Advancement simulation of parallel tunnels and their interchange with two other subway lines using a new FEM approach, a case study

Similar documents
Numerical Modeling of Grouted Soil Nails

EFFECT OF CHANGING CONFIGURATIONS AND LENGTHS OF PILES ON PILED RAFT FOUNDATION BEHAVIOUR

Settlement Analysis of Piled Raft System in Soft Stratified Soils

INFLUENCE OF PILES ON LOAD- SETTLEMENT BEHAVIOUR OF RAFT FOUNDATION

NALYSIS OF STABILIZING SLOPES USING VERTICAL PILES

Journal of American Science 2015;11(8) Soil Nailing For Radial Reinforcement of NATM Tunnels

Optimum Design of Nailed Soil Wall

Bearing Capacity of Strip Footings on Two-layer Clay Soil by Finite Element Method

Modelling of Rebar and Cable Bolt Behaviour in Tension/Shear

Finite Element Study of Using Concrete Tie Beams to Reduce Differential Settlement Between Footings

Numerical Analysis of Piled Raft Foundation using Fem with Interaction Effects

Title. Author(s) P. WULANDARI. Issue Date Doc URLhttp://hdl.handle.net/2115/ Type. Note. File Information AND ANALYTICAL METHODS

SImulation of MONopile installation - JIP SIMON

Predicting the temperature and strength development within cemented paste backfill structures

Monopile as Part of Aeroelastic Wind Turbine Simulation Code

Effect of Tie Beam Dimensions on Vertical and Horizontal Displacement of Isolated Footing

Study on embedded length of piles for slope reinforced with one row of piles

STABILITY. SECURITY. INTEGRITY.

TIE BEAMS RESTING ON REPLACED SOIL. 1 and 2 Civil Engineering department Faculty of Engineering, Al Azhar University Cairo, Egypt IJSER

Ground Improvement Prof. G. L. Sivakumar Babu Department of Civil Engineering Indian Institute of Science, Bangalore. Lecture No.

Analysis of a Nailed Soil Slope Using Limit Equilibrium and Finite Element Methods

ANALYSIS OF PILE-RAFT FOUNDATIONS NON- RESTED AND DIRECTLY RESTED ON SOIL

Research on Deformation of Soil Nailing Structure with Flexible Facing

Failure of Engineering Materials & Structures. Code 34. Bolted Joint s Relaxation Behavior: A FEA Study. Muhammad Abid and Saad Hussain

Transactions on Engineering Sciences vol 7, 1995 WIT Press, ISSN

Experimental Study on Pile Groups Settlement and Efficiency in Cohesionless Soil

Secondary Consolidation (Creep)

CHAPTER 2 ELECTROMAGNETIC FORCE AND DEFORMATION

Stress Analysis of Flanged Joint Using Finite Element Method

Piled raft foundation for the W-TOWER Tel Aviv

Load-Displacement behavior of passive piles in cohesive soils

Radial Basis Function to Predict the Maximum Surface Settlement Caused by EPB Shield Tunneling

Numerical simulation of screw piles under axial loads in a cohesive soil

The UCD community has made this article openly available. Please share how this access benefits you. Your story matters!

Numerical investigation of soil nail wall during construction

Effect of Pile Bending Stiffness on Static Lateral Behavior of a Short Monopile in Dry Sand

Module 5 : Design of Deep Foundations. Lecture 20 : Introduction [ Section 20.1 : Introduction ]

The effect of underground cavities on design seismic ground motion

Should We Upgrade to Phase 2 6.0?

Tabriz Urban Railway Organization. An Introduction to Tabriz Metro Line 3 Project

AN INNOVATIVE FEA METHODOLOGY FOR MODELING FASTENERS

SEA SELF DRILLING, THREADED, HOLLOW BAR / GROUT-ABLE SOIL NAILS / ANCHORS

Dimension Effect on P-y Model Used for Design of Laterally Loaded Piles

Information Systems and Artificial Intelligence Technology Applied in Pile Design

A Full 3-D Finite Element Analysis of Group Interaction Effect on Laterally Loaded Piles

ABSTRACT INTRODUCTION. Immediate Displacement of the Seabed During Subsea Rock Installation (SRI) 3

