Reliability Analysis Update

Similar documents
Reliability Analysis Update

Artificial Island Proposal Window

Sub Regional RTEP Committee South

Jason Harchick, P.E. Sr. Manager, System Planning and Protection Ryan Young Manager, Substation Engineering

Sub Regional RTEP Committee Mid-Atlantic - PSEG Solution Meeting

TPL Transmission System Planned Performance for Geomagnetic Disturbance Events

Maine Public Service Reliability Solutions Update

Texas Reliability Entity Event Analysis. Event: May 8, 2011 Loss of Multiple Elements Category 1a Event

LONG-RANGE TRANSMISSION PLAN

DUKE ENERGY CAROLINAS TRANSMISSION SYSTEM PLANNING GUIDELINES. Transmission Planning

MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology

Central Hudson Gas & Electric Corporation. Transmission Planning Guidelines

GridLiance Reliability Criteria

CONSOLIDATED EDISON CO. OF NEW YORK, INC 4 IRVING PLACE NEW YORK, N.Y

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 4: (June 10, 2013) Page 1 of 75

ESB National Grid Transmission Planning Criteria

The Engineering Problem. Calculating GIC Flow through the EHV System

MidAmerican Energy Company Reliability Planning Criteria for 100 kv and Above

PRC Generator Relay Loadability. Guidelines and Technical Basis Draft 5: (August 2, 2013) Page 1 of 76

Central East Voltage and Stability Analysis for Marcy FACTS Project Phase I

Bulk Electric System Definition Reference Document

Bulk Electric System Definition Reference Document

ITC Holdings Planning Criteria Below 100 kv. Category: Planning. Eff. Date/Rev. # 12/09/

Transmission Interconnection Requirements for Inverter-Based Generation

System Operating Limit Definition and Exceedance Clarification

Module 10. Initiation Code RELIABILITY ACCOUNTABILITY

1

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g

Bulk Electric System Definition Reference Document

Standard Development Timeline

AC Transmission Cases: Updated Powerflow Analysis

MidAmerican Energy Company 100 kv and Above Facility Ratings Methodology

Southern Company Interconnection Requirements for Inverter-Based Generation

Document C-29. Procedures for System Modeling: Data Requirements & Facility Ratings. January 5 th, 2016 TFSS Revisions Clean Open Process Posting

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Aggregated Generating Facilities Technical Requirements

Kansas City Power & Light Company. Transmission Facility Rating Methodology

(Circuits Subject to Requirements R1 R5) Generator Owner with load-responsive phase protection systems as described in

MidAmerican Energy Company 69 kv Facility Ratings Methodology

Great Northern Transmission Line: Behind the (Electrical) Design

Transmission Availability Data System (TADS) DATA REPORTING INSTRUCTION MANUAL

ROCHESTER PUBLIC UTILITIES FACILITY RATINGS METHODOLOGY FOR TRANSMISSION, SUBSTATION, & GENERATION EQUIPMENT

INTRODUCTION. General Design Criteria o (include charts from Section 2 of TSS) Functional Criteria o (from TSS section 3) Accessibility and Layout

Appendix S: PROTECTION ALTERNATIVES FOR VARIOUS GENERATOR CONFIGURATIONS

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

VAR Voltage and Reactive Control. A. Introduction

Final ballot January BOT adoption February 2015

Commercial Deployments of Line Current Differential Protection (LCDP) Using Broadband Power Line Carrier (B-PLC) Technology

AMEREN s (On Behalf of Its Transmission Owning Affiliates, Including Ameren Missouri, Ameren Illinois, and Ameren Transmission Company of Illinois)

PJM Manual 07:: PJM Protection Standards Revision: 2 Effective Date: July 1, 2016

Module 9. Fault Type Form 4.X RELIABILITY ACCOUNTABILITY

Operational Experiences of an HV Transformer Neutral Blocking Device

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0

Industry Webinar Draft Standard

NERC Protection Coordination Webinar Series June 16, Phil Tatro Jon Gardell

FACILITY RATINGS METHOD TABLE OF CONTENTS

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Wind Aggregated Generating Facilities Technical Requirements

Geomagnetic Disturbances. IEEE PES Chicago Chapter Technical Presentation March 12, Alan Engelmann Transmission Planning ComEd.

