Office for Nuclear Regulation

Similar documents
Office for Nuclear Regulation

New Reactors Programme. GDA close-out for the AP1000. GDA Issues GI-AP1000-CI-05 Smart Device Justification

ONR-NR-PAR Rev 2

The UK Generic Design Assessment

Chief Nuclear Inspector s Inspection of NNB GenCo Ltd. s Supply Chain Management Arrangements for the Hinkley Point C Project

Office for Nuclear Regulation

New Reactor Division Generic Design Assessment. Step 2 Assessment of the Fault Studies of UK HPR1000 Reactor

GDA Step 2 Assessment of the Probabilistic Safety Analysis and Severe Accident Analysis of Hitachi GE s UK Advanced Boiling Water Reactor (UK ABWR)

Office for Nuclear Regulation

IOP Nuclear Industry Group

New Nuclear Reactors: Generic Design Assessment

ONR perspectives on design assessment and licensing of SMRs

SMR Conference Manchester 2014 Regulator s view UK and International. Bob Jennings Systems Lead for ONR s Generic Design Assessment (GDA)

Wylfa Nuclear Power Station

Phase 2 Executive Summary: Pre-Project Review of AECL s Advanced CANDU Reactor ACR

LICENSING THE PALLAS-REACTOR USING THE CONCEPTUAL SAFETY DOCUMENT

Use of the Graded Approach in Regulation

THE USE OF A SAFETY CASE APPROACH TO SUPPORT DECISION MAKING IN DESIGN

For information on how we regulate geological disposal, and for copies of this and other reports in the series, visit:

GDA Issue GI-AP1000-SI-05: Compliance of AP1000 Main Structural Components with ASME III Design Rules.

June Phase 3 Executive Summary Pre-Project Design Review of Candu Energy Inc. Enhanced CANDU 6 Design

Goals, progress and difficulties with regard to the development of German nuclear standards on the example of KTA 2000

Background to and experience using the nii s new safety assessment principles learning for the high hazard sector?

Office for Nuclear Regulation Strategy

Health Based Exposure Limits (HBEL) and Q&As

SAFETY CASE ON A PAGE

Engineering Recommendation M30 Issue Standard Electricity Network Operator Electricity Smart Meter Configurations

Public Information and Disclosure RD/GD-99.3

Type Approval JANUARY The electronic pdf version of this document found through is the officially binding version

Public and Aboriginal Engagement Public Information and Disclosure REGDOC-3.2.1

Identification and recording of 'hot' sites - joint procedure for Electricity Industry and Communications Network Providers

Nuclear Regulation: Purpose, Philosophy, Principles, Processes and Values - A View. By Mike Weightman

A/AC.105/C.1/2006/NPS/CRP.7 16 February 2006

Integrity of safety-related systems in the gas industry

RE: Land at Boundary Hall, Aldermaston Road, Tadley. INSPECTORATE REF: APP/H1705/V/10/

SAFETY ASSESSMENT METHODOLOGIES AND THEIR APPLICATION IN DEVELOPMENT OF NEAR SURFACE WASTE DISPOSAL FACILITIES ASAM PROJECT

Guide to the Requirements for Public Information and Disclosure GD-99.3

Yolande Akl, Director, Canadian Nuclear Safety Commission Ottawa, Canada. Abstract

INFCIRC/57. 72/Rev.6. under. Safetyy. read in. Convention. involve. National Reports. on Nuclear 2015.

1 HPC Knowledge Management 1 January 2014 EDF Energy plc. All rights Reserved

EDS GRID AND PRIMARY SUBSTATION CIVIL DESIGN STANDARDS

Use of the Bowtie Methodology in the Generic Pre-Construction Safety Report (GDA PCSR) for Advanced Water Cooled NPPs

GE/GN8648. Guidance on Positioning of Lineside Telephones. Rail Industry Guidance Note for GE/RT8048

SMR Regulators Forum. Pilot Project Report. Report from Working Group on Graded Approach

Applied Safety Science and Engineering Techniques (ASSET TM )

The economic impact of ONR safety regulation: Final Report The Office for Nuclear Regulation

ETSI EN V1.3.1 ( )

IGEM/TD/101 Edition 2 Communication 1740 Adoption of pipe systems by a GT management of UIP activities

ECP HV INSULATION TESTING

Heads of European Radiological

The creation of the Emergency Preparedness and Response Expert Group (EPREG) which held its second meeting last month.