ANALYSIS OF LATERALLY LOADED PILE GROUPS

R&D for OWT Foundation Design

[47] Strain wave gearing design system

Parametric Study on Piled Raft Foundation in Sand Using Numerical Modelling

Data Acquisition in TBM tunnelling. Tim and Lars Babendererde, Frank Stahl, Philipp Elsner

TEST SERIES TO EVALUATE THE STRUCTURAL BEHAVIOUR OF ISOBOARD OVER RAFTER SYSTEM

VIBRATIONAL TESTING OF A FULL-SCALE PILE GROUP IN SOFT CLAY

Reinforcement with Soil Nails

LAPPING FOR MIRROR-LIKE FINISH ON CYLINDRICAL INNER AND END SURFACES USING THE LATHE WITH LINEAR MOTOR

GEM-P Progress Report Mechanics (July 2006)

SKIN FRICTION OF PILES COATED WITH BITUMINOUS COATS Makarand G. Khare 1 and Shailesh R. Gandhi 2

Piles Capacity Reference Manual

Risk control online deformation monitoring inside an urban TBMdriven tunnel using the tshape measurement system

IJSRD - International Journal for Scientific Research & Development Vol. 4, Issue 05, 2016 ISSN (online):

INTERNATIONAL JOURNAL OF GEOMATICS AND GEOSCIENCES Volume 5, No 2, 2014

CHAPTER 4 COMPARISON OF DYNAMIC ELASTIC BEHAVIOUR OF COTTON AND COTTON / SPANDEX KNITTED FABRICS

SIMULATION AND EXPERIMENTAL WORK OF SINGLE LAP BOLTED JOINT TESTED IN BENDING

Use of Soil Nails to Upgrade Loose Fill Slopes

Fastener Modeling for Joining Parts Modeled by Shell and Solid Elements

Expanding the Frontiers of Geotechnical Engineering

Dependence of Predicted Dewatering on Size of Hydraulic Stress Used for Groundwater Model Calibration

Sprocket and Hub Bolt Analysis for Slip-Critical Bolted Applications in Mining and Mineral Processing Equipment

Heat-Mechanics Interaction Behavior of Laminated Rubber Bearings under Large and Cyclic Lateral Deformation

The DFI Institute is organized to serve as a primary means through which members of the Institute may participate in improvement of the planning,

Module 6 : Design of Retaining Structures. Lecture 30 : Dewatering [ Section 30.1 : Introduction ]

Printed in U.S.A., Copyright Penton Media, Inc. All rights reserved. Machine Design (ISSN ) is published semimonthly by Penton Media,

Rotary Steering Spindle System Parameter Design Based on Fatigue Life

Nomograms for calculating the safety factor of homogeneous earth dams in long-term stability

LS-DYNA USED TO ANALYZE THE MANUFACTURING OF THIN WALLED CANS AUTHOR: CORRESPONDENCE: ABSTRACT

EFFECTS OF GEOMETRY ON MECHANICAL BEHAVIOR OF DOVETAIL CONNECTION

Design, Development and Analysis of Clamping Force of a Cylinder of Fixture for Casing of Differential

DESIGN AND ANALYSIS OF FORM TOOL

Advanced Ground Investigation Techniques to Help Limit Risk or Examine Failure. Advanced Subsurface Investigations

3-D Finite Element Analysis of Bolted Joint Using Helical Thread Model

Drawing of Hexagonal Shapes from Cylindrical Cups

Materials. Density, Hooke's law, Young modulus. 174 minutes. 174 marks. Page 1 of 29

3.3.3 Station Locations

Investigation of the Behavior of Piled Raft Foundations in Sand by Numerical Modeling

Nonlinear behavior of Reinforced Concrete Infilled Frames using ATENA 2D

Consideration of Tool Chamfer for Realistic Application of the Incremental Hole-Drilling Method

Structure Analysis of Transmitter Coil in Electromagnetic Launch Interceptors

Analysis and Parametric Study of Piled Raft Foundation Using Finite Element Based Software

TESTING EQUIPMENT SHEAR STRENGTH PARAMETERS SOIL. established in 1972

CALIBRATION OF COMPUTER PROGRAM SASSI FOR VIBRATION TRANSMISSIBILITY ANALYSIS IN UNDERGROUND STRUCTURES USING FIELD MEASURED DATA

FEKO-Based Method for Electromagnetic Simulation of Carcass Wires Embedded in Vehicle Tires

Available online at ScienceDirect. Procedia Engineering 125 (2015 )

