A Review on Load Sharing of Transformer

Similar documents
Automatic Load Sharing of Transformers using Microcontroller

LOAD SHARING OF TRANSFORMERS BASED ON MICROCONTROLLER

Busbars and lines are important elements

Power System Protection Part VII Dr.Prof.Mohammed Tawfeeq Al-Zuhairi. Differential Protection (Unit protection)

Ground Fault Detection using Zigzag Grounding Transformer in Ungrounded System

Induction Motor Protection using Micro Controller

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

Substation Testing and Commissioning: Power Transformer Through Fault Test

CONTENTS. 1. Introduction Generating Stations 9 40

Advanced Paralleling of LTC Transformers by VAR TM Method

3 Phase Induction Motor Protection using Numerical Relay

Notes 1: Introduction to Distribution Systems

Voltage Variation Compensation

DESIGN ANALYSIS AND REALIZATION OF MICROCONTROLLER BASED OVER CURRENT RELAY WITH IDMT CHARACTERISTICS: A PROTEUS SIMULATION

Capacitive Voltage Substations Ferroresonance Prevention Using Power Electronic Devices

Unit 3 Magnetism...21 Introduction The Natural Magnet Magnetic Polarities Magnetic Compass...21

Preface...x Chapter 1 Electrical Fundamentals

Numbering System for Protective Devices, Control and Indication Devices for Power Systems

TRANSFORMER THEORY. Mutual Induction

Hamdy Faramawy Senior Application Specialist ABB Sweden

ISSN: [IDSTM-18] Impact Factor: 5.164

Overview of Grounding for Industrial and Commercial Power Systems Presented By Robert Schuerger, P.E.

MONITORING OF DISTRIBUTION TRANSFORMER PARAMETERS USING PLC

AGN 026 Harmonic Voltage Distortion

Digital Monitoring Cum Control of a Power Transformer with Efficiency Measuring Meter

PROTECTION of electricity distribution networks

Design and Construction of Synchronizing Check Relay

Methods of secondary short circuit current control in single phase transformers

Power systems Protection course

UPGRADING SUBSTATION RELAYS TO DIGITAL RECLOSERS AND THEIR COORDINATION WITH SECTIONALIZERS

Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc GE Consumer & Industrial Multilin

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

An induced emf is the negative of a changing magnetic field. Similarly, a self-induced emf would be found by

Electrical Theory. Power Principles and Phase Angle. PJM State & Member Training Dept. PJM /22/2018


System Protection and Control Subcommittee

ARDUINO BASED POWER FACTOR CORRECTION

Level 6 Graduate Diploma in Engineering Electrical Energy Systems

AUTO-TRANSFORMER. This is having only one winding; part of this winding is common to both primary and secondary.

Fixed Series Compensation

Protection of Electrical Networks. Christophe Prévé

Adaptive Autoreclosure to Increase System Stability and Reduce Stress to Circuit Breakers

Preventing transformer saturation in static transfer switches A Real Time Flux Control Method

Reducing the Effects of Short Circuit Faults on Sensitive Loads in Distribution Systems

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

Universal Protection System for Ac Industrial Motors

How to maximize reliability using an alternative distribution system for critical loads

Relay Types and Applications Dr. Sasidharan Sreedharan

ACS 1000 Transformer Failure Investigation. Nathan Schachter, Peng

~=E.i!=h. Pre-certification Transformers

Mitigation of voltage disturbances (Sag/Swell) utilizing dynamic voltage restorer (DVR)

ECE 422/522 Power System Operations & Planning/Power Systems Analysis II 5 - Reactive Power and Voltage Control

Chapt ha e pt r e r 11 Inductors

WIRELESS THREE PHASE LINE FAULT MONITORING

Generator Advanced Concepts

EH2741 Communication and Control in Electric Power Systems Lecture 2

NERC Protection Coordination Webinar Series June 9, Phil Tatro Jon Gardell

Unit Auxiliary Transformer (UAT) Relay Loadability Report

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network

R10. IV B.Tech I Semester Regular/Supplementary Examinations, Nov/Dec SWITCH GEAR AND PROTECTION. (Electrical and Electronics Engineering)

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad

Design and Implementation of High Precision Automated Online Monitoring of Distribution Transformer (OMDT) Device

Design of Differential Protection Scheme Using Rogowski Coil

Integration of Linear Displacement Encoder and Servo Motor for 180 Ton Powder Compacting Press

