Ferroresonance on Transformer 13-kV Ungrounded Tertiary at Arab

Similar documents
TECHNICAL BULLETIN 004a Ferroresonance

FERRORESONANCE SIMULATION STUDIES USING EMTP

This document covers common questions concerning the design of an effectively grounded system.

Overvoltage and undervoltage. Dr Audih 1

Protection Basics Presented by John S. Levine, P.E. Levine Lectronics and Lectric, Inc GE Consumer & Industrial Multilin

Line to Ground Voltage Monitoring on Ungrounded and Impedance Grounded Power Systems

Tab 2 Voltage Stresses Switching Transients

Course 11 Distribution Transformer Applications Instructor: David R. Smith, PE Due: April 24, 2017 (EV), April 25, 2017 (LC)

Ferroresonance Conditions Associated With a 13 kv Voltage Regulator During Back-feed Conditions

BUS2000 Busbar Differential Protection System

The study of ferroresonance effects in electric power equipment

Parameter Study of Ferro-Resonance with Harmonic Balance Method

Modeling Ferroresonance Phenomena on Voltage Transformer (VT)

Ferroresonance in MV Voltage Transformers: Pragmatic experimental approach towards investigation of risk and mitigating strategy

A Study on Ferroresonance Mitigation Techniques for Power Transformer

Evaluating the Response of Surge Arresters

Bus protection with a differential relay. When there is no fault, the algebraic sum of circuit currents is zero

Ferroresonance Experience in UK: Simulations and Measurements

Back to the Basics Current Transformer (CT) Testing

2 Grounding of power supply system neutral

A Special Ferro-resonance Phenomena on 3-phase 66kV VT-generation of 20Hz zero sequence continuous voltage

Validation of a Power Transformer Model for Ferroresonance with System Tests on a 400 kv Circuit

Upgrading Your Electrical Distribution System To Resistance Grounding

Module 2 : Current and Voltage Transformers. Lecture 8 : Introduction to VT. Objectives. 8.1 Voltage Transformers 8.1.1Role of Tuning Reactor

GENERATOR INTERCONNECTION APPLICATION Category 5 For All Projects with Aggregate Generator Output of More Than 2 MW

Topic 6 Quiz, February 2017 Impedance and Fault Current Calculations For Radial Systems TLC ONLY!!!!! DUE DATE FOR TLC- February 14, 2017

Tertiary Winding Design in wye-wye Connected Transformers Restricted Siemens Energy 2013 All rights reserved.

Ironing out resonance

Grounding for Power Quality

Sequence Networks p. 26 Sequence Network Connections and Voltages p. 27 Network Connections for Fault and General Unbalances p. 28 Sequence Network

Need for grounding Codes and Standards for grounding Wind Turbine Generator grounding design Foundation + Horizontal Electrode grounding design

Relay Protection of EHV Shunt Reactors Based on the Traveling Wave Principle

DISTRIBUTION SYSTEM VOLTAGE SAGS: INTERACTION WITH MOTOR AND DRIVE LOADS

GENERATOR INTERCONNECTION APPLICATION FOR ALL PROJECTS WITH AGGREGATE GENERATOR OUTPUT OF MORE THAN 2 MW

Effects of Phase-Shifting Transformers, and Synchronous Condensers on Breaker Transient Recovery Voltages

Demagnetization of Power Transformers Following a DC Resistance Testing

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser, OMICRON electronics Corp. USA

ARC FLASH PPE GUIDELINES FOR INDUSTRIAL POWER SYSTEMS

OPEN-PHASE DETECTION TECHNIQUES FOR CRITICAL STANDBY SUPPLIES

of the improved scheme is presented. Index Terms Inrush current, power quality, transformer.

