Progress Report 2 Document

Similar documents
Retractable Pool Cover

Sheet Metal Brake Plans for a 6' Sheet Metal Brake

Separation Connector. Prototyping Progress Update March 1, 2013

Ford Pick Up Rear leaf Spring Kit Installation Instructions

Mobile Computer Cart

INSTALLATION MANUAL IOWA MOLD TOOLING CO., INC. BOX 189, GARNER, IA MANUAL PART NUMBER:

H20 Beam for Elevated Slabs Application Guide

Orbital Test Stand. Operations and Assembly Manual. Department of Mechanical Engineering Northern Arizona University Flagstaff, AZ 86011

This manual will aid in the assembly of the FireBall V90 and FireBall X90. The assembly of both machines will be identical, unless specified.

Project Identity. Assistive Robotic Arm Week 9 March April 4, 2007 Megan Madariaga

`48-`56 Ford Pickup Rear leaf Spring Kit Installation Instructions Tech Line:

400A 40113V, 401A 40120V, & 401AL 40120VL ALUMINUM VERTICAL 4000 LB LIFT INCLUDES SCREW LEG ASSEMBLY INSTRUCTIONS

Precision Steel Car s 100 T Steel Coil Car

Bow Press - Homemade

ASSEMBLY INSTRUCTIONS FOR SERVICE BODY A MOUNT RACKS

southpaw enterprises, inc.

Reversing Gear. Shay Reversing Gear

TOOLS REQUIRED: HARDWARE INCLUDED: 13MM FLAT WRENCH FOR LEVELING THE STRUCTURE RATCHET WITH 5MM HEX BIT FOR CORNER SCREWS ON TOP TRAVERSE BEAMS

Travis Bishop. Submitted to: Dr. John Davis. Date: 3 December Course: ETME 310 Section: 004. Lab Topic: Milling Project (Vise)

INSPECTION AND CORRECTION OF BELLHOUSING TO CRANKSHAFT ALIGNMENT

A Few Helpful Hints: A Word Of Caution:

Hollywood Swing Away 2 and 4 Bike Racks Assembly and Installation Guide


Document Revision No.: 0 Revised: 05/11/2015 RIT KGCOE MSD Program DUAL PURPOSE WHEELCHAIR-PLATFORM SWING ASSEMBLY MANUAL

1949 to 1954 Chevrolet Dual Master Cylinder Conversion

Hydraulic Clamp Carrier. Installation & Operation Manual

Make a Safe. Description. Lesson Objectives. Assumptions. Terminology

ETX Powered Loudspeaker Accessories

Haukaas Bale Rack Kit

Important Note. Tools Required: Welder capable of fully welding 10 GA.135 steel

METAL BENDER OPERATING & MAINTENANCE INSTRUCTIONS Model Nos: CCB1 & CCB2 Part Nos: & CCB2 CCB1

INSPECTION AND REMOVAL CRITERIA

An Adjustable Threading Feed Attachment for a Lathe Without Metric Threading Capability, by Ted Clarke

FLIP TARP SINGLE & DOUBLE UNDERBODY TRAILERS

MM340 Installation Instructions IMPORTANT SAFETY INSTRUCTIONS - SAVE THESE INSTRUCTIONS

GlideRite Retractable Cover System For HotSpring & Tiger River Spas (except Classic & pre-2000 Landmark Spas)

MODULAR TRACKER SOLAR

CIRRUS AIRPLANE MAINTENANCE MANUAL

OWNERS MANUAL MODEL F660 HIP SLED

A Captured Fastener, version 1.2

Technicians of Terror. This is the air valve we make to use with our air

Independent Containment System (ICS)

Hatchback Wing Riser Kit

MECHANICAL ASSEMBLY John Wiley & Sons, Inc. M. P. Groover, Fundamentals of Modern Manufacturing 2/e

N. 15th Street, Middlesboro, KY FLIP TARP DUMP BODY INSTALLATION INSTRUCTIONS

POWER RACK STRENGTH TRAINING SYSTEM INSTRUCTION MANUAL MODEL : F430 POWER RACK

Bolt-together frame kit guide for Compact Camping Concepts Explorer Box Camping Trailer Revision /01/17

INSTRUCTION SHEET. PIECE INVENTORY - MOBILE BASES Refer to the diagram for part identification.