TECHNICAL SPECIFICATION

High Performance Engineering

TECHNICAL SPECIFICATION

This document is a preview generated by EVS

Licensing Documentation and Licensing Process for Dismantling and Decontamination projects in Lithuania

ECP HV INSULATION TESTING

English - Or. English NUCLEAR ENERGY AGENCY COMMITTEE ON THE SAFETY OF NUCLEAR INSTALLATIONS FINAL REPORT AND ANSWERS TO QUESTIONNAIRE

EDS LV SUPPLIES TO MOBILE PHONE BASE STATIONS MOUNTED ON TRANSMISSION TOWERS

IAEA Training in level 1 PSA and PSA applications. PSA Project. IAEA Guidelines for PSA

Public and Aboriginal engagement Public Information and Disclosure REGDOC-3.2.1

ISO INTERNATIONAL STANDARD. Petroleum and natural gas industries Offshore production installations Basic surface process safety systems

IAB Europe Guidance THE DEFINITION OF PERSONAL DATA. IAB Europe GDPR Implementation Working Group WHITE PAPER

EUROPEAN ETS TELECOMMUNICATION July 1997 STANDARD

Bulk Electric System Definition Reference Document

UKEPR Issue 04

The EUR: a great achievement and still on its way Eric de FRAGUIER, EDF EUR Steering Committee Chairman

This document is a preview generated by EVS

DEVELOPMENT OF INTERNAL FLOODING PSA FOR NEW BUILD UK GENERIC DESIGN ASSESSMENT

Brad Luke. Director Peddle Thorp Auckland

IS LIMITED REGISTRATION OF IRON OXIDE PELLETS UNDER REACH AN OPTION?

DNVGL-CP-0338 Edition October 2015

Adoption of pipe systems by a GT management of UIP activities

Keeping Your House in order?

COMMISSION IMPLEMENTING DECISION

Voluntary Carbon Standard

Decommissioning conduct Working Group

INTERNATIONAL STANDARD

Fiscal 2007 Environmental Technology Verification Pilot Program Implementation Guidelines

SPECIFICATIONS SUBJECT TO CHANGE WITHOUT NOTICE

INTERNATIONAL STANDARD

RELEVANT ELECTRICAL STANDARDS

Centre for the Development Of Academic Skills (CeDAS) Royal Holloway Proofreading Scheme Handbook and Code of Practice

EDS FAULT LEVELS

Design submission using DTC or Engineering Certified solution.

Quarterly News. April June Cover Introduction Corporate update Q1 at a glance Programme updates Spotlight 1 Spotlight 2 Looking ahead

July Contents. Gas Demand Side Response Methodology Final Version. UK Gas Transmission

ISO INTERNATIONAL STANDARD

Continuous On-line Measurement of Water Content in Petroleum (Crude Oil and Condensate)

Task on the evaluation of the plasma response to the ITER ELM stabilization coils in ITER H- mode operational scenarios. Technical Specifications

TeesRep policy document

SUBJECT HEADING: Switching Programmes ISSUE: 18

SATELLITE NETWORK NOTIFICATION AND COORDINATION REGULATIONS 2007 BR 94/2007

TITLE V. Excerpt from the July 19, 1995 "White Paper for Streamlined Development of Part 70 Permit Applications" that was issued by U.S. EPA.

Estates Development & Projects

IAASB Main Agenda (March, 2015) Auditing Disclosures Issues and Task Force Recommendations

Revision 24 of Issue 3 of the Grid Code has been approved by the Authority for implementation on 19 th November 2007.