CURRENT TRANSFORMER CONCEPTS

FGJTCFWP"KPUVKVWVG"QH"VGEJPQNQI[" FGRCTVOGPV"QH"GNGEVTKECN"GPIKPGGTKPI" VGG"246"JKIJ"XQNVCIG"GPIKPGGTKPI

Adi Mulawarman, P.E Xcel Energy Minneapolis, MN. Pratap G. Mysore, P.E Pratap Consulting Services, LLC Plymouth, MN

ISSN: X Impact factor: (Volume 3, Issue 6) Available online at Modeling and Analysis of Transformer

TABLE OF CONTENT

Summary of the Impacts of Grounding on System Protection

Impacts of the Renewable Energy Resources on the Power System Protection by: Brent M. Fedele, P.E., National Grid for: 11 th Annual CNY Engineering

148 Electric Machines

Understanding and Extracting Valuable Information from Basic and Advanced Power Transformer Testing Techniques

Insulation Co-ordination For HVDC Station

22.0 Harmonics in Industrial Power Systems

(2) New Standard IEEE P (3) Core : (4) Windings :

Transformer Protection

Innovative Science and Technology Publications

Switching Induced Transients:

Section 6: System Grounding Bill Brown, P.E., Square D Engineering Services

Notes 1: Introduction to Distribution Systems

Analysis of Temporary Over-Voltages from Self-Excited Large Induction Motors in the Presence of Resonance - Case Studies

MILWAUKEE SCHOOL OF ENGINEERING LABORATORY SESSION 4 THREE PHASE TRANSFORMERS

Alternative Testing Techniques for Current Transformers. Dinesh Chhajer, PE Technical Support Group MEGGER

Solving Customer Power Quality Problems Due to Voltage Magnification

Unit 3 Magnetism...21 Introduction The Natural Magnet Magnetic Polarities Magnetic Compass...21

STRAY FLUX AND ITS INFLUENCE ON PROTECTION RELAYS

Modern transformer relays include a comprehensive set of protective elements to protect transformers from faults and abnormal operating conditions

Preface...x Chapter 1 Electrical Fundamentals

Primary Metering. What is Primary Metering?

CONTENTS. 1. Introduction Generating Stations 9 40

Simulation Analysis of Ferromagnetic Resonance of Low Magnetic Flux Density-Type PT under Single-Phase Earth Fault of 10kV Power Grid

Babak Enayati National Grid Thursday, April 17

Beyond the Knee Point: A Practical Guide to CT Saturation

Reducing the magnetizing inrush current by means of controlled energization and de-energization of large power transformers

CHAPTER 4. Distribution Transformers

ECE 528 Understanding Power Quality

ELECTRICAL POWER TRANSMISSION TRAINER

Surge Protection for Ladle Melt Furnaces

IVE(TY) Department of Engineering. Electrical Machines 1. Electrical Machines 1. Hour 13. slide 1

This webinar brought to you by The Relion Product Family Next Generation Protection and Control IEDs from ABB

www. ElectricalPartManuals. com Type CGR Ratio Ground Relay Descriptive Bulletin Page 1

Transformers. 4.1 Basics

Overview of Grounding for Industrial and Commercial Power Systems Presented By Robert Schuerger, P.E.

UNDERSTANDING SUB-HARMONICS

Transformer Protection Principles

Long lasting transients in power filter circuits

Webinar: An Effective Arc Flash Safety Program

A DUMMIES GUIDE TO GROUND FAULT PROTECTION

Are snubbers required with Eaton s Cooper Power series liquid-filled hardened transformers?

Module 1. Introduction. Version 2 EE IIT, Kharagpur

REDUCTION OF TRANSFORMER INRUSH CURRENT BY CONTROLLED SWITCHING METHOD. Trivandrum

Education & Training

Ground Fault Currents in Unit Generator-Transformer at Various NGR and Transformer Configurations

Type KLF Generator Field Protection-Loss of Field Relay

VOLTAGE OSCILLATION TRANSIENTS CAUSED BY CAPACITOR BANKING ENERGIZING FOR POWER FACTOR CORRECTION IN THE POWER SYSTEM

Power Factor & Harmonics

SWITCHING OVERVOLTAGES IN A 400-KV CABLE SYSTEM

SATURATION ANALYSIS ON CURRENT TRANSFORMER

TRANSFORMER THEORY. Mutual Induction

thepower to protect the power to protect i-gard LITERATURE Low and medium voltage