ZROADZ Grille series - LED Installation Guide

ASSEMBLY INSTRUCTIONS FOR MAR-K BEDSIDES AND GM FLUSH TAILGATE WITH HANDLE

M2 Assembly. M2 Sub-Assemblies mm Belt Sub-Assembly mm Belt Sub-Assembly Spider Sub-Assembly... 4

MM540 Installation Instructions IMPORTANT SAFETY INSTRUCTIONS - SAVE THESE INSTRUCTIONS

Customer Notice: Congratulations again on your SawStop purchase, and thank you! -SawStop Tualatin, OR

SatNOGS. SatNOGS Rotator v3 Mechanical Assembly. This is the assembly guide for the third version of the SatNOGS Rotator.

Parts list Instruction guide Warnings Please read carefully before assembling and using product.

1-CYLINDER TORNADO LIFT INSTALLATION MANUAL

Warnings. Description. Prior to Installation Tools Needed

model tsa-sa48 Sliding Crosscut Table installation guide

Hubble GOTO Installation Instruction (1.3, 04/30/2014)

Separation Connector. Needs Identification Document

WOOD 4 BEAM DELUXE PERGOLA INSTRUCTIONS

SolarMount (E)volution

Advanced Modeling Techniques Sweep and Helical Sweep

6-CYLINDER TORNADO LIFT INSTALLATION MANUAL

3DOF Leg Kit Assembly Guide VERSION 1.0

1. ANSI/ASME Standard B , Square and Hex Bolts and Screws, Inch Series

Elevator Assembly. To assemble the SR3500 Elevator, you will need the following tools:

GlideRite Retractable Cover System For Hot Spot Spas (SE & SLX only)

LEG CURL IP-S1315 INSTALLATION INSTRUCTIONS

Installation Instructions for Vista Air Vertically Folding Walls

GEARBOX CONSTRUCTION E.M.G.S. MANUAL ( 9) The Girder Gearbox

Log Hauler. Senior Design Project. Department of Mechanical Engineering Trevor Kline 4/19/2011

INTRODUCTION. EqunioxRoof.com. Pro Tip

Important Note. Tools Required: Welder capable of fully welding 10 GA.135 steel

Note: This assembly instruction will cover all configurations of Alloy adjustable height double bases.

STEEPLE GATE BARRIER SET INSTRUCTIONS

bridges Installation Manual

Hinge Mortising Jig. One of the make it or break it parts of building a. 6 ShopNotes No. 74

Installation Instructions

BHJ Products, Inc. Parts List & Instructions

Legend. Machining required. Refer to schedule on sheet 9 of 9 for more information.

Dehydrator Box Build Plan

Coil Winder Instructions.

Sit Down Table Assembly Instructions

ASSEMBLY INSTRUCTIONS FOR HAULER II SERVICE BODY A RACK

Always be your solar support

BEAST THE. Tube and Pipe Notcher Operating Instructions. Notches In Bends Straight Notches. Angled Notches. Offset Notches

INSTRUCTION MANUAL LEG PRESS OPTION OF ELITE GYM

U.S. Rack, Inc Falcon Drive, Madera, CA APR17 INSTALLATION AND USE INSTRUCTIONS for SIDE-MOUNT LADDER RACK

SECTION HELICAL PILES AND HELICAL ANCHORS

Click Here To View Item at

BIFOLD FUTON FRAME TRINITY ARM. Seat Rails and Slats x 1. *Note: Use 4pc of 100mm Bolts and 4pc of 60mm Bolts to attach the arms to the Stretchers.

DIY Lowery Inspired Embroidery Floor Stand

Instruction Manual. EASY / WHISPER 2, 3, 4 & 5 Blades. Scan the QR code with a mobile device to view the installation video.

Pneumatic Clamp Carrier. Installation & Operation Manual

Steele TV Stand Stock # BH

Make a Portable Hibachi

Replacing worn out MS hinges

Sunrise Deck Assembly Instructions for Kingston Left

Congratulations on purchasing the Spirit Rails Magnetic Attach that allows easy wand to pack removal and reattachment by just getting close!

