In Denver, a recently completed flyover

Similar documents
Precast Bridge. in only Eight Days. profile. Minimizing construction-related traffic delays and improving workzone

The $13.2 billion Central Artery/Tunnel Project (CA/

BRIDGE TYPE CONCEPT EVALUATION

THE TRANSPORTATION ISSUE

Segmental Bridge Technology Established and Evolving. W. Jay Rohleder, Jr, P.E., S.E. Senior Vice President / Project Development FIGG

Accelerated Bridge Construction (ABC) and the Utah Experience

Segmental Bridge Construction. Segmental Bridges It s a Construction Technique with Design Implications. Plans Review Group

Total precast solution for large stadium projects meet tight schedule

James Luebke, PE Structural Development Engineer WisDOT Bureau of Structures

Dauphin Island Bridge

Radiused Precast Concrete

State-of-the-art Report On FULL-DEPTH PRECAST CONCRETE BRIDGE DECK PANELS (SOA )

PRECAST CONCRETE BRIDGE SUBSTRUCTURE COMPONENTS. Presented by: Matthew Youngblood, PE, SE Scott Noyer, PE Janssen & Spaans Engineering

State of the Art Precast, Prestressed Concrete Bridges and Industry Innovations

PCI Update on Transportation Activities and elearning Modules for AASHTO Technical Committee T-4 AASHTO SCOBS --- Spokane Washington

Precast Concrete Panels for Rapid Pavement Repair

Name two reasons why bridges are built. Name two places where you would find a bridge?

Amajor transportation infrastructure undertaking, billed

Construction Tolerances - The following tolerances apply to cast-in-place structures:

Precast Concrete Pavement Background Concepts. Project 1517 FHWA, CTR & TxDOT Gary Graham November 15, 2001

California Department of Transportation

ABC and Innovative Bridge Construction for Minnesota Local Roads

Precast Concrete Pavement

TECHNICAL NOTE SEGMENTAL BRIDGE WIZARD. Introduction. Segmental Bridge Span Assembly

6/19/2014. Milton Madison Bridge Slide. Project Partners. The Challenge. Aaron L. Stover, PE, SE Michael Baker Jr., Inc.

Overview of Precast ABC Projects in the Pacific Northwest. Chuck Prussack, P.E., Oldcastle Precast, Inc - Spokane

Chapter 6: SHOP DRAWINGS AND OTHER SUBMITTALS

How to Estimate the Cost of a. Precast Concrete Parking Structure

shawprecastsolutions.com BEBO Arch Systems PRODUCT GUIDE & TECHNICAL REFERENCE MANUAL Providing the right solutions.

TARGET FIELD: REMOVING THE VARIABLES THROUGH BIM

Michelle Muro, AIA, NCARB

NEW METHOD FOR THE PRODUCTION OF DECK SLABS OF STEEL-CONCRETE-COMPOSITE BRIDGES

Deep Creek Canyon US Highway 12

Demolition of Ramp C (SN ): Westbound Ontario Street to Eastbound I-90/94) over I-90/94 (JF Kennedy Expressway)

OpenBridge Modeler: What is it and how can I use it today?

Arch Bridge in Nijmegen - new 3D Approach to Workshop Plans

Update: July 20, 2012

Update on Bridge Deck Fastener Performance on the FAST Steel Bridge. By Duane Otter and Brian Doe ABSTRACT

IABSE SYMPOSIUM NANTES, 2018

FIGG. Accelerated With Bridge Construction. Concrete Segmental. Bridges. William R. (Randy) Cox, P.E. American Segmental Bridge Institute

Guide Sign Policy for Secondary State Highways Edition

Jointed Precast Concrete Pavement

Suggested Reinforcement Detailing Practices Based on comments from R&D and ES ESS Committees

INDEX. Initial SOL Approval. 1. Evergreen Retaining Wall System (Deleted) 3. Sound Barrier Walls (Deleted) Standard Details

adopted in Hong Kong

STANDARD MSGDET4AC: NOTES TO DESIGNER

Precast / Prestressed Concrete Trade Coordination Case Study Jason P. Lien, PE, FPCI EnCon United, Denver, Colorado

Unit 8 Precast Concrete

SPECIFICATIONS FOR THE MANUFACTURE AND DESIGN OF PRECAST THREE SIDED ARCH STRUCTURES, WINGWALLS AND HEADWALLS

Value Engineering Design Build MODULAR INFRASTRUCTURE

MANuFACturers industry QuALity statement.