Operation Analysis of Current Transformer with Transient Performance Analysis Using EMTP Software

Understanding the Value of Electrical Testing for Power Transformers. Charles Sweetser - OMICRON

Tertiary Winding in Power Transformers P Ramachandran,India

Transcription:

Ferroresonance on Transformer 13-k Ungrounded Tertiary at Arab Gary L. Kobet, P.E. Tennessee alley Authority In October 1997, at TA s Arab AL 161k Substation, a distributor built a 13k switchyard to load the previously unloaded (except for single-phase station service) 13k delta tertiary of the 161k wye grounded/46k wye grounded/13k delta transformer bank (two banks in parallel). A three-phase three-element metering package was used, using 7200-120 metering Ts. When switch 247 (three-phase gang-operated) was closed to energize the portion of bus containing only Y-Y connected metering potential transformers (see Figure 1), two gapped lightning arresters on the 13-k transformer bank faulted, tripping both banks by bank differential. The cause of the lightning arrester failure was suspected to be overvoltage due to ferroresonance. EMTP simulation supported this theory. No actual waveforms were available (all relaying electromechanical, no station DFR at this location).. 161-k source To 46- k load 247 Lightning Arresters This switch closed to pick up bus up to bank breaker 13-k Metering PTs (Y-Y connected) To revenue meter (l) 13-k bank breaker (Open) (l) Zig-Zag Grounding Transformers (l) (l) Bank #1 Bank #2 To 13-k feeder breakers Lightning Arresters (Op) Figure 1. Arab 13-k switchyard Reasons Ferroresonance Occurred Ferroresonance is an effect which can occur on ungrounded systems with Y-Y connected potential transformers. Actually there are no ungrounded systems; there is always some stray distributed capacitance of the bus runs, insulators, switches, transformer bushings and windings, etc. It is this small (hundreds of picofarads) capacitance which interacts with the nonlinear magnetizing inductance of the potential transformer which can cause resonance. The resonant circuit causes the magnetizing branch of the potential transformer to draw higher-than-normal magnitudes of excitation current. This current, across the T magnetizing impedance, produces the overvoltage.

Page 2 of 10 TA-Ferroresonance at Arab Note that the Arab 13k buswork up to the open 13k bank breaker is an ungrounded system, due to the delta-connected 13k power transformer windings. losing switch 247 energized only the 13k Y-Y connected metering Ts and buswork up to the open 13k bank breaker. The saturation voltage of the potential transformer is an important factor in determining the probability of ferroresonance occurring. As the normal operating voltage of the system approaches the T saturation voltage, it becomes easier for ferroresonance to occur and more difficult to prevent it from persisting. 1 It was discovered that these metering Ts were being operated well above their saturation point. A combination of these factors (switching Y-Y connected Ts on an ungrounded bus, and operating the Ts above the saturation point) resulted in ferroresonance. EMTP Simulation The Arab 13k switchyard was modeled in EMTP in an attempt to simulate the event. Notes concerning the EMTP modeling of the Arab 13-k switchyard are as follows: A system equivalent was calculated at the Arab 161-k bus. Both power transformer banks were modeled as two banks of three single-phase transformers. Leakage impedances were calculated from nameplate values. The 161-k neutral reactor was included. Winding-to-ground and winding-to-winding capacitances were calculated from Doble test results. 13-k bus capacitance was modeled at 10 pf/ft per 37-011 table 4. The zig-zag grounding transformers were modeled as two banks of three singlephase transformers. Leakage impedances were calculated from nameplate values. Load was connected to the 46-k windings typical of the load at the time of the disturbance. The potential transformers (7200-120, 1500A thermal rating) were modeled using the EMTP saturable transformer model. Leakage impedances were obtained from the manufacturer s test report, and winding-to-ground capacitances derived from Doble test results. The excitation curve (exciting volts vs. exciting amps) was obtained from the manufacturer and was fed into the auxiliary magnetic saturation routine, which provided the required peak current vs. flux data. This table was placed into the EMTP data file. The excitation curve is shown in Figure 2. As 1 p. 609, Ferroresonance of Grounded Potential Transformers on Ungrounded Power Systems, 1959 AIEE Transactions on Power Apparatus and Systems.