Transmission Availability Data System Definitions

Case Study Effects of Geomagnetically Induced Current (GIC) Neutral Blocking Device

EE 741. Primary & Secondary Distribution Systems

FACILITIES STUDY PID 211 INTERCONNECTION LEWIS CREEK 138 KV

Arizona Public Service Company and the Transmission Partnership for National Electric Power Company of Jordan

May 30, Errata to Implementation Plan for the Revised Definition of Remedial Action Scheme Docket No. RM15-13-_

PRC Generator Relay Loadability. A. Introduction 1. Title: Generator Relay Loadability 2. Number: PRC-025-1

PRC Disturbance Monitoring and Reporting Requirements

TTC Study for: the PEGS-Ambrosia Lake 230 kv Line and the PEGS-Bluewater 115 kv Line

HVDC High Voltage Direct Current

Control of Over-voltages on Hydro-Québec 735-kV Series-Compensated System During a Major Electro-mechanical Transient Disturbance.

SOLUTION REPORT FOR THE INTERSTATE RELIABILITY PROJECT AUGUST, 2008 THE CONNECTICUT LIGHT AND POWER COMPANY NATIONAL GRID, USA

CONNECTING to the TRANSMISSION GRID in TODAY S RTO WORLD

System Ratings, Limits and Real-Time Monitoring. Presented to: Operating Committee April 21, 2016

ReliabilityFirst Regional Criteria 1. Disturbance Monitoring and Reporting Criteria

Standard VAR Voltage and Reactive Control

Functional Specification Revision History

Study on the Improvement of the Special Protection Scheme (SPS) in the Korean power system

10. DISTURBANCE VOLTAGE WITHSTAND CAPABILITY

MODEL POWER SYSTEM TESTING GUIDE October 25, 2006

NPCC Regional Reliability Reference Directory # 12. Underfrequency Load Shedding Program Requirements

NORMES DE FIABILITÉ DE LA NERC (VERSION ANGLAISE)

Standard Development Timeline

Shunt Reactors. Global Top Energy, Machinery & Plant Solution Provider

Remedial Action Scheme Definition Development

Transmission Facilities Rating Methodology for Florida

A. Introduction. VAR Voltage and Reactive Control

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules. 45-day Formal Comment Period with Initial Ballot June July 2014

VAR Voltage and Reactive Control

Transmission System Phase Backup Protection

Consideration of Comments on FRCC Regional Bulk Electric System Definition Clarification Project Version 1

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

Standard VAR-002-2b(X) Generator Operation for Maintaining Network Voltage Schedules

Protective Relaying Philosophy and Design Guidelines. PJM Relay Subcommittee

Notes 1: Introduction to Distribution Systems

6 th December South West Scotland Forum

NERC Requirements for Setting Load-Dependent Power Plant Protection: PRC-025-1

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) )

ATTACHMENT Y STUDY REPORT

kv AC substation

Implementation Plan Project Modifications to PRC Reliability Standard PRC-025-2

ELECTRIC TRANSMISSION (ET) Guideline G0104

Project System Operating Limits Drafting Team Meeting Notes

Transcription:

Reliability Analysis Update Transmission Expansion Advisory Committee August 11, 2016

2016 RTEP Window #3 Anticipated Scope and Timeline

Anticipated 2016 RTEP Window #3 Anticipated 2016 RTEP Window #3 Scope 2021 Winter 2021 Light Load Reliability Analysis Short Circuit Timing Post preliminary results Open Window Close Window Window Duration 3

2016 RTEP Proposal Window #2

2016 RTEP Proposal Window 2 Scope: Baseline N-1 (thermal and voltage) Generation Deliverability and Common Mode Outage N-1-1 (thermal and voltage) Load Deliverability (thermal and voltage) Window Opened: 6/29/2016 Window Closed: 7/29/2016 Proposal definitions, simulation data and planning cost estimate due Detailed Cost due: 8/15/2016 Additional 15 days to develop and provide detailed cost data See the window documentation for additional information 5

2016 RTEP Proposal Window 2 140 total flowgates Test/kV Level* 100kV - 200kV 230kV 345kV 500kV 765kV Total N-1 Thermal 1 2 3 N-1 High Voltage 0 N-1 Low Voltage 0 N-1 Voltage Drop 0 Gen Deliv & CMO 76 9 13 3 1 102 Load Deliv Thermal 0 Load Deliv Voltage 0 N-1-1 Thermal 10 10 N-1-1 Low Voltage 2 2 N-1-1 Voltage Drop 2 18 20 N-1-1 Voltage Collapse 0 Total 91 27 15 3 1 137 *xfmr are categorized based on low side kv 6

2016 RTEP Proposal Window 2 Violation Locations 7

Window Opened: 6/29/2016 Window Closed: 7/29/2016 Additional 15 day window close: 8/15/2016 2016 RTEP Proposal Window 2 137 Flowgates Identified, 71 Flowgates Recommended for proposals ( Remaining flowgates related to Retired Generators) 87 Proposals Received from 13 Entities addressing 12 TO Zones 46 Greenfield Cost Range $5M - $224M 41 Transmission Owner Upgrades Cost Range $0.03M - $125M 8