BUREAU OF LAND MANAGEMENT INFORMATION QUALITY GUIDELINES

EGS-CC. System Engineering Team. Commonality of Ground Systems. Executive Summary

Validation and Verification of Field Programmable Gate Array based systems

Transcription:

Office for Nuclear Regulation ASSESSMENT REPORT Civil Nuclear Reactors Programme NNB Genco: Hinkley Point C Pre-Construction Safety Report 2012 Assessment Report for Work Stream B14, Radiation Protection Assessment Report: ONR-CNRP-AR-13-100 Version 2 13 March 2014 Template Ref. ONR-DOC-TEMP-004 Revision 4

Crown copyright 2014 COPYRIGHT You may reuse this information (excluding logos) free of charge in any format or medium, under the terms of the Open Government Licence. To view the licence visit TTUUwww.nationalarchives.gov.uk/doc/opengovernment-licence/, write to the Information Policy Team, The National Archives, Kew, London TW9 4DU, or email psi@nationalarchives.gsi.gov.uk. Some images and illustrations may not be owned by the Crown so cannot be reproduced without permission of the copyright owner. Enquiries should be sent to copyright@hse.gsi.gov.uk. Unless otherwise stated, all corporate names, logos, and Registered and Trademark products mentioned in this Web site belong to one or more of the respective Companies or their respective licensors. They may not be used or reproduced in any manner without the prior written agreement of the owner(s). For published documents, the electronic copy on the ONR website remains the most current publically available version and copying or printing renders this document uncontrolled. Page 1

EXECUTIVE SUMMARY This assessment report (AR) reviews that portion of the Hinkley Point C Pre-Construction Safety Report 2012 (HPC PCSR 2012) that falls within the scope of Work Stream B14 Radiological Protection. This material lies in HPC PCSR 2012 sub Chapters 12.2 and 12.6. A final version of the Generic Design Assessment (GDA) Pre-Construction Safety Report (PCSR) issued in November 2012 formed the basis for issue by ONR on 13 December 2012 of a Design Acceptance Confirmation (DAC) for the UK EPR design. The GDA PCSR addressed only the key elements of the design of a single UK EPR unit (the generic features on the nuclear island ) and excluded ancillary installations that a potential purchaser of the design could choose after taking the site location into account. Certain matters were also deemed to be outside the scope of the GDA PCSR. In contrast HPC PCSR2012 addresses the whole Hinkley Point C licensed site comprising the proposed twin UK EPR units and all ancillary installations. Some matters that were outside the scope of GDA PCSR are also addressed in HPC PCSR2012. As the generic features were addressed in the GDA process, my focus is on site-specific documentation that has not been formally assessed by ONR previously. The remaining, generic documentation has been copied into PCSR2012 from an earlier March 2011 GDA PCSR but this has now been superseded by the November 2012 GDA PCSR report.. It is important to note that HPC PCSR2012 alone is not sufficient to inform a future ONR decision on whether to permission construction of Hinkley Point C. NNB Genco intends to submit a major revision to HPC PCSR2012 before seeking consent for Nuclear Island construction which will fully integrate the final GDA PCSR and will be supported by other documentation I have examined the changes in sub-chapters 12.2 and 12.6 of PCSR 2012. I conclude that they are satisfactory, but reserve my position on the detailed supporting documents, which may merit a more detailed analysis later in the regulatory process. I do not have any Regulatory Findings as a result of the changes. Page 2

LIST OF ABBREVIATIONS AF Assessment Finding BMS (ONR) How2 Business Management System DAC Design Acceptance Confirmation GDA Generic Design Assessment HSE Health and Safety Executive HPC PCSR2012 Hinkley Point C Pre-Construction Safety Report 2012 LC Licence Condition ONR Office for Nuclear Regulation (an agency of HSE) PCSR Pre-construction Safety Report SAP Safety Assessment Principle(s) (HSE) SSC System, Structure and Component TAG Technical Assessment Guide(s) (ONR) Page 3