Page 3 of 10 TA-Ferroresonance at Arab previously stated, note that the normal operating voltage is located well above the knee of the saturation curve. Simple examination of this curve showed that there was a potential problem. Excitation urve for 7200-120 PTs 1000 Normal Operating oltage Saturated Region Secondary oltage () Unsaturated Region Operating oltage if bus at 4160- (see case 5) 100 10 0.01 0.1 1 10 Exciting Amps (A) Figure 2. 7200-120 T saturation curve The EMTP data file is listed in Appendix A. The T excitation data file is listed in Appendix B. The EMTP graphs are as follows: 1 Figure 3a. 7200-120 Ts connected Y-Y. oltage waveform.

Page 4 of 10 TA-Ferroresonance at Arab Figure 3b. 7200-120 Ts connected Y-Y. Waveform for current drawn by T magnetizing branch (saturated). In examining the graphs, it should be noted that normal phase-to-ground voltage is 7.5- k rms, and normal peak voltage (maximum and minimum) should be 10.6-k (see case 1). The voltages examined in the EMTP output graphs are phase-to-ground voltages, since this is the voltage which stresses the system insulation, cause lightning arresters to sparkover, and can damage equipment connected to the T secondary. Note that peak voltage spikes of 60-k (six times normal) were predicted. This would have been enough to cause lightning arrester failure. Mitigating Solution Several solutions were considered, including replacing Ts with models having a saturation voltage well above the expecting operating voltage, rearranging the switchyard so that the Ts were on the same bus as the grounding transformers, adding secondary loading resistance to the Ts, and installing additional phase-toground capacitance to the 13k bus. The solution chosen in this case was to replace the three Y-Y connected Ts with two 14400-120 Ts connected delta-wye. The bus section between the transformer bank and the open bank breaker was energized successfully on December 16, 1997. onclusions It is very important to recognize the potential for ferroresonance. Equipment characteristics and connections must be thoroughly reviewed to avoid creating an operating arrangement which could result in equipment damage or, more importantly, safety hazards to operating personnel or the public.

Page 5 of 10 TA-Ferroresonance at Arab In the case of Arab, the 247 switch was being closed manually by a human operator. The lightning arresters that failed were within 10 to 20 feet of the switchplate on which the operator was standing. Had the arresters blown apart, the operator could have been severely injured. The results of the EMTP studies also revealed that two classical solutions for mitigating ferroresonance were not effective in this particular case. Specifically, the addition of T secondary loading resistance would not have prevented ferroresonance without significantly degrading the metering T accuracy, due to the additional burden. Additionally, this case also demonstrates that three-phase switching will not always prevent ferroresonance. This was proven both by EMTP study and in actual practice, since switch 247 was a three-phase gang-operated switch.