Transcription:

Solar Tracking Structure Design By: Joshua Belsheim, Travis Francis, Jiayang He, Pengyan Liu, Anthony Moehling, and Micah Ziemkowski Team 07 Progress Report 2 Document Submitted towards partial fulfillment of the requirements for Mechanical Engineering Design I Spring 2014 Department of Mechanical Engineering Northern Arizona University Flagstaff, AZ 86011

Table of Contents: Section Page Number Introduction 1 Solar Panel Frame 1 Bottom Frame 2 3 Pivot Hole and Pin Tracking 4 Worm Gears and Shafts 5 Hydraulic Stabilizers 5-7 Mounted Bearing/Hinge Assembly 7-8 Gantt Chart 9-10 Conclusion 11

Introduction Our team has been tasked with designing a solar tracking system. The team reviewed and made the necessary alterations to better accommodate the design. Not only did the team s design witness changes, but both our needs and objectives also changed. Currently, solar tracking systems available on the market do not include manuals on how these systems work and ones that do have operator s manuals that are confusing and difficult to understand. Due to this problem, the team has embarked on a new design objective. Our new objective is to design a solar tracking system that enables students to experience the fundamentals of solar tracking systems. In order to facilitate this, the solar panels need to be operated automatically and must also be operated manually, if the system should malfunction and/or fail. Since students will be doing hands on learning exercises, the system also needs to be relatively simple and user friendly. The system will be accompanied by an input panel. The input panel will allow users to input pertinent information that will operate the system. Solar Panel Frame We assembled the frame that will hold the solar panel as seen in Figure 1 below. The frame was made out of angle bar with dimensions 71 X 48. Flat bar was welded onto the frame to add extra stability. A frame was made for each solar panel. Figure 1: Solar Panel Frame. 1

Bottom Frame The first thing we did was drill 18 holes for the manual North-South tracking. The next step was to cut the legs for our design. We originally cut 6 legs of 12 inch length based upon our final design. The 1 1 1/16 square tubing was cut at a 45 o for the widths of the bottom frame as well as the legs at the 4 corners of the frame. The bottom frame consists of two square tubing sections for the width of the frame of 72 inches and two angled bars for the lengths of the frame of 96 inches. After cutting all the pieces to the proper dimensions we got the frame welded by the student welders at the shop, since we are not allowed to weld in the shop due to legal issues. The frame was welded together on a Friday by two members of our team and the machine shop staff. However, when we came in on Tuesday we discovered that one of the sides with pivot holes was welded backwards. Two legs were also welded onto the frame one inch shorter than the 4 corner legs in the middle of the lengths of the square tubing instead of the angled bars and the middle support beam was not welded into place. We had two options the first being to just drill 18 more holes backwards on the square tubing, which would have resulted in improperly spaced holes. Or the second being to cut the backwards section and flip it and re-weld it to the frame. We decided to cut the section and flip it, however to ensure that the tubing stayed structurally strong we had to weld two small square sections of solid steel into the holes where the cuts were made as seen below in Figure 2 Figure 2: Fixed welded joint for square tubing 2

Then we also welded two legs into the middle of angled bar as well as welding a section of square tubing in the middle of the angled bar. The full assembly of the bottom support is shown in Figure 3 below. Figure 3: Bottom support Frame With the frame finally built correctly we got some sheet metal that was ¼ inches thick and cut 6 square feet for the legs with dimensions of 4 4 as well as 2 feet with dimensions of 3 3 for the extra legs that were welded onto the frame as seen in Figure 4 below. Figure 4: square sections for leveling pads 3

Pivot Hole and Pin Tracking By Dr. Acker s request our solar tracking system has the capability to manual track the sun North-South axis of rotation. The tracking system has a pin and hole system to move the panels at different angles every 10 days. The panels can lay almost perfectly flat and has the range of 60 to 30 degrees with 18 increments two inches apart to better track the sun. For the best results to track the sun move the panels one hole every 10 days, increasing the angle as the as the days grow shorter and decreasing the angle as the days grow longer. Pivot hole and pin tracking is seen in Figure 5 and 6 below. Figure 5: Pivot Hole and Pin Figure 6: Side view of pivot and top frame system 4