System Protection and Control Subcommittee

NOVEL PROTECTION SYSTEMS FOR ARC FURNACE TRANSFORMERS

This webinar brought to you by The Relion Product Family Next Generation Protection and Control IEDs from ABB

Table of Contents. Table of Figures. Table of Tables

Experiment 45. Three-Phase Circuits. G 1. a. Using your Power Supply and AC Voltmeter connect the circuit shown OBJECTIVE

Voltage and Current Waveforms Enhancement using Harmonic Filters

BUS2000 Busbar Differential Protection System

Design and Development of Protective Circuit against Voltage Disturbances

NATIONAL SENIOR CERTIFICATE GRADE 12

A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation Equipment

Transmission Lines and Feeders Protection Pilot wire differential relays (Device 87L) Distance protection


Question Paper Profile

Outcomes from this session

International Journal of Current Research and Modern Education (IJCRME) ISSN (Online): & Impact Factor: Special Issue, NCFTCCPS -

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

Feeder Protection From Over Load and Earth Fault Relay

Single-Phase Transformation Review

Protection from Voltage Sags and Swells by Using FACTS Controller

TABLE OF CONTENT

I. INTRODUCTION IJSRST Volume 3 Issue 2 Print ISSN: Online ISSN: X

COPYRIGHTED MATERIAL. Index

Section L5: PRE-ENERGIZATION TEST PROCEDURES FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

Electrical Protection System Design and Operation

FAULT AND STABILITY ANALYSIS OF A POWER SYSTEM NETWORK BY MATLAB SIMULINK

Simulation & Realization of Feeder Protection with Micro Controller

CHAPTER 1 INTRODUCTION

HARMONICS CAUSES AND EFFECTS

Symmetrical Components in Analysis of Switching Event and Fault Condition for Overcurrent Protection in Electrical Machines

Power System Protection Manual

TRANSFORMERS INTRODUCTION

Page ENSC387 - Introduction to Electro-Mechanical Sensors and Actuators: Simon Fraser University Engineering Science

Bus Protection Fundamentals

Modern transformer relays include a comprehensive set of protective elements to protect transformers from faults and abnormal operating conditions

VOLTAGE BALANCING TECHNIQUES FOR FLYING CAPACITORS USED IN SOFT-SWITCHING MULTILEVEL ACTIVE POWER FILTERS

Trade of Electrician. The Transformer

Transcription:

IJSTE - International Journal of Science Technology & Engineering Volume 3 Issue 07 January 2017 ISSN (online): 2349-784X A Review on Load Sharing of Transformer Mohammad A. Lakdawala Bhavik Patel Vaibhav Patel Pushprajsinh Jadeja Manish Mishra Assistant Professor Abstract The transformer is a very bulky and costly equipment of electrical power system that steps up/down the level of power of the system. The transformer operates throughout the day in the supply system which makes it one of the most important part of the electrical power system. Many of the times the condition occurs in the system when the load on the transformer fluctuates outside the normal operating range which may lead to the overload condition and damage of the insulation of windings resulting the failure in operation of the transformer, thus causing interruption of the supply. One of the main reasons of overloading is the improper load sharing of the transformers. One of the best solutions to avoid the overloading is to operate the number of transformers in parallel. It is same like parallel operation of transformers where the number of transformers shares the system load. The transformers work efficiently and thus damage is prevented. The outcome of this project is based on reliable power supply and safety of transformer. By implementation of this scheme, the problem of interruption of supply due to transformer overloading or overheating can be avoided. Keywords: Load Sharing, Transformer I. INTRODUCTION There are different terms used in power system like load shedding, load sharing etc... So first we have to differentiate between load shedding and load sharing. Load shedding It is process of cut-off the loads on the approximated area according to the load priority to reduce the increase demand greater than the supply. Load sharing - Load sharing means generally equally share the load in power system. In power system load sharing of transformer is achieved with different techniques. It means in distributed power system if two transformer is connected. One transformer share the load in normal condition. If load demand is increasing and one transformer is connected not able to fulfill demand than another transformer is directly connected with main transformer in parallel and share the load. In power system it is called load sharing of transformer. Main transformer is called power transformer and another transformer that are connected with the main transformer are called slave transformer in power system. For supplying a load in more than the rating of an existing transformer, two or more transformers may be connected in parallel with the existing (main) transformer. The transformers are connected in parallel when load on one of the transformers is more than its capacity. Due to the parallel operation of transformer reliability of power system is increase and damage to the various equipment in substation like transformers are reduces. To archive parallel operation of transformers some conditions are to be satisfied compulsory. Fig 1 shows the two transformers are connected parallel. There are total two buses in the system one is supply bus and another one is load bus. At the load bus, load is connected. E1 is primary side voltage and E2 is secondary side voltage. If a condition occurs and load is suddenly increased, then second transformer is in parallel with the main transformer to supply the load demand. All rights reserved by www.ijste.org 181