Formulae for calculations A) Nomenclature

DEVELOPMENT OF SMALL-BORE, LONG DISTANCE, CURVED-CONDUIT TUNNELING ROBOT

Design of structural connections for precast concrete buildings

UNIVERSITY OF HANNOVER Institute of Soil Mechanics, Foundation Engineering and Waterpower Engineering Prof. Dr.-Ing. Martin Achmus

Design and Analysis of Spindle for Oil Country Lathe

UNIT 2.1: Routine check before machines operation. Unit Objectives Tools and Equipment for Routine Check. Spanner Set

Finite element analysis of circular cross sections subjected to combined loading

DENTAL IMPLANT NUMERICAL MODELING USING PILE MODLEING SCHEME IN CIVIL ENGINEERING FIELD

Transcription:

Geotechnics for Sustainable Development - Geotec Hanoi 0, Phung (edt). Construction Publisher. ISBN 978-60-8-00-8 Advancement simulation of parallel tunnels and their interchange with two other subway lines using a new FEM approach, a case study Alireza Afshani Waseda University, Tokyo, Japan. E-mail: aafshani@moegi.waseda.jp Hiroshi Dobashi Metropolitan Expressway Company Limited, Japan, E-mail: h.dobashi8@shutoko.jp Kazuhito Komiya Chiba Institute of Technology, Japan, E-mail: komiya.kazuhito@it-chiba.ac.jp Hirokazu Akagi Waseda University, Tokyo, Japan. E-mail: akagi@waseda.jp Keywords: D FEM, EPB tunneling, interchange, tunnel, case study, parallel tunnels, monitoring. ABSTRACT: Advancement of a tunnel face results in the disturbance and redistribution of the primary in situ stress field. Soil deformation, pore water pressure generation, and induced stress and strain are among engineer s interest. Depending on soil type, rate of TBM machine advancement, and also tunnelling method, soil may behave between the two extreme cases of drained or undrained condition. Understanding soil drainage condition often is not an easy task, however using numerical simulation programs, generated pore water pressure can be estimated and as a result effective and total stress can be obtained. In this paper, a simple procedure has been employed for drainage determination to be used in pre-codded Finite Element Analysis (FEA) program. The method is described and then an Earth Pressure Balance (EPB) tunnelling case study is analysed using proposed procedure. In this case study, two parallel tunnel lines which are being excavated by EPB method interchange with another two subway lines almost perpendicularly. Induced ground movement due to these underground constructions are measured in several locations and then a comparison is made with finite element analysis result.. INTRODUCTION In congested and populated areas like Tokyo metropolitan, it is almost impossible to avoid performing underground construction close to various structures. Currently, underground construction is performed at larger area and deeper depth than before (Akagi, 00). Starting of new underground activity, in these cases, could be challenging and many considerations should be taken into account. Limited knowledge of actual ground condition may lead to some assumptions and simplification to enable designer to do the predictions. Numerical simulations are mighty tool for prediction and investigation of soil behaviour due to tunnelling. Accessibility to monitoring field data made it possible to improve numerical prediction to match actual ground behaviour during underground construction. Advancement of a tunnel face results in the disturbance and redistribution of the primary in situ stress field (Eberhardt, 00). Soil deformation, pore water pressure generation, and induced stress and strain are among engineer s interest. Depending on soil type, rate of TBM machine advancement, and also tunnelling method, soil may behave between the two extreme cases of drained or undrained condition. Understanding soil drainage condition often is not an easy task, however using FEA programs, generated pore water pressure can be estimated and as a result effective and total stress can be obtained. In this paper, a simple procedure has been employed for drainage determination to be used in pre-codded FEA program. In the first part, the method is described. In the second part an EPB tunnelling case study is analyzed using proposed procedure. In this case study, two parallel tunnel lines which are being excavated by EPB method interchange with another two subway lines almost perpendicularly. Induced ground movements due to

