QUESTIONNAIRE for Wind Farm Power Stations only

Similar documents
Initial Application Form for Connection of Distributed Generation (>10kW)

IDAHO PURPA GENERATOR INTERCONNECTION REQUEST (Application Form)

Embedded Generation Connection Application Form

Embedded Generation Connection Application Form

Impact Assessment Generator Form

Embedded Generation Connection Application Form

WFPS1 WIND FARM POWER STATION GRID CODE PROVISIONS

NORTH CAROLINA INTERCONNECTION REQUEST. Utility: Designated Contact Person: Address: Telephone Number: Address:

Form B. Connection Impact Assessment Application Form Distribution System

Connection Impact Assessment Application Form

OPERATING, METERING AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 25,000 KILOWATTS

Remotes Case 2&3 Form REINDEER Cases 2&3 -Connection Impact Assessment (CIA) Application

INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY

APPENDIX 1 to LGIP INTERCONNECTION REQUEST FOR A LARGE GENERATING FACILITY

Revision Control. 0 18/07/2012 Initial Document Creation. STAKEHOLDERS The following positions shall be consulted if an update or review is required:

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

Owner/Customer Name: Mailing Address: City: County: State: Zip Code: Phone Number: Representative: Address: Fax Number:

Issued: September 2, 2014 Effective: October 3, 2014 WN U-60 Attachment C to Schedule 152, Page 1 PUGET SOUND ENERGY

Connection Impact Assessment Application

Summary of Relaying Reviews Reporting

ADVANCED CONTROLS FOR MITIGATION OF FLICKER USING DOUBLY-FED ASYNCHRONOUS WIND TURBINE-GENERATORS

Company Directive POLICY DOCUMENT: SD4/7. Relating to 11kV and 6.6kV System Design

ENGINEERING DATA SUBMITTAL For the Interconnection of Generation System

PART 1 OWNER/APPLICANT INFORMATION

Course ELEC Introduction to electric power and energy systems. Additional exercises with answers December reactive power compensation

Level 6 Graduate Diploma in Engineering Electrical Energy Systems

Demand Customer Connection Connection Application Form to the Transmission System

OPERATING, METERING, AND EQUIPMENT PROTECTION REQUIREMENTS FOR PARALLEL OPERATION OF LARGE-SIZE GENERATING FACILITIES GREATER THAN 2,000 KILOWATTS

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW

Table of Contents. Introduction... 1

SOUTH CENTRAL INDIANA REMC Application for Operation of Member-Owned Small Power Generation Systems

Generation Interconnection Study Data Sheet Synchronous Machines

EASTERN ILLINI ELECTRIC COOPERATIVE Application for Operation of Member-Owned Generation

APPLICATION FOR INTERCONNECTION & OPERATIONS OF MEMBER-OWNED GENERATION

Distributed Generation Application Form (Generation of Greater than 20 kw to 15 MW)

APPENDIX B: Generation Interconnection Application Form

If any queries arise ESB Networks DAC can be contacted at or

, ,54 A

Company Directive STANDARD TECHNIQUE: SD7F/2. Determination of Short Circuit Duty for Switchgear on the WPD Distribution System

High Wind Speed Shutdown / Power Available

Fault Ride Through Technical Assessment Report Template

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

State of North Dakota Engineering data submittal Page 1 For interconnection of distributed generation to Otter Tail Power Company

Southern Company Interconnection Requirements for Inverter-Based Generation

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

Company Directive STANDARD TECHNIQUE: SD1E/2. Technical Requirements for Customer Export Limiting Schemes

Shortcomings of the Low impedance Restricted Earth Fault function as applied to an Auto Transformer. Anura Perera, Paul Keller

MEASUREMENT CAMPAIGN AND ASSESSMENT OF THE QUALITY OF SUPPLY IN RES AND DG FACILITIES IN SPAIN

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

How Full-Converter Wind Turbine Generators Satisfy Interconnection Requirements

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 150 KW BUT LESS THAN OR EQUAL TO 550 KW

Intermittent Renewable Resources (Wind and PV) Distribution Connection Code (DCC) At Medium Voltage (MV)

each time the Frequency is above 51Hz. Continuous operation is required

Case Study 1. Power System Planning and Design: Power Plant, Transmission Lines, and Substations

R10. III B.Tech. II Semester Supplementary Examinations, January POWER SYSTEM ANALYSIS (Electrical and Electronics Engineering) Time: 3 Hours

BE Semester- VI (Electrical Engineering) Question Bank (E 605 ELECTRICAL POWER SYSTEM - II) Y - Y transformer : 300 MVA, 33Y / 220Y kv, X = 15 %

Revision 24 of Issue 3 of the Grid Code has been approved by the Authority for implementation on 19 th November 2007.