Worm Gears and Shafts The worm gears were purchased and have arrived. A 1 diameter bar was cut in 7 inch segments then grinded down for a more appropriate fit in the mounted bearings and gears. The finished product is seen below in Figure 7. Hydraulic Stabilizer Figure 7: Worm Gears and Shafts The hydraulics were purchased from an auto parts store. Each of the hydraulic stabilizer is rated to hold up to 150 lbs. The holes for the hydraulics were drilled into the 1 1 1/16 square tubing. A picture of the hydraulics and bolts to be used is shown below in Figure 8. 5

Figure 8: Hydraulic Stabilizer To make the angle adjustment easier and safer, a car hood hydraulic stabilizer is installed close to the pivot point to provide the extra support to the solar panel. The precise location of the hydraulic stabilizer wasn t included in the solid works design since it depends on the size of the hydraulic stabilizer. Once we purchased the hydraulic stabilizer which has a 12.75 in fully extended length and 7.1 in contracted length. Figure 9 shows the triangle that the stabilizer and the frame will create. Point A and point C indicates the locations where the stabilizer is installed. Point D indicates the pivot point. Point B is where the point A will reach if the solar panel is laid flat. The triangle can be solved using the dimensions of the stabilizer. The distance CD turns out to be 7.62 in. and the distance AD turns out to be 14.72 in. These calcuations were done at the largest angle of 60 o which is not reflected in Figure 9. The force needed to contract the stabilizer is about 10 lb. If the stabilizer is installed in the right place, it should be contracted easily with the weight of the solar panel itself. 6

Figure 9: Hydraulic hole location calculation Mounted Bearings/Hinge Assembly Currently we have not actually welded the mounted bearing sections onto the top frame of our design because we ran into a couple of problems regarding the hinges and motor placement onto our system. For the bottom part of the top frame where the gears and motors will go we ran into the issue of spacing in between the mounted bearing housings and the hinges. Originally we were going to just bolt the bearings into place on the top frame, however we realized that during movement of the North-South tracking system we would run into the angled bar on the bottom frame if the bolts are exposed. So after talking to the welders in the machine shop they suggested that we should drill 2 holes all the way through the square tubing and then insert the bolts as normal and fix the nuts onto the top of the mounted bearings. Once that is done they suggested that we cut the bottom of the bolt off and weld the threaded section of the bolt in 7

place so that the bolt head does not interfere with the angled bar on the bottom part of the frame. The proposed build for the bottom mounted bearings is seen below in Figure 10. Figure 10: Proposed bearing build 8

Gantt Chart Figure 11: Previous Gantt Chart for spring 2014 The Figure 11 above is of our previous Gantt Chart from the beginning of this semester. When the team started executing the tasks on the list, it took more time than we expected to build the solar tracking system. In order to make sure the project will be done on time the team updated the Gantt Chart which clearly shows the changes of the schedule as seen in Figure 12 below. 9

Figure 12: Updated Gantt Chart for spring 2014 The design modification process is going to take the team one more week than originally planned, the materials purchasing process was postponed until week 7 because our budget required authentication by our client. The building process started at week 7. At the end of week 10, the team has finished the bottom and top frame. The gears have arrived and 2 control systems and one motor are on their way. One of the motors is on back order for 1 week. The team is going to get the building process and structural testing done before week 12. On week 13, team members will start writing the program for the tracking system and get the program testing done. The testing is projected to take 7 days to finish. Upon return the analysis of the solar panel system will be initiated as well as the analysis of the efficiency of the system. Team members will start writing the final report, presntation, and operations manuel in week 14 and will be finished by week 17. 10

Conclusion In this report we went over the sections of our design which we have completed at this point in time. We provided information on how we built the different sections of our design as well as problems we have run into. The team has completed the bottom frame and box frame for solar panels and the angle supports are ready to be assembled. Due to the motors not being here yet the construction of the gear, motor assembly has not been completed. We were also wondering how to get the solar tracking system to the shack; however we have decided that we will leave the system at the machine shop until the U-Grads presentation when it has to be moved anyway. The Gantt chart has been updated to account for the unforeseen delays and to help the team finish the project on time. The analysis dates have not changed because of these unexpected problems. The final report and presentation are to be presented to Dr. Raju on April 17 th. An operation manual for the solar tracking system will be available by the end of the semester. 11