these underground constructions are measured in several locations and then a comparison is made with FEM output.. NUMERICAL APPROACH. Outlines of Used numerical simulation Numerical D finite element analysis program used here is a Fortran coded FEM program which was developed by Komiya et al. (Komiya, 999). Tunnel advancement simulation is carried out by dividing of whole excavation process into a number of stages. Tunnel face pressure in front of TBM machine changes linearly from top to the bottom of shield machine face. Tail void grouting is also applied perpendicular to tunnel perimeter through the length of one ring at the back of shield machine. Difference load between face pressure and initial earth pressure and also between grouting pressure and initial earth pressure are applied respectively to elements in front and at the back of shield machine.. Superposing method In each step, same mesh is used for input loads to be applied. Applying these forces, nodes of elements are displaced, and stress and strain are developed throughout the mesh. Developed stresses in elements at each step are used as an initial stress for the next loading step. Final displacement of any node at any step (any advancement step of tunnels) is obtained by adding of all deformation of previous steps plus developed deformation of current step. Same procedure is taken for stress and strain calculation.. Drained and Undrained criteria Depending on soil type, rate of TBM machine advancement, and also tunneling method, soil may behave between the two extreme cases of drained or undrained condition. For lowpermeability and high rate of tunnel advancement, undrained behavior is dominant. On the other hand, for high permeability soil, and slow rate of advancement, drained condition is expected. For other cases, soil condition varies between these two extreme cases. If the soil condition and TBM machine advancement rate do not vary too much, distance of tunnel face which is considered drainage boundary from monitoring location also play important role in drainage determination (Anagnostou, 996). In other words, the areas too close and too far from drainage boundaries show drained and undrained behaviour respectively. Latter factor which is called distance factor was used for drainage determination in FEM calculation. It should be noted that during drained condition, earth pressure is calculated using effective stress of soil, while during undrained condition total stress of soil is used for earth pressure calculation. Figure. Yokohama site; launching shaft, Inbound and Outbound lines, Subway line A and B have been shown

. CASE STUDY. Site description A motorway of total length about 8. km is under construction in Yokohama, Japan by Tokyo Metropolitan Expressway Company to link between the Kohoku Interchange of the Third- Keihin Road and the Namamugi Junction of the Yokohama-Haneda Airport Line. About 5.9 km of this so called Yokohama Circular Northern Route is a side by side parallel tunnel, (Outbound and Inbound lines) each of them having diameter of about.5 m. Main part of this route is excavated using Earth Pressure Balanced (EPB) Shield tunneling method. Each of the lines is excavated separately and one of the lines is about 0 meter ahead of the other one. In order to check the safety of underground construction, three monitoring locations (ML, ML, ML), were located along the two tunnel lines after of about 5, 50, and 80 meter respectively from launching shaft. Parallel tunnels in their path also interchange with another two subway lines (Subway line A, and Subway line B) almost perpendicularly. In addition to mentioned measurement locations (ML, ML, ML), some measurement devices were also located on subway lines to measure their deformation during excavation of parallel tunnels. Subway lines were under operation during construction of new parallel tunnels, so it was uppermost important to minimize the ground deformation during new tunnels installation. Measurement points in monitoring locations and also in subway lines measure soil deformation before, during, and after of passing parallel tunnels. Fig. shows an aerial image of Yokohama area in Japan, in which paralle ltunnels (Outbound and Inbound lines), subway lines (Subway line A and subway line B) and also launching shaft have been highlighted. Newly parallel tunnels have a few degrees of downward inclination. These lines (Outbound and Inbound lines) pass below the subway lines (line A and Line B) by vertical clearance varying between.5 to 6.5 meters. The parallel shield tunnels lining composed of concrete rings with an outer diameter of. m and an inner diameter of.5 m, each having length of m. Groundwater level was nearly close to surface, typically between. to.8 below ground surface.. Filed measurement data Numbers of measurement devices in ML and also along subway lines have been shown in Table. Table. Number of measurement devices Name Number ML 6 on Outbound line and 6 on Inbound line according to Fig.. Subway 9 along the subway springline, line A according to Fig. (AV to AV9) Subway 0 along the subway springline, line B according to Fig (BV to BV0) As previously mentioned, in order to check the safety of tunneling construction, three monitoring location (ML, ML, and ML) and also some measurement point on subway lines were installed. Vertical and horizontal displacements of soil were measured in these locations. As in this paper only part of the route dealing with ML, and interchange by subway lines were taken into account, therefore, only field data regarding these location have been presented. Fig. shows the cross section of Outbound and Inbound lines in monitoring location (ML). Figure. Cross section of newly constructed parallel tunnels in the ML; Outbound and Inbound lines as well as measurement devices location are shown.. Numerical model and material property In Yokohama site, part of the route including ML and interchange of parallel tunnels with subway lines were taken into account and then a mesh was created for this part to be used for FEM analysis. Width, length, and height of created D mesh are 8 m, 6 m, and 55 m respectively. Fig. shows the D mesh. Furthermore, orientation of parallel tunnels and their interchange with subway lines of A and B have been illustrated in Fig.. The shield tunnels advance through the ground mainly composed of mudstone (Km), sandy mudstone (Kms) and sand and sandstone (Ks), all of which