Effects of Harmonic Distortion I

WIND FARM Flexible AC Transmission Systems

Technical compliance report (TCR) and guidelines. 1. Objective of the TCR (and guidelines) 2. Technical compliance. 3. Content of the TCR

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Application for A Sub-harmonic Protection Relay. ERLPhase Power Technologies

EUROPEAN CONNECTION CONDITIONS (ECC) CONTENTS. (This contents page does not form part of the Grid Code)

Energy Networks Association

Tasmanian Networks Pty Ltd Guideline. Technical Requirements for the Connection of Embedded Generation

Fault Ride Through Principles. and. Grid Code Proposed Changes

TABLE OF CONTENT

Wind Power Facility Technical Requirements CHANGE HISTORY

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH

ELECTRICAL POWER ENGINEERING

SYSTEMS AND COMPONENTS FOR TRANSFORMER TESTING

Network Monitoring and Visibility Summary

Version 2.6 October Comments to this document can be forwarded to:

Company Directive STANDARD TECHNIQUE: TP6F/1. Power Measurement Conventions

DATA REGISTRATION CODE SCHEDULE 1 Page 2 of 15 GENERATING UNIT (OR CCGT MODULE) TECHNICAL DATA POWER STATION NAME: DATA to RTL CUSC Cont ract

Cork Institute of Technology. Autumn 2008 Electrical Energy Systems (Time: 3 Hours)

Simulations of open phase conditions on the high voltage side of YNd05-power plant transformers

1

Distribution Code. Approved by CER. Version: 5.0 Date: April Distribution System Operator ESB Networks Limited

Customer Standard. Standard for Embedded Generation (5MW and above)

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR SMALL GENERATION INTERCONNECTIONS

GENERATOR INTERCONNECTION APPLICATION Category 3 For All Projects with Aggregate Generator Output of More Than 150 kw but Less Than or Equal to 550 kw

Comparison of the Behaviour of Wind Farms and Conventional Power Stations during Grid Failure Conditions

Generation and Load Interconnection Standard

TECHNICAL SPECIFICATIONS AND OPERATING PROTOCOLS AND PROCEDURES FOR INTERCONNECTION OF GENERATION FACILITIES NOT SUBJECT TO FERC JURISDICTION

Induction Machine Test Case for the 34-Bus Test Feeder -Distribution Feeders Steady State and Dynamic Solutions

SIMPLE SOLUTIONS FOR IMPROVING LIFE OF BREAKERS USED IN TRANSMISSION AND DISTRIBUTION SYSTEMS

APPENDIX A MATLAB CODE FOR CALCULATION OF MOTOR TORQUE

Transmission Interconnection Requirements for Inverter-Based Generation

AGN 022 Conditions for Parallel Operation

Advanced Test Equipment Rentals ATEC (2832) CP RC. Resonance circuit for GIS testing

CONTENTS. 1. Introduction Generating Stations 9 40

Need for grounding Codes and Standards for grounding Wind Turbine Generator grounding design Foundation + Horizontal Electrode grounding design

DP&L s Technical Requirements for Interconnection and Parallel Operation of Distributed Generation

Title Substation Auxiliary Transformer from Rectifier Transformer Secondary. Reference Number PDS 01 (RIC Standard: EP SP)

Influence of Wind Generators in Voltage Dips

Electrical Theory. Power Principles and Phase Angle. PJM State & Member Training Dept. PJM /22/2018

STS Fully automatic. Large graphic display. Primary injection testing capabilities: up to 3000 A, with the optional module BUX 3000

Functional Specification Revision History

Transcription:

TRANSMISSION SYSTEM OPERATOR QUESTIONNAIRE for Wind Farm Power Stations only To be submitted by the Generation Licensees together with the Application for Connection Certificate according to IEC 61400-21 must be submitted The Questionnaire has been completed by... (name) of the company.... Signature:.... Date:.. Table 1. General Information for the Power Station 1.1 Power Station Name 1.2 Number of generating units 1.3 Total installed capacity of Wind Farm Power Station (MW) 1 1.4 Generation Export Connection Capacity Required (MW) 2 1.5 Reactive Power Export Connection Capacity Required (MVAR) Table 2. Application for Dedicated or Non-Dedicated connection (Dedicated Connection means satisfying the reliability criteria N-1) Note: For plants with overall licenced capacity over 50MW a dedicated connection is compulsory. Applications to request terms for dedicated connection are also accepted for plants with licenced capacities less than 50MW. The increased connection cost is covered by the applicant. 2.1 Application for non-dedicated connection between the Entry Substation and the Network Substation (YES/ NO) 1 Total licenced capacity (as stated in the Generation Licence) (MW) 2 1

