person hours of work related to the White Rose Development Project. Approximately 83.0% of these person hours were worked in Newfoundland and Labrador. Table 3.2: Summary of Person Hours Worked in Newfoundland & Labrador, Other Canadian, and Foreign Locations April 1 to June 30, 2004 Project to Date 6 Project Component Newfoundland & Labrador Newfoundland & Other Canadian Foreign Total Other Canadian Foreign Total Labrador Husky Project Management 56,276 0 0 56,276 398,649 766 15,520 414,935 FPSO Project Management 1 44,858 1,758 2,273 48,889 257,009 10,291 84,567 351,867 FPSO Topsides 2 808,834 184,493 5,455 998,782 3,799,902 743,743 43,606 4,587,251 FPSO Hull 3 0 0 0 0 5,228 0 1,779,935 1,785,163 FPSO Turret 4 3,190 0 0 3,190 31,971 0 1,158,261 1,190,232 Subsea 5 Subsea Production System 135,569 485 57,808 193,862 489,942 5,495 492,670 988,107 Glory Holes 0 0 0 0 136,325 0 29,702 166,027 Drilling 137,688 1,346 92 139,126 510,180 13,703 1,838 525,721 Logistics 53,690 0 39 53,729 180,324 0 39 180,363 TOTAL 1,240,104 188,082 65,667 1,493,853 5,809,529 773,998 3,606,138 10,189,665 Notes: 1. FPSO Project Management also includes hours associated with Siemens ICSS contracts, excluding hours previously reported for turret ICSS. 2. Foreign person hours represent on-the-job training with respect to M01. Several engineering and skilled trades employees from CSE are working in the MacNulty Yard in Scotland as a part of a technology / skills transfer exercise. These workers will bring back learned skills to enable them to carry out specialty work on MO1. In addition a similar contingent from Scotland has been posted to the Ontario yard to further facilitate the transfer of knowledge and skills to Canadian workers. A portion of foreign person hours is also attributed to titanium pipe spool fabrication in New Jersey. 3. Hull also includes hours associated with lighting (MariTeam) and VSAT (Aliant). 4. FPSO Turret also includes hours associated with Turret fabrication (Gulf Piping Corporation, Abu Dhabi), TER (various contractors, St. John s), ICSS (Siemens) and lighting (MariTeam). 5. Subsea includes hours associated with Subsea Production System (TOCL/Camserv), TGBs (Cameron) and Glory Holes (Boskalis and Vasco) activity. 6. Project to date adjustment of 758 hours to account for hours that were not previously captured AOMS. Re-allocation of hours for Seabase Maersk 930 hours from CDN to NL Offshore. August 2004 Page 5 HDMS ID: 003839954

4.0 PROJECT EXPENDITURE For the period February 1, 2002 to June 30, 2004, Project expenditures (as a percentage of total cost) were 31.7% Newfoundland and Labrador content, 11.7% Other Canadian and 56.6% Foreign content. August 2004 Page 6 HDMS ID: 003839954