have an Nspt value of 50 or higher. The unconfined compressive strength is 000 kn/m or higher for Km and Kms. The ground is hard. Orientation of parallel tunnels interchanging with subway lines have been illustrated in Fig. Soil layers and related soil properties of these layers are summerized in Table. In Table, γ is unit weight of soil, c is cohesion, φ is internal friction angel, E is elastic mudulus, ν is possion ratio, K 0 coefficient of earth pressure at rest, and OCR os overconsolidation ratio. As it can be seen, the major part of the tunnel instalation is carried out in hard soil (Km, Kms, and Km). Reference to Table, because of high value of soil Elastic modulus, and OCR, and due to the large and complex mesh, linear elsatic was selcted as a constitutive relationship between stress and strain for all soil type. By comparison of result of FEA with measurement data, later it was found that in this kind of hard soil, this assumption is not far from reality. Because induced strains in Earth Pressure Balance method in which input forces are nearly equall to initial soil condition, are quiet small. In this model, whole of numerical simulation includes 5 loading step. Used values of face pressure, and tail void grouting pressure in numerical simulation were exact the same as field values... Monitoring location After passing about 80 meter (90 rings) from launching shaft along the parallel tunnel route, a monitoring section namely ML was placed to measure ground horizontal and vertical deformation. Figure. Finite Element Model (Dimension in m) Figure. Orientation of new tunnels and existeing subway lines Table. Soil layer s properties Depth (m) Symbol Soil type γ (kn/m ) c (kn/m ) φ (degree) E (MPa) ν K 0 OCR 0-.5 B Fill material.0 0 0. 0.5 0.8 -.5-0 Ac Cohesive soil 5.5 5. 0.5 0.8.9 0-. As Sand 8.0 0 6.0 0.0 0.6..-.5 Ks Sand and sandstone 9.5 60 89 0.0 0. >0.5-7.5 Kms Sandy mudstone 8.0 80 0 9 0.5 0.6 >0 7.5-9 Ks Sand and sandstone same as Ks 9- Km Mudstone 8.5 00 7 0 0.5 0.6 >0-7 Ks Sand and sandstone same as Ks 7-8.5 Kms Sandy mudstone same as Kms 8.5-0 Ks Sand and sandstone same as Ks 0- Kms Sandy mudstone same as Kms -.5 Ks Sand and sandstone same as Ks.5-55 Km Mudstone same as Km Based on STANDARD SPECIFICATIONS FOR SHIELD TUNNELING, Japan Society of Civil Engineers A value of experience.

Vertical displacement (mm) Vertical displacement (mm) Measured field data of vertical displacement at this location on Outbound and Inbound line are shown in Fig. 5... Subway lines of A and B Along the parallel tunnels, after about 8, and 70 meter respectively ( and 5 lining rings) from launching shaft, subway line A and B are under operation. Depth of existing subway lines are about 5.5 meter below the ground surface. According to Fig., subway line B is almost parallel to Y axes and perpendicular to newly excavating tunnels, but subway line A is somehow diverging from Y axes. On the springline of each of subway line, some measurement devices have been installed (Refer to Table, and Fig. ) for horizontal and vertical movement control. Vertical displacement recorded at field has been shown in Fig. 6 for both Subway line A, and B. Displacement of some points along subway lines far away from tunneling route has not been shown (only AV5 to AV6, and BV6 to BV7 were illustrated in Fig. 6). Reference to Fig. 6, it can be understood that displacement of subway line were less than mm. Because the subway lines were under operation, their movements were strictly controlled probably using ground improvement agents like grouting in soil enclosed between parallel tunnel, and subway lines. Referring to Fig. 7 which shows the vertical displacement along subway lines, it can be also seen that at the points where parallel tunnels are passing (In Fig. 7, this locations have been shown by arrow), vertical displacement are nearly equal to zero. According to field data, parallel tunnel excavation rate (TBM machine advancement rate) on both lines averagely was between 5-0 m/day, while this rate increased to m/day during passing under the subway lines. Fast passing of TBM machine also dictates undrained condition which leads to small amount of ground deformation.. RESULTS After creating of the mesh, excavation steps for parallel tunnels were performed using FEM program. Whole of simulation carried out in 5 loading steps in which each of the tunnel lines moved 68 rings length. After performing of simulation, vertical displacement of points in the same location of field measurement points in ML, and also along subway lines were plotted. In each of loading steps same mesh was used with the aforementioned mentioned method as section...0 TBM face under ML Tail of TBM under ML Outbound line, Filed data.0 9.0 7.0 5.0.0.0 5 -.0 Ground surface -.0 Distance from ML (m).0 TBM face under ML Tail of TBM under ML Inbound line, field data 9.0 7.0 5.0.0.0 -.0 -.0 5 Ground surface -5.0 Distance from ML (m) Figure 5. Recorded data in field; vertical displacement of soil at ML, Inbound and Outbound line (Refer to Fig. for measurement points location) 5