2.2 Application for dedicated connection between the Entry substation and the Network Substation (YES/ NO) 2.3 For licenced capacities less than 50MW: State whether you would like to be notified by the TSO for the preliminary connection costs for the two alternatives (dedicated or non-dedicated connection) so you can decide upon this for the type of connection. (YES/ NO) Table 3. Other information to be submitted 3.1 Provide a 1:5000 Survey map, with the location of the facility clearly shaded. 3.2 Provide a plan of the site (1:200 or 1:250) of the proposed facility, indicating the proposed location of generators, transformers, site buildings etc. The plan shall be submitted in hard copy format. A digitised format shall also be submitted if available. 3.3 Provide an electrical single line-diagram of the proposed facility detailing all significant items of plant, i.e: Provide a map Provide a map Provide a Single Line Diagram Numbered generating units Step-up transformers Circuit breakers/ means of isolation/ protection system arrangements Table 4. Information concerning the Generating Units The TSO suggests the installation of synchronous generators. 4.1 Μanufacturer 4.2 Type of generating unit 4.3 Generating unit with Induction Generator (YES/ NO) 4.4 Generating unit with Synchronous Generator (YES/ NO) 4.5 Registered capacity (MW) 4.6 Generator Rating (MVA) 4.7 State if the wind turbines are fixed or variable speed 4.8 State whether the connection of the Wind Farm Power Station to the grid involves a power electronic converter 4.9 Type of aerodynamic control (pitch, stall, ect) 4.10 Wind Turbine short-circuit capacity (MVA) 4.11 Normal maximum reactive capability export (MVAr) 2

4.12 Normal maximum reactive capability import (MVAr) 4.13 Turbine Generator Inertia Constant (H) for the entire rotating mass (kws/ kva) 4.14 Reactive power demand at zero output ('no load') (kvar) 4.15 Duration of inrush / starting current (ms) 4.16 Magnitude of inrush / starting current (Amps) 4.17 Description of synchronising process with the network 4.18 Wind Farm Lightning protection and Earthing arrangements 4.19 Describe the process and the compensation devices that will be installed so that the Wind Farm Power Station does not absorb in any case reactive power from the network more than what corresponds to a power factor of 0.95. Table 5. Information required for each Generator Transformer 5.1 Transformer Rating (MVA) 5.2 Number of windings 5.3 Vector group 5.4 Rated current of each winding (Amps) 5.5 Transformer nominal LV Voltage (kv) 5.6 Transformer nominal HV Voltage (kv) 5.7 Nominal Transformer ratio 5.8 Tapped winding 5.9 Transformer zero sequence impedance Ζ ο at nominal tap (Ohms) Table 6. Information required for the Wind Farm Power Station Step-up Transformer (Medium to High Voltage) of the Wind Farm Power Station 6.1 Transformer Rating (MVA) 6.2 Number of windings 6.3 Vector group 6.4 Rated current of each winding (Amps) 3

6.5 Transformer nominal LV Voltage (kv) 6.6 Transformer nominal HV Voltage (kv) 6.7 Nominal Transformer ratio 6.8 Tapped winding 6.9 Transformer ratio at each Transformer tap 6.10 Transformer impedance at each tap (% on rating) 6.11 Transformer zero sequence impedance at nominal tap (Ohms) 6.12 Core type (number of limbs, shell or core type) 6.13 Open-circuit characteristic Provide a graph 6.14 Earthing Arrangements including neutral earthing resistance & reactance Table 7. Generator Forecast and Availability Data 7.1 List the anticipated maximum export level in MW for each calendar month. 7.2 Ιndicate how generation would vary over a typical 24 hour period during the month of maximum export. 7.3 Give details of expected rapid or frequent variations in output, including magnitude, max rate of change expected, frequency and duration. 7.4 Expected Maintenance Requirements (days per year) 7.5 Expected Maintenance (timesheet) (Give periods of maintenance, duration of each period and the expected time of the year that this will take place). Provide a timetable 7.6 Forecast Availability apart from the expected scheduled maintenance requirements Table 8. Metering System and Data Transmission 8.1 According to the Transmission and Distribution Rules, installation of bidirectional metering equipment that will record the Active and Reactive Energy and Power that is exported and/or imported at a metering point is required. (I AGREE/ I DISAGREE) 8.2 According to the Transmission and Distribution Rules, for Very Small Power Stations (for Wind Farm Power Stations these have a capacity less than 5 MW), a telephone connection is required (e.g 4

ISDN, GSM or analogue connection) for transmission of data from the Power Station to the Energy Control Centre of the TSO at the end of the day. (I AGREE/ I DESAGREE) 8.3 According to the Transmission and Distribution Rules, for Small, Medium and Large Power Stations, (for Wind Farm Power Stations these have a capacity larger than 5 MW), a telecommunication and an RTU is required so that a continuous and even transmission of data (e.g circuit breakers mode, active and reactive power measurements etc.) from the Wind Farm Power Station to the Energy Control Centre of TSO is achieved. (I AGREE/ I DESAGREE) Table 9. Other Requirements. Provide Certificate according to IEC 61400-21 9.1 The characteristics of the electric power produced shall be compatible to the specifications for the Transmission and Distribution System Performance as determined in the Transmission and Distribution Rules. (YES/ NO) 9.2 The Independent Power Producer shall provide assurance that the installations are compatible to International Standards of Electromagnetic Compatibility (YES/ NO) 9.3 Provide a certificate according to IEC 61400-21, Wind Turbine Generator Systems, Part 21: Measurement and Assessment of Power Quality Characteristics of Grid Connected Wind Turbines. Provide a certificate 5