PSE&G Transmission Zone PSE&G End Of Life Assessment Metuchen Edison Trenton Burlington Corridor www.pjm.com 9

PSE&G s FERC 715 Transmission Owner criterion addresses equipment condition assessments PSE&G assessed the condition of the Metuchen to Trenton (MT-T) and Trenton to Burlington (T- BU)138 kv circuits. PSE&G Transmission Zone www.pjm.com 10

Refer to PSE&G criteria: PSE&G Transmission Zone VII. EQUIPMENT ASSESSMENT AND STORM HARDENING http://www.pjm.com/~/media/planning/planning-criteria/pse&gplanning-criteria.ashx Metuchen to Trenton is approximately 30 miles of 138 kv circuit and the average structure age is 86 years. Trenton to Burlington is approximately 22 miles of 138 kv circuit and the average structure age is 75 years. www.pjm.com 11

Assessment Result: Consultant - Foundation assessment PSE&G Transmission Zone 23% and 30% of structures for MT-T and T-BU respectively will require extensive foundation rehabilitation or total foundation replacement. Consultant Tower line assessment 25 % of the tower structures exceed the tower load carrying design capability 35% of the towers are at 99-100% of the tower s load bearing capability, and 81% of the towers at 95-100% of the tower s capability. www.pjm.com 12

PSE&G Transmission Zone Problem: PSE&G FERC 715 Transmission Owner Criteria Equipment condition assessment for the entire corridor Equipment has reached its end of life NERC Reliability Criteria N-1-1 voltage violations in the Metuchen vicinity in the 2016 RTEP Window #2 www.pjm.com 13

PSE&G Transmission Zone Potential Solution for Metuchen - Brunswick: Convert the R-1318 and Q1317 (Edison Metuchen) 138 kv circuits to one 230 kv circuit Metuchen 138 kv will be eliminated The Brunswick 230/138 kv autotransformer will be eliminated The new converted 230 kv circuit will be terminated at the existing Metuchen and Brunswick 230 kv stations. Project Benefits: Resolves voltage violation in the Metuchen vicinity identified in the 2016 RTEP 2 nd Window Eliminates the need for baseline upgrade (B2590 Install two 75 MVAR 230 kv capacitors at Sewaren station) identified in the 2014 RTEP window. Strengthens the system by replacing 138 kv circuits with 230 kv circuits, improving capacity and voltage. Creates a strong tie between Southern and Central PSE&G Increases transfers capability to Central PSE&G Addresses future reliability and economic needs Estimated Project Cost: $ 125 M Alternatives Considered: Rebuild the existing transmission corridor in-kind at 138 kv www.pjm.com 14

PSE&G Transmission Zone Metuchen Brunswick Existing and Future Diagram Before After Pierson Ave H-2286 Pierson Ave H-2286 Meadow Rd Metuchen Meadow Rd Metuchen R-1318 R-1318 Q-1317 Brunswick Edison Brunswick Edison D-2204 S-2219 D-2204 S-2219 Deans Deans www.pjm.com 15

PSE&G Transmission Zone Potential Solution for Brunswick - Trenton: Convert the N-1340 and T-1372/D-1330 (Brunswick Trenton) 138 kv circuits to 230 kv circuits The converted circuits will be terminated at the existing Brunswick 230 kv The Deans 230 kv station will be expanded with additional two breaker and half bay The converted two 230 kv circuits will be looped in to Deans 230 kv station The new converted 230 kv circuit will be terminated at the Trenton 138 kv station with two 138 kv transformers Project Benefit: Strengthens the system by replacing 138 kv circuits with 230 kv circuits, improving capacity and voltage. Provides better transfers across the network Addresses future reliability and economic needs Estimated Project Cost: $ 327 M Alternatives Considered: Rebuild the existing transmission corridor in-kind at 138 kv www.pjm.com 16

PSE&G Transmission Zone Brunswick Trenton Existing and Future Diagram Before After Brunswick R-1318 To Metuchen Q-1317 Brunswick To Metuchen D-2204 D-2204 Deans S-2219 Deans S-2219 To PECO Plainsboro Devils Brook To PECO Plainsboro Devils Brook Mercer Trenton Mercer Trenton To Burlington To Burlington www.pjm.com 17