vertical displacement (mm) vertical displacement (mm) Vertical displacement (mm) Vertical displacement (mm).0.0.0 0.0 -.0 Subway line A, Field data -.0 /9 /0 / / / / /5 /6 /7 /8 /9 /0 / / / / /5 /6 /7 /8 /9 /0 / / / / -.0 Date of exvacation (day) Outbound line tunnel passes under Subway Line A Inbound line tunnel passes under Subway Line A AV5 AV6 AV7 AV8 AV9 AV0 AV AV AV AV AV5 AV6.00.00.00 0.00 -.00 -.00 /9 /0 / / / / /5 /6 /7 /8 /9 /0 / / / / /5 /6 /7 /8 /9 /0 / / / / -.00 Date of exvacation (day) Subway line B, Field data Outbound line tunnel passes under Subway Line B Inbound line tunnel passes under Subway Line B BV6 BV7 BV8 BV9 BV0 BV BV BV BV BV5 BV6 BV7 Figure 6. Recorded data in field; vertical displacement of measurement points on subway line A, and B..0.0 Passing location of Outbound line Subway line A, Filed data Passing location of Inbound line Distance of TBM machines along Outbound and Inbound tunnels from subway line A in meter.0-6.0 -.0 0.0.0-9.0 -.0 8.0-7.0.0 -.0 -.0 -.0 AV AV5 AV6 AV7 AV8 AV9 AV0 AV AV AV AV AV5 AV6 AV7 AV8 measurement points along subway line A 7.0 -.0 57.0 -.0 6.0 6.0.0.0.0 Passing location of Outbound line Subway line B, Filed data Passing location of Inbound line Distance of TBM machines along Outbound and Inbound tunnels from subway line B in meter -5.0-70.0 0.0 -.0-60.0 -.0 9.0-5.0 6.0 -.0 -.0 BV BV5 BV6 BV7 BV8 BV9 BV0 BV BV BV BV BV5 BV6 BV7 BV8 8.0-9.0.0 -.0 -.0 0.0 0.0 measurement points along subway line B 0.0.0 Figure 7. Recorded vertical displacement along subway line A, and B. Comparison results of measured data and calculated output have been shown in Figs. 8, 9, and 0. Fig. 8 illustrates vertical displacement of the points in measured data and calculated output at ML. Similarly, Figs. 9, and 0 respectively show measured data and calculated output of measurement points along subway line A, and B. In Fig. 8, calculated results show few millimeter larger values than measured data. Points close to tunnel in depth have larger deformation. Majority of this deformation is about tail void grouting, when TBM machine tail passing the monitoring section. Part of the difference between measured and calculated data arise from the point that overburden due to surface irregularity in field is changing, but in FEM calculation, ground surface is considered to be uniform and flat and overburden value does not change as it does in field. 6