TABLE OF CONTENTS 1 INTRODUCTION... 5 1.1 Background... 5 1.2 Scope... 5 1.3 Methodology... 6 2 ASSESSMENT STRATEGY... 7 2.1 Standards and Criteria... 7 2.2 Safety Assessment Principles... 7 2.2.1 Technical Assessment Guides... 7 2.3 Use of Technical Support Contractors... 7 2.4 Integration with other Assessment Topics... 7 2.5 Out-of-scope Items... 7 3 LICENSEE S SAFETY CASE... 8 3.1 HPC PCSR2012 Material Assessed... 8 4 ONR ASSESSMENT... 9 4.1 Scope of Assessment Undertaken... 9 4.2 Assessment... 9 4.2.1 Sub-chapter 12.2: Definition of Radioactive Sources in the Primary Circuit... 9 4.2.2 Sub-chapter 12.6: Normal Operation Dose Assessment For Public... 10 5 CONCLUSIONS AND RECOMENDATIONS... 11 5.1 Conclusions... 11 6 REFERENCES... 12 Tables Table 1: Relevant Safety Assessment Principles Considered During the Assessment Page 4

1 INTRODUCTION 1.1 Background 1 This report presents the findings of the assessment of that portion of the Hinkley Point C Pre-Construction Safety Report 2012 (HPC PCSR2012, Ref. 1) that falls within the scope of Work Stream B14, Radiation Protection. 2 Assessment was undertaken in accordance with the requirements of the Office for Nuclear Regulation (ONR) How2 Business Management System (BMS) procedure AST/003 (Ref. 2). The ONR Safety Assessment Principles (SAP), Ref. 3, together with supporting Technical Assessment Guides (TAGs), Ref. 4, have been used as the basis for this assessment. 3 This AR has been written to support a Summary Assessment Report that addresses whether HPC PCSR2012 demonstrates suitable progress towards meeting ONR s requirement for an adequate Pre-Construction Safety Report. To this end this AR provides guidance through Assessment Findings (AF) on matters that need to be addressed in the next revision of HPC PCSR 1.2 Scope 4 The scope of this report covers Work Stream B14, Radiation Protection. This material lies in HPC PCSR2012 Chapter 12. 5 A final version of the Generic Design Assessment (GDA) Pre-Construction Safety Report (PCSR) issued in November 2012 formed the basis for issue by ONR on 13 December 2012 of a Design Acceptance Confirmation (DAC) for the UK EPR design. The GDA PCSR addressed only the key elements of the design of a single UK EPR unit (the generic features on the nuclear island ) and excluded ancillary installations that a potential purchaser of the design could choose after taking the site location into account. Certain matters were also deemed to be outside the scope of the GDA PCSR. 6 In contrast HPC PCSR2012 addresses the whole Hinkley Point C licensed site comprising the proposed twin UK EPR units and all ancillary installations. Some matters that were outside the scope of GDA PCSR are addressed in HPC PCSR2012. As the generic features were addressed in the GDA process, attention has been concentrated here on site-specific documentation that has not been formally assessed by ONR previously. The remaining, generic documentation has been copied into PCSR2012 from an earlier March 2011 GDA PCSR but this has now been superseded by the November 2012 GDA report. The generic documentation has only been revisited if recent developments have materially affected the case being made. 7 It is important to note that HPC PCSR2012 alone is not sufficient to inform a future ONR decision on whether to permission construction of Hinkley Point C and NNB Genco intends to submit other supporting documentation. Note also that HPC PCSR2012 will be superseded by a further site-specific revision intended to fully reflect the final GDA PCSR and other design changes from Flammanville 3 which is the reference design for Hinkley Point C. 8 It should also be noted the approach to safety function categorisation and safety system classification agreed during GDA is not fully reflected in HPC PCSR2012 which largely uses the approach employed on Flammanville 3. The integration of the methodology agreed during GDA will be demonstrated in the next revision of HPC PCSR. Page 5

1.3 Methodology 9 The methodology for the assessment follows the requirements of the ONR BMS produce assessments step in the nuclear safety permissioning process and Ref. 2 in particular in relation to mechanics of assessment. Page 6