Page 6 of 10 TA-Ferroresonance at Arab Appendix A EMTP Data File Arab, AL, 161-k Substation Study ase Gary L. Kobet October 1997 This case uses a system equivalent at the Arab 161-k bus. BEGIN NEW DATA ASE Floating-point miscellaneous data (See Section 5.2.1) ----dt<---tmax<---xopt<---opt<-epsiln<-tolmat<-tstart 25E-6 1.0...^...^...^...^...^...^...^ Integer miscellaneous data (See Section 5.2.2) -Iprnt<--Iplot<-Idoubl<-Kssout<-Maxout<---Ipun<-Memsav<---Icat<-Nenerg<-Iprsup 1001 1 1 1 1 0 0 2...^...^...^...^...^...^...^...^...^...^ Source impedance data (looking into TA system at 161-k bus) Bus1->Bus2->Bus3->Bus4-><----R<----L<---- SRA B16SA 1.751 26.7 SRB B16SB 1.751 26.7 SR B16S 1.751 26.7 Power transformer model Bank 1 A-phase TRANSFORMER <--Ref<----><--Iss<--Phi<-Name<-Rmag<----------------------IOUTMAG TRANSFORMER.1 9999.BANK1A1.58E5 9999 <-Bus1<-Bus2<----------><---Rk<---Lk<-olt<-------------------------------IMAG 01 B161A B161N 1.13 176.1 88.9 02 B46A 0.052 0.1 26.6 03 B131A B131B 0.0231.6878 13.2 Bank 1 B-phase TRANSFORMER <--Ref<----><--Iss<--Phi<-Name<-Rmag<----------------------IOUTMAG TRANSFORMER BANK1A BANK1B <-Bus1<-Bus2<----------><---Rk<---Lk<-olt<-------------------------------IMAG 01 B161B B161N 02 B46B 03 B131B B131 Bank 1 -phase TRANSFORMER <--Ref<----><--Iss<--Phi<-Name<-Rmag<----------------------IOUTMAG TRANSFORMER BANK1A BANK1 <-Bus1<-Bus2<----------><---Rk<---Lk<-olt<-------------------------------IMAG 01 B161 B161N 02 B46 03 B131 B131A Bank 2 A-phase TRANSFORMER <--Ref<----><--Iss<--Phi<-Name<-Rmag<----------------------IOUTMAG TRANSFORMER BANK1A BANK2A <-Bus1<-Bus2<----------><---Rk<---Lk<-olt<-------------------------------IMAG 01 B161A B161N 02 B46A 03 B132A B132B Bank 2 B-phase TRANSFORMER <--Ref<----><--Iss<--Phi<-Name<-Rmag<----------------------IOUTMAG TRANSFORMER BANK1A BANK2B <-Bus1<-Bus2<----------><---Rk<---Lk<-olt<-------------------------------IMAG 01 B161B B161N 02 B46B 03 B132B B132 Bank 2 -phase TRANSFORMER <--Ref<----><--Iss<--Phi<-Name<-Rmag<----------------------IOUTMAG TRANSFORMER BANK1A BANK2 <-Bus1<-Bus2<----------><---Rk<---Lk<-olt<-------------------------------IMAG 01 B161 B161N 02 B46 03 B132 B132A

Wye grounding impedance Bus1->Bus2->Bus3->Bus4-><----R<----L<---- B161N 26.5 Bank 1 capacitances Bus1->Bus2->Bus3->Bus4-><----R<----L<---- B131A 0.0042 B131B 0.0042 B131 0.0042 B161A 0.0011 B161B 0.0011 B161 0.0011 B46A 0.0009 B46B 0.0009 B46 0.0009 B46A B131A 0.0035 B46B B131B 0.0035 B46 B131 0.0035 B161A B46A 0.0024 B161B B46B 0.0024 B161 B46 0.0024 Bank 2 capacitances Bus1->Bus2->Bus3->Bus4-><----R<----L<---- B132A 0.0042 B132B 0.0042 B132 0.0042 B161A 0.0011 B161B 0.0011 B161 0.0011 B46A 0.0009 B46B 0.0009 B46 0.0009 B46A B132A 0.0035 B46B B132B 0.0035 B46 B132 0.0035 B161A B46A 0.0024 B161B B46B 0.0024 B161 B46 0.0024 Station service transformer on bank #1 13-k bus (single phase connected A-B) B131A 0.0002 B131B 0.0002 Station service transformer on bank #1 13-k bus (single phase connected A-B) B132A 0.0002 B132B 0.0002 14400-120 Instrument transformers TRANSFORMER <--Ref<----><--Iss<--Phi<-Name<-Rmag<----------------------IOUTMAG TRANSFORMER 0.004954.452 PTA1.75E6 3 <---urrent---<-----------flux 0.61282588E-03 0.71845242E+01 0.85340258E-03 0.12856517E+02 0.10037076E-02 0.16097656E+02 0.12661239E-02 0.22039743E+02 0.15167492E-02 0.27441641E+02 0.19281731E-02 0.34842241E+02 0.23213816E-02 0.39271798E+02 0.31695871E-02 0.45970151E+02 0.48836398E-02 0.52452429E+02 0.15215124E-01 0.64768756E+02 0.39100056E-01 0.69252331E+02 0.86113602E-01 0.72817584E+02 0.13466451E+00 0.74978343E+02 0.16349163E+00 0.76436855E+02 0.21548177E+00 0.78489576E+02 9999 <-Bus1<-Bus2<----------><---Rk<---Lk<-olt<-------------------------------IMAG 01 B13A B13B 942.0 14.4 1 02 SEA 0.057 0.507 0.12 TRANSFORMER <--Ref<----><--Iss<--Phi<-Name<-Rmag<----------------------IOUTMAG TRANSFORMER PTA PT 3 <-Bus1<-Bus2<----------><---Rk<---Lk<-olt<-------------------------------IMAG Page 7 of 10 TA-Ferroresonance at Arab