Plan Preparation Checklist

BUILDING PLANS. BUILDING DEPARTMENT

Union Station Tunnel Overall DBE Goal Calculation

PANEL CRIB PIERS AND TOWERS

moment and shear tables 8 inch High strength precast & prestressed concrete lintels

24" B B Joint X501 Joint See MARKINGS Note PCB-RXX-350-TL3 " X501 Y301 (Typ.) " A PLAN (reinforced casting option shown) A " dia. Hinge Bar (Typ.) NOT

Projector Test Screen. Slides Ready

PRECAST CONCRETE STRUCTURES

BUILDING PLANS. BUILDING INSPECTIONS DEPARTMENT

CHAPTER 10 MICHIGAN DESIGN MANUAL BRIDGE DESIGN (SI) SHOP DRAWING REVIEW TYPES OF SHOP DRAWINGS Structural Steel

Designing for Seismic Success with Precast Concrete

Robotic Welding of and I-Beam using a GMAW Gantry System

CITY OF FOLSOM SUBMITTAL REQUIREMENTS FOR INSTALLATION OF A COMMERCIAL REFUSE OR CARDBOARD COMPACTOR FOR AN EXISTING BUILDING

SECTION STRUCTURAL STEEL. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

White Paper on: Recommended Practices for Specifying and Delegating Responsibilities for Precast Concrete Building Structures in Colorado

MTJ Outdoor Baggage Claim

11/15/2010. Construction. Accelerated Bridge Construction (ABC) Definition. Systems (PBES) Definition

1.1 RELATED DOCUMENTS

Jointing Rural Intersections

Designer s NOTEBOOK DESIGN ECONOMY, PART 3

SECTION 1050 STEEL BRIDGE SUPERSTRUCTURE

SECTION 1085 PRECAST REINFORCED CONCRETE BOX CULVERT

Name: Kimio SAITO. 1. General Information (10min.) 2. History and Applications in U.S. (15min.) 3. Recent Applications in Japan (10min.

PRECAST FLOOR PRODUCTION SEMI - PRO - EDGE

Intermediate Mathematics League of Eastern Massachusetts

Proven precast solutions for every application

Step 2 - Measure and install joist hangers every 16". See Figure "B" above. Fill every hole in each

Challenges for productivity and industrialized Construction Bmst. Ing. Martin Dobler Austria

A. Extent of structural precast concrete work is shown on drawings and in schedules.

FORM - 2 THE PATENTS ACT, (39 of 1970) THE PATENTS RULES, 2003 COMPLETE. Specification. (See Section 10; Rule 13) OVERPASS BRIDGE

d e n v e r a r t m u s e u m

CONTRACT PLANS READING

series cutoff Radial Arm Saw simplifying

DELINEATOR REFERENCE POINT 200' TYPICAL SPACING (YELLOW DELINEATORS) END OF MERGE LANE TAPER DELINEATOR REFERENCE POINT

SUBSTATION SECURITY WALL INSTALLATION MANUAL

SECTION 58 PRECAST CONCRETE BOX CULVERT. This work consists of furnishing and installing Pre-cast Concrete Box Culverts.

AASHTO TIG Promoting the use of Precast Concrete Pavement Systems. Highways for Life PCPS Showcase NJDOT, Mt. Arlington NJ Timothy J.

Perimeters of Composite Figures

712 - STRUCTURAL STEEL CONSTRUCTION SECTION 712 STRUCTURAL STEEL CONSTRUCTION

Helical Pier Frequently Asked Questions

WVDE Math 7 G Draw, Construct, and Describe Geometrical Figures and Describe the Relationsips between Them Test

Bridge Design and Drafting Manual Oregon Department of Transportation

SHADOW ARRAY SOUTH TERMINAL REDEVELOPMENT PROJECT. DIA. PATRICK MAROLD STUDIOS INC 2013

PCI Design Awards Buildings Submission Guidelines

Project Reference Catalogue

LETTING : CALL : 029 COUNTIES : GOODHUE

CONSTRUCTION / HOUSING

PRACTICE NOTE NO: 13 Version 1 Amended March 2001 Page 1 of 6 PRECAST CONCRETE ELEMENT DESIGN RESPONSIBILITIES AND CONTRACTUAL ARRANGEMENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS

Transcription:

ASCENT CASE STUDY 36 A Fast Learning Curve Colorado flyover provides strong example of the concept of curved U-girders for use in a variety of bridge projects In Denver, a recently completed flyover ramp, which features U-shaped precast concrete girders, may open an entirely fresh chapter in bridge designers search for additional ways to use precast components. We designed a bridge with several design features that have never been done before in Colorado. [These features allow precast concrete girders to compete with steel in the design of longer span interchanges, with complex geometry], says Gregg Reese, president of Summit Engineering Group in Littleton, Colo. The project, completed this summer, spans Interstate 25 just north of the US- 36 and I-76 interchanges. Traditionally, such structures have used structuralsteel girders. The Colorado Department of Transportation took a bold step by offering contractors the option of using precast components on the 1,428-footlong bridge and while contractors had the option of bidding the project with steel girders or precast, they were limited to one or the other. The contract went to SEMA Construction Inc. in Centennial, Colo. As we were working on our bid, steel prices were on an upswing, explains Brad Spies, SEMA president. We analyzed the costs for steel and concrete, and we determined that concrete would be less costly. Ironically, on the morning that SEMA submitted its bid, steel prices dropped, Spies says, and the differential between the two materials appeared negligible. However, by this time SEMA and its partners Summit and precaster EnCon Bridge Co. in Denver, had committed themselves to the concrete alternative. Even so, when the bids were opened, the team s bid came in Two cranes swing a curved girder into place over an existing roadway. pci.org Click for more Cranes lower a girder into place atop site-cast piers. Scaffolding provided temporary support until the structure was post-tensioned.

Falsework provides support for beams erected between two cantilevered sections. Once in place, the beams were post-tensioned to provide continuity. Fact Sheet Project Name: Interstate 25 Flyover Location: Denver Bridge length: 1,420 feet Deck width: 47 feet Precast components: Six 7-footdeep straight, open-top trapezoidal sections, both pretensioned and post-tensioned. Maximum length 103'7", maximum weight, 250,000 pounds; 22 7-foot-deep curved (radius 962 feet, super elevation 5.6 percent) post-tensioned, open-top trapezoidal section with a maximum length of 104 feet and a maximum weight of 254,000 pounds; 184 17' 8" long by 8-foot-wide deck panels, 6 inches deep (131 pie-shaped) at 8,900 pounds each. Owner: Colorado Department of Transportation, Denver Prime Contractor: SEMA Construction Inc., Centennial, Colo. Precaster: EnCon Bridge Co., Denver Engineer of Record: Summit Engineering Group Inc., Littleton, Colo. Engineering Substructure Consultant: PBS&J, Greenwood Village, Colo. Erector: RMS Cranes, Englewood, Colo. Cost: $4.8 million Of those, only six were straight. The other 22 were cast with a super elevation and a radius to create a graceful structure with an uninterrupted curve. The 7-foot-deep girders featured 10-inch webs, according to Jim Fabinski, vice president of EnCon Bridge, a PCI-certified plant in Denver. The two-lane, eight-span structure consists of two girders spanned by 17-foot- 8-inch-long and 8-foot-wide deck panels that vary from 4½ to 6 inches deep. Of these panels, 131 were pie-shaped to accommodate the structure s curve. The curve and super elevation of the girders are evident in this view. approximately $200,000 lower than the next-lowest bid, which used steel girders. In fact, due to competition between steel and concrete options, the contractors had to sharpen their pencils at bid. The bid price of structural steel came out at $1.14 per pound, which is unprecedented in recent history for structural steel box girder. The winning design called for 28 U- girders, each approximately 100 feet long. Largest Beams Ever Cast The huge beams, some of the largest ever cast by EnCon, used several new design techniques. For example, the units curved and super-elevated configuration required special casting forms. To achieve that shape, EnCon turned to Jones & Gardner Engineering of Golden, Colo., which created a form for the beams.