PSE&G Transmission Zone Potential Solution for Trenton - Burlington: Convert the F-1358/Z1326 and K1363/Y-1325 (Trenton - Burlington) 138 kv circuits to 230 kv circuits Trenton 138 kv substation will be replaced with six bay breaker and half 230 kv substation The A-130-27 138 kv currently from Trenton - US Steel (PECO) will be terminated at Mercer 230 kv with 230/138 kv transformer and the Trenton Mercer portion of the circuit will be converted to 230 kv Mercer station will be expanded with additional breaker and half bay. Project Benefit: Eliminates the need for baseline upgrade (B2589 Install a 100 MVAR 230 kv shunt reactor at Mercer station) identified in the 2014 RTEP window. Strengthens the system by replacing 138 kv circuits with 230 kv circuits, improving capacity and voltage. Provides better transfers across the network Addresses bottled generation issue at Mercer Estimated Project Cost: $ 349 M Alternatives Considered: Rebuild the existing transmission corridor in-kind at 138 kv www.pjm.com 18

PSE&G Transmission Zone Trenton Burlington Existing and Future Diagram Before After To PECO To Lawrence To Brunswick/Metuchen To PECO To Lawrence To Brunswick/Metuchen Mercer Trenton Mercer Trenton Yardville Yardville Burlington Crosswicks Burlington Crosswicks Bustleton Bustleton www.pjm.com 19

PSE&G Transmission Zone PSE&G End Of Life Assessment Newark Switch Review www.pjm.com 20

Problem: PSE&G FERC 715 Transmission Owner Criteria Newark Switch Aging Infrastructure PSE&G Transmission Zone PSE&G FERC 715 Transmission Owner Criteria Age Substation: 1953 Transformer 1: 1972 Transformer 2&3: 1958 Spare: 1992 Housed in an urban building Equipment condition assessment Equipment has reached its end of life Alternatives Considered: 1. Build new Newark GIS station in a building located adjacent to the existing Newark Switch and demolish the existing Newark Switch 2. Build a new Newark GIS station elsewhere in Newark and relocate all transmission and distribution cables and protection equipment Potential Solution: Alternative #1 - Build new Newark GIS station in a building located adjacent to the existing Newark Switch and demolish the existing Newark Switch Estimated Cost: $353 M www.pjm.com 21

Immediate Need Baseline Upgrades

PPL/JCPLTransmission Area Problem: Stability Martins Creek and Lower Mount Bethel Energy units go unstable for a 3-Phase fault at 80% of Martins Creek Morris Park 230 kv line with zone 2 clearing Immediate Need: Due to the immediate need, the timing required for an RTEP proposal window is infeasible. As a result, the local Transmission Owner will be the Designated Entity. Alternatives Considered: Due to the immediate need of the project no alternatives were considered Proposed Solution: Install 12 mi of optical pilot ground wiring (OPGW) between Gilbert and Springfield substations 7 mi of construction by PPL on bulk power lines (b2754.1) 5 mi of construction by JCPL on bulk power lines (b2754.2) Install 7 mi of all-dielectric self-supporting (ADSS) fiber optic cable between Morris Park and Northwood substations (JCPL) (b2754.3) Use ~ 40 route mi. of existing fibers on PPL system to establish direct fiber circuits (b2754.4) Upgrade relaying at Martins Creek (PPL) (b2754.5);, Morris Park (JCPL) (b2754.6); and Gilbert (JCPL) (b2754.7) Estimated Cost: $ 1.001 M(PPL) $1.456 M (JCPL) Projected IS Date:12/01/2019 23

Short Circuit Upgrades

PPL Transmission Area Problem: Short Circuit The Martins Creek 230kV breakers are overdutied Immediate Need: Due to the immediate need, the timing required for an RTEP proposal window is infeasible. As a result, the local Transmission Owner will be the Designated Entity. Alternatives Considered: Due to the immediate need of the project no alternatives were considered Proposed Solution: Install 2% reactors at Martins Creek 230kV (B2756) Estimated Cost: $ 10 M Required IS Date: 06/01/2018 25

Artificial Island Update

PJM Board Meeting week of August 1 st, 2016 Artificial Island Update The PJM Board decided to suspend all elements of the Artificial Island project and directed PJM staff to perform a comprehensive analysis to support a future course of action. Andy Ott Letter on Behalf of the PJM Board http://www.pjm.com/~/media/documents/reports/20160805-artificialisland-update.ashx Steve Herling Letter to Members and Stakeholders http://www.pjm.com/~/media/documents/reports/20160805-stevenherling-letter-on-artificial-island-suspension.ashx 27

RTEP Next Steps

Questions? Email: RTEP@pjm.com 29

Revision History V1 - Original version posted to PJM.com 8/8/2016 Revision History V2 Added Metuchen Edison Trenton Burlington Corridor diagrams 8/9/2016 V3 Updated the equipment ages of the Newark Switch (current slide #21) and added a potential solution 30