01 B13 B13B 02 SE 7200-120v Instrument transformers TRANSFORMER <--Ref<----><--Iss<--Phi<-Name<-Rmag<----------------------IOUTMAG TRANSFORMER 0.008827.009 PTA2.88E6 3 <---urrent---<-----------flux 0.56568542E-03 0.22417876E+01 0.79173890E-03 0.45105847E+01 0.10896106E-02 0.67523724E+01 0.13681169E-02 0.89941600E+01 0.16026080E-02 0.11262957E+02 0.19218959E-02 0.13504745E+02 0.22513641E-02 0.15746532E+02 0.27214398E-02 0.18015329E+02 0.32708947E-02 0.20257117E+02 0.43632949E-02 0.22498905E+02 0.59547641E-02 0.24767702E+02 0.87782054E-02 0.27009489E+02 0.15240792E-01 0.29251277E+02 0.36669038E-01 0.31520074E+02 0.17977154E+00 0.33761862E+02 9999 <-Bus1<-Bus2<----------><---Rk<---Lk<-olt<-------------------------------IMAG 01 B13A 417.3 7.2 1 02 SEA 0.085 0.498 0.12 TRANSFORMER <--Ref<----><--Iss<--Phi<-Name<-Rmag<----------------------IOUTMAG TRANSFORMER PTA PTB 3 <-Bus1<-Bus2<----------><---Rk<---Lk<-olt<-------------------------------IMAG 01 B13B 02 SEB TRANSFORMER <--Ref<----><--Iss<--Phi<-Name<-Rmag<----------------------IOUTMAG TRANSFORMER PTA PT 3 <-Bus1<-Bus2<----------><---Rk<---Lk<-olt<-------------------------------IMAG 01 B13 02 SE Damping resistance Bus1->Bus2->Bus3->Bus4-><----R<----L<---- SEA 32. SEB 32. SE 32. T apacitance to ground Bus1->Bus2->Bus3->Bus4-><----R<----L<---- B13A 1.1E-4 B13B 1.1E-4 B13 1.1E-4 13k bus capacitances (all aluminum bus @10 pf/ft per 37-011 Table 4) 13-k bus from switches to phase reactors (94.5 feet) B13A 9.5E-4 B13B 9.5E-4 B13 9.5E-4 Phase reactors between 13-k transformer bus and bank breaker B13A 0.0002 B13B 0.0002 B13 0.0002 Load on 46-k bus (30+j5) MA <---Nodes--><---Refer--><-Ohms<---mH<---uF<-----------------------------Output Bus1->Bus2->Bus3->Bus4-><----R<----L<---- B46A 68.8 30.2 B46B 68.8 30.2 B46 68.8 30.2 Load on 13-k bus (15+j5) MA <---Nodes--><---Refer--><-Ohms<---mH<---uF<-----------------------------Output Bus1->Bus2->Bus3->Bus4-><----R<----L<---- B13A 10.1 8.97 3 B13B 10.1 8.97 3 B13 10.1 8.97 3 Zig-zag grounding transformers on load side of bank breaker Page 8 of 10 TA-Ferroresonance at Arab