Fig. 1: Parallel Operation of Transformer. II. NEED OF PARALLEL OPERATION OF TRANSFORMER If a large size means large rating of transformer is not available which can actually fulfill the total requirement of load, two or more small size transformers can be connected in parallel to increase the capacity. If installation place like substation is located far away, then transportation of smaller size of transformer is easier and may be economical. It will directly affect the cost. If more than one the transformers run in parallel, is out due to fault of other parallel transformers is the system will share the load, hence power supply may not be interrupted. If numbers of transformers run in parallel, we can shut down any one of them for maintenance purpose. Other parallel transformers in system will fulfill the load without total interruption of power. III. CONDITIONS FOR PARALLEL OPERATION OF TRANSFORMER When two or more transformers run in parallel, they must satisfy the following conditions for satisfactory performance. Voltage Ratio or Turns Ratio If the transformer connected in parallel have voltage ratio different than this will not good condition for system. Due to the different voltage ratio induced emf generated at the secondary side will be different. Which cause circulating current flows in the loop which are formed by the secondary windings under no-load conditions. The value of this circulating current is much higher than no load current. So chances of damage the winding of transformer. Circulating current cause the losses and damage the insulation of the winding. So the voltage ratio should be proper manner to achieve better parallel operation of transformer. V 1 V 2 = N 1 N 2 Same Polarity Polarity of all transformers that run in parallel, should be the same otherwise huge circulating current that flows in the transformer but no load will be fed from these transformers. Polarity of transformer means the direction of induced emf in secondary. If the directions of induced secondary emf in two transformers are opposite to each other when same input power is fed to both of the transformers, the transformers are said to be in opposite polarity. If the directions of induced secondary emf in two transformers are same when same input power is fed to the both of the transformers, the transformers are said to be in same polarity. Same Phase Sequence The voltage between two phases is called line voltages. In this case the phase sequence of line voltages of main transformer and auxiliary transformer which are connected parallel with main transformer must be identical for parallel operation in case of threephase transformers. If the phase sequence is not same, in every cycle each pair of phases will get short-circuited. Same Impedance Ratio We know the relation of current with impedance. Current is inversely proportional to the impedance. If we consider two transformers which has different per unit impedence.one transformer have less impedance will draw more current and which has All rights reserved by www.ijste.org 182

more per unit impedance will draw less current. This leads unequal load sharing. This is not beneficial. Due to this condition, the transformers will not share the load according to their kva ratings. In that case, it can be corrected by inserting proper amount of resistance or reactance or both in series with either primary or secondary circuits of the transformers where the impedance is below the value required to fulfil this condition. IV. DIFFERENT TECHNIQUES USED FOR TRANSFORMER LOAD SHARING There are different techniques used for transformer load sharing. Let see one by one. Microcontroller based transformer load sharing [1] This is microcontroller based system. Power supply to the Loads from a single transformer under normal condition and a standby transformer is connected in parallel through a circuit breaker. A current transformer measures the load current continuously and send it to the microcontroller by converting it to a corresponding digital value in order to compare with the reference value set by the user. Whenever the load current more than reference value, the controller give output signal to the relay which energizes the relay coil. The relay coil thus sends a tripping signal to the circuit breaker. Then standby transformer is directly connected to the main transformer. Thus the load is shared by the transformers equally. The current transformer continuous measures the load current and compares it with the reference value. Whenever the load current go below reference value one transformer is shut down. If the load value increases further beyond the capacity of two transformers, load will be cut-off from the main supply based on the priority level set by the user. This is done to provide un-interrupted power supply to higher priority loads. The load parameters are continuously displayed in the LCD. Due to this we can show the peak load time duration. Comparator based transformer load sharing [2] Fig. 2: microcontroller based transformer load sharing Here there are three transformer are used. Transformer T1 is main transformer and transformer T2 and T3 is called slave transformer. In normal operating condition transformer t1 is fulfill load demand. Suppose condition occur that load on consumer side is increase above the capacity of main transformer. If there is no such arrangement to full fill the load chance of the damage of the transformer should be there. So in these condition parallel operation of transformer is used. In these scheme comparator is used to compare reference voltage and system voltage and in condition of load increase signal is given to the relay driver circuit. Relay driver gives the signal to the changeover relay. Change over relay closes its contact when load on the main transformer is more than its rated capacity and the transformer T2 is directly connected with main transformer in parallel. If load is increase beyond the both transformer capacity than transformer T3 is connected with both transformer. All rights reserved by www.ijste.org 183