Vertical Displacement (mm) Vertical Displacement (mm) vertical displacement (mm) vertical displacement (mm) 8 6 0 8 6 Outbound TBM face is passing Outbound TBM tail is passing ML, OUTBOUND 0 - -0-5 -0-5 0 5 0 5 0 5 0 5 0 5 50 55 60 65 70 75 80 85 90 95 00 05 0 Distance of TBM face from ML, outbound (m) FEA, FEA, FEA, FEA, FEA, 5 FEA, Ground surface Fiedl, Field, Field, Field, Field, 5 Field, Ground surface 0 8 6 Inbound TBM face is passing Inbound TBM tail is passing 0-0 -5-0 -5 0 5 0 5 0 5 0 5 0 5 50 55 60 65 70 75 80 85 90 95 00 05 0 - Distance of TBM face from ML, inbound (m) ML, INBOUND FEA, FEA, FEA, FEA, FEA, 5 FEA, Ground surface Field, Field, Field, Field, Field, 5 Field, Ground surface Figure 8. Comparison result of field data with FEA output in ML (refer to Fig. for points location). 0 - - / / /6 /8 /0 / / /6 /8 /0 / / /6 /8 /0 / - - Subway Line A, FEA output Date of excavation (day) Outbound TBM under Subway Line A Inbound TBM under Subway Line A FEA, A6 FEA, A5 FEA, A FEA, A FEA, A FEA, A FEA, A0 FEA, A9 FEA, A8 FEA, A7 FEA, A6 FEA, A5 Field, A5 Field A6 Field, A7 Field, A8 Field, A9 Field A0 Field A Filed A Field A Field A Figure 9. Comparison result of field data with FEA output along subway line A. 0 - /6 /7 /8 /9 /0 / / / / /5 /6 /7 /8 /9 /0 / / / / /5 /6 /7 /8 /9 /0 / / / - - Subway Line B, FEA output Date of excavation (day) Outbound TBM under Subway Line B Inbound TBM under Subway Line B FEA, B7 FEA, B6 FEA, B5 FEA, B FEA, B FEA, B FEA, B FEA, B0 FEA, B9 FEA, B8 FEA, B7 FEA, B6 Field, B6 Field B7 Field, B8 Field, B9 Field, B0 Field B Field B Filed B Field B Field B5 FieldB6 Figure 0. Comparison result of field data with FEA output along subway line B. These changes in overburden depth affect earth pressure value which leads to not uniform displacement during tunnel advancement. According to Figs. 9 and 0, it can be seen that field measured vertical displacement is less than mm. Referring to the same figures, calculated value have value less than mm in line A and less than mm in Line B. It should be noted that due to fact that subway lines were under operation during excavation of parallel tunnels, for sure some sort of ground improvement like large extent grouting has been used to lower the ground deformation around subway line to less than allowable value in which in this case is mm. In FEM calculation effect of such soil improvement has not been taken into 7

account. However, trend and value of vertical displacement between measured and calculated date were in good harmony. 5. CONCLUSIONS This paper dealt with EPB tunnelling advancement simulation. In the first part of this paper, a used finite element method is described in brevity. In second part, an EPB tunnel case was studied. In the presented case study, two parallel tunnels were passing under previously constructed subway lines. Because most of the lands above the tunnel routes were private property, and also subway lines were under operation, some monitoring points in both lines ( measurement points in so called ML) as well as along each of subway lines (9, and 0 measurement points in subway A, and B respectively) were considered to check the safety of underground construction by measuring ground displacement. Using previously codded finite element analysis program, tunnelling construction of above mentioned case study was simulated. In this way, pertinent mesh was created, and displacements of same measurement points were obtained. Investigating measured data, and calculated results, and also making a comparison between them, following results is highlighted: A finite element analysis used for tunnelling simulation used a so called superposing method to calculated ground displacement, stress and strains. Output results of FEA displayed that this method is reliable way to calculate ground displacement. Using this method for simulation of mentioned case study showed good harmony between calculated results and measured data. Vertical displacement along subway lines in measured data were less than mm, while this value in calculated results were less than mm for line A, and less than mm for line B. The difference arises from the point that exerted extensive ground improvement in field to decrease the subway settlement and heave to less than allowable value has not been taken into account in finite element calculation. Anagnostou, G and Kovari, K. (996). Face stability conditions with earth-pressure-balanced shields. Journal of Tunneling and Underground Space Technology, vol, pp65-7. Eberhardt, E. (00). Numerical modelling of three-dimension stress rotation ahead of an advancing tunnel face. International Journal of Rock Mechanics and Mining Sciences, vol 8, pp 99-58. Komiya. K, Soga. k, Akagi. H, Hagiwara T, Bolton M.D. (999). Finite element modeling of excavation and advancement processes of a shield tunneling machine. Soils Foundations, Vol. 9, pp7-5. 6. REFERENCES Akagi, H. (00). Geotechnical aspects of current underground construction in Japan. Journal of soils and foundation, vol, pp -. 8

9