TRANSFORMER <--Ref<----><--Iss<--Phi<-Name<-Rmag<----------------------IOUTMAG TRANSFORMER 0.001 0.031 ZZA 1.E6 9999 <-Bus1<-Bus2<----------><---Rk<---Lk<-olt<-------------------------------IMAG 01ZIGAGAB13ZZA 0.044 0.623 1.0 1 02ZIGAG 0.044 0.623 1.0 1 TRANSFORMER ZZA ZZB 01ZIGAGBB13ZZB 1 02ZIGAGA 1 TRANSFORMER ZZA ZZ 01ZIGAGB13ZZ 1 02ZIGAGB 1 Additional capacitance on 13-k bus (attempt to detune ferroresonance) Bus1->Bus2->Bus3->Bus4-><----R<----L<---- B13A 0.75 3 B13B 0.75 3 B13 0.75 3 BLANK end of circuit data 13-k switch to connect bank #1 to 13-k transformer bus <-Bus1<-Bus2<---Tclose<----Topen<-------Ie<----Flash<--Request<-----Target<--O B131A B13A 1.E-3 999. B131B B13B 1.E-3 999. B131 B13 1.E-3 999. 161-k switch to check energization from high-side of power bank B16SA B161A -1.E-3 999. B16SB B161B -1.E-3 999. B16S B161-1.E-3 999. 13-k switch to connect grounding bank to 13-k main bus B13ZZA B13A -1.E-3 999. B13ZZB B13B -1.E-3 999. B13ZZ B13-1.E-3 999. BLANK end of breaker data Source voltage data (1.03 pu) <--Bus<I<-----Ampl<-----Freq<----Phase<-------A1<------T1><---Tstart<----Tstop 14 SRA 1 135399.6 60.0 0.0-1.0 9999 14 SRB 1 135399.6 60.0-120.0-1.0 9999 14 SR 1 135399.6 60.0 120.0-1.0 9999 BLANK end of source data Output request Bus-->Bus-->Bus-->Bus-->Bus-->Bus-->Bus-->Bus-->Bus-->Bus-->Bus-->Bus-->Bus--> SRA B13A SEA SRB B13B SEB SR B13 SE B161A B161B B161 B13ZZAB13ZZBB13ZZ BZZAB BZZB BZZA 345678901234567890123456789012345678901234567890123456789012345678901234567890 BLANK END OF OUTPUT REQUEST BLANK ARD ENDING PLOT ARDS BLANK END OF DATA ASE BEGIN NEW DATA ASE BLANK END OF ALL ASES Page 9 of 10 TA-Ferroresonance at Arab

Page 10 of 10 TA-Ferroresonance at Arab Magnetic Saturation Data file for 7200-120 Ts Appendix B T Excitation Data File BEGIN NEW DATA ASE alculation of the current vs flux saturation curves from the knowledge of the RMS magnetization current of the transformer. SATURATION --Freq<-Kbase<MAbase<-Ipunch<-kthird 34567890123456789012345678901234567890 60. 7.2 0.0015 0 0 <---------Irms<-----------rms 0.00192 0.083 0.00296 0.167 0.00392 0.250 0.00488 0.333 0.00576 0.417 0.00672 0.500 0.00776 0.583 0.00904 0.667 0.01056 0.750 0.01296 0.833 0.01664 0.917 0.02272 1.000 0.03552 1.083 0.0752 1.167 0.32464 1.250 9999 BLANK End of Saturation ases BEGIN NEW DATA ASE BLANK End of Run Magnetic Saturation Data file for 14400-120 Ts BEGIN NEW DATA ASE alculation of the current vs flux saturation curves from the knowledge of the RMS magnetization current of the transformer. SATURATION --Freq<-Kbase<MAbase<-Ipunch<-kthird 34567890123456789012345678901234567890 60. 14.4 0.002 0 0 <---------Irms<-----------rms 0.00312 0.133 0.00468 0.238 0.00546 0.298 0.00684 0.408 0.00810 0.508 0.01002 0.645 0.01152 0.727 0.01476 0.851 0.02052 0.971 0.05658 1.199 0.11700 1.282 0.24300 1.348 0.37380 1.388 0.47280 1.415 0.63600 1.453 9999 BLANK End of Saturation ases BEGIN NEW DATA ASE BLANK End of Run