2 ASSESSMENT STRATEGY 10 My assessment strategy is set out in this section. This identifies the scope of the assessment and the standards and criteria that have been applied. 2.1 Standards and Criteria 11 The relevant standards and criteria adopted within this assessment are principally the Safety Assessment Principles (SAP), Ref. 2, internal ONR Technical Assessment Guides (TAG), Ref. 3, relevant national and international standards and relevant good practice informed from existing practices adopted on UK nuclear licensed sites. The key SAPs and relevant TAGs are detailed within this section. National and international standards and guidance have been referenced where appropriate within the assessment report. Relevant good practice, where applicable, has also been cited within the body of the assessment. 2.2 Safety Assessment Principles 12 The key SAPs applied within the assessment are included within Table 1 of this report. 2.2.1 Technical Assessment Guides 13 The following Technical Assessment Guides have been used as part of this assessment (Ref. 4): Radiological Protection. T/AST/038 Radiological Analysis Normal Operation. T/AST/043 2.3 Use of Technical Support Contractors 14 Technical support contractors were not used for this assessment. 2.4 Integration with other Assessment Topics 15 There were no interfaces with other topic areas within ONR for this assessment due to the very limited changes from the GDA PSR. Whilst the Environment Agency have an interest in this area they did not take part in the review of PCSR 2012. 2.5 Out-of-scope Items 16 Doses to persons off-site resulting from routine discharges of radioactive material are outside the scope of the assessment, as explained in section 4 below. Page 7

3 LICENSEE S SAFETY CASE 3.1 HPC PCSR2012 Material Assessed 17 The material relating to Work Stream B14, Radiation Protection, is located in Chapter 12. However the majority of this chapter is unchanged from the GDA PCSR. The only documentation that has not been formally assessed by ONR previously, and therefore falls to me to consider, is in sub chapters 12.2 and 12.6. However even these chapters require little new assessment, the reasons for this are detailed in section 4 of this report. Page 8

4 ONR ASSESSMENT 18 This assessment has been carried out in accordance with ONR HOW2 BMS policy (Ref. 2). 4.1 Scope of Assessment Undertaken 19 I have considered sub chapters 12.2, Definition of Radioactive Sources in the Primary Circuit, and 12.6 Normal Operation Dose Assessment for Public. 4.2 Assessment 4.2.1 Sub-chapter 12.2: Definition of Radioactive Sources in the Primary Circuit 20 The quantification and use of the inventory of radioactive material is important in the estimation of radiation exposures, and its optimisation is a key factor in the achievement of maintaining doses as low as reasonably achievable (ALARP), which is fundamental to radiation protection. A great deal of work was put into this at GDA by the requesting parties, and by ONR in it s assessment. In particular a regulatory observation, RO- UKEPR-73 (Ref. 5) was generated, and the response to this by the requesting parties was key to ONR s findings. The assessor s conclusion was In my opinion and in the opinion of the TSC, the evidence to substantiate the arguments relating to radiation sources regarding information on the source term, and reductions in the source term through selection of materials associated with the primary circuit, was suitable and sufficient. This is clearly important to my assessment of PCSR 12. 21 The assessor also made the finding The licensee shall provide procurement procedures that require a review of materials associated with the primary coolant before purchase of those materials from their supplier in order to identify if there are any improvements in reductions in levels of cobalt or any other elements in materials which might lead to further reductions in radiation exposure of workers, and which would not compromise the functionality of those materials. This shall be complete before mechanical, electrical and control and instrumentation systems are delivered to site. NNB Genco are currently working on resolution of this finding, and it will be of importance in respect of future submissions. However it does not impact on the 2012 version of the PCSR and I do not consider it further here. 22 NNB Genco have developed sub-chapter 12.2 of PCSR 2012 from GDA PCSR 2011 consolidating the primary source term information within this sub-chapter, incorporating information on the source term definition from GDA PCSR 2011 sub-chapter 11.1. The crucial information defining the radioactive sources in the primary circuit (the subject of this sub-chapter) is in tables 1 to 3 and figures 1 and 2. These give the specific concentrations of radionuclides in the primary circuit for steady-state operation and shutdown transient, and for corrosion product deposits in the primary loops. This information is identical to that in tables 1 and 2 of the GDA PCSR sub-chapter 11.1, table 3 of sub-chapter 12.2 and figures 1 & 2 of sub-chapter 11.1. Hence everything that flows from these figures, and was assessed in depth by ONR assisted by the TSC during GDA, is unchanged, and I do not need to revisit it. 23 The rest of the changes in sub-chapter 12.2 are largely corrections, clarifications and amplifications. However, further references have been added, one of which is Analysis of UK EPR Source Term: Identification, Quantification and Characterisation (Ref 6), which provides analyses to substantiate the primary circuit source term. This is a major (154 pages) highly technical report covering a wide range of technical disciplines. Detailed Page 9