GSM based transformer load sharing [3] Fig. 3: Comparator based transformer load sharing Here the transformer load sharing is archived by the simple operation of micro controller and GSM technique. For this configuration of the program through GSM module is done. Here two transformer is used one is main transformer and second is sharing transformer which is used to share the load.here in normal condition the load is supply by main transformer. Condition occur that load on main transformer is increases above the rating of the main transformer capacity. Here when load is increase the relay will be connect sharing transformer with the main transformer. And this relay will be operating with the micro controller. To check the exceeding limit micro controller takes digital current value from the line. If condition is occurring that load increase that micro controller checks the instruction and give command to the GSM. From GSM module the SMS will be sending to the respected engineers. Fig. 4: GSM based transformer load sharing Transformer load sharing with power factor improvement technique [4] In overload condition there is stress created on the winding of transformer. Due to this the temperature of transformer is get increase and these indicate overloading. In this scheme the protection of the over loading, over temperature of transformer is archived by the perfect load sharing and also scheme involves the power factor improvement technique. In most cases the load side power factor is lagging. Here automatic load sharing module also consist the automatic power factor correction circuit. All rights reserved by www.ijste.org 184

Loads are inductive in nature so the power factor is lagging in nature. So to improve power factor nearer to the 1.0 capacitor or inductors banks are used. Fig. 5: load sharing with power factor improvement. V. CONCLUSION We all know that transformer is the main equipment in power system. So safety of transformer is very important. This paper is give information about the importance of transformer load sharing. What are the different techniques used in load sharing with safety is given. A required condition for the load sharing is also mentioned.so the power that can be transferred to the consumer is uninterrupted. Power system operation will be reliable. ACKNOWLEDGEMENT We wish to express my sincere thanks to Dr. Shrikant J. Wagh, Principal of SRICT, for providing me with all the necessary facilities for the research. We place on record, my sincere thank you to Mr. Praful P. Chudasama, Head of the Department, for the continuous encouragement. We are also grateful to Mr. Manish P. Mishra, Assistant Professor in the, SRICT. We are extremely thankful and indebted to him for sharing expertise, and sincere and valuable guidance and encouragement extended to us. We take this opportunity to express gratitude to all of the Department faculty members for their help and support. We also thanks our parents for the unceasing encouragement, support and attention. We are also grateful to our partners who supported me throughout this venture. REFERENCES [1] Akhil Krishnan V, Arun P S, D Yathishan, Jomice Thomas, D K Narayanan, Automatic Load Sharing of Transformers using Microcontroller, International Journal of Innovative Research in Science, Engineering and Technology (IJIRSET) Vol. 5, Issue4, April 2016. DOI:10.15680/ IJIRSET.2016.0504176 5434 [2] Ashish R. Ambalkar, Nitesh M. Bhoyar, Vivek V. Badarkhe, Vivek B. Bathe, Automatic Load Sharing of Transformers, IJSRD - International Journal for Scientific Research & Development Vol. 2, Issue 12, 2015 ISSN (online): 2321-0613 [3] Poonam Patil,Kshma kandekar,priyanka Pokharkar Active Demand Response using Shared Energy Storage International Engineering Research Journal (IERJ)ISSN 2395-1621Volume 2 Issue 1,March 2016 [4] Rekha. T, Bindu Prakash Asna.S,Dinesh.S, Nandana.S.Prasad, An Intelligent Method For Load Sharing Of Transformers With Temperature Monitoring And automatic Correction Of Power Factor International Journal Of Engineering Sciences & Research Technology ISSN: 2277-9655 Month: March 2015 [5] PRABHA KUNDUR Power System Stability and Control All rights reserved by www.ijste.org 185