38 Precast concrete panels span the opening between the curved U-beams. The final roadway was cast on top of the panels and girders. Already, precasters from other parts of the country are showing interest in this new technology, Fabinski says. The straight beams were pretensioned by EnCon. However, for handling and continuity, the curved beams were post-tensioned in the plant and in the field. Another major stumbling block was transporting the huge beams from the EnCon plant to the job site 4 miles away. In order to move the 250,000-pound units, Apex Transportation of Henderson, Colo., had to add two hauling units to its fleet. Even at that, the girders bordered on the maximum load allowed on Colorado highways. To handle the heavy lifting chores at the site, the erection contractor, RMS Cranes, a division of Rocky Mountain Prestress Inc. in Englewood, Colo., put three large cranes to work. Building On The Past The new Colorado bridge represents a step forward in the use of precast concrete girders for building curved structures. But curved beams were used in earlier projects. These comprise the elevated monorail at Disney World in Orlando, Fla., and curved interstate entrance ramps at the Philadelphia International Airport. The first were designed by ABAM Engineers in Federal Way, Wash., and the second by Schupack Suarez Engineers, Inc., South Norwalk, Conn. The newest incarnation in Colorado represents several steps forward, including the size of the beams and the fact that not only are they continuously curved, but they also were cast with a super-elevation. For information on the Philadelphia Airport job, see the PCI publication JR-350, Precast Prestressed Concrete Horizontally Curved Bridge Beams. It is available for free download or as a $2 hard copy at the Designer s Knowledge Bank at www.pci.org or your local precaster s Web site. Click on the DKB icon, then use the Advanced Search in Bridges for curved beams. Spliced-Girder Technology The erection sequence had to be carefully planned. The longest span of the bridge, 200 feet, required the application of spliced-girder methods already in common use in Colorado. One-hundredfoot segments were balanced on the piers and temporarily supported on falsework. A one-hundred-foot drop-in segment A precast deck panel spans the opening between parallel girders before a composite concrete deck is placed.

The new flyover spans several roadways. This design required careful erection sequencing to minimize traffic disruptions. was added in between the cantilevered beams, and the entire assembly was posttensioned for continuity. Erection was a bit tricky, Reese says, since there are four traffic crossings at the site. With all of the other roadways at the site, we had to carefully plan our erection sequence. The erection process also was impacted by C-DOT s requirement that traffic be interrupted for no more than five hours each morning, Spies says. We More To Come The Colorado bridge opens the door to a whole new technology, designers say. Already, a similar project is planned in Nebraska. Plans are currently being drawn by Tadros Associates of Omaha, Neb., for a curved, two-span bridge carrying Arbor Road over Highway I-80. Working with Concrete Industries of Lincoln, Neb., Tadros presented a bid substituting a concrete structure for the originally proposed steel-plate girders. At press time, plans were still being completed for the bridge, according to Shane Hennessey of Tadros. Casting was to begin in June with delivery of the beams to the job site in August. The Nebraska beams will be posttensioned after the forms are stripped, Hennessey says. The bridge will feature four girder lines spaced at 9'4" instead of the originally proposed fivegirder lines. The 38'4" wide structure will include two spans, 141'10" long and 135' 10" long, Hennessey says. originally thought we would be able to set two girders each day, but we found that with the window provided for stopping traffic set at only five hours, we were able to set only one girder each day. That limitation extended the time expected for erection. This is the first bridge of its kind in the state of Colorado, notes Jamal Elkaissi, C-DOT staff Bridge in charge of the project. The project was initially designed as a steel structure, but when we saw that the price of steel was rising, we elected to add alternative concrete option in addition to the steel option for contractors to bid on. The concrete option was a design built utilizing precast Colorado U-girder type. That resulted in the new design. The new bridge could provide a prototype for future designs, he notes. What we ve done here is develop a new concept that has never been used in Colorado before. In fact, as far as I know, this use of curved, concrete U- girders is unique. Other curved structures have been built using precast concrete, but the girders themselves were either straight or did not include the use of curved U-girders cast with a radius and super elevation. For more on those past pci.org projects, see the sidebar. The project has opened the door for more projects of its type, says Elkaissi. In fact, a second flyover using precast concrete U-beams is in the planning stage for that same site. This initial project has more than lived up to expectations. We are very satisfied with the bridge. We feel that we saved time and money using the concrete girders, although at this time we have not been able to put numbers on those savings. The biggest benefit is that it s been proven that the concept works, he says. The project has presented us with a good learning curve, agrees Spies. The experience we ve gained with this job shows that it can be done. However, we found that it was a bit more complicated than we had at first thought. The key is that we have added to our knowledge with this job. Click For More Wayne A. Endicott For additional information on this story, visit www.pci.org/pdf/ knowledgebank/i25_05.pdf. (Adobe Acrobat version 4 or greater required.) To learn more about precast concrete bridges, visit the Designer s Knowledge Bank by clicking on the DKB icon at www.pci.org or at your local precaster s Web site. 39

ASCENT CASE STUDY

CASE STUDY ASCENT

ASCENT CASE STUDY

CASE STUDY ASCENT

ASCENT CASE STUDY

CASE STUDY ASCENT

ASCENT CASE STUDY

CASE STUDY ASCENT

ASCENT CASE STUDY

CASE STUDY ASCENT