assessment of this would require a review by a TSC. In view of what was done for GDA as described above, I do not consider that this would be proportionate or well targeted at this juncture. However this does not preclude commissioning such a review at a later stage in the development of the design and the safety case. 4.2.2 Sub-chapter 12.6: Normal Operation Dose Assessment For Public 24 This sub-chapter is new; there was no equivalent sub chapter in the GDA PCSR. Notwithstanding this, an assessment was carried out by ONR for GDA (Ref 7). 25 Routine exposures of the public are regulated by the environment agency, with the exception of direct radiation originating within the licensed site boundary, which falls to ONR. My assessment is limited to this aspect, which is covered in section 4.4.2 and table 4 of sub-chapter 12.6 of PCSR 2012. 26 The licensee estimates conservatively that the most exposed member of the public for direct radiation would receive an exposure of 1.5 microsievert per year. The numerical values in the SAPs give the target and a legal limit for effective dose in a calendar year for any person off the site from sources of ionising radiation originating on the site as a BSL of 1000 microsievert and BSO of 20 microsievert. Thus the licensee s conservative estimate is more than a factor of 10 below the BSO. 27 HSE s SAPs state: The BSOs also recognise that there is a level beyond which further consideration of the case would not be a reasonable use of NII resources, compared with the benefit of applying the effort to other tasks. Inspectors need not seek further improvements from the dutyholder but can confine themselves to assessing the validity of the arguments that the dutyholder has presented. In accordance with this I have restricted my assessment to the simple question of whether the figure of 1.5 microsievert per year is the right order of magnitude. This is clearly the case based on the assessment done by ONR and calculations performed by its TSC for GDA (Ref 7) and the fact that the assumptions on distance and occupancy were more conservative than the real situation at Hinkley. 28 I therefore conclude that the changes introduced in PCSR 2012 are satisfactory. Page 10

5 CONCLUSIONS AND RECOMENDATIONS 5.1 Conclusions 29 I have examined the changes in sub-chapters 12.2 and 12.6 of PCSR 2012 compared with the GDA PCSR. I conclude that they are satisfactory, but reserve my position on the detailed supporting documents, which may merit a more detailed analysis later in the regulatory process. I do not need to make any Regulatory Findings as a result of the changes. No recommendations are necessary. Page 11

6 REFERENCES 1 NNB GenCo Submission of HPC PCSR 2012, Letter NNB-OSL-RIO-000322, ONR-HPC-20337N, 6 December 2012, TRIM 2013/16143 2 ONR How2 Business Management System. Guidance on Production of Reports, AST/003 Revision 7, September 2013 3 Safety Assessment Principles for Nuclear Facilities. 2006 Edition Revision 1. HSE. January 2008. www.hse.gov.uk/nuclear/sap/sap2006.pdf 4 Technical Assessment Guides (TAGs). www.hse.gov.uk/nuclear/tagsrevision.htm 5. RO-UKEPR-73.A1- Source term. Letter from EDF AREVA Project Front Office to ND. EPR00518N. 10 August 2010. TRIM Ref. 2010/349163 6. Analysis of UK EPR source term: identification, quantification and characterisation, July 2011, EDF EDF NNB ECEF110448 Revision A 7. Step 4 Radiological Protection Assessment of the EDF and AREVA UK EPR Reactor. ONR Assessment Report ONR-GDA-AR-11-025. TRIM Ref. 2010/581507. Page 12

Report ONR-CNRP-AR-13-XXX Table 1 Relevant Safety Assessment Principles Considered During the Assessment SAP No. SAP Title Description NT.1 Assessment against targets A safety case should be assessed against numerical targets and legal limits for normal operation, design basis faults, and radiological accident risks to people on and